Supreme Court of IndiaSupreme Court · 2015Single JudgeAppeal allowed; suit dismissed; no costs.

STATE OF GUJARAT v. M/S KOTHARI AND ASSOCIATES

Case / Petition Number:
Civil Appeal No. 1770 of 2005
Neutral Citation:(2015) 10 SCR 133

Case Synopsis & Summary

State of Gujarat v. M/S Kothari and Associates concerns a public works contract for lining a main canal. The respondent, a registered partnership, was contracted to carry out the works from 15 November 1976 to 14 June 1978, with the site handed over late in several seasons. Delays by the State in handing over the site and in supplying cement led to repeated extensions through 1980, during which the respondent sought compensation for additional costs, labour and fuel price escalations, overstay of capital and overheads. The Final Bill was signed under protest on 1 January 1982, and a statutory notice under Section 80 CPC was issued on 7 August 1983, claiming damages. The respondent then filed suit on 25 January 1985 for damages across thirteen heads. The Trial Court granted compensation under most heads and the High Court, in 2003, allowed the respondent’s cross-objection to claim interest from 1982. The State challenged the decision, arguing, among other things, that the suit was time-barred. The Supreme Court, however, held that the claim is for damages arising from successive breaches and must be considered under Article 55 of the Limitation Act, not the residuary Article 113. It concluded that the cause of action arose on each breach and that the suit was time-barred since the last breach occurred in 1982 and the suit was filed after the applicable period. The appeal is allowed, and the suit is dismissed.

Precedent Explorer

Find Cases Like This

Explore other judgments dealing with similar legal situations, facts, or statutory provisions.

Case Details & Bench

Court
Supreme Court of India
Hon'ble Judges
  • Vikramajit Sen
  • Shiva Kirti Singh
Judgment Date
2015-10-16
Court Decision / Holding
Appeal allowed; the suit is dismissed for limitation; no order as to costs.
Final Disposition
Appeal allowed; suit dismissed; no costs.

Parties to the Case

Appellants / Petitioners

  • STATE OF GUJARAT

Respondents

  • M/S KOTHARI AND ASSOCIATES

Legal Representation & Advocates

Counsels for Petitioners

  • • Pritesh Kapur
  • • Kabir Hathi
  • • Jesal Wahi
  • • Hemantika Wahi

Counsels for Respondents

  • • Meenakshi Arora
  • • Shirish D. Patel
  • • Bina Gupta
  • • Ranjit B. Raut

Provisions of Law Cited

Limitation Act, 1963 - Article 55Limitation Act, 1963 - Article 113Limitation Act, 1963 - Section 3Limitation Act, 1963 - Section 15(2)Limitation Act, 1963 - Section 18Limitation Act, 1963 - Section 19Civil Procedure Code - Section 80Indian Contract Act - Section 73

Legal Doctrines & Maxims

  • For successive breaches, the period of limitation begins anew with each breach under Article 55.
  • Damages arising out of breach within a works contract fall under Article 55, not the residuary Article 113.
  • A fresh contract is deemed entered on grant of each extension.
  • Limitation is a mandate to the court and must be considered even if not pleaded (Union of India v. British India Corporation).
  • Limitations principles can be urged in the Court of last resort (Lachhmi Sewak Sahu).
  • Gannon Dunkerley distinguished on facts; damages within contract differ from enhanced rates outside contract.

Submissions & Arguments

Contentions of Appellants / Petitioners

The State contends that the suit for damages is barred by limitation and that the High Court erred in treating the claim as arising from a series of extensions rather than a continuous breach. It emphasizes that the claim failed to start a new limitation clock with each extension and that the last breach dated 15 November 1982 would anchor a three-year period ending in 1985, by which time the suit was filed; it argues that payments and final bills accepted without objection did not extend the period for fresh claims. It also rejects reliance on Section 19 and Section 18 to extend time, noting explicit refusals to compensate for extensions and the absence of a continuing debt until adjudication.

Contentions of Respondents

The Respondent argues that delays were successive breaches of the contract entitling it to damages for extension-related costs under Article 55. It asserts that each extension created a fresh cause of action and a fresh three-year period, and that the suit filed within three years of the last breach should be timely. It relies on pre-1985 authority to show limitation is a fungal issue and must be examined by the court even if not pleaded. The Respondent also cites related doctrines on limitation and debt to justify extending consideration beyond the last breach and contends that Section 19 does not apply to fresh damages claims.

Legal Doctrine & Issue Explorer

Explore This Legal Issue

Find relevant judgments and authoritative positions on the legal questions discussed here.

Cited Precedents (8)

Case NameCitationTreatmentExplanation
Union of India v. British India Corporation Ltd2003 (9) SCC 505PositiveCited to support the proposition that limitation is a mandate to the forum and must be considered by the court even if not pleaded.
Lachhmi Sewak Sahu v. Ram Rup SahuAIR 1944 Privy Council 24PositiveCited for the proposition that limitation can be urged in the Court of last resort.
Gannon Dunkerley and Co. Ltd. v. Union of India(1969) 3 SCC 607DistinguishedCited as a comparative authority but distinguished on facts since damages arise within a contract here.
Rohtas Industries Ltd v. Maharaja of Kasimbazar China Clay MinesILR (1951) 1 Cal 420PositiveCited for the principle that a cause of action for breach arises at the end of each period due to monthly deliveries.
Union of India v Raman Iron Foundry(1974) (2) SCC 231PositiveCited to illustrate the treatment of damages as not a debt until adjudicated and its relation to limitation.
J.C. Budharaja v. Chairman, Orissa Mining Corporation Ltd. & Anr(2008) 2 SCC 444PositiveCited to discuss Section 19’s effect on extending limitation for existing debts but not for fresh claims.
Mis Disha Constructions v. State of Goa(2012) 1 SCC 690Mentioned OnlyCited for Section 15(2) but not applied to extend the period in this case.
Jones v. Thompson(1858) 27 L.J.Q.B. 234PositiveCited to support the principle that damages are not a debt and must be analyzed accordingly.
Case Applicability Diagnostic

Apply This to My Facts

Share your situation and test whether this judgment governs, supports, or challenges your case.

Official Judgment Record
•4,005 words•~19 min read

In The Court Record

STATE OF GUJARAT v. M/S KOTHARI AND ASSOCIATES

[2015) 10 S.C.R. 133 A ## STATE OF GUJARAT v. ## M/S KOTHARI AND ASSOCIATES (Civil Appeal No. 1770 of 2005) B OCTOBER 16, 2015 **[VIKRAMAJIT SEN AND SHIVA KIRTI SINGH, JJ.)** - - _Limitation Act, 1963 Art._ 55 - _Work contracts_ - - _Successive breaches Extension· of contract Claim for_ C _damages- Delay by appellant-State in handing over the site to respondent resulting in non-completion of work within the_ - _stipulated period by respondent Extension of period from time to time, though compensation sought by respondent_ - _denied by the appellant Final Bill signed under protest by_ o _respondent- Issuance of notice u/s. 80 CPC by respondent to appellant claiming damages-After period of three years,_ - _respondent filing of suit for damages for additional costs Grant of compensation with 12% interest from the date of statutory notice by trial court- In appeal, High Court granted_ E _interest for an extended period and held that since there were successive breaches by appellant, and the date of the last breach was relevant, the suit was within limitation- On appeal, held: The suit claims are damages incurred due to the extension of the contract period and the resultant damages_ F _are incurred by respondent, thus, suit would fall under Article_ - 55 _and not Article 113, which is a residuary provision There were successive or multiple breaches, rather than continuous breach_ - _Each breach was distinct and complete in itself and gave rise to_ a _separate cause of action for which respondent_ G _could have rescinded the contract- Suit was required to be_ - _filed within three years of the happening of each breach Period of limitation did not commence at the termination of the contract period or the date of final payment_ - _Suit was_ H 133 SUPREME COURT REPORTS [2015] 10 S.C.R. 134 A _filed after the limitation period of three years for even the_ - _final breach Respondent made claim for compensation_ - _on every occasion Appellant granted the extensions but rejected the claims, thus, the cause of action for making the claim for damages undoubtedly arose on each of those_ B _occasions_ - _Fresh contract would be deemed to have been entered into between the parties on the grant of each of the_ - _extensions Respondent should have initiated legal action_ - _on each of these occasions Having not done so, it_ - _abandoned the claim The suit is for damages for additional_ C _costs incurred, not on account of_ a _debt or of interest on legacy, and thus s. 19 would not per se extend the period of limitation_ - _There could be no extension uls. 18 on account of the acknowledgement in writing as each claim was specifically refuted by the Appellant- Notice perforce should_ 0 _have been issued before the suit became time barred, and only if so done would the period have been extended for a_ - _further two months under s. 80 CPC Thus, respondent failed to file the suit for damages within the period prescribedand the suit is dismissed._ E· _Union of India vs. British India Corporation Ltd_ (2003) 9 SCC 505; _Lachhmi Sewak Sahu vs. Ram Rup Sahu_ AIR 1944 Privy Council 24; _Gannon Dunkerley and_ Co. _Ltd. vs. Union of India_ (1969) 3 SCC 607:1970 (3) SCR 47; _Rohtas Industries Ltd vs. Maharaja of Kasimbazar China Clay Mines_ ILR (1951) 1 Cal 420; _Union oflndia vs. Raman Iron Foundry_ 1974 (2) SCC 231:1974 (3) SCR 556; _J.C. Budharaja vs Chairman, Orissa Mining Corporation Ltd._ andAnr(2008) 2 SCC 444: 2008 (1) SCR 821; _Mis Disha Constructions vs. State of_ Goa (2012) 1sec690: 2011 (13) SCR 496referred to. F G _Jones v. Thompson_ [1858) 27 L.J.Q.B. 234 - referred to. H 135 STATE OF GUJARAT v. M/S KOTHARI AND ASSOCIATES ||CaseLaw|LawReference||A| |---|---|---|---|---| ||c2003) 9sec505|referredto.|Para6|| ||AIR1944PrivyCouncil24|referredto.|Para6|| ||1970 (3)SCR47|referredto.|Para 8|B| ||ILR(1951) 1Cal420|referredto.|Para9|| ||1974(3)SCR556|referredto.|Para12|| |. 2008|. 2008(1)SCR821|referredto.|Para12|| ||2011 (13)SCR496|referredto.|Para13|c| CIVIL APPELLATE JURISDICTION : Civil Appeal No. 1770 of 2005 Fram the Judgment and Order dated 30. 07 .2003 of the 0 High Court of Gujarat atAhmedabad in First Appeal No. 34 of 1992. Pritesh Kapur, Kabir Hathi, Jesal Wahi, Hemantika Wahi for the Appellant. · E Meenakshi Arora, Shirish D. Patel, Bina Gupta, Ranjit B. Raut for the Respondent. The Judgment of the Court was delivered by F VIKRAMAJIT SEN, J. 1. This Appeal lays siege to the decision of the Division Bench of the High Court of Gujarat at Ahmedabad which dismissed the appeal of the Appellant before us while allowing the cross-objection filed by the Plaintiff/ Respondent by holding.it to be entitled to claim interest for an G extended period. For the reasons which will follow, we have set aside these concurrent findings against the Appellant State, principally on the ground that the claim of the Respondent stood barred by the principles of prescription as conta.ined in the Limitation Act, 1963. H [2015) 10 S.C.R. · SUPREME COURT REPORTS 136 A 2. The Appellant State invited tenders for providing lining to the main canal line. The Respondent, a registered partnership, submitted a tender that was accepted by the Appellant State. Thereafter a regular agreement was entered into according to which the Respondent would have from 15t11 B November to 14[1] h June as its working period. Under the WorkOrder dated 24.9.1976, the Respondent was required to complete the work within 18 months, i.e. on or before 23.3.1978. The case of the Respondent, which we have no cause to disbelieve, is that there were repeated and C consecutive delays in handing over the site due to which the Respondent could not complete the work within the stipulated time. The first season was to extend from 15.11.1976 to 14. 7 .1977, but the canal was only made available on 15.1.1977 and even then the cement was not issued to the Respondent 0 by the Appellant State till 31.1.1977. The second season was to extend from 15.11.1977 to 23.3.1978, but the canal was handed over on 15.3.1978. At the Respondent's request, the contract period was extended to 14.6.1978, buttheAppellant E State specifically stated that no compensation would be payable for the extension. Pursuant to a written request by the Respondent, a third season from 15.11.1978to14.6.1979was granted, but yet again the site was handed over as late as on 15.3.1979. The Respondent sought further time to complete F the project, and was consequently granted a fourth season which was to extend from 15.11.1979 to 29.6.1980. The site was once again made available with delay only on 15.3.1980. The work was finally completed on 20.6.1980. It is noteworthy that in each request for an extension, the Respondent sought G compensation for monetary loss due to the extended time limit, but while allowing each extension the Appellant State denied the claim for compensation each time. The Respondent's case was that as per the contract period, 342 days should have been made available to it to conduct the stipulated work, but H as a result of the delay in handing over the site and the A STATE OF GUJARAT v. M/SKOTHARIAND ASSOCIATES [VIKRAMAJIT SEN, J.] 137 materials, the Respondent had to seek extensions, and A nevertheless managed to complete the project in 288 working days, thus indicating that there was no laxity on its part. The Respondent signed the Final Bill under protest on 1.1.1982; and the Security Deposit was refunded on 27 .1.1982. Thereupon, the Respondent addressed a statutory notice B under Section 80 of the C.P.C. dated 7.8.1983 to the Appellant State, claiming damages as a result of the additional costs incurred due to the abovementioned delays. The Respondent eventually filed a suit on 25.1.1985 seeking damages under thirteen different heads, including price escalation in labour C due to the prolongation of the work, price escalation in fuel lubricants etc., overstay of capital and machinery, and overheads such as staff, kitchen, office etc. 3. The Trial Court found that the delay was caused by the D Appellant State; that work was completed by the Respondent well within the number of days contractually allocated to complete it. Noting that under Section 73 of the Indian Contract Act compensation is payable for any loss or damage for breach of a contract, the Trial Court granted compensation under E twelve of the thirteen heads of claims itemised by the Respondent. In terms of its Judgment dated 4.5.1991 the Trial Court observed that the factual matrix pertaining to these amounts claimed have remained uncontroverted, and F accordingly decreed the suit. The Respondent was granted ~s.13,61,571/-with interest at 12 percent per annum with effect from 7.8.1983 viz. the date of the statutory notice. Th~Appellant State appealed against the decree and the Respondent filed a counter-claim seeking interest from the date of written G demand of the suit claim instead of from the date of statutory notice. The High Court, vide its judgment dated 30. 7.2003, dismjssed the appeal filed by the Appellant State and allowed the Respondent's cross objection, granting interest thereon from 5.3.1982. H [2015] 10 S.C.R. 138 SUPREME COURT REPORTS c A B 4. The Appellant State has contended thatthe High Court ignored its myriad objections/submissions in connection with the various different heads; that the bills paid from time to time by the Respondent including the Final Bill were accepted without any remonstration or reservation being raised, thereby inexorably leading to the conclusion that the suit was clearly an afterthought; and that the suit was barred by limitation as the claims were raised after a lapse of more than three years from the arising of the causes of action. It is only the last contention to which we shall advert our attention. 5. It would be pertinent to note that the issue of limitation was not pleaded as a ground before the Trial Court or the High Court. It was pressed for the first time in the course of oral arguments before the High Court. Nonetheless, it has been D discussed in the impugned Order. The High <;;ourt; noting the contention raised by the Respondent that the point of limitation was a mixed question of fact and law and could therefore not be adjudicated at this point, held that even if it could be adjudicated, the suit would not be barred by principles of E prescription as it was based on a series of successive breaches committed by the Appellant State, and in such circumstances the date of the last breach was relevant. The High Court was of the opinion that limitation ·need not F mandatorily be computed on the basis of each cause of action. It held the date of return of the Security Deposit as the last date of payment for the work done, and concluded that the suit had been filed within three ye.ars from this date. The suit was therefore found to be within the prescribed period of limitation. G 6. Se;::tion 3 of the Limitation Act explicitly states that "every suit instituted, appeal preferred, and application made after the prescribed period shall be dismissed, altho~gh limitation has not been set up as a defence." It is thus incumbent H upon the Court to satisfy itself that the suit is not barred by limitation, regardless of whether such a plea has been raised STATE OF GUJARAT v. M/S KOTHARI AND ASSOCIATES [VIKRAMAJIT SEN, J.] 139 by the parties. In Union of India vs. British India Corporation A Ltd (2003) 9 sec 505, it. has been opined that "the question of limitation is a mandate to the forum and, irrespective of the fact whether it was raised or not, the forum must consider and apply it, if there is no dispute on facts." It is thus irrelevant that the Appellant State had not raised the issue of limitation before B the Trial Court. A duty was cast on the Court to consider this aspect of law, even on its own initiative, and since it failed to do so, the Appellant State was competent to raise this legal question in appeal or indeed even in any successive appeal. Close to a century ago, in Lachhmi Sewak Sahu vs. Ram Rup C Sahu AIR 1944 Privy Council 24, it has been held that the point of limitation is available to be urged even in the Court of last resort. Furthermore, we are not confronted with a situation where the plea of limitation is a mixed question of fact and 0 law, or where additiona! evidence needs to be adduced. The submissions of Learned Counsel for the Respondent to the effect that the Appellant is foreclosed and precluded from urging the plea of the bar of limitation are meretricious and are rejected. We shall now proceed to consider whether the suit E was in fact barred by limitation. 7. The period of limitation would be computed under either Article 55 or Article 113, both of which are laid out below of the facility of reference: |Descrip:ion_cl_Slit|Perialof<br>Unitation|lirreframvich!Jlfiod<br>rnairstorun| |---|---|---| |_M55._<br>For<XIIp:ilisaliai_fa_<br>thel::ree::hofar/cmlra'.i,<br>exµessorirrjlia:l,rdherein<br>spe:::ia1ypu.iida:l_fa._<br>.|lhrEeyeas|Wienthea:rtroctisl:xd<enrr_i_<br>(v\lle'eth:rearesux:essi\e•<br>treoches)Wa1trel:xea:hin:<br>resµnofvJlidl tresuitis<br>irstitLta:lcm.usor(W'erethe<br>1<br>trecrlliscx:rtinuing)W1enit•<br>ceases.<br>'I| |_M._113.AA/sit_fa_vJlidlno<br>peiod_cl_lirritaionispu.iidad<br>elsevh::reintlis&tedlle|lhrEeyeas|Wientherightto~ro:rues.<br>'<br>' '<br>'<br>I| [2015] 10 S.C.R. SUPREME COURT REPORTS 140 A A 8. It would be pertinent, at this point, to recall the decision of this Court in Gannon Dunkerley and Co. Ltd. vs. Union of India (1969) 3 SCC 607, though that matter dealt with the provisions of the Indian Limitation Act, 1908. The Appellants/ Plaintiff therein filed a suit seeking an enhanced rate of B compensation in light of the deviation in the nature of the work being rendered more complex, the increase in costs due to undue prolongation of the period of work, the increase in the quantity of work, and the grant of contracts to other competing parties at substantially higher rates. This Court held that the C "suit filed by the appellant Company is not a suit for compensation for breach of contract express or implied: it is a suit for enhanced rates because of change of circumstances, and in respect of work not covered by the contract." The claim for enhanced rates was found to arise outside the contract 0 and for this reason was not in the genre of an action for compensation for breach of contract. It was therefore held that the claim was not covered under Article 115 of the 1908 Act (which is _in pari materia_ to Article 55 of the Limitation Act), E and would have to fall within the ambit of Article 120 of the 1908 Act (which is akin to Article 113 of the Limitation Act). The facts at hand are dissimilar to those in Gannon Dunkerley in that the damages sought by the present Respondent are for work covered by the contract, and the F change in circumstances was directly caused by breaches ascribable to the Appellant State in not handing-over the site on time. Facially, the suit claims are damages incurred due to the extension of the contract period and the resultant damages are incurred by the Respondent. The suit would therefore fall G within the ambit of Article 55. Article 113, which is a residuary provision, cannot be resorted to. • 9. It also appears to us that the contract was clearly not broken as the Respondents chose to keep it alive despite its H repeated breaches by the Appellant State. The factual matrix STATE OF GUJARAT v. M/S KOTHARI AND **141** ## ASSOCIATES [VIKRAMAJIT SEN, J.] presents a situation of successive or multiple breaches, rather A than of a continuous breach, as each delay in handing over the canal/site by the Appellant State constituted to a bread 1 that was distinct and complete in itself and gave rise to a separate cause of action for which the Respondent could have rescinded the contract or possibly claimed compensation due B to prolongation of time and resultant escalation of costs. Of course the Respondent is enabled to combine all these causes of action in one plaint, as postulated in the C.P.C provided each claim is itself justiciable. Even the Respondent has argued before the High Court that the suit was based on successive C breaches committed by the Appellant State. In our opinion, the suit was required to be filed within three years of the happening of each breach, which would constitute a distinct cause of action. Article 55 specifically states that in respect of 0 successive breaches, the period begins to run when the breach in respect of which the suit is instituted, occurs. In this vein, Rohtas Industries Ltd vs. Maharaja of Kasimbazar China Clay Mines ILR (1951) 1 Cal 420 is apposite as it has held that when a party agrees to deliver certain goods every month for E a duration spanning certain years, the cause of action for breach for failure to deliver in a particular month arises at the end of that month and not at the end of the period of the contract. The situation before us is similar in that the cause of action had arisen on each occasion when the Appellant State failed F to hand over the site at the contractually stipulated time. Specifically, the limitation periods arose on 15.11.1976, 15.11.1977, 15.11.1978 and 15.11.1979, i.e. on the first day of each season, when the Respondent State committed a breach by failing to hand over the site. Thus the period of G limitation did not commenqe at the termination of the contract period or the date offinal payment. The High Court's conclusion that the last date of breach and last date of payment were relevant, not each cause of action, was thus patently erroneous. For each breach, a corresponding amount of damages for H [2015] 105.C.R. SUPREME COURT REPORTS 142 - A additional costs could have been sought. The suit, however, was filed on 25.1.1985, we.II after the limitation period of three years for even the final breach, as the various causes of action became time barred on 15.11.1979, 15.11.1980, 15.11.1981 and 15 .11. 1982 respectively. - B 10. There is another perspective on the method or manner in which limitation is to be computed. We have already narrated that the Respondent, on every occasion when the extension was sought by it, had requested to be compensated C for delay. The Appellant State had granted the extensions but had repudiated and rejected the Respondent's claims for damages. The effect of these events would be that the cause of action for making the claim for damages indubitably arose on each of those occasions. It is certainly argua~le that the D Appellant State may have also been aggrieved by the delay, although the facts of the case appear to be unfavourable to this prediction, since delay can reasonably be laid at the door of the Appellant. The Respondent, however, could _prima facie_ be presumed to have accepted a renewal or extension in the - E period of performance but with the rider that the claim for damages had been abandoned by it. If this assumption was not to be made against the Respondent, it would reasonably be expected that the Respondent should have filed a suit for - F damages on each of these occasions. In a sense, a fresh contract would be deemed to have been entered into between the parties on the grant of each of the extensions. It is therefore not legally possible for the Respondent to contend that there was a continuous breach which could have been litigated upon - G when the contract was finally concluded. In other words, contemporaneous with the extensions granted, it was essential for the Respondent to have initiated legal action. Since this was not done, there would be a reasonable presumption that. the claim for damages had been abandoned and given a go- - H by by the Respondent. STATE OF GUJARAT v. M/S KOTHARI AND 143 ## ASSOCIATES [VIKRAMAJIT SEN, J.] 1 :1. In a works contract, more often than not, delays occur, A and that is why it is assumed that time is not of the essence. Where extensions are asked for and granted, there must be a clear and discernable stand on behalf of either of the parties that the extension is granted and/or accepted without prejudice to the claim of damages. It has become commonplace that B neither party lodges a claim for damages, but waits for the end of the contract to raise these ·disputes, taking advantage of the nebulous and equivocal nature of the transactions between them. This, however, is not the position that obtains before us since the Appellant State had categorically posited C that the claim for damages for the alleged delay on its part would not be entertained. > 12. The Respondent has sought to place reliance on > Section 19 of the Limitation Act. It would be apposite to D reproduce this Section: 19. Effect of payment on account of debt or of interest on legacy.-Where payment on account of a debt or of interest on a legacy is made before the expiration of the prescribed period by the person liable to pay the debt or E legacy or by his agent duly authorised in this behalf, a fresh period of limitation shall be computed from the time when the payment was made. This Section would not come to the aid of the Respondent, as F the suit before us is not for payment on account of a debt or of interest on leg.acy, but is a suit for damages for additional costs incurred as a result of the extension of the contract period. This Court in Union of India vs. Raman Iron Foundry 197 4 (2) SCC 231 , afte·r placing reliance on Jones v. Thompson [1858) G 27 L.J.Q.B. 234, has opined that a claim for damages does not give rise to a debt until the liabiiity is adjudicated and damages have been assessed by a decree or any order of a Court or any other adjudicatory authority or forum. Furthermore, in J.C. Budharaja vs Chairman, Orissa Mining Corporation Lttj. H [2015] 10S.C.R. SUPREME COURT REPORTS 144 A and Anr (2008) 2 SCC 444, it has been held that the effect of Section 19 would be to allow a fresh period of limitation with regard to the 'existing debt' in respect of which acknowledgment and payment has been made. It would not extend the period of limitation for any fresh claim, or any amount B not accepted by the other party. In the factual scenario before us, the payment of the Final Bill and Security Deposit could not be construed to accepf or acknowle~ge the damages raised by the Respondent and therefore Section 19 would not _per se_ extend the period oflimitation .-Furthermore, there could C be no extension under Section 18 on account of the acknowledgement in writing, as at each point that the Respondent raised a claim for damages, it was specifically refuted by the Appellant State, and the amounts that were accepted by the Appellant State were limited to the liabilities 0 within the contract, not fresh liabilities for damages. 13. The Respondent has also argued that since notice under Section 80 of the C.P.C. was served to the Appellant State claiming damages on 7.8.1983, a period of two months E from the date of the notice would have to be excluded when calculating the period of limitation, as per Section 15(2) of the Limitation Act. It has relied on _Mis_ Disha Constructions vs. State of Goa (2012) 1SCC690 to this end. However, since the limitation period for the last breach alleged by the F Respondent itself ended on 15.11.1982 and the notice under Section 80 C.P.C. is dated 7.8.1983, this provision is irrelevant. The notice perforce should have been issued before the suit became time barred, and only if so done would the period have been extended for a further tWo months. G 14. It is thus clear that the Respondent failed to file the suit for damages within the period prescribed in the Limitation Act. The suit is required to be dismissed on this ground alone. The impugned Order is, therefore, set aside, and the Appeal H is allowed, but with no order as to costs. Nidtii Jain Appeal allowed.
End of Judgment Record
Browse All Supreme Court of India (2015) Decisions
2015-09-30

The Committee-GFIL v. Libra Buildtech Private Ltd. & Ors.

The Committee-GFIL v. Libra Buildtech Private Ltd. & Ors. concerns a court-monitored sale of assets of Golden Forest India Limited (GFIL) conducted by the GFIL Committee in liquidation. Bidders Libra Buildtech Pvt. Ltd. and other investors were declared successful at auction and deposited substantial sums. The Supreme Court later confirmed the sale in 2009 and directed possession to be handed over, but the transfer of ownership did not occur. On 26 September 2012, the Court cancelled the sale and directed the GFIL Committee to refund the entire sale consideration with interest, while permitting the bidders to pursue a refund of stamp duty from the State Government. The GFIL Committee refunded the sale price but deducted TDS, prompting the bidders to seek refund of stamp duty totaling Rs. 6.22 crores. The State of Punjab, through the SDM, Dera Bassi, and others, rejected the stamp duty refund on the grounds of limitation. The Supreme Court held that the stamp duty refund claim cannot be time-barred given the court-monitored nature of the transaction, the equity involved, and the fact that the contract was cancelled by the Court. It relied on the Indian Stamp Act provisions (ss. 49(d)(2) and 50(3)), the Contract Act (s. 65), and the maxim actus curiae neminem gravabit to justify refund. The Court ultimately allowed IA Nos. 9 and 10, directing the State to refund Rs. 6.22 crores within four weeks.

2015-03-19

HMT WATCHES LTD. v. M.A. ABIDA & ANR.

These appeals challenge a Kerala High Court order that quashed multiple criminal complaints under Section 138 of the Negotiable Instruments Act, 1881, by invoking jurisdiction under Section 482 of the Code of Criminal Procedure. The Supreme Court held that the High Court committed a grave error of law in quashing the proceedings by accepting disputed factual defences and treating them as uncontroverted at the Section 482 stage. The disputed issues — such as whether the cheques were given as security, whether there was an outstanding liability, or whether the signatory of the demand notice was authorized — were factual in nature and could only be resolved by the trial court after producing evidence. The Court reaffirmed that the jurisdiction under Section 482 Cr.P.C. is limited and should not be invoked to decide disputed questions of fact or to bypass the proper trial procedure. It also clarified that an instruction of stop payment can attract liability under Section 138 NI Act, citing Pulsive Technologies, Modi Cements, and related authorities. The judgment underscores that the purpose of criminal proceedings under Section 138 is to secure prompt payment, and courts should avoid premature discharge of the proceedings when material facts remain in dispute. Accordingly, the appeals are allowed and the trial court is directed to proceed with the trials.

2015-12-01

Medical Council of India v. Mediciti Institute of Medical Sciences (MIMS) & Ors.

This is a Civil Appeal involving the renewal of permission for increasing MBBS admissions at Mediciti Institute of Medical Sciences (MIMS) from 100 to 150 for the academic year 2015-16. The Medical Council of India (MCI) conducted inspections in December 2014 and subsequently in May 2015, finding deficiencies in faculty strength, resident numbers, facilities (including a girls’ common room and operating theatres), and other norms. The Executive Committee of the MCI recommended against renewing the permission for the 4th batch of 150 MBBS seats. MIMS challenged the decision in the Delhi High Court, which directed the MCI to conduct a re-inspection to verify whether deficiencies had been removed. The Supreme Court, however, reversed the High Court’s direction, holding that where the norms set by the apex regulatory body are not fulfilled, the judiciary should not compel the regulator to deviate from those fixed standards or to indulge in an additional inspection beyond the prescribed schedule. It emphasized the Establishment of Medical College Regulations, 1999 and the time schedule laid down by this Court for grant of permissions, noting that re-inspection is not warranted. The result: appeals allowed, with no order as to costs, and the High Court’s direction stood set aside.

2015-04-17

H. Lakshmaiah Reddy v. L. Venkatesh Reddy

This Supreme Court is hearing Civil Appeal Nos. 3725-3726 of 2015 arising from a dispute between H. Lakshmaiah Reddy (and others) and L. Venkatesh Reddy regarding the title to a suit property originally owned by Guramma, mother of the plaintiff and first wife of the first defendant. After Guramma’s death, the first defendant furnished a declaration before revenue authorities to change the Katha in the plaintiff’s name, and mutation was effected, with revenue records showing the plaintiff as owner for a long period. The first defendant later married again and had further children; the plaintiff and the first defendant, as class-I heirs, claimed half-share each in the property. The trial court dismissed the suit, the lower appellate court partially decreed in favor of the plaintiff, and the High Court allowed the respondent’s Second Appeal. The core legal issue concerns whether mutation entries in revenue records convey title. The Court held that mutation does not create or extinguish title and is only for land-revenue purposes; it cannot divest the first defendant of his half share. The High Court’s view that the first defendant’s conduct, via mutation, divested him of title was incorrect. The Court affirmed the lower appellate court’s decree, set aside the High Court judgment, and allowed the appeals, emphasizing that Article 142 relief is not to override the governing law of succession. The order closes with “Appeals allowed” and no costs.