This Supreme Court appeal concerns an ongoing redevelopment dispute over a 22,000 sq ft plot in Vittalwadi, Chembur, Mumbai, leased in 1972 to a partnership firm (M/s Silver Chem India) and subsequently owned by the appellant, Tushar Himatlal Jani. After termination of the lease, Respondent No.1 claimed tenancy rights through a family settlement and separate proceedings, asserting rights in a 550 sq ft portion. Respondent No.1 obtained interim protection in April 2023 from the Small Causes Court and again from the High Court in 2024, restraining the appellant from dispossessing him or creating third-party interests. The High Court restored the interim injunction on a modified term during the pendency of the eviction suit, prompting this appeal. The Supreme Court recalls the settled test for interim relief: prima facie case, balance of convenience, and irreparable injury. It held that Respondent No.1 failed to establish a prima facie tenancy right at this stage, and that the balance of convenience clearly favored the appellant, given that the disputed area is only 550 sq ft of 22,000 sq ft and that the appellant has already entered into a leave-and-license arrangement for 2,200 sq ft. Therefore, the impugned injunction unduly impeded redevelopment and caused irreparable delay. The Court set aside the High Court order but directed that 550 sq ft be kept reserved as security pending adjudication.
Find Cases Like This
Explore other judgments dealing with similar legal situations, facts, or statutory provisions.
Case Details & Bench
- Court
- Supreme Court of India
- Hon'ble Judges
- Surya Kant
- Nongmeikapam Kotiswar Singh
- Judgment Date
- 2025-05-13
- Court Decision / Holding
- The Supreme Court allowed the appeal, set aside the impugned High Court order, and directed that a unit measuring about 550 sq ft be kept reserved in the developed property to protect any rights of Respondent No.1, pending the Small Causes Court’s decision in RAD Suit No. 519/2023. The Court clarified that it is not expressing views on the tenancy merits and that the Small Causes Court should adjudicate the matter uninfluenced by observations in this judgment.
- Final Disposition
- Appeal allowed.
Parties to the Case
Appellants / Petitioners
- Tushar Himatlal Jani
Respondents
- Jasbir Singh Vijan
- M/s Silver Chem (India)
Legal Representation & Advocates
Counsels for Petitioners
- • Shyam Divan
- • Amit Dhingra
- • Anirudh Arunkumar
- • Rohit Mahajan
- • Dua Associates
Counsels for Respondents
- • Arunabh Chowdhury
- • Anuroop Chakravarti
- • Ramit Singh
- • M S Vishnu Sankar
- • Mitesh Parekh
- • Ms. Athira G Nair
- • Lawfic
- • C. George Thomas
Legal Doctrines & Maxims
- Prima facie case
- Balance of convenience
- Irreparable injury
Submissions & Arguments
Contentions of Appellants / Petitioners
The appellant contends that the High Court erred in granting an interim injunction in favour of Respondent No.1, effectively halting a substantial redevelopment project over a disputed 550 sq ft out of 22,000 sq ft. There were no eviction proceedings initiated by the appellant; Respondent No.1’s claimed tenancy rights are sub-judice before the Small Causes Court. The appellant also argues that Respondent No.1 lacks locus standi to stall development since surrendered tenancy rights and a completed leave-and-license arrangement with M/s KMG Global weaken his claims. Given the small size of the disputed portion and the appellant’s ongoing redevelopment plans, the balance of convenience and potential irreparable financial harm favor allowing redevelopment and safeguarding rights through a court process rather than broad injunction.
Contentions of Respondents
Respondent No.1 asserts tenancy rights under a Family Settlement Agreement and seeks interim protection on a 550 sq ft portion, arguing that the rights flow from partnership and mediation efforts. He emphasizes that a consent order/settlement and prior interim protections must guide the dispute; the eviction action is sub-judice and altering the interim protection would undermine due process and the mediated settlement. He maintains the injunction preserves rights until adjudication by the Small Causes Court, consistent with due process and prior Court orders.
Explore This Legal Issue
Find relevant judgments and authoritative positions on the legal questions discussed here.
Apply This to My Facts
Share your situation and test whether this judgment governs, supports, or challenges your case.
In The Court Record
Tushar Himatlal Jani v. Jasbir Singh Vijan & Ors.
Related Decisions & Precedents from Supreme Court of India (2025)
Krishna Devi @ Sabitri Devi (Rani) M/s S.R. Engineering Construction v. Union of India & Ors.
Krishna Devi @ Sabitri Devi (Rani) approaches the Supreme Court seeking pronouncement of judgment in terms of an arbitral award under Section 17 of the Arbitration Act, 1940. The appellant’s husband secured a favourable award on 31 May 2022 in a dispute over a Tezpur work contract. Although the award was not published due to outstanding arbitrator fees, a district court order dated 21 September 2022 directed the respondents to clear the balance and stated that once paid, the award would be furnished. The appellant filed a Section 17 application on 10 November 2022 seeking the court to pronounce judgment in terms of the award. The trial court and the Gauhati High Court held the application premature, because it was filed before the expiry of the 30-day objections window under Article 119(b) of the Limitation Act, calculated from 18 November 2022 (alleged formal notice). The Supreme Court, however, held that the start of limitation is not tied to a formal notice but to awareness of the award’s existence. It relied on earlier decisions establishing that Section 14(2) only requires awareness that an award exists; a court’s order directing payment of fees can constitute such notice. Consequently, the 30-day limitation expired by 20 October 2022, rendering the Section 17 application timely. The appeal is allowed, and directions are issued to dispose of the related matter expeditiously with no costs.
Saranga Anilkumar Aggarwal v. Bhavesh Dhirajlal Sheth & Ors.
This Civil Appeal concerns whether execution of penalty orders imposed by the National Consumer Disputes Redressal Commission (NCDRC) can be stayed under the interim moratorium provisions of Section 96 of the Insolvency and Bankruptcy Code, 2016 (IBC), while insolvency proceedings are pending under Section 95 of the IBC. The appellant, a real estate developer, sought a stay of 27 penalties levied for deficiency in service and delay in possession of residential units, arguing that an application under Section 95 of the IBC had triggered an interim moratorium. The NCDRC had rejected the stay, holding that consumer-claims and penalties are not “debts” within the moratorium’s ambit. The Supreme Court affirmed that the damages awarded in consumer disputes arise to compensate home-buyers and deter malpractice, and are not ordinary contractual debts susceptible to IBC restructuring; such damages fall within the category of “excluded debts” under Section 79(15) of the IBC, and their enforcement remains unaffected by insolvency proceedings. The Court emphasized the essential distinction between debt-recovery proceedings and regulatory/penal actions under consumer protection laws, rejected reliance on contrary authorities (notably Sheetal Gupta per incuriam), and held that criminal penalties under the CP Act do not automatically fall within the moratorium. The appeal was dismissed; the appellant was directed to comply with the NCDRC penalties within eight weeks.
Serious Fraud Investigation Office v. Aditya Sarda
This batch of sixteen interconnected criminal appeals arises from SFIO's complaint against multiple respondents including Aditya Sarda for serious economic offences under the Companies Act, 2013 and the IPC. The Special Court at Gurugram took cognizance of the offences and issued bailable warrants to the accused, who allegedly concealed themselves or otherwise obstructed the process. Non‑bailable warrants were issued, and some proclamations under CrPC Section 82 were initiated against certain respondents. The High Court granted anticipatory bail to several respondents, notwithstanding the cognizance, warrant proceedings, and proclamations, leading to a series of challenges before the Supreme Court. The Court emphasises that anticipatory bail is an extraordinary remedy not available as a routine in cases involving serious economic offences, and that the twin mandatory conditions in Section 212(6) of the Companies Act, 2013 must be considered: (i) Public Prosecutor must be given an opportunity to oppose; and (ii) where opposed, the court must be satisfied of reasonable grounds to believe the accused is not guilty and unlikely to commit an offence while on bail. It reasons that respondents who evade process by concealing themselves after cognizance and after non‑bailable warrants were issued should not receive anticipatory bail. Accordingly, the High Court orders granting anticipatory bail are set aside, and the respondents are directed to surrender within one week to the Special Court, with subsequent bail determinations to be made in accordance with law. The judgment reiterates that economic offences require a cautious, exception‑based approach to bail and underscores the importance of ensuring due process and the unobstructed progress of judicial proceedings.
K.S. Mehta v. M/s Morgan Securities and Credits Pvt. Ltd.
This is a Supreme Court decision under Criminal Appeal No. 1105 of 2025 arising from quashing under Section 482 CrPC of criminal proceedings instituted under Section 138 read with Section 141 of the Negotiable Instruments Act, 1881. The appellants, K.S. Mehta and Basant Kumar Goswami, were non-executive directors of M/s Blue Coast Hotels & Resorts Ltd., chosen to meet SEBI’s governance requirements (Clause 49 of Listing Agreement). They were not present at the 09.09.2002 board meeting that approved an Inter-Corporate Deposit (ICD) of ₹5 crores nor signatories to the ICD agreement or related instruments. Later, two cheques issued to discharge the debt were dishonored, leading to criminal proceedings against the directors. The High Court of Delhi dismissed petitions under Section 482 CrPC seeking quashing. The Supreme Court held that non-executive and independent directors cannot be fastened with vicarious liability under Section 141 NI Act unless the record demonstrates their direct involvement in the company’s affairs at the relevant time. Here, there was no evidence of their involvement, no signatory status, and mere attendance at board meetings cannot establish liability. The Court emphasized the need for specific averments showing the director was in charge of and responsible for the company’s conduct. Consequently, the proceedings against the appellants were quashed and the appeals allowed.