Civil Appeal No. 2956 of 2007; with Civil Appeal Nos. 2318 of 2013 and 7241 of 2016

Larsen & Toubro Limited v. Additional Deputy Commissioner of Commercial Taxes & Anr.

Larsen & Toubro Limited (L&T), a contractor/engineer, appeals against Karnataka Sales Tax Act taxation on turnover, challenging inclusion of payments to subcontractors in the main contractor’s total turnover for levy of turnover tax under Section 6-B. The three connected appeals arise from assessments and revisions under Sections 5-B and 6-B of the Karnataka Act, with disputes over whether payments to subcontractors form part of the dealer’s "total turnover". The Court undertakes a close reading of key definitions—“sale,” “taxable turnover,” “total turnover,” and “turnover”—and differentiates between Section 5-B (taxable turnover for transfer of property in goods in works contracts) and Section 6-B (turnover tax on total turnover). Rule 6(1)(c) of the Karnataka Sales Tax Rules, 1957 is examined: it treats as total turnover the amount paid for transfer of property in goods involved in a works contract, but only where a transfer of property occurs. The Court then aligns with the Andhra Pradesh decision that, in works contracts, property in goods passes by accretion and that payments to subcontractors do not constitute transfer of property to the main contractor. In consequence, the appeals by the assessee are allowed and the Revenue’s appeals are dismissed, with no costs. The decision invokes the single transaction theory and seeks to prevent double taxation under the Karnataka Act.

Supreme Court of India
Criminal Appeal No. 1218 of 2016

MOHD. HASHIM v. STATE OF UP & ORS.

Mohd. Hashim v. State of Uttar Pradesh & Ors. (Criminal Appeal No. 1218 of 2016) was heard by a Division Bench comprising Justices Dipak Misra and Amitava Roy and decided on 28 November 2016. The appeal concerns the scope of the Probation of Offenders Act, 1958 (PO Act) in cases where the underlying offences do not prescribe any minimum sentence. The respondents were convicted under IPC sections 323 and 498-A and under Section 4 of the Dowry Prohibition Act, 1961. The Sessions Court and later the Allahabad High Court (Lucknow Bench) had extended the benefit of probation of good conduct under Section 4 of the PO Act, a decision challenged by the informant who relied on decisions such as Shyam Lal Verma and Ratan Lal Arora to contend that PO Act relief is impermissible where a statute fixes a minimum sentence. The Court clarifies the distinction between a true minimum sentence and discretionary minimum provisions. It holds that if a statute prescribes a minimum sentence with no discretion, it is mandatory and non-derogable; however, if a minimum sentence is present but discretionary, the court may grant a lower sentence or none at all, subject to reasons recorded. In the present case, the offences do not prescribe a minimum sentence, so PO Act can apply, and the matter is remitted to the appellate court for disposal in accordance with law, with other points on merits including possible PO Act relief being open for consideration. The decision reiterates the rehabilitative aim of the PO Act and the need for reasoned orders concerning release on probation.

Supreme Court of India
Civil Appeal No. 4914 of 2016

MEDICAL COUNCIL OF INDIA v. KALINGA INSTITUTE OF MEDICAL SCIENCES

This appeal concerns the admission of extra MBBS seats at Kalinga Institute of Medical Sciences (KIMS) and the role of the Medical Council of India (MCI) in regulating medical education facilities. After KIMS was permitted to admit 100 students annually, it sought approval for an additional 50 seats for 2015-16. An inspection by MCI in January 2015 revealed numerous deficiencies, prompting recommendations to deny the extra seats. The Central Government directed KIMS not to admit students in the second batch, but the Orissa High Court granted provisional permission to admit 50 students subject to conditions and ongoing inspections. A subsequent High Court order and fresh inspections again highlighted deficiencies, and the High Court treated the latest inspection report as if it were an appeal under Article 226, scrutinizing detailed facility metrics. The Supreme Court held that such appellate scrutiny of an expert inspection report is outside the High Court’s jurisdiction, emphasizing deference to neutral expert findings absent mala fides, ex facie perversity, or jurisdictional error. The Court allowed MCI’s appeal, set aside the High Court’s orders, and preserved admissions already made, while imposing costs of Rs. 5 crores on KIMS and restraining further increases in intake for 2016-17 and 2017-18. It directed the preparation of a Standard Operating Procedure for inspections and transparency via websites.

Supreme Court of India
Writ Petition (C) No. 36 of 2016

Vasanthakumar v. H. C. Bhatia and Ors.

This public-interest writ petition debates the future architecture of the Indian judiciary, focusing on whether the Supreme Court should reform its structure to ease backlogs and broaden access to justice. The petitioner—Vasanthakumar—argues for structural reforms such as establishing four Regional Courts of Appeal or a National/Regional Court of Appeal to divert routine/non-constitutional matters away from the Supreme Court, thereby preserving its constitutional mandate while reducing delays. The petition traces a line of Law Commission reports (14th, 95th, 229th) and precedents (Bihar Legal Support Society, Mathai@Joby, N. Suriyakala, etc.) that underscore the Court’s original role as a Constitutional Court rather than a regular court of appeal and call for calibrated changes rather than blanket expansion. While agreeing that access to justice is a fundamental right and that enormous pendency plagues the system, the Court cautions against overreach and notes that constitutional amendments may be required for sweeping changes. After extensive submissions from the Attorney General, amici curiae, and intervenors, the Court decides to refer the issue to a Constitutional Bench for authoritative pronouncement, effectively placing the matter before a higher tribunal for a final, considered decision on the viability of regional/national appellate architecture and its compatibility with the Constitution’s basic structure.

Supreme Court of India
Civil Appeal No. 6119 of 2016

MULIN SHARMA v. STATE OF ASSAM AND OTHERS

MULIN SHARMA v. STATE OF ASSAM AND OTHERS concerns reinstatement and back wages of a schoolteacher who alleges coercion to resign. Mulin Sharma, holding an MA in Sanskrit, was employed as an Assistant Teacher at Rangsina High School, Karbi Anglong. Due to conflicts with the headmistress, he contends that Respondent No. 6 and his men forced him to sign a resignation on 22 May 1998, and he did not receive salary from 23 May 1998. He sought redress via writ petitions, alleging illegal resignation and denial of wages. The Deputy Commissioner later held the resignation voluntary and directed acceptance of the resignation from 16 October 2003 with no financial benefits from 22 May 1998. The Gauhati High Court single judge held that the resignation was not voluntary but did not grant back wages; the Division Bench dismissed the back wages claim while granting Rs 25,000 for wrongful denial of service. The Supreme Court, while acknowledging that the resignation was not voluntary, held that back wages are discretionary and not automatically due on reinstatement. It affirmed reinstatement with consequential benefits but denied back wages due to lack of evidence of unemployment; nonetheless, it awarded an additional Rs 25,000 for wrongful denial of service, disposing of the appeal.

Supreme Court of India
Criminal Appeal No. 2057 of 2010

Gajanan Dashrath Kharate v. State of Maharashtra

Gajanan Dashrath Kharate v. State of Maharashtra concerns an appeal against conviction for murder of Dashrath, the appellant's father, in village Dapura in April 2002. The prosecution relied on eye-witness testimony of PW-1 Nagorao Kharate (cousin of the deceased) and PW-2 Ratnaprabha (wife of PW-1), and on recovered blood-stained clothing of the accused containing blood group ‘B’, matching the deceased. Autopsy (PW-6) established death due to injuries to vital organs/head. The accused, a habitual drinker and gambler, allegedly demanded money and quarreled with his father on the night of 07.04.2002; the father was found dead in a pool of blood the next morning. The defence contended that PW-1 was not an eyewitness and that the case rested on suspicion, urging that there were lapses in the prosecution case and that the delay in filing the FIR undermined credibility. The trial court and the Bombay High Court convicted under Section 302 IPC and sentenced the appellant to life imprisonment, relying on the two eyewitnesses and the blood-stained clothes, plus the accused’s failure to offer a plausible explanation under Section 106 of the Evidence Act. The Supreme Court, after evaluating the evidence and noting the credibility of PW-1 and PW-2, affirmed the concurrent findings, held that the delay in lodging the FIR was satisfactorily explained, and that there was no reason to doubt the prosecution’s case. The appeal is dismissed, upholding the conviction and sentence.

Supreme Court of India
Civil Appeal No. 5958 of 2015

MIS. SURYACHAKRA POWER CORPORATION LTD. v. ELECTRICITY DEPARTMENT, REP. BY ITS SUPERINTENDING ENGINEER, PORT BLAIR AND OTHERS

This appeal under Section 125 of the Electricity Act, 2003 challenges a decision of the Appellate Tribunal for Electricity. MIS. Suryachakra Power Corporation Ltd. sought condonation of a 161-day delay in filing the Supreme Court appeal following the Tribunal’s 28.11.2014 order and the 07.05.2015 withdrawal of a review petition. The appellant contends that the delay was largely caused by the time spent pursuing the review petition before the Appellate Tribunal for Electricity and by the 2015 summer vacations, and urges that Section 125 allows filing within 60 days, with a further 60 days for sufficient cause (i.e., a maximum of 120 days) and that Section 5 of the Limitation Act cannot extend beyond this limit. The Court clarifies that while Section 5 cannot override the Electricity Act’s special limitation, Section 14 of the Limitation Act may apply if the party is prosecuting another civil proceeding with due diligence and in good faith. The Bench, however, finds lack of due diligence and good faith, recalls an earlier order that condoned the delay, and dismisses the interlocutory application for condonation as well as the appeal for delay. The judgment emphasizes strict adherence to the Electricity Act’s time limits, with limited resort to general limitation principles.

Supreme Court of India
Civil Appeal No. 1853 of 2016

ALAULI ANCHAL BOAT TRAFFIC COOPERATIVE SOCIETY LTD., PHULTORA AND ANR. v. STATE OF BIHAR AND ORS.

This Supreme Court judgment reviews the challenge by ALAULI ANCHAL BOAT TRAFFIC COOPERATIVE SOCIETY LTD., PHULTORA AND ANR. (the appellant-society) to an open public auction held for settlement of the Ghurandera Kilagarai Ghat for the year 2008-2009, in Alauli, Khagaria district, Bihar. A public notice fixed a reserve price and three bidders participated; the highest bid was around Rs 16 lakh (Rs 16,00,000/-, with record variations noting Rs 16,00,100- in some entries). Although the appellant-society did not bid, its opinion was sought on the highest bid, and it accepted the bid amount under protest. The Single Judge had remanded the matter to reconsider in light of State circulars. The Patna High Court Division Bench allowed the State’s Letters Patent Appeal, holding that every year the bid amount tends to rise and that the court should not re-examine disputed factual questions about bid amounts. The Supreme Court affirmed, holding that open auction for ghat settlements is mandatory for every three years per Government instructions to augment revenue and ensure transparency, and that the auction process cannot be deemed arbitrary or violative of circulars. Since other ghats saw higher bids and the appellant had not challenged the process earlier, the appeal was dismissed with costs.

Supreme Court of India
Review Petition (C) No. 3538 of 2016 in Civil Appeal No. 8543 of 2009

Dravya Finance Pvt. Ltd. & Anr. v. S.K. Roy & Ors.

Dravya Finance Pvt. Ltd. and Anr. challenged Life Insurance Corporation’s (LIC) circulars restricting assignment of life insurance policies as collateral and the interim orders that allowed only provisional registration of such assignments during the pendency of Civil Appeal No. 8543 of 2009. The Bombay High Court had struck down the circulars in 2007, and LIC challenged those judgments through SLPs before this Court. This Court initially granted interim relief in favour of LIC, allowing only temporary registrations and preventing death or maturity claims while the appeal proceeded. In 2015, the final order disposing of the appeal was based on undertakings furnished by LIC and accepted by the Court; provisional registrations were made permanent and the interim orders were recalled. The present contempt petition was treated as a limited review petition to determine the precise date from which LIC must pay interest to the petitioners in light of that final order. The Court considered Regulation 8(5) of the IRDA Regulations and observed that interest would be payable at the prevailing bank rate (without penal interest), but to correct an omission in the final order it held that interest would commence from the later of 30 days after death or maturity or 4 April 2008, whichever is later, with an expectation of prompt discharge of liabilities by LIC.

Supreme Court of India
Civil Appeal No.11247 of 2016

UCO Bank and Anr. v. Dipak Debbarma & Ors.

The appellant bank challenged a sale notification under the Securitisation and Reconstruction of Financial Assets and Enforcement of Security Interest Act, 2002 (Act of 2002) for sale of immovable security property without restriction as to buyer class. The Tripura Land Revenue and Land Reforms Act, 1960 (Tripura Act, 1960) with Section 187 imposes an embargo on sale to non-members of Scheduled Tribes, creating a potential conflict between central banking legislation and state land reform law. The Gauhati High Court struck down the sale notification, reasoning that the Ninth Schedule protection under Article 31-B would prevail over the central act. The Supreme Court reversed, holding that Article 246 confers federal supremacy and that where the central Act (2002) relates to banking (Entry 45, List I) and the Tripura Act relates to land revenue and reform (Entries 18 and 45, List II), the central law prevails when there is a repugnancy or inconsistency. It held the state provision pro tanto invalid to the extent of inconsistency with the central Act, since sale of mortgaged assets is an inseparable aspect of banking. The Court emphasized reconciliation only where possible, and ultimately allowed the appeals, setting aside the High Court’s order and holding that there is no embargo on the central sale provisions in this context. The result is that the Act of 2002 governs the sale of secured assets, notwithstanding the Tripura Act’s restrictions, with no costs awarded.”

Supreme Court of India
Civil Appeal Nos. 10418-10419 of 2016

Pratap Singh Yadav v. Haryana Urban Development Authority & Anr.

Pratap Singh Yadav v. Haryana Urban Development Authority & Anr. concerns allotment of Residential Plot No. 2342 in Sector II, HUDA, Faridabad. The appellant deposited 25% of the tentative price in 1998 and later filed for surrender; the Estate Officer allowed surrender and refunded the balance after deducting 10% of the earnest money. A consumer complaint was filed seeking restoration of the plot or an alternative plot with compensation. The District Forum allowed relief; the State Commission held the appellant was not a consumer since he voluntarily surrendered the plot and the claim was time-barred, and the National Commission dismissed the revision. On appeal, post-pleadings revealed a Conveyance Deed transferring the plot to the appellant, sanction of building plans, occupancy certificate, and a no-due certificate, all of which pointed to alleged connivance of HUDA officials. The Court directed disciplinary action against those responsible. Given the peculiar facts and the hardship of demolishing the house, the Court partially allowed the appeals: the allotment would continue subject to the appellant paying the prevailing price for the plot (Rs. 18,000 per sq m) within six months. If not paid, the National and State Commission orders would be affirmed, and HUDA could dispossess if the superstructure remained. The judgment also cites a parallel decision in Pradeep Sharma v. Chief Administrator, Haryana Urban Development Authority (CA Nos. 52-53 of 2016) supporting continuation of allotment under the prevailing rate.

Supreme Court of India
Civil Appeal Nos. 3778-3780 of 2016

Kedar Mishra v. The State of Bihar & Ors.

This Civil Appeal arises from a common judgment in writ petitions challenging pre-emption under the Bihar Land Reforms Act, 1961, and the accompanying Rules of 1963. Kedar Mishra, appellant, claimed the right of pre-emption as an adjoining raiyat and co-sharer of the land sold by Ramadhar Mishra. Three separate pre-emption cases were filed following three sale deeds in February 1988. The Deputy Collector, Land Reforms, allowed the pre-emption on 10 July 1995, but subsequent appellate and revisional orders reversed that, culminating in a Board of Revenue decision that deposit made under a different treasury head failed to comply with Rule 19 and Form LC-13. The High Court in Patna dismissed writ petitions on this basis. The Supreme Court, noting that the appellant deposited ten percent of the purchase money in the treasury, albeit under the wrong head, held that such misdirection does not defeat the right of pre-emption. It emphasized that the deposit was to the credit of the treasury and that a raiyat cannot be presumed to know the correct treasury head; a pedantic evaluation of the treasury challan would undermine the benevolent objective of Section 16(3). The Court set aside the High Court/Board of Revenue orders and remitted the matter to the Board of Revenue for fresh adjudication on merits after providing proper opportunity of hearing, without prejudging the merits.

Supreme Court of India
Civil Appeal No. 4997 of 2016

Mukul Sharma v. Orion India (P) Ltd. Through Its Managing Director

This appeal concerns a dispute over the definition of 'built-up area' in a sale agreement for a multi-block complex. The appellant Mukul Sharma sought specific performance of the instrument dated 25 August 1992, claiming entitlement to a portion of built-up area on three floors of the North Block. The core issue was whether 'built-up area' included common spaces such as lift wells, corridors, lobbies, and ducts. The contract deed did not define the term; a dispute arose after five years when the plaintiff insisted the built-up area included common areas, while the defendant contended otherwise. After initial litigation, the trial court decreed in the plaintiff's favor, but the High Court reversed. The matter turned on letters exchanged in 1997–1998. On 15 September 1997 the plaintiff asserted that built-up area included common areas; subsequently, the defendant issued letters in March 1998 to define built-up area excluding common areas. The Supreme Court held that the defendant himself later accepted the dispute and that, under the true spirit of Section 5 of the Indian Contract Act, the defendant cannot resile from the mutually agreed position. The court set aside the High Court judgment, restored the trial court’s decree, and directed recalculation of the built-up area consistent with this judgment, with the suit to be disposed of expeditiously and no costs awarded. The decision clarifies that extrinsic evidence can elucidate instrument meaning when terms are ambiguous and that conduct of the parties after the instrument is relevant.

Supreme Court of India
Civil Appeal No. 589 of 2010; Civil Appeal No. 599 of 2010

Tin Plate Dealers Association Pvt. Ltd. & Ors. v. Satish Chandra Sanwalka & Ors.

Tin Plate Dealers Association Pvt. Ltd. and Gupta Group challenged orders of the Calcutta High Court and sought relief under the Companies Act, 1956, in two linked matters (Civil Appeals Nos. 589 and 599 of 2010). The core issues included whether the Company Petition under Sections 397/398 was maintainable, the legality of bonus shares issued out of revaluation reserves, the propriety of issuing 25,000 new ordinary shares, and the conversion of 3,065 preference shares into equity shares. A further contest concerned the removal and re-induction of directors and a lease of an industrial plot. The Supreme Court examined the facts to determine whether the share certificates disclosed a fresh, independent allotment, whether the call notice under Section 53 was properly proved, and whether the Articles permitted actions such as bonus-share issuance and share-conversion. It held that the call notice and forfeiture procedure were not proven in conformity with Articles and the Act, and that the Articles did not empower bonus shares from revaluation reserves. The Court ultimately dismissed the Gupta Group’s appeal (589/2010) and disposed of the Sanwalka Group’s appeal (599/2010) with directions, underscoring the need for fair play, proportionate allotment, and adherence to Article–Act constraints in governance.

Supreme Court of India
Civil Appeal No. 12 of 2016

Sri Aurobindo Ashram Trust & Ors. v. R. Ramanathan

Sri Aurobindo Ashram Trust and Others (the appellants) challenged a Madras High Court/revision order under Section 92 CPC, seeking removal of trustees and a scheme for administration of the trust. The respondents, devotees and residents of the Sri Aurobindo Ashram at Pondicherry, had filed a suit alleging misgovernance by trustees for not taking action against an objectionable biography, The Lives of Sri Aurobindo by Peter Heehs, and for permitting its dissemination. The trial court refused revocation of leave to sue; the High Court upheld that decision. On appeal in the Supreme Court, the key issue was whether the suit fell within the domain of Section 92 CPC. The Court held that the determination must rest on the plaint’s allegations and the suit’s purpose; since the plaint sought to highlight the trustees’ inaction in banning or dissociating from the book, but the authorship and the book’s objectionable status were still pending adjudication in Orissa High Court, it would be premature to construe the inaction as maladministration. The Court acknowledged the trustees’ wide discretion in administering trusts and noted that mere mild expressions of displeasure or non-sponsorship do not amount to mismanagement. The appeal was allowed, revoking the leave granted under Section 92 CPC and encouraging amicable settlement between the parties.

Supreme Court of India
Civil Appeal No. 3783 of 2016

Delhi Development Authority v. M/S Anant Raj Agencies Pvt. Ltd.

This is a Civil Appeal arising from a long-running dispute over the lease of a Nazul plot in Delhi. The Delhi Development Authority (DDA) had leased plot no. 2, Jhandewalan, to Balraj Virmani for 20 years from 1948 with an option to renew for another 20 years, subject to compliance with lease covenants and potential rent enhancement. The original lessee sought renewal in 1967; the DDA issued show-cause notices in 1968 for multiple breaches (mezzanine use for a printing press, unauthorized subletting of cold storage, residential use by staff, alteration of the building) and ultimately terminated the lease on 1 September 1972. The lessee filed a suit for perpetual injunction; the Sub-Judge granted relief in his favor, and both the ADJ and High Court upheld the view that acceptance of rent after expiry amounted to renewal. During pendency, the respondent purchased the property under a compromise decree and was substituted in the appeal. The High Court further directed conversion of the lease to freehold by the DDA and accepted rent as renewal. The Supreme Court reversed, holding that there was no renewal (Clause III(b) of the lease, DD Act, and Nazul Rules apply), and that the lessee became an unauthorised occupant after expiry. It directed possession to DDA, damages for unauthorised occupation, adjustment of conversion charges, and costs. The decision clarifies that there is no automatic renewal of a terminated lease in public premises under the Public Premises Act, 1971.

Supreme Court of India
Civil Appeal No. 6120 of 2016

JAMSHED ANSARI v. HIGH COURT OF JUDICATURE AT ALLAHABAD

Jamshed Ansari, appearing in person, challenged the constitutional validity of Rule 3 and Rule 3A of Chapter XXIV of the Allahabad High Court Rules, 1952, which require a non-roll advocate to file an appointment with a local advocate on the High Court roll to appear before the Allahabad High Court. The High Court had rejected this challenge, and the writ petition challenging the rules was dismissed. The appellant argued that the right to practice law is protected as a fundamental right under Article 19(1)(g) and that these Rules impose an unreasonable prohibition, or at least unreasonable restrictions, on the right to practice. The respondents contended that the Rules are regulatory measures enacted under the High Court’s powers under Section 34 of the Advocates Act, designed to ensure accountability, improve administration of justice, and facilitate service of notices by maintaining a verifiable roll of advocates. The Supreme Court examined the nature of the right to practice, distinguishing it from the right to appear in court, and held that the Rules do not prohibit practice but regulate it, subject to reasonable restrictions under Article 19(6) and the Act. The Court reaffirmed that the High Court has power to frame such rules to regulate the practice before the Court, and that the administration of justice requires such safeguards. Ultimately, the appeal was dismissed, with no costs.

Supreme Court of India
I.A. No. 4 of 2016 in Special Leave Petition (Civil) No. 4754 of 2014

Harshita Bhasin v. State of West Bengal & Ors

Harshita Bhasin v. State of West Bengal & Ors concerns a matrimonial dispute culminating in a guardianship and custody dispute over two minor children of Mukul and Harshita Bhasin. The matter began with a petition under the Guardian and Wards Act, 1890, filed before the Civil Judge (Senior Division), Gautam Budh Nagar (UP), seeking dissolution of marriage and custody. The respondent-wife had filed a habeas corpus petition before the Calcutta High Court, which resulted in an interim custody arrangement in favour of the wife, directing the father to facilitate visitation by bringing the children to Kolkata on Sundays and permitting meetings at the wife’s advocate’s chambers. The Supreme Court, in 2014, disposed of the Special Leave Petition while noting the interim arrangement would continue and asking the guardianship proceedings to be expedited. In 2016, the husband (joined as the fifth respondent to a Constitution Article 136 petition) sought modification of the visitation order, arguing that the extensive travel—three-year-old and eight-year-old children shuttling between Noida, Delhi, and Kolkata early Sundays and late returns—was physically and mentally stressful and detrimental to schooling. Counsel for the husband urged a Delhi-centred visitation with monthly Kolkata visits and offered to fund travel for the mother. The Court brokered a compromise: the High Court order stands modified to a pattern where the father accompanies the children to Kolkata for the first fortnight’s visit, and the mother visits in Delhi in the second fortnight, with monthly monetary support and travel arrangements until final guardianship adjudication."

Supreme Court of India
Civil Appeals Nos. 9856-9860 of 2016; Civil Appeal No. 9861 of 2016

R. Venkata Ramudu & Another Etc. v. State of A.P. & Others

R. Venkata Ramudu and two other direct-recruitment Assistant Executive Engineers in the Andhra Pradesh Engineering Service challenged a government memo dated January 20, 2007 extending their probation and revising the dates of commencement of probation. The matter traces to initial appointments in 1992 and a statutory framework: the Andhra Pradesh Engineering Service Rules, 1967 (Special Rules) prescribe a two-year probation within a three-year period (Rule 6(2)) and require probationers to pass the Account Test (Rule 8(c)); the General Rules, 1996 (among others) govern probation, extension, and seniority (Rules 16, 17, 18, 33). Ramudu had passed the Account Test in 1997, but the government later communicated in 2003 and again in 2007 to extend probation and fix revised commencement dates, ostensibly under Rule 16(a) of the General Rules with Rule 16(h) and Rule 31 and the related exempting language in the Departmental Test Rules. The Administrative Tribunal and the Andhra Pradesh High Court upheld these extensions. The core issue was whether a government memo extending probation and altering dates, and Schedule-like notes appended to Rule 8, could override the statutory framework and affect seniority. The Supreme Court held that the Note to Rule 8 is a legislative device and, in proper circumstances, Rule 16(h) can override, but in this case the extension and altered commencement ran contrary to the statutory provisions, and therefore the OA should be allowed. The appeals were allowed, and Ramudu and others were to be considered for promotion based on their original date of appointment.

Supreme Court of India
Civil Appeal No. 4816 of 2016

MUDDASANI VENKATA NARSAJAH (D) TH. LRS. v. MUDDASANI SAROJANA

This Civil Appeal concerns a suit for possession of property by Mudassani Venkata Narsajah (through his legal representatives) based on a title to the property that had been held by Yashoda as a widow’s estate. After Yashoda’s lifetime, the surviving sister of Balaiah, Buchamma, inherited the property and sold it to the plaintiff, who was subsequently evicted by the defendants. The trial court dismissed the suit, while the first appellate court decreed it. The Andhra Pradesh High Court reversed, finding that the sale deed to the plaintiff was not proved for want of examination of Buchamma, and held that the plaintiff should have sought a declaration of title rather than a suit for possession. The Supreme Court, allowing the appeal, held that concurrent findings showed no serious cloud on the plaintiff’s title and that the adoption claim of the defendant no. 3 had not been established. It reaffirmed that the sale deed executed by Buchamma, as the sole surviving Class II heir of Balaiah, conferred title enabling the plaintiff to seek possession, even if possession was not delivered. The Court relied on established principles: a cloud on title necessitates a declaration of title, but disclosure of a clear title permits a possession suit; denial for want of knowledge is not a denial; and passing of consideration cannot be questioned by a third party. The appeal is allowed; the High Court’s order is set aside and the first appellate Court’s decree is restored.