Tenetowl LogoTenetowl
Supreme Court of IndiaSupreme Court · 2025Division BenchAppeal allowed; impugned order set aside; direc...

Krishna Devi @ Sabitri Devi (Rani) M/s S.R. Engineering Construction v. Union of India & Ors.

Case / Petition Number:
Civil Appeal No. 47 of 2025
Neutral Citation:[2025] 1 S.C.R. 81

Case Synopsis & Summary

Krishna Devi @ Sabitri Devi (Rani) approaches the Supreme Court seeking pronouncement of judgment in terms of an arbitral award under Section 17 of the Arbitration Act, 1940. The appellant’s husband secured a favourable award on 31 May 2022 in a dispute over a Tezpur work contract. Although the award was not published due to outstanding arbitrator fees, a district court order dated 21 September 2022 directed the respondents to clear the balance and stated that once paid, the award would be furnished. The appellant filed a Section 17 application on 10 November 2022 seeking the court to pronounce judgment in terms of the award. The trial court and the Gauhati High Court held the application premature, because it was filed before the expiry of the 30-day objections window under Article 119(b) of the Limitation Act, calculated from 18 November 2022 (alleged formal notice). The Supreme Court, however, held that the start of limitation is not tied to a formal notice but to awareness of the award’s existence. It relied on earlier decisions establishing that Section 14(2) only requires awareness that an award exists; a court’s order directing payment of fees can constitute such notice. Consequently, the 30-day limitation expired by 20 October 2022, rendering the Section 17 application timely. The appeal is allowed, and directions are issued to dispose of the related matter expeditiously with no costs.

Precedent Explorer

Find Cases Like This

Explore other judgments dealing with similar legal situations, facts, or statutory provisions.

Case Details & Bench

Court
Supreme Court of India
Hon'ble Judges
  • Pamidighantam Sri Narasimha
  • Sandeep Mehta
Judgment Date
2025-01-03
Court Decision / Holding
Appeal allowed. Impugned order set aside. District Judge, Sonitpur, Tezpur, is directed to take up and dispose of Misc. (J) 61 of 2022 as expeditiously as possible, preferably within five months from the date of receipt of this judgment. There shall be no order as to costs.
Final Disposition
Appeal allowed; impugned order set aside; directions issued to expedite disposal; no costs.

Parties to the Case

Appellants / Petitioners

  • Krishna Devi @ Sabitri Devi (Rani) M/s S.R. Engineering Construction

Respondents

  • Union of India
  • Ors.

Legal Representation & Advocates

Counsels for Petitioners

  • • Ms. Madhusmita Bora
  • • Pawan Kishore Singh
  • • Dipankar Singh

Counsels for Respondents

  • • Debojit Borkakati
  • • Mrs. Anuradha Gayeen Saikia

Provisions of Law Cited

Arbitration Act, 1940 – Sections 14(2), 17Section 14(2) of the Arbitration Act, 1940Section 38(1) of the Arbitration Act, 1940Limitation Act, 1963 – Article 119(b) of the First ScheduleCode of Civil Procedure, 1908

Legal Doctrines & Maxims

  • Section 14(2) merely requires awareness of the existence of the award, not a formal notice.
  • Notice under Section 14(2) can be informal (oral or through pleader) and need not be in writing.
  • The objective of Article 119(b) is to start limitation from the date the award is notice to exist, not from a formal notice date.
  • Informal intimation to the award-debtor suffices to trigger the limitation period, to prevent delay in arbitration.
  • The pleader acts as an agent of the party and his awareness is sufficient for compliance with Section 14(2).

Submissions & Arguments

Contentions of Appellants / Petitioners

The appellant argued that the District Judge’s 21 September 2022 order directing the respondents to clear the balance arbitrator’s fees constituted a valid notice of filing the award. Once paid, the award would be furnished; the awarding court’s directive signified that the award existed and therefore initiated the 30-day limitation under Article 119(b). Based on Nilkantha Sidramappa Ningashetti and subsequent authorities, mere awareness of the award’s existence suffices under Section 14(2). The appellant contended that the 18 November 2022 formal notice date is not the triggering event; the limitation expired by 20 October 2022, rendering the 10 November 2022 Section 17 application timely.

Contentions of Respondents

The respondents contended that a formal notice of filing the award is essential under Section 14(2) and Article 119(b). They submitted that only the 18 November 2022 date of notice of filing constitutes valid triggering for the 30-day period, and the Section 17 application filed on 10 November 2022 was premature. They argued that the court must strictly adhere to the text of Section 14(2) and that the 21 September 2022 order did not, in itself, constitute a formal notice of filing the award.

Legal Doctrine & Issue Explorer

Explore This Legal Issue

Find relevant judgments and authoritative positions on the legal questions discussed here.

Cited Precedents (6)

Case NameCitationTreatmentExplanation
Nilkantha Sidramappa Ningashetti v. Kashinath Somanna Ningashetti[1962] 2 SCR 551 : 1961 SCC OnLine SC 75PositiveCourt relied on this case to support the proposition that Section 14(2) can be satisfied by awareness of the award, not necessarily a formal notice.
Ch. Ramalinga Reddy v. Superintending Engineer[1994] Supp. 6 SCR 266 : (1999) 9 SCC 610PositiveUsed to illustrate that notice under Section 14(2) need not be written; sub-section (2) does not require a written notice.
Food Corporation of India v. E. Kuttappan[1993] 3 SCR 1028 : (1993) 3 SCC 445PositiveHeld that communication of filing to pleaders suffices for Section 14(2); no strict formal notice is required.
Indian Rayon Corporation Ltd. v. Raunaq and Co. (P) Ltd.[1988] Supp. 2 SCR 231 : (1988) 4 SCC 31PositiveThe court noted that the objective of Section 14(2) is to make parties aware of the award’s existence, constituting substantive compliance.
Bharat Coking Coal Ltd. v C.K. Ahuja[1995] 2 SCR 65 : 1995 Supp 1 SCC 744PositiveUsed to align with the interpretative approach accepting awareness as compliance.
Deo Narain Choudhury v. Shree Narain Choudhury[2000] Supp. 4 SCR 307 : (2000) 8 SCC 626PositiveReferred to in support of non-formal notice sufficiency; awareness suffices for Section 14(2).
Case Applicability Diagnostic

Apply This to My Facts

Share your situation and test whether this judgment governs, supports, or challenges your case.

Official Judgment Record
•4,551 words•~21 min read

In The Court Record

Krishna Devi @ Sabitri Devi (Rani) M/s S.R. Engineering Construction v. Union of India & Ors.

[2025] 1 S.C.R. 81 : 2025 INSC 24 # **Krishna Devi @ Sabitri Devi (Rani) M/s S.R. Engineering Construction** ## **v.** ## **Union of India & Ors.** (Civil Appeal No. 47 of 2025) 03 January 2025 **[Pamidighantam Sri Narasimha* and Sandeep Mehta, JJ.]** ## **Issue for Consideration** Whether the time for filing an application under Section 17, Arbitration Act, 1940 commences when the party seeking to challenge the award receives a formal notice of the making of the award, or from the date such party is aware of the existence of the award. ## **Headnotes[†]** **Arbitration Act, 1940 – ss.17, 14(2) – Award to be signed and filed – Judgment in terms of award – Limitation Act, 1963 – Article 119(b) of the First Schedule – 30 days period for filing objections to the award – Start of limitation, when – Appellant filed application u/s.17 on 10.11.2022 for pronouncement of the judgment in terms of the award – Dismissed by Trial Court holding that the application was premature as it was filed before the expiry of the 30 days period for filing objections to the award, reckoned from 18.11.2022, when formal notice of the Award was said to have been received by the respondent – Order upheld by High Court – Correctness:** **Held:** The date of receiving a copy of the award is not the requirement of Section 14(2), but merely awareness that it is available to the parties – Respondent had notice of filing of the award due to the order dated 21.09.2022, wherein the District Court directed the respondents to hand over the balance fee to the arbitrators, following which the award shall be furnished – Thus, respondent was fully aware of the making of the Award by 21.09.2022, for the law does not require a formal notice of the making of the Award, as against knowledge/notice of the Award – District Court and the High Court erred in holding that the limitation for filing objections was still running when the appellant filed the application under Section 17 on 10.11.2022 – The formal * Author [2025] 1 S.C.R. 82 ## **Digital Supreme Court Reports** date of notice of filing of the award on the respondents, that is, 18.11.2022 holds no significance as they were made sufficiently aware of the award’s filing on 21.09.2022 itself – The court directing the respondents to clear the fees was a clear intimation about its filing – Limitation expired on 20.10.2022 – Thus, appellant’s application seeking pronouncement of judgment in terms of the award was valid and well beyond the period for filing objections to the award – Impugned order set aside. [Paras 18, 14, 2, 19, 20] **Words and Phrases – ‘notice’; ‘service of notice’ – Arbitration Act, 1940 – ss.14, 17 – Award to be signed and filed – Judgment in terms of award – Limitation Act, 1963 – Article 119(b) of the First Schedule – 30 days period for filing objections to the award – Limitation to start running from when:** **Held:** The limitation for filing objections to the award is 30 days, and is governed by Article 119(b) of the First Schedule to the Limitation Act, 1963 – The trigger for the limitation to start running specified therein is the date of service of notice of the filing of the award – Further, Section 14(2) requires that the court of relevant jurisdiction should give notice to the concerned parties when an award is filed – From a plain reading of the provisions, it appears that the parties need to be notified of the filing of award – While Art.119(b) of the Limitation Act requires that there be a ‘service of notice’ for the limitation to start running, Section 14(2) merely states that court ‘give notice’ to the parties – The precise form of what constitutes as a ‘notice’ of filing the award is unspecified – However, interpreted reasonably, what must be required is that the parties come to know about the existence of the award so that any objections to it may be filed – What appears from the usage of the word ‘notice’ is that the parties merely reach a state of awareness about the award and plan their next steps accordingly, and not the imposition of another procedural step. [Paras 14, 15] ## **Case Law Cited** _Nilkantha Sidramappa Ningashetti v. Kashinath Somanna Ningashetti_ **[1962] 2 SCR 551 : 1961 SCC OnLine SC 75;** _Ch. Ramalinga Reddy v. Superintending Engineer_ **[1994] Supp. 6 SCR 266 : (1999) 9 SCC 610;** _Food Corporation of India v. E. Kuttappan_ **[1993] 3 SCR 1028 : (1993) 3 SCC 445;** _Indian Rayon Corporation Ltd. v. Raunaq and Co. (P) Ltd_ **[1988] Supp. 2 SCR 231 : (1988) 4 SCC 31;** _Bharat Coking Coal Ltd. v C.K. Ahuja_ **[1995] 2 SCR 65 : 1995 Supp 1 SCC 744 – relied on.** [2025] 1 S.C.R.  83 ## **Krishna Devi @ Sabitri Devi (Rani) M/s S.R. Engineering Construction v. Union of India & Ors.** _Deo Narain Choudhury v. Shree Narain Choudhury_ **[2000] Supp. 4 SCR 307 : (2000) 8 SCC 626 – referred to.** ## **List of Acts** Arbitration Act, 1940; Limitation Act, 1963; Code of Civil Procedure, 1908. ## **List of Keywords** Application under Section 17, Arbitration Act, 1940; Application to pronounce judgment according to the award; Premature; Limitation for filing objections to the award; Limitation to start running; Formal notice of the making of the award; Formal notice of the Award; Filing of the award; Formal date of notice of filing of the award; Date of receiving a copy of the award; Awareness about the award; Existence of the award; Knowledge/notice of the Award; Arbitrator’s fees; Balance fee to the arbitrators; ‘notice’; ‘service of notice’. ## **Case Arising From** CIVIL APPELLATE JURISDICTION: Civil Appeal No. 47 of 2025 From the Judgment and Order dated 27.03.2024 of the Gauhati High Court in CRP No. 138 of 2022 ## **Appearances for Parties** Ms. Madhusmita Bora, Pawan Kishore Singh, Dipankar Singh, Advs. for the Appellant. Debojit Borkakati, Mrs. Anuradha Gayeen Saikia, Advs. for the Respondents. ## **Judgment / Order of the Supreme Court** ## **Judgment** ## **Pamidighantam Sri Narasimha, J.** 1. Leave granted. 2. The appellant’s husband secured an award in his favour on 31.05.2022 under the Arbitration Act, 1940, hereinafter referred to as the ‘Act’. [2025] 1 S.C.R. 84 ## **Digital Supreme Court Reports** Application under Section 17 of the Act was filed by the appellant on 10.11.2022 _to pronounce the judgment according to the award_ , was dismissed by the Trial and the High Courts on the ground that the said application is premature as it was made before the expiry of the 30 days period, reckoned from 18.11.2022, when formal notice of the Award is said to have been received by the respondent. The question for consideration is whether the time for filing a Section 17 application commences when the party seeking to challenge the award receives a formal notice (18.11.2022) of the making of the award, or from the date such party is aware of the existence of the award. In fact, this issue is no more res-integra. Following certain precedents of this Court, we have allowed the appeal having found that the respondent was fully aware of the making of the Award (by 21.09.2022), for the law does not require a formal notice of the making of the Award, as against knowledge/notice of the Award. Before considering the relevant provisions of the Act, precedents, submissions for drawing our conclusions, the short facts of the case are necessary: 3. _**Facts:**_ The appellant’s husband was the sole proprietor of a firm M/S S.R. Engineering Construction, which had secured a work order bearing CA No. CWE/TEZ/8 in 1987-1988 from the respondents. The work order was governed by the general conditions of contract, of which Cl. 70 contained an arbitration clause. The agreement involved the firm constructing a permanent ‘armament section’ at Tezpur. The firm completed the work and raised a bill for the same on 18.01.1993. However, as the respondents did not make the payment,the appellant was compelled to request for arbitration to resolve the dispute. The respondents declined and thus the appellant filed an application before the Delhi High Court seeking the appointment of an arbitrator which was dismissed due to lack of jurisdiction. Another application by the appellant before the Addl. District Judge, Delhi met the same fate, and it was only on 26.08.2019 that the appellant’s application under Section 20 was allowed and an arbitrator was appointed by the District Judge, Sonitpur by an order in T.S. (Arb.) Case No. 19/2003. The appellant’s husband passed away during the course of the arbitral proceedings and she came to represent him as his legal heir. 4. Finally, the arbitrator heard the parties and made an award dated 31.05.2022 in favour of the appellant and directing the respondents to pay a sum of Rs. 1,33,47,268.92/- with an interest of 9% p.a. till realization. [2025] 1 S.C.R.  85 ## **Krishna Devi @ Sabitri Devi (Rani) M/s S.R. Engineering Construction v. Union of India & Ors.** 5. Despite proceedings culminating in an award, it could not be published as the respondents had not cleared its dues towards the arbitrator’s fees. The appellant felt compelled to file an application before the District Judge, Sonitpur under Section 38[1] of the 1940 Act, seeking a direction to the respondents to clear its part of the arbitrator’s fees. 6. The District Judge, Sonitpur passed an order on 21.09.2022 directing the respondents to clear the said dues of Rs. 47,212.33/-. The order further stated that upon the clearance of the dues, a copy of the award shall be furnished to both the parties. 7. It is an admitted fact that the appellant received the copy of the award on 22.09.2022. Notably, the respondents had neither cleared the balance share of the arbitrator’s fees nor did they collect the award by the above-mentioned date. In fact, they deposited a cheque towards the balance payment for the fees only on 18.11.2022, after which it received the notice of filing the award on the same date. 8. On 10.11.2022, the appellant filed an application under Section 17 of the 1940 Act bearing no. Misc.(J) No. 61/2022 before the District Judge, Sonitpur, seeking pronouncement of judgment according to the arbitral award. 9. The District Court dismissed the appellant’s application filed under Section 17 vide order dated 23.11.2022, holding it to be premature filed even before the limitation for filing objections to the award could expire. According to the court, the limitation began only on 18.11.2022 when the formal notice of the award was received by the respondent and the application to pronounce judgment according to the award was filed only on 10.11.2022 when the limitation period of 30 days was still running at the said point of time. 10. Questioning the above referred order, the appellant filed a Civil Revision Petition No. 138/2022 under Section 115, Code of Civil Procedure, 1908 before the High Court. By way of the impugned order impugned before us, the High Court dismissed the revision and > 1 **38. Disputes as to arbitrator’s remuneration or costs.** - (1) If in any case an arbitrator or umpire refuses to deliver his award except on payment of the fees demanded by him, the Court may, on an application in this behalf, order that the arbitrator or umpire shall deliver the award to the applicant on payment into Court by the applicant of the fees demanded, and shall after such inquiry, if any, as it thinks fit, further order that out of the money so paid into Court there shall be paid to the arbitrator or umpire by way of fees such sum as the Court may consider reasonable and that the balance of the money, if any, shall be refunded to the applicant. [2025] 1 S.C.R. 86 ## **Digital Supreme Court Reports** upheld the District Court’s order. The High Court also held that the application for pronouncing the judgment according to the Award was filed during the subsistence of the period for objections by treating 18.11.2022 as the date as ‘notice of filing the award’. It referred to the text of Sections 14 and 17 of the 1940 Act as well as Article 119 of the Schedule to the Limitation Act, 1963 to hold that only a formal notice issued by a court will satisfy the requirement of Section 14(2). 11. _**Submissions:**_ We have heard the submissions of the counsels for both the parties. Ms. Madhusmita Bora, counsel for the appellant submitted that when the District Judge decided the application under Section 38 on 21.09.2022 and directed the respondents to pay the balance fees of the arbitrator, the said date becomes the date of ‘notice of filing the award.’ That is the date when the limitation of 30 days for filing objections to an award as per Article 119(b) began to run and it expired on 20.10.2022. It is only after the limitation expired that the appellant filed the application under Section 17 on 10.11.2022,since no objections were filed by the respondents during the said period. It was further argued that the respondents never raised the plea that they had not received ‘notice of award’, their only plea was that they did not receive the ‘copy of the award’. - 11.1 The Ld. Counsel further submitted that the essential requirement of Section 14(2) of the 1940 Act is that the award-debtor merely has to have information that the award has been filed. She relies on _Nilkantha Sidramappa Ningashetti_ v. _Kashinath Somanna Ningashetti_ ,[2] where this court held that for Section 14(2), communication of information may not necessarily take the form of a formal notice, and that intimation by some means is sufficient compliance. This communication may be oral and not necessarily in writing, and to support this contention she places reliance on _Deo Narain Choudhury_ v. _Shree Narain Choudhury_ .[3] She further relied on _Ch. Ramalinga Reddy_ v. _Superintending Engineer_ ,[4] wherein this court had noticed that while sub-section (1) of Section 14 required a written notice, the text of sub-section (2) did not. Hence, the order dated > 2 [1962] 2 SCR 551 : 1961 SCC OnLine SC 75 > 3 [2000] Supp. 4 SCR 307 : (2000) 8 SCC 626 > 4 [1994] Supp. 6 SCR 266 : (1999) 9 SCC 610 [2025] 1 S.C.R.  87 ## **Krishna Devi @ Sabitri Devi (Rani) M/s S.R. Engineering Construction v. Union of India & Ors.** 21.09.2022 was valid ‘notice of award’ as it sufficiently conveyed to the respondents about the award’s existence. 12. On the other hand, Mr. Debojit Borkakati, counsel for the respondents submitted that both the High Court and the District Court were correct in taking the starting point of limitation to be on 18.11.2022. It is on this date that the respondents received a notice of the award from the District Court, and therefore filed an objection to the award under Section 30 on 22.11.2022. It was argued that what the law requires is to be done in that manner, and Section 14(2) was only satisfied when the respondents received a formal notice of the award. The mere direction to pay the balance fees of the arbitrator cannot be taken to be a formal notice that the award is filed. The text of Section 14(2) is very specific in its requirements, and if any other legal event is taken to be sufficient compliance with the provision, its text will be rendered otiose. - 12.1 It was further submitted that the intention of Section 14(2) is to enable the award-debtor to apprise himself of the award’s contents, so as to file any objections effectively. Hence, the intent of the provision cannot be ignored and mere communication about the existence of the award cannot be a compliance with the provision. In any case, even if the order dated 21.09.2022 is to be considered, it merely states that the respondents are required to clear the balance fees of the arbitrator, following which the award may be published. That is, the order itself envisages that the payment of fees _per se_ shall not satisfy the requirements of Section 14(2), and the court has to take the legal step of notifying the parties of its filing. Accordingly, a formal notice was issued by the court on 18.11.2022, confirming the argument advanced. Further, he argued that if the appellant’s interpretation is allowed, the legal event which constitutes as ‘notice of the filing of award’ will vary from case to case, which does not seem to the intention behind Section 14(2). 13. We have given our thoughts to the facts of the case and have carefully considered the submissions of the parties. 14. _**Analysis:**_ In our view, the respondents had notice of filing of the award due to the order dated 21.09.2022, wherein the District Court had directed the respondents to hand over the balance fee to the arbitrators, following which the award shall be furnished. [2025] 1 S.C.R. 88 ## **Digital Supreme Court Reports** The respondents were completely aware of this direction, which sufficiently states that clearing the fees will result in the court notifying the filing of award. The limitation for filing objections to the award is 30 days, and is governed by Article 119(b) of the First Schedule to the Limitation Act, 1963. The trigger for the limitation to start running specified therein is the date of service of notice of the filing of the award. Section 14(2) of the 1940 Act requires that the court of relevant jurisdiction should give notice to the concerned parties when an award is filed. The texts of both these provisions along with Section 17 are reproduced here for convenience: ## 14.1 Article 119(b), Schedule I of the Limitation Act, 1963 is as under: ||_Description of application_|_Period_<br>_of_<br>_limitation_|_Time from which_<br>_period begins to run_| |---|---|---|---| |[…]|[…]|[…]|[…]| |_119._|_Under the Arbitration Act,_<br>_1940(10 of 1940),—_||| ||_(a) for the filing in court_<br>_of an award;_|_Thirty_<br>_Days._|_The date of service_<br>_of the notice of the_<br>_making of the award;_| ||_(b) for setting aside_<br>_an award or getting_<br>_an award remitted for_<br>_reconsideration._|_Thirty_<br>_Days._|_The date of service_<br>_of the notice of the_<br>_filing of the award_| |[…]|[…]|[…]|[…]| 14.2 Sections 14 and 17 of the Arbitration Act, 1940 are extracted herein below: ## **“** _**14. Award to be signed and filed** –_ _(1) When the arbitrators or umpire have made their award, they shall sign it and shall give notice in writing to the parties of the making and signing thereof and of the amount of fees and charges payable in respect of the arbitration and award._ _(2) The arbitrators or umpire shall, at the request of any party to the arbitration agreement or any person claiming under such party or if so directed by the Court and upon_ [2025] 1 S.C.R.  89 ## **Krishna Devi @ Sabitri Devi (Rani) M/s S.R. Engineering Construction v. Union of India & Ors.** _payment of the fees and charges due in respect of the arbitration and award and of the costs and charges of filing the award, cause the award or a signed copy of it, together with any depositions and documents which may have been, taken and proved before them, to be filed in Court, and the Court shall thereupon give notice to the parties of the filing of the award._ _(3) Where the arbitrators or umpire state a special case under clause (b) of section 13, the Court, after giving notice to the parties and hearing them, shall pronounce its opinion thereon and such opinion shall be added to, and shall form part of, the award_ . _**17. Judgment in terms of award.** - Where the Court sees no cause to remit the award or any of the matters referred to arbitration for reconsideration or to set aside the award, the Court shall, after the time for making an application to set aside the award has expired, or such application having been made, after refusing it, proceed to pronounce judgment according to the award, and upon the judgment so pronounced a decree shall follow, and no appeal shall lie from such decree except on the ground that it is in excess of, or not otherwise in accordance with the award._ ” ## ( **emphasis supplied** ) 15. From a plain reading of the provisions, it appears that the parties need to be notified of the filing of award. While Art. 119(b) of the Limitation Act requires that there be a ‘service of notice’ for the limitation to start running, Section 14(2) of the 1940 Act merely states that court ‘give notice’ to the parties. The precise form of what constitutes as a ‘notice’ of filing the award is unspecified. However, interpreted reasonably, what must be required is that the parties come to know about the existence of the award so that any objections to it may be filed. What appears from the usage of the word ‘notice’ is that the parties merely reach a state of awareness about the award and plan their next steps accordingly, and not the imposition of another procedural step. 16. In our view, the appellant’s submissions are correct insofar as they rely on this court’s decision in _Nilkantha Sidramappa Ningashetti_ (supra). Therein, while a partition suit was underway between the [2025] 1 S.C.R. 90 ## **Digital Supreme Court Reports** parties, an arbitral award came to decide the disputes partly. The suit was adjourned asking the parties to apprise themselves of the award, and this was taken as a sufficient compliance of Section 14(2) of the 1940 Act. It was held that the term ‘notice’ in this provision nowhere excluded its informal expressions. Furthermore, if the literal interpretation is taken and limitation is paused until a formal notice is issued, the Court held, would allow a party otherwise aware of the award to sit over it and delay filing objections. This would undercut the speedy intent governing arbitration. Similarly, the decision in _Ramalinga Reddy_ (supra) allowed the mere receipt of information by the award-debtor’s pleader as valid compliance with the text of Section 14(2). As is discernible from the texts of sub-sections (1) and (2) of Section 14, the notice is under sub-section (2) need not be a written one. 17. Apart from the authorities cited by the appellant, this Court has otherwise clarified that Section 14(2) merely functions to apprise the parties about the existence of the award. In _Food Corporation of India_ v. _E. Kuttappan_ ,[5] the communication of the filing of an award to the parties’ pleaders was taken to be sufficient notice for Section 14(2). It was reasoned that what is required is that the party comes to know about the decision for/against it, and there was no insistence of a specific form in the 1940 Act. The pleader acts as an agent of the party and his awareness is sufficient for the parties to access and scrutinise the contents of the award. Even if a formal notice is issued thereafter, it is at best an act of court which cannot disturb rights accrued in law. This is squarely applicable to the case before us, wherein the order dated 21.09.2022 precisely laid out that the award is available, and the only formality withholding the respondent’s access to it is clearance of the arbitrator’s fees. While a formal notice of filing of the award was only issued on 18.11.2022, applying this decision to the facts this case, it does not take away from the fact that the respondents were well aware of the award’s filing on 21.09.2022 itself. Similarly, the decision in _Indian Rayon Corporation Ltd._ v. _Raunaq and Co. (P) Ltd._[6] clarifies that the only objective of Section 14(2) is that the parties are aware of the award’s existence and suggests that this a substantive compliance. If this were to be a procedural stipulation, > 5 [1993] 3 SCR 1028 : (1993) 3 SCC 445 > 6 [1988] Supp. 2 SCR 231 : (1988) 4 SCC 31 [2025] 1 S.C.R.  91 ## **Krishna Devi @ Sabitri Devi (Rani) M/s S.R. Engineering Construction v. Union of India & Ors.** the party intending to file objections can insist of technicalities like the mode of notice, and use those unfairly to gain time. 18. As far as the respondents’ contention of taking the date of receiving the copy of the award is concerned, it is taken to be an impermissible departure from Section 14(2)’s text. This Court in _Bharat Coking Coal Ltd._ v _C.K. Ahuja_[7] has laid down that what this provision requires is that parties simply become aware of the filing of the award. In the said case, the Supreme Court had referred a dispute to arbitration and its registry had issued a notice to both parties about the filing of the award. The award-holder, however, relied on the much later date of a formal notice to calculate limitation for filing objections to the award. Relying on the authorities discussed above, it was held that the date of receiving a copy of the award is not the requirement of Section 14(2), but merely awareness that it is available to the parties. This holding signifies that the parties have to take steps to scrutinise the award themselves as soon as it becomes accessible and they are aware of its accessibility. We find that the interpretation in this decision is in line with the intent of the 1940 Act, which is designed to resolve disputes at a quick pace. Any contrary interpretation will give a licence to the award-debtor to delay the arbitration by insisting on procedural nuances despite of being aware that an award exists and that its contents are accessible to it. 19. Applying these principles to the fact of this case, it is seen that both the District Court and the High Court fell into error that the limitation for filing objections was still running when the appellant filed an application under Section 17 of the Act on 10.11.2022. The formal date of notice of filing of the award on the respondents, that is, 18.11.2022 holds no significance as they were made sufficiently aware of the award’s filing on 21.09.2022 itself. The court directing the respondents to clear the fees was a clear intimation about its filing. Holding otherwise would not only be departing from precedents of this Court, but also allowing the respondents to take advantage of their own inaction. Hence, the limitation is to be treated as expired on 20.10.2022, and the appellant’s application seeking pronouncement of judgment in terms of the award was valid and well beyond the period for filing objections to the award. 7 [1995] 2 SCR 65 : (1995) Supp. 1 SCC 744 [2025] 1 S.C.R. 92 ## **Digital Supreme Court Reports** 20. _**Conclusion:**_ In light of the above, we allow the present appeal and set aside the order dated 27.03.2024 passed by the High Court in Civil Revision Petition No. 138/2022. 21. In facts and circumstances there shall be a direction that the District Judge, Sonitpur, Tezpur, to take up and dispose of the Misc. (J) 61 of 2022 as expeditiously as possible, preferably within a period of five months from the date of receipt of this judgment. 22. There shall be no order as to costs. _Result of the case:_ Appeal allowed. - _†Headnotes prepared by:_ Divya Pandey
End of Judgment Record
Browse All Supreme Court of India (2025) Decisions
2025-03-04

Saranga Anilkumar Aggarwal v. Bhavesh Dhirajlal Sheth & Ors.

This Civil Appeal concerns whether execution of penalty orders imposed by the National Consumer Disputes Redressal Commission (NCDRC) can be stayed under the interim moratorium provisions of Section 96 of the Insolvency and Bankruptcy Code, 2016 (IBC), while insolvency proceedings are pending under Section 95 of the IBC. The appellant, a real estate developer, sought a stay of 27 penalties levied for deficiency in service and delay in possession of residential units, arguing that an application under Section 95 of the IBC had triggered an interim moratorium. The NCDRC had rejected the stay, holding that consumer-claims and penalties are not “debts” within the moratorium’s ambit. The Supreme Court affirmed that the damages awarded in consumer disputes arise to compensate home-buyers and deter malpractice, and are not ordinary contractual debts susceptible to IBC restructuring; such damages fall within the category of “excluded debts” under Section 79(15) of the IBC, and their enforcement remains unaffected by insolvency proceedings. The Court emphasized the essential distinction between debt-recovery proceedings and regulatory/penal actions under consumer protection laws, rejected reliance on contrary authorities (notably Sheetal Gupta per incuriam), and held that criminal penalties under the CP Act do not automatically fall within the moratorium. The appeal was dismissed; the appellant was directed to comply with the NCDRC penalties within eight weeks.

2025-04-09

Serious Fraud Investigation Office v. Aditya Sarda

This batch of sixteen interconnected criminal appeals arises from SFIO's complaint against multiple respondents including Aditya Sarda for serious economic offences under the Companies Act, 2013 and the IPC. The Special Court at Gurugram took cognizance of the offences and issued bailable warrants to the accused, who allegedly concealed themselves or otherwise obstructed the process. Non‑bailable warrants were issued, and some proclamations under CrPC Section 82 were initiated against certain respondents. The High Court granted anticipatory bail to several respondents, notwithstanding the cognizance, warrant proceedings, and proclamations, leading to a series of challenges before the Supreme Court. The Court emphasises that anticipatory bail is an extraordinary remedy not available as a routine in cases involving serious economic offences, and that the twin mandatory conditions in Section 212(6) of the Companies Act, 2013 must be considered: (i) Public Prosecutor must be given an opportunity to oppose; and (ii) where opposed, the court must be satisfied of reasonable grounds to believe the accused is not guilty and unlikely to commit an offence while on bail. It reasons that respondents who evade process by concealing themselves after cognizance and after non‑bailable warrants were issued should not receive anticipatory bail. Accordingly, the High Court orders granting anticipatory bail are set aside, and the respondents are directed to surrender within one week to the Special Court, with subsequent bail determinations to be made in accordance with law. The judgment reiterates that economic offences require a cautious, exception‑based approach to bail and underscores the importance of ensuring due process and the unobstructed progress of judicial proceedings.

2025-03-04

K.S. Mehta v. M/s Morgan Securities and Credits Pvt. Ltd.

This is a Supreme Court decision under Criminal Appeal No. 1105 of 2025 arising from quashing under Section 482 CrPC of criminal proceedings instituted under Section 138 read with Section 141 of the Negotiable Instruments Act, 1881. The appellants, K.S. Mehta and Basant Kumar Goswami, were non-executive directors of M/s Blue Coast Hotels & Resorts Ltd., chosen to meet SEBI’s governance requirements (Clause 49 of Listing Agreement). They were not present at the 09.09.2002 board meeting that approved an Inter-Corporate Deposit (ICD) of ₹5 crores nor signatories to the ICD agreement or related instruments. Later, two cheques issued to discharge the debt were dishonored, leading to criminal proceedings against the directors. The High Court of Delhi dismissed petitions under Section 482 CrPC seeking quashing. The Supreme Court held that non-executive and independent directors cannot be fastened with vicarious liability under Section 141 NI Act unless the record demonstrates their direct involvement in the company’s affairs at the relevant time. Here, there was no evidence of their involvement, no signatory status, and mere attendance at board meetings cannot establish liability. The Court emphasized the need for specific averments showing the director was in charge of and responsible for the company’s conduct. Consequently, the proceedings against the appellants were quashed and the appeals allowed.

2025-05-15

Mohit Kumar v. State of Uttar Pradesh and Ors.

These appeals challenge UPPRPB's rejection of OBC certificates not in the format prescribed in the recruitment notification. Mohit Kumar applied for Sub-Inspector posts and took the examination in May 2022. He produced an OBC (Non-Creamy Layer) certificate in the format applicable to the Central Government, not the State Government. Kiran Prajapati similarly submitted a Central Government-format certificate. UPPRPB treated them as unreserved, with lower cut-offs and their shortlisting affected. Mohit and Kiran filed writ petitions; the High Court directed the UPPRPB to accept the certificates and proceed. The Division Bench affirmed. The Supreme Court, after reviewing, held that although there is no statutory mandate to produce a specific certificate, the requirement is nonetheless mandatory and must be scrupulously followed because a recruitment process must ensure equal treatment for all aspirants and avoid different yardsticks. It emphasized that the recruiting authority is the best judge of its requirements; an ambiguity in the terms should have been clarified earlier, and aspirants could have sought tehsildars' certificates in the required format. The certificates submitted did not meet the Format-I specification that includes three-year parental income, wealth criteria under the Wealth Tax Act, and other State parameters. Consequently, Mohit and Kiran cannot obtain relief; the lead appeal is dismissed, and the connected appeal is allowed; appeals disposed of.