Supreme Court of IndiaSupreme Court · 2025Division BenchAppeal allowed.

Tushar Himatlal Jani v. Jasbir Singh Vijan & Ors.

Case / Petition Number:
Civil Appeal No. 6636 of 2025
Neutral Citation:2025 INSC 663

Case Synopsis & Summary

This Supreme Court appeal concerns an ongoing redevelopment dispute over a 22,000 sq ft plot in Vittalwadi, Chembur, Mumbai, leased in 1972 to a partnership firm (M/s Silver Chem India) and subsequently owned by the appellant, Tushar Himatlal Jani. After termination of the lease, Respondent No.1 claimed tenancy rights through a family settlement and separate proceedings, asserting rights in a 550 sq ft portion. Respondent No.1 obtained interim protection in April 2023 from the Small Causes Court and again from the High Court in 2024, restraining the appellant from dispossessing him or creating third-party interests. The High Court restored the interim injunction on a modified term during the pendency of the eviction suit, prompting this appeal. The Supreme Court recalls the settled test for interim relief: prima facie case, balance of convenience, and irreparable injury. It held that Respondent No.1 failed to establish a prima facie tenancy right at this stage, and that the balance of convenience clearly favored the appellant, given that the disputed area is only 550 sq ft of 22,000 sq ft and that the appellant has already entered into a leave-and-license arrangement for 2,200 sq ft. Therefore, the impugned injunction unduly impeded redevelopment and caused irreparable delay. The Court set aside the High Court order but directed that 550 sq ft be kept reserved as security pending adjudication.

Precedent Explorer

Find Cases Like This

Explore other judgments dealing with similar legal situations, facts, or statutory provisions.

Case Details & Bench

Court
Supreme Court of India
Hon'ble Judges
  • Surya Kant
  • Nongmeikapam Kotiswar Singh
Judgment Date
2025-05-13
Court Decision / Holding
The Supreme Court allowed the appeal, set aside the impugned High Court order, and directed that a unit measuring about 550 sq ft be kept reserved in the developed property to protect any rights of Respondent No.1, pending the Small Causes Court’s decision in RAD Suit No. 519/2023. The Court clarified that it is not expressing views on the tenancy merits and that the Small Causes Court should adjudicate the matter uninfluenced by observations in this judgment.
Final Disposition
Appeal allowed.

Parties to the Case

Appellants / Petitioners

  • Tushar Himatlal Jani

Respondents

  • Jasbir Singh Vijan
  • M/s Silver Chem (India)

Legal Representation & Advocates

Counsels for Petitioners

  • • Shyam Divan
  • • Amit Dhingra
  • • Anirudh Arunkumar
  • • Rohit Mahajan
  • • Dua Associates

Counsels for Respondents

  • • Arunabh Chowdhury
  • • Anuroop Chakravarti
  • • Ramit Singh
  • • M S Vishnu Sankar
  • • Mitesh Parekh
  • • Ms. Athira G Nair
  • • Lawfic
  • • C. George Thomas

Legal Doctrines & Maxims

  • Prima facie case
  • Balance of convenience
  • Irreparable injury

Submissions & Arguments

Contentions of Appellants / Petitioners

The appellant contends that the High Court erred in granting an interim injunction in favour of Respondent No.1, effectively halting a substantial redevelopment project over a disputed 550 sq ft out of 22,000 sq ft. There were no eviction proceedings initiated by the appellant; Respondent No.1’s claimed tenancy rights are sub-judice before the Small Causes Court. The appellant also argues that Respondent No.1 lacks locus standi to stall development since surrendered tenancy rights and a completed leave-and-license arrangement with M/s KMG Global weaken his claims. Given the small size of the disputed portion and the appellant’s ongoing redevelopment plans, the balance of convenience and potential irreparable financial harm favor allowing redevelopment and safeguarding rights through a court process rather than broad injunction.

Contentions of Respondents

Respondent No.1 asserts tenancy rights under a Family Settlement Agreement and seeks interim protection on a 550 sq ft portion, arguing that the rights flow from partnership and mediation efforts. He emphasizes that a consent order/settlement and prior interim protections must guide the dispute; the eviction action is sub-judice and altering the interim protection would undermine due process and the mediated settlement. He maintains the injunction preserves rights until adjudication by the Small Causes Court, consistent with due process and prior Court orders.

Legal Doctrine & Issue Explorer

Explore This Legal Issue

Find relevant judgments and authoritative positions on the legal questions discussed here.

Case Applicability Diagnostic

Apply This to My Facts

Share your situation and test whether this judgment governs, supports, or challenges your case.

Official Judgment Record
•2,554 words•~12 min read

In The Court Record

Tushar Himatlal Jani v. Jasbir Singh Vijan & Ors.

[2025] 6 S.C.R. 414 : 2025 INSC 663 ## **Tushar Himatlal Jani** ## **v.** ## **Jasbir Singh Vijan & Ors.** (Civil Appeal No. 6636 of 2025) 13 May 2025 ## **[Surya Kant* and Nongmeikapam Kotiswar Singh, JJ.]** ## **Issue for Consideration** Whether the High Court was justified in restoring the interim injunction in favour of Respondent No.1 in a modified term during the pendency of the Suit. ## **Headnotes[†]** **Interim injunction – Grant of – When not proper – High Court restored the order of the small causes court and granted injunction in favour of Respondent No.1 restraining the appellant from dispossessing him or creating any third-party interest in the disputed premises – Interference with:** **Held:** High Court erred in granting the injunction in favour of Respondent No.1 – Respondent No.1 failed to establish a _prima facie_ case in his favour as the question of tenancy rights claimed by him is pending adjudication before the Small Causes Court – Balance of convenience also tilts in favour of the Appellant as the disputed area is merely 550 square feet out of the total area of 22,000 square feet and the Appellant has already entered into a leave and license agreement with one M/s KMG Global covering a built-up area of 2,200 square feet – Thus, the injunction inordinately impeded the entire redevelopment project for a relatively small disputed portion – Moreover, the Appellant would suffer irreparable injury if the injunction is allowed to operate, given that the protracted delay is not only causing substantial financial losses but also affecting the Appellant’s contractual obligations which cannot be adequately compensated at a belated stage – Impugned order set aside. [Paras 16, 17, 19] **Interim injunction – Grant of – Pre-requisites for – Discussed.** [Para 15] * Author [2025] 6 S.C.R.  415 **Tushar Himatlal Jani v. Jasbir Singh Vijan & Ors.** ## **List of Keywords** Interim injunction; Injunction; Tenancy rights; Tenancy dispute; Disputed premises; _Prima facie_ case; Balance of convenience; Irreparable injury or harm; Not adequately compensable in damages; Small Causes Court; Impleadment; Partnership firm; Family Settlement Agreement; Leave and license agreement; Redevelopment project; Small disputed portion; Surrender of tenancy rights; Equities balanced. ## **Case Arising From** CIVIL APPELLATE JURISDICTION: Civil Appeal No. 6636 of 2025 From the Judgment and Order dated 30.07.2024 of the High Court of Judicature at Bombay in WP No. 763 of 2024 ## **Appearances for Parties** _Advs. for the Appellant:_ Shyam Divan, Sr. Adv., Amit Dhingra, Anirudh Arunkumar, Rohit Mahajan, M/s. Dua Associates. _Advs. for the Respondents:_ Arunabh Chowdhury, Sr. Adv., Anuroop Chakravarti, Ramit Singh, M S Vishnu Sankar, Mitesh Parekh, Ms. Athira G Nair, M/s. Lawfic, C. George Thomas. ## **Judgment / Order of the Supreme Court** ## **Judgment** ## **Surya Kant, J.** Leave granted. 2. The instant appeal is directed against the order dated 30.07.2024 passed by the High Court of Bombay ( **High Court** ) restraining the Appellant from dispossessing Respondent No. 1 or creating any third-party interest in the disputed premises. 3. The facts leading to the instant appeal are that the Appellant’s father was the owner of a plot admeasuring 22,000 square feet bearing C.T.S. Nos.443(part), 451(part), 452A(part) at Vittalwadi, Ghatala [2025] 6 S.C.R. 416 ## **Supreme Court Reports** Village, Chembur, Mumbai. Out of the said area, the Appellant’s father leased out 11,250 square feet i.e. the subject land, to a partnership firm, namely M/s Silver Chem (India)/Respondent No.2, which was owned by the Vijan family members in 1972. It seems that upon the death of his father, the entire property devolved upon the Appellant. The Appellant terminated the above-mentioned lease agreement _vide_ notice dated 11.02.2008 and, in furtherance thereof, filed Eviction Suit No. 119/148 of 2008 before the Small Causes Court at Bombay ( **Small Causes Court** ). 4. Notably, Respondent No.1, who claims to be the legal heir of one of the partners of Respondent No. 2, allegedly runs a business from the suit structure in the name and style of M/s Asset Motors. He, thus, filed an Impleadment Application in the Eviction Suit, contending that he is a necessary and proper party whose rights would be directly affected by the outcome of the proceedings. Respondent No.1 postulated his undivided share in the business of Respondent No. 2 by virtue of a Memorandum of Understanding executed amongst the Vijan family members and further relied on his institution of a separate suit (bearing No.441/2014) before the High Court seeking partition of his 1/6[th] undivided share in all the properties owned and held by the Vijan family. The Small Causes Court allowed the impleadment application _vide_ order dated 06.10.2016. The Appellant, being aggrieved by the aforesaid order, preferred a revision petition before the Appellate Small Causes Court, which was allowed _vide_ order dated 03.05.2019, setting aside the order of impleadment. 5. Members of the Vijan family, i.e. the partners of Respondent No. 2 and Respondent No. 1, purportedly entered into a Family Settlement Agreement on 09.06.2021 to resolve their _inter se_ differences, which referred to Respondent No. 1’s entitlement to 550 square feet area within the subject land. This Family Settlement was the outcome of mediation efforts facilitated by a learned Mediator appointed by this Court in several petitions between members of the Vijan family. According to Respondent No.1, the Agreement ostensibly provided him with an undivided share in the premises, wherein he claims to have been allocated 550 square feet out of the total area of 22,000 square feet with entitlement to ‘receive right, title, interest, free of any encumbrances’ therein. [2025] 6 S.C.R.  417 ## **Tushar Himatlal Jani v. Jasbir Singh Vijan & Ors.** 6. In the aftermath of this settlement, several consequential events unfolded. Evidently, the partners of Respondent No. 2, along with Respondent No.1, entered into a Lease and License Agreement dated 15.10.2021, with M/s KMG Global as the licensee, for a period of 12 months in respect of the subject land. The Appellant has categorically asserted that this Agreement was executed without his consent and knowledge. Subsequently, Respondent No. 2 firm and its partners claimed to have surrendered their tenancy rights on 19.10.2022 _qua_ the subject land. Pursuant to these developments, Respondent No. 1 once again filed an impleadment application in the Eviction suit relying on the Family Settlement Agreement. He simultaneously lodged an application before the Registrar of Firms seeking recognition as a partner in Respondent No. 2 firm. Whilst these applications remained pending, Respondent No. 1 instituted a separate suit, which, according to the Appellant, was merely an attempt to create a paper trail of Respondent No. 1’s alleged physical possession of the disputed area in the subject land. 7. It appears that following the surrender of tenancy rights by Respondent No. 2 and its partners, the Appellant unconditionally withdrew the Eviction Suit _vide_ order dated 13.01.2023, wherein the Small Causes Court also rejected Respondent No. 1’s second application for impleadment. Consequently, the Appellant effectuated a leave and license agreement dated 11.04.2023 with M/s KMG Global over a built-up area of 2,200 square feet. 8. Thereafter, Respondent No.1, asserting his status as one of the partners of Respondent No.2, on the basis of the Family Settlement Agreement, filed a suit bearing R.A.D. Suit No. 519/2023 before the Small Causes Court seeking declaration of his tenancy rights with respect to an undivided area of 550 square feet purportedly forming part of the premises leased to Respondent No. 2. Respondent No.1 averred in this fresh suit that by virtue of his partnership status in Respondent No.2 as per the Family Settlement Agreement, any surrender of tenancy rights by Respondent No.2 firm _qua_ the subject land without his signature or consent would be illegal and non-binding. Respondent No.1 also filed an application bearing No. Exhibit 10 praying for interim protection in the form of his possession over the area measuring 550 square feet and restraining the Appellant from dispossessing him therefrom. The Small Causes Court, _vide_ order [2025] 6 S.C.R. 418 ## **Supreme Court Reports** dated 27.04.2023 granted interim protection to Respondent No.1 and subsequently confirmed the same _vide_ order dated 10.05.2023. The aggrieved Appellant preferred an appeal which was allowed by the Appellate Bench of the Small Causes Court _vide_ order dated 20.12.2023. 9. Respondent No.1 consequently filed Writ Petition (C) No.763/2024, which stands allowed and by way of impugned order, the High Court has restored the order dated 27.04.2023 of the Small Causes Court and granted injunction in favour of Respondent No. 1. 10. The aggrieved Appellant is thus before this Court. 11. Mr. Shyam Divan, learned Senior Counsel for the Appellant, contended that the impugned injunction order has effectively paralyzed the Appellant’s legitimate redevelopment plans, causing substantial financial detriment. He underscored that despite the disputed area of 550 square feet being merely a small fragment of the entire property, the restraint _qua_ this portion has brought the entire project to a grinding halt. He further propounded that the High Court gravely erred in issuing an injunction in the absence of any eviction proceedings initiated by the Appellant against Respondent No. 1. Mr. Divan posited that Respondent No. 1 lacks the _locus standi_ to obstruct the Appellant’s development rights as he is neither in lawful nor actual possession of the subject land. It was advanced that the original tenants had unequivocally surrendered their tenancy rights, thereby conferring complete and unencumbered rights upon the Appellant to deal with his property. 12. _Per Contra_ , Mr. Arunabh Chowdhury, learned Senior Counsel appearing on behalf of Respondent No. 1, vigorously urged that the impugned order is in the nature of a _simpliciter_ injunction not to dispossess Respondent No.1 from the subject property without due process of law and has been in force for more than 20 months with only a brief hiatus in the _interregnum_ . He staunchly maintained that the Appellant has not filed any suit to evict Respondent No. 1, rather he withdrew the Eviction Suit filed against Respondent No. 2 unconditionally _vide_ order dated 13.01.2023. He further expounded that rights in the disputed property emanate from a Family Settlement Agreement mediated through a Mediator appointed by this Court, and allowing the instant petition would overturn the Consent Order passed [2025] 6 S.C.R.  419 ## **Tushar Himatlal Jani v. Jasbir Singh Vijan & Ors.** by this Court in SLP (Crl.) No. 5587 of 2020. Mr. Chowdhury adduced that the putative Surrender Letter relied upon by the Appellant is _ex facie_ forged and illegal, inasmuch as it is bereft of any reference to any area being surrendered; it is not signed by all partners; and it inexplicably purports to surrender valuable property rights without any consideration. 13. Having heard learned Senior Counsels on behalf of both the parties and after perusing the record, we deem it approprite to clarify at the outset that the issue regarding the tenancy rights of Respondent No. 1 or of the partners of Respondent No. 2, who happen to be his family members, is sub-judice before the Small Causes Court in R.A.D. Suit No. 519/2023. The short question that falls for our consideration thus is whether the High Court was justified in restoring the interim injunction in favour of Respondent No. 1 in a modified term during the pendency of the Suit. 14. The High Court has, in the impugned order, noted that Respondent No.1 is a tenant/joint tenant of the subject land based on the Appellant’s alleged admission acknowledging his possession. Mr. Shyam Divan, however, strongly refuted this finding, contending that the Appellant’s counsel had characterized Respondent No. 1 as a rank trespasser during the course of inter-party negotiations and such references, made in the context of settlement discussions, cannot be construed as conclusive admissions for the purpose of granting injunction by the High Court. 15. The law governing the grant of interim injunction is well-settled. This Court, through a catena of decisions, has consistently held that before granting an interim injunction, the Court must satisfy itself of three essential prerequisites: _firstly_ , the existence of a _prima facie_ case in favour of the applicant evincing a reasonable probability of success at trial; _secondly_ , that the balance of convenience lies in favour of granting the injunctive relief; and _thirdly_ , that the applicant would suffer irreparable injury or harm not adequately compensable in damages if the injunction is refused. It is only when these three conditions are cumulatively fulfilled that an interim injunction ought to be granted. 16. Applying the principles delineated above to the facts at hand, we are of the considered view that the High Court erred in granting the [2025] 6 S.C.R. 420 ## **Supreme Court Reports** injunction in favour of Respondent No.1. We say so for the reason that the Appellant is incontrovertibly the absolute owner of the property, with the disputed area constituting merely a fraction of the entire premises. The Appellant has already entered into an agreement to redevelop the property. In these circumstances, the restraint imposed by the impugned injunction significantly circumscribes the Appellant’s legal right to derive commercial benefit from his property. 17. It further seems to us that Respondent No.1 has failed to establish a _prima facie_ case in his favour as the question of tenancy rights claimed by him is pending adjudication before the Small Causes Court, and at this stage, material ambiguities persist regarding the validity of his claim. Even though Respondent No. 1 claims rights and partnership in the Respondent No. 2 firm through a Family Settlement Agreement, such contention requires deeper scrutiny, which can only be undertaken during the course of trial of his civil suit. Concerning the balance of convenience, it decidedly tilts in favour of the Appellant, considering that the disputed area is merely 550 square feet out of the total area of 22,000 square feet, and the Appellant has already entered into a leave and license agreement dated 11.04.2023 with M/s KMG Global covering a built-up area of 2,200 square feet. The injunction has thus inordinately impeded the entire redevelopment project for a relatively small disputed portion. Moreover, the Appellant would suffer irreparable injury if the injunction is allowed to operate, given that the protracted delay is not only causing substantial financial losses but also affecting the Appellant’s contractual obligations, which cannot be adequately compensated at a belated stage. 18. Conversely, Respondent No. 1 would not suffer any irremediable loss as his alleged tenancy rights over an area measuring 550 square feet can be adequately safeguarded. 19. For the reasons aforestated, we allow the instant appeal and set aside the impugned order of the High Court dated 30.07.2024. However, with a view to balance equities, the Appellant is hereby directed to keep one unit measuring about 550 square feet reserved in the developed property as a security to protect the alleged rights of Respondent No.1, in the event that the Suit pending before the Small Causes Court is decided in his favour. [2025] 6 S.C.R.  421 ## **Tushar Himatlal Jani v. Jasbir Singh Vijan & Ors.** 20. We clarify that this order does not express any opinion on the merits of the tenancy dispute pending before the Small Causes Court. The said Court shall proceed to adjudicate the matter in R.A.D. Suit No.519/2023 in accordance with law, uninfluenced by any observations made herein and expeditiously. _Result of the case:_ Appeal allowed. - _†Headnotes prepared by:_ Divya Pandey
End of Judgment Record
Browse All Supreme Court of India (2025) Decisions
2025-01-03

Krishna Devi @ Sabitri Devi (Rani) M/s S.R. Engineering Construction v. Union of India & Ors.

Krishna Devi @ Sabitri Devi (Rani) approaches the Supreme Court seeking pronouncement of judgment in terms of an arbitral award under Section 17 of the Arbitration Act, 1940. The appellant’s husband secured a favourable award on 31 May 2022 in a dispute over a Tezpur work contract. Although the award was not published due to outstanding arbitrator fees, a district court order dated 21 September 2022 directed the respondents to clear the balance and stated that once paid, the award would be furnished. The appellant filed a Section 17 application on 10 November 2022 seeking the court to pronounce judgment in terms of the award. The trial court and the Gauhati High Court held the application premature, because it was filed before the expiry of the 30-day objections window under Article 119(b) of the Limitation Act, calculated from 18 November 2022 (alleged formal notice). The Supreme Court, however, held that the start of limitation is not tied to a formal notice but to awareness of the award’s existence. It relied on earlier decisions establishing that Section 14(2) only requires awareness that an award exists; a court’s order directing payment of fees can constitute such notice. Consequently, the 30-day limitation expired by 20 October 2022, rendering the Section 17 application timely. The appeal is allowed, and directions are issued to dispose of the related matter expeditiously with no costs.

2025-03-04

Saranga Anilkumar Aggarwal v. Bhavesh Dhirajlal Sheth & Ors.

This Civil Appeal concerns whether execution of penalty orders imposed by the National Consumer Disputes Redressal Commission (NCDRC) can be stayed under the interim moratorium provisions of Section 96 of the Insolvency and Bankruptcy Code, 2016 (IBC), while insolvency proceedings are pending under Section 95 of the IBC. The appellant, a real estate developer, sought a stay of 27 penalties levied for deficiency in service and delay in possession of residential units, arguing that an application under Section 95 of the IBC had triggered an interim moratorium. The NCDRC had rejected the stay, holding that consumer-claims and penalties are not “debts” within the moratorium’s ambit. The Supreme Court affirmed that the damages awarded in consumer disputes arise to compensate home-buyers and deter malpractice, and are not ordinary contractual debts susceptible to IBC restructuring; such damages fall within the category of “excluded debts” under Section 79(15) of the IBC, and their enforcement remains unaffected by insolvency proceedings. The Court emphasized the essential distinction between debt-recovery proceedings and regulatory/penal actions under consumer protection laws, rejected reliance on contrary authorities (notably Sheetal Gupta per incuriam), and held that criminal penalties under the CP Act do not automatically fall within the moratorium. The appeal was dismissed; the appellant was directed to comply with the NCDRC penalties within eight weeks.

2025-04-09

Serious Fraud Investigation Office v. Aditya Sarda

This batch of sixteen interconnected criminal appeals arises from SFIO's complaint against multiple respondents including Aditya Sarda for serious economic offences under the Companies Act, 2013 and the IPC. The Special Court at Gurugram took cognizance of the offences and issued bailable warrants to the accused, who allegedly concealed themselves or otherwise obstructed the process. Non‑bailable warrants were issued, and some proclamations under CrPC Section 82 were initiated against certain respondents. The High Court granted anticipatory bail to several respondents, notwithstanding the cognizance, warrant proceedings, and proclamations, leading to a series of challenges before the Supreme Court. The Court emphasises that anticipatory bail is an extraordinary remedy not available as a routine in cases involving serious economic offences, and that the twin mandatory conditions in Section 212(6) of the Companies Act, 2013 must be considered: (i) Public Prosecutor must be given an opportunity to oppose; and (ii) where opposed, the court must be satisfied of reasonable grounds to believe the accused is not guilty and unlikely to commit an offence while on bail. It reasons that respondents who evade process by concealing themselves after cognizance and after non‑bailable warrants were issued should not receive anticipatory bail. Accordingly, the High Court orders granting anticipatory bail are set aside, and the respondents are directed to surrender within one week to the Special Court, with subsequent bail determinations to be made in accordance with law. The judgment reiterates that economic offences require a cautious, exception‑based approach to bail and underscores the importance of ensuring due process and the unobstructed progress of judicial proceedings.

2025-03-04

K.S. Mehta v. M/s Morgan Securities and Credits Pvt. Ltd.

This is a Supreme Court decision under Criminal Appeal No. 1105 of 2025 arising from quashing under Section 482 CrPC of criminal proceedings instituted under Section 138 read with Section 141 of the Negotiable Instruments Act, 1881. The appellants, K.S. Mehta and Basant Kumar Goswami, were non-executive directors of M/s Blue Coast Hotels & Resorts Ltd., chosen to meet SEBI’s governance requirements (Clause 49 of Listing Agreement). They were not present at the 09.09.2002 board meeting that approved an Inter-Corporate Deposit (ICD) of ₹5 crores nor signatories to the ICD agreement or related instruments. Later, two cheques issued to discharge the debt were dishonored, leading to criminal proceedings against the directors. The High Court of Delhi dismissed petitions under Section 482 CrPC seeking quashing. The Supreme Court held that non-executive and independent directors cannot be fastened with vicarious liability under Section 141 NI Act unless the record demonstrates their direct involvement in the company’s affairs at the relevant time. Here, there was no evidence of their involvement, no signatory status, and mere attendance at board meetings cannot establish liability. The Court emphasized the need for specific averments showing the director was in charge of and responsible for the company’s conduct. Consequently, the proceedings against the appellants were quashed and the appeals allowed.