Supreme Court of IndiaSupreme Court · 2025Division BenchAppeal allowed.

M/s Ferro Concrete Construction (India) Pvt. Ltd. v. The State of Rajasthan

Case / Petition Number:
Civil Appeal No. 4723 of 2025
Neutral Citation:[2025] 4 S.C.R. 529

Case Synopsis & Summary

The Supreme Court weighs whether a contractual clause barring interest in payments, contained in Clause 22 of a 1988 contract, prevents an arbitrator from awarding pendente lite interest under the Arbitration Act, 1940. The appellant contractor was awarded a works contract; disputes arose; the arbitrator granted 15% pendente lite interest from 18.12.1991 until payment. The District Judge set aside the interest; the High Court upheld that ruling. The Court recalls the settled law: under the 1940 Act, arbitrators can award pre-reference, pendente lite, and post-award interest unless there is an express bar in the contract; a general prohibition that merely says no interest on amounts payable is not automatically an express bar to pendente lite interest. The Court traces the evolution from Engineers-De-Space-Age through First Ambica and Reliance Cellulose, distinguishing the extent to which contractual phrasing and the statutory regime (1940 Act vs 1996 Act) shape the power to award interest. It concludes Clause 22 does not expressly bar pendente lite interest; accordingly, it allows the appeal, sets aside the High Court decision, and awards 9% pendente lite interest from 18.12.1991 to 07.03.1995, with no costs order. The decision clarifies the need for an explicit bar in ouster clauses and the differential treatment under the 1940 and 1996 Acts.

Precedent Explorer

Find Cases Like This

Explore other judgments dealing with similar legal situations, facts, or statutory provisions.

Case Details & Bench

Court
Supreme Court of India
Hon'ble Judges
  • Pamidighantam Sri Narasimha
  • Joymalya Bagchi
Judgment Date
2025-04-02
Court Decision / Holding
The Supreme Court allowed the appeal, set aside the High Court’s judgment, and held that Clause 22 does not expressly bar pendente lite interest under the 1940 Act. It directed payment of 9% pendente lite interest on the arbitral sum from 18.12.1991 to 07.03.1995 (date of the award), within 60 days. No order as to costs. Pending applications disposed of.
Final Disposition
Appeal allowed.

Parties to the Case

Appellants / Petitioners

  • M/s Ferro Concrete Construction (India) Pvt. Ltd.

Respondents

  • The State of Rajasthan

Legal Representation & Advocates

Counsels for Petitioners

  • • Vinayak Mehrotra
  • • Ms. Sonali Jain
  • • Ms. Nandini

Counsels for Respondents

  • • Ms. Sansriti Pathak
  • • AAG
  • • Aman Prasad
  • • Milind Kumar

Provisions of Law Cited

Arbitration Act, 1940Arbitration and Conciliation Act, 1996Section 31(7) of the Arbitration and Conciliation Act, 1996Interest Act, 1978

Legal Doctrines & Maxims

  • Strict construction of contractual clauses prohibiting payment of interest under the Arbitration Act, 1940
  • Party autonomy under the Arbitration and Conciliation Act, 1996 (Section 31(7))
  • Difference in interpretation of ouster clauses under 1940 Act vs 1996 Act
  • Express bar requirement for pendente lite interest requires explicit contractual language
  • Ouster of arbitrator’s power depends on clause wording, arbitration powers, nature of claim, and period affected

Submissions & Arguments

Contentions of Appellants / Petitioners

The appellant argued that Clause 22 does not expressly bar the arbitrator from awarding pendente lite interest. Relying on Reliance Cellulose and Pam Developments, they contended that a broad 'no interest' phrasing is not a clear and express bar to pendente lite interest under the 1940 Act; thus the arbitrator’s 15% pendente lite interest should stand unless a clear express bar exists.

Contentions of Respondents

The respondent contended that ouster clauses must be interpreted strictly; Clause 22’s language—no interest on any payment, arrears, or balance ‘found due at any time’—is an express bar to pendente lite interest. They highlighted the differences between the 1940 Act and the 1996 Act, emphasising clause wording and statutory provisions (Section 31(7)) that limit arbitrators’ power when an express contract bars such interest.

Legal Doctrine & Issue Explorer

Explore This Legal Issue

Find relevant judgments and authoritative positions on the legal questions discussed here.

Cited Precedents (16)

Case NameCitationTreatmentExplanation
Secretary, Irrigation Department, Government of Orissa v. G.C. Roy[1991] Supp. 3 SCR 417 : (1992) 1 SCC 508PositiveConstitution Bench recognizing arbitrator's power to award pre-reference, pendente lite, and post-award interest unless expressly barred by an agreement.
Executive Engineer, Dhenkanal Minor Irrigation Division v. N.C. Budharaj[2001] 1 SCR 264 : (2001) 2 SCC 721PositiveFollowed as part of the settled approach to interest under the 1940 Act.
Reliance Cellulose Products Ltd v. Oil and Natural Gas Corporation Limited[2018] 6 SCR 618 : (2018) 9 SCC 266PositiveParadigm for the test of express bar; reliance on para 24 guiding the need for express contractual bar to pendente lite interest.
Union of India v. Ambica Construction[2016] 2 SCR 810 : (2016) 6 SCC 36PositiveFirst Ambica case clarifying that ouster depends on contract wording; supports differentiated treatment of clauses.
Pam Developments Private Limited v. State of West Bengal[2024] 8 SCR 615 : (2024) 10 SCC 715PositiveConfirmed distinction between 1940 and 1996 Acts and the impact of express bar on pendente lite interest.
M.B. Patel & Co. v. ONGC[2008] 8 SCR 35 : (2008) 8 SCC 251PositivePart of the propositions about 1940 Act interpretations and interest.
Union of India v. Krafters Engg. & Leasing (P) Ltd.[2011] 8 SCR 196 : (2011) 7 SCC 279PositiveReferred in discussions of 31(7) and ouster concepts; supports autonomy under 1996 Act.
Board of Trustees For The Port of Calcutta v. Engineers-De-Space-Age[1995] Supp. 6 SCR 327 : (1996) 1 SCC 516DistinguishedRead down in light of First Ambica; not treated as general, universal rule.
Sayeed Ahmed & Co. v. State of U.P.[2009] 12 SCC 26PositiveEmphasises dependency on the nature of the clause in determining interest.
Sree Kamatchi Amman Constructions v. Railways[2010] 8 SCC 767PositiveSupports the principle that clause wording affects interest entitlement.
Union of India v. Bright Power Projects (India) (P) Ltd.[2015] 6 SCR 488 : (2015) 9 SCC 695PositiveDeals with interpretation of 'unless otherwise agreed' in Section 31(7) of the 1996 Act.
Chittaranjan Maity v. Union of India[2017] 9 SCC 611PositiveShows consistent stance on express bar and pendente lite under the 1996 Act context.
Garg Builders v. BHEL(2022) 11 SCC 697PositiveRecent guidance on pendente lite and contractual bar interplay in arbitration.
Madnani Construction Corpn. (P) Ltd. v. Union of India[2009] 16 SCR 216 : (2010) 1 SCC 549PositiveCited in the context of early interpretations of ouster clauses for interest.
Tehri Hydro Development Corpn. Ltd. v. Jai Prakash Associates Ltd.[2012] 8 SCR 813 : (2012) 12 SCC 10Mentioned OnlyCited among authorities but not central to the final reasoning on pendente lite bar here.
Reliance Cellulose Products Ltd v. Oil and Natural Gas Corporation Limited[2018] 6 SCR 618 : (2018) 9 SCC 266PositiveRepeated as a guiding authority for the express bar concept in the 1940 Act context.
Case Applicability Diagnostic

Apply This to My Facts

Share your situation and test whether this judgment governs, supports, or challenges your case.

Official Judgment Record
•4,967 words•~23 min read

In The Court Record

M/s Ferro Concrete Construction (India) Pvt. Ltd. v. The State of Rajasthan

[2025] 4 S.C.R. 529 : 2025 INSC 429 ## **M/s Ferro Concrete Construction (India) Pvt. Ltd. v.** ## **The State of Rajasthan** (Civil Appeal No. 4723 of 2025) 02 April 2025 ## **[Pamidighantam Sri Narasimha* and Joymalya Bagchi, JJ.]** ## **Issue for Consideration** Whether the contractual clause that bars the appellant/contractor from claiming any interest on any payment, arrears or balance due to it amounts to an express bar on the arbitrator’s power to grant _pendente lite_ interest as per the law under the Arbitration Act, 1940. ## **Headnotes[†]** **Arbitration Act, 1940 – Appellant was awarded a works contract by the respondent – A Clause 22 of the agreement barred the appellant from claiming interest on any payment or arrears or balance due to him – Disputes arose between the parties – Arbitration invoked – Arbitral award came out in favour of appellant – Arbitrator granted 15% pendente lite interest – However, the District Judge granted 9% simple interest on the Principal sum – Same was upheld by the High Court – Correctness:** **Held:** Both the decisions in Reliance Cellulose and the First Ambica case emphasise the need for an express contractual bar on the payment of pendente lite interest to create a bar on the arbitrator from awarding interest – They also emphasise that a bar on the arbitrator’s power would depend on the phraseology of the contractual clause in that case – In the instant case, the Clause 22 prohibits the appellant (contractor) from claiming interest on any payment, arrears or balance, which may be found due to him at any time – Applying the above-stated law, this Court finds that this clause does not expressly bar the award of pendente lite interest in the event of disputes, differences, or misunderstandings between the parties, or on delayed payment, or in any other respect whatsoever – Under the 1940 Act, this Court has not readily inferred a bar on the arbitrator from clauses that merely bar the * Author [2025] 4 S.C.R. 530 ## **Digital Supreme Court Reports** contractor from claiming interest, and the same will apply to this case as well – In view thereof, the judgment of the High Court is set aside – However, considering that the arbitrator entered reference in 1991 and the award was made in 1995, along with the passage of time in litigation as well as the amounts already paid by the respondent including post-award interest @ 9%, this Court deems it appropriate to grant 9% pendente lite interest, instead of 15% as granted by the arbitral tribunal, from 18.12.1991 till 07.03.1995 (date of the arbitral award). [Paras 14, 15, 16] ## **Arbitration Act, 1940 – Arbitration and Conciliation Act, 1996 – Position of law on the grant of interest – Discussed.** ## **Case Law Cited** _Secretary, Irrigation Department, Government of Orissa v. G.C. Roy_ **[1991] Supp. 3 SCR 417 : (1992) 1 SCC 508;** _Executive Engineer, Dhenkanal Minor Irrigation Division v. N.C. Budharaj_ **[2001] 1 SCR 264 : (2001) 2 SCC 721 – followed.** _Reliance Cellulose Products Ltd v. Oil and Natural Gas Corporation Limited_ **[2018] 6 SCR 618 : (2018) 9 SCC 266;** _Union of India v. Ambica Construction_ **[2016] 2 SCR 810 : (2016) 6 SCC 36 – relied on.** _Pam Developments Private Limited v. State of West Bengal_ **[2024] 8 SCR 615 : (2024) 10 SCC 715;** _M.B. Patel & Co. v. ONGC_ **[2008] 8 SCR 35 : (2008) 8 SCC 251;** _Union of India v. Krafters Engg. & Leasing (P) Ltd._ **[2011] 8 SCR 196 : (2011) 7 SCC 279;** _Board of Trustees For The Port of Calcutta v. Engineers-De-Space-Age_ **[1995] Supp. 6 SCR 327 : (1996) 1 SCC 516;** _Sayeed Ahmed & Co. v. State of U.P._ **[2009] 10 SCR 841 : (2009) 12 SCC 26;** _Sree Kamatchi Amman Constructions v. Railways_ **[2010] 10 SCR 487 : (2010) 8 SCC 767;** _Union of India v. Bright Power Projects (India) (P) Ltd._ **[2015] 6 SCR 488 : (2015) 9 SCC 695;** _Chittaranjan Maity v. Union of India_ **[2017] 11 SCR 722 : (2017) 9 SCC 611;** _Garg Builders v. BHEL_ **(2022) 11 SCC 697;** _Madnani Construction Corpn. (P) Ltd. v. Union of India_ **[2009] 16 SCR 216 : (2010) 1 SCC 549;** _Tehri Hydro Development Corpn. Ltd. v. Jai Prakash Associates Ltd._ **[2012] 8 SCR 813 : (2012) 12 SCC 10 – referred to.** ## **List of Acts** Arbitration Act, 1940; Arbitration and Conciliation Act, 1996. [2025] 4 S.C.R.  531 # **M/s Ferro Concrete Construction (India) Pvt. Ltd. v. The State of Rajasthan** ## **List of Keywords** Grant of interest under Arbitration Act, 1940; Contractual clauses; Payment of interest; Pendente lite interest on arbitral sum; Phraseology of the agreement; Clauses conferring powers relating to arbitration; Power to award interest; Express contractual bar on payment of pendente lite interest. ## **Case Arising From** CIVIL APPELLATE JURISDICTION: Civil Appeal No. 4723 of 2025 From the Judgment and Order dated 06.01.2023 of the High Court of Judicature for Rajasthan at Jaipur in SBCMA No. 3175 of 2006 ## **Appearances for Parties** _Advs. for the Appellant:_ Vinayak Mehrotra, Ms. Sonali Jain, Ms. Nandini. _Advs. for the Respondent:_ Ms. Sansriti Pathak, AAG, Aman Prasad, Milind Kumar. ## **Judgment / Order of the Supreme Court** ## **Judgment** ## **Pamidighantam Sri Narasimha, J.** 1. Leave granted. 2. _It is just as necessary to follow a precedent as it is to make a precedent._ 3. The short issue arising for consideration in this appeal is whether the contractual clause that bars the appellant/contractor from claiming any interest on any payment, arrears or balance due to it amounts to an express bar on the arbitrator’s power to grant _pendente lite_ interest as per the law under the Arbitration Act, 1940[1] . While the arbitrator granted 15% _pendente lite_ interest, the same was set aside by the District Judge while deciding objections against the award, and upheld by the High Court by order dated 06.01.2023, which is impugned 1 Hereinafter “1940 Act”. [2025] 4 S.C.R. 532 ## **Digital Supreme Court Reports** herein. By relying on settled case-law on the grant of interest under the 1940 Act and the interpretation of contractual clauses barring payment of interest, we have allowed the present appeal and have directed payment of _pendente lite_ interest on the arbitral sum. 4. The relevant facts are that the appellant was awarded a works contract by the respondent, and they entered into an agreement dated 06.02.1988 that contains the following clause barring the appellant from claiming interest on any payment or arrears or balance due to him at any time: - _“22. Payments :-_ - _(i) Payments will be made to the contractor within one month of the issuing of the corresponding bills. The contractor shall comply with the procedure that may be prescribed for all operations from the recording of progress measurements upto payment of bills._ - _(ii) All materials and work for which payment is made in part or full shall become the sole property of the Govt, but this provision shall not relieve the contractor of his responsibility for the care and protection of the materials and works at his own cost nor his liability to make good the damage if any unless and until the whole work has been deemed to have been completed and handed over to the Government._ _The contractor shall not be entitled to claim any interest upon any payment, any arrears or upon any balance, which may be found due to him at any time_ .” (emphasis supplied) 5. When disputes arose under the contract, the appellant invoked arbitration and filed its claim, resulting in arbitral award dated 07.03.1995 for a sum of Rs. 1,78,17,146 in its favour. The arbitrator also directed payment of 15% interest p.a. on all dues payable from 18.12.1991 (when the arbitrator entered reference) till payment or the date of decree, whichever is earlier. The respondent filed an application to set aside the award, which was decided by the District Judge’s order dated 16.08.2005 that only set aside the interest awarded by the arbitrator, and instead granted 9% simple interest [2025] 4 S.C.R.  533 ## **M/s Ferro Concrete Construction (India) Pvt. Ltd. v. The State of Rajasthan** on the principal sum from that date till the date of payment. The other objections against the award were rejected and the rest of the award was upheld. It was held that the arbitrator did not consider that Clause 22 of the contract is widely worded and prohibits the appellant from claiming interest _at any time_ . Both parties preferred appeals against this order, which were dismissed by the High Court by order dated 06.01.2023, impugned herein. 6. While issuing notice on 24.04.2023 in the present special leave petition converted to a civil appeal, this Court passed the following order: - “ _1. Learned counsel appearing on behalf of the petitioner relies upon paragraph 24 of the decision of this Court in_ _**Reliance Cellulose Products Ltd Vs Oil and Natural Gas Corporation Limited** ._ _**[2]** He urges that Clause 22 of the agreement does not specifically exclude either the power of the arbitrator to grant pendente lite interest or rule out the claimant from claiming interest pendente lite in the course of arbitration._ _2. Issue notice returnable in four weeks._ ” 7. We have heard Mr. Vinayak Mehrotra, learned counsel for the appellant, and Ms. Sansriti Pathak, learned Additional Advocate General for the respondent State on the issue of whether Clause 22 amounts to a bar on the arbitrator from awarding _pendente lite_ interest under the 1940 Act. - 7.1 Mr. Mehrotra submits that the present issue is covered by this Court’s decision in _Reliance Cellulose_ (supra). He submits that the contractual clause in the present case does not clearly and expressly bar the arbitrator from awarding interest on the arbitral sum. He has also referred to this Court’s decision in _Pam Developments Private Limited v. State of West Bengal_[3] in support of his argument. - 7.2 On the other hand, Ms. Pathak has made detailed submissions regarding the interpretation of the contractual clause, which are as follows: _First_ , the interpretation of an ouster clause is the > 2 (2018) 9 SCC 266. > 3 (2024) 10 SCC 715, para 23. [2025] 4 S.C.R. 534 ## **Digital Supreme Court Reports** same under the 1940 Act and the Arbitration and Conciliation Act, 1996[4] . Under both statutes, the arbitrator can award interest _unless the agreement provides otherwise_ . The key difference between the statutes is that the 1996 Act contains an express statutory provision for the grant of interest in Section 31(7), but this is based on the principle in _G.C. Roy_[5] that recognised the arbitrator’s power to award interest under the 1940 Act. Further, that Section 31(7)(a) of the 1996 Act does not differentiate prereference and _pendente lite_ interest. However, these differences do not have any bearing on the interpretation of contractual clauses. _Second_ , by referring to various decisions of this Court, she submits that narrower contractual clauses have been treated as ouster clauses that bar the arbitrator from awarding _pendente-lite_ interest.[6] _Third_ , she submits that paragraph 24 of _Reliance Cellulose_ (supra), which is relied on by the appellant, is based on this Court’s decision in _Board of Trustees For The Port of Calcutta v. Engineers-De-Space-Age_ ,[7] which has been doubted in several cases. A 3-judge bench of this Court in _Union of India v. Ambica Construction_[8] _(First Ambica_ case _)_ held that the observations in _Engineers-De-Space-Age_ (supra) cannot be considered as general observations and each contractual clause barring payment of interest must be interpreted by the words used therein. _Fourth_ , in the facts of the present case, the respondent has already paid a sum of Rs. 4.65 crores to the appellant, of which Rs. 2.83 crores is the interest component. Hence, a further award of _pendente lite_ interest is not warranted in the present case. 8. The position of law on the grant of interest under the 1940 Act and the 1996 Act is well-settled. The constitution bench decisions of this Court in _GC Roy_ (supra) and _NC Budharaj[9]_ recognised the arbitrator’s power to grant pre-reference, _pendente lite_ , and post-award interest on an arbitral award made under the 1940 Act unless there is a > 4 Hereinafter “1996 Act”. > 5 _Secretary, Irrigation Department, Government of Orissa v. G.C. Roy_ , (1992) 1 SCC 508. > 6 Relied on _M.B. Patel & Co. v. ONGC_ , (2008) 8 SCC 251; _Union of India v. Krafters Engg. & Leasing (P) Ltd._ , (2011) 7 SCC 279 under the 1940 Act. > 7 (1996) 1 SCC 516. > 8 (2016) 6 SCC 36. > 9 _Executive Engineer, Dhenkanal Minor Irrigation Division v. N.C. Budharaj_ , (2001) 2 SCC 721. [2025] 4 S.C.R.  535 ## **M/s Ferro Concrete Construction (India) Pvt. Ltd. v. The State of Rajasthan** contractual bar.[10] The question that falls for our consideration is whether the contractual bar in the present case prohibits the arbitrator from granting _pendente lite_ interest, which necessarily entails an interpretation of the clause. 9. This Court has, on multiple occasions, noted that a contractual clause which bars the payment of interest is interpreted differently under the 1940 Act and the 1996 Act. In fact, while deciding cases under the 1996 Act, this Court has been slow to rely on the principles laid down under the 1940 Act, considering the legislative incorporation of the arbitrator’s power to grant interest through Section 31(7) of the 1996 Act.[11] The difference in the interpretative approach has been expounded by this Court in _Reliance Cellulose_ (supra) as follows: “ _24. A conspectus of the decisions that have been referred to above would show that under the 1940 Act, an arbitrator has power to grant pre-reference interest under the Interest Act, 1978 as well as pendente lite and future interest. However, he is constricted only by the fact that an agreement between the parties may contain an express bar to the award of pre-reference and/or pendente lite interest. Since interest is compensatory in nature and is parasitic upon a principal sum not having been paid in time, this Court has frowned upon clauses that bar the payment of interest. It has therefore evolved the test of strict construction of such clauses, and has gone on to state that unless there is a clear and express bar to the payment of interest that can be awarded by an arbitrator, clauses which do not refer to claims before the arbitrators or disputes between parties and clearly bar payment of interest, cannot stand in the way of an arbitrator awarding pre-reference or pendente lite interest._ _Thus, when one contrasts a clause such as the clause in Second Ambica Construction case with the clause in Tehri Hydro Development Corpn. Ltd., it becomes clear that_ > 10 _GC Roy_ (supra), para 45. > 11 _Sayeed Ahmed & Co. v. State of U.P._ , (2009) 12 SCC 26, para 24; _Sree Kamatchi Amman Constructions v. Railways_ , (2010) 8 SCC 767, paras 18-19; _Union of India v. Bright Power Projects (India) (P) Ltd._ , (2015) 9 SCC 695, paras 17-19; _Chittaranjan Maity v. Union of India_ , (2017) 9 SCC 611, para 16; _Garg Builders v. BHEL_ , (2022) 11 SCC 697, para 17. [2025] 4 S.C.R. 536 ## **Digital Supreme Court Reports** _unless a contractor agrees that no claim for interest will either be entertained or payable by the other party owing to dispute, difference, or misunderstandings between the parties or in respect of delay on the part of the engineer or in any other respect whatsoever, leading the Court to find an express bar against payment of interest, a clause which merely states that no interest will be payable upon amounts payable to the contractor under the contract would not be sufficient to bar an arbitrator from awarding pendente lite interest under the 1940 Act. As has been held in First Ambica Construction case, the grant of pendente lite interest depends upon the phraseology used in the agreement, clauses conferring power relating to arbitration, the nature of claim and dispute referred to the arbitrator, and on what items the power to award interest has been taken away and for which period. We hasten to add that the position as has been explained in some of the judgments above under Section 31(7) of the 1996 Act, is wholly different, inasmuch as Section 31(7) of the 1996 Act sanctifies agreements between the parties and states that the moment the agreement says otherwise, no interest becomes payable right from the date of the cause of action until the award is delivered._ ” (emphasis supplied) 10. The difference in the interpretative approach can be stated as follows. Under the 1940 Act, a stricter approach is followed that requires a clear and express clause against the payment of interest in case of difference, dispute, or misunderstanding, in case of delay of payment, or any other case whatsoever, to constitute a bar on the arbitrator from granting interest. A clause that only provides that interest shall not be granted on amounts payable under the contract would not be sufficient. On the other hand, under the 1996 Act wherein Section 31(7)(a) sanctifies party autonomy, interest is not payable _the moment the contract provides otherwise_ . This distinction has been reiterated by us in a recent decision in _Pam Developments_ (supra), which summarised the position of law as follows: - “ _23. The power of the arbitrator to grant pre-reference interest, pendente lite interest, and post-award interest_ [2025] 4 S.C.R.  537 ## **M/s Ferro Concrete Construction (India) Pvt. Ltd. v. The State of Rajasthan** _under Section 31(7) of the Act is fairly well-settled. The judicial determinations also highlight the difference in the position of law under the Arbitration Act, 1940. The following propositions can be summarised from a survey of these cases:_ _23.1. Under the Arbitration Act, 1940, there was no specific provision that empowered an arbitrator to grant interest. However, through judicial pronouncements, this Court has affirmed the power of the arbitrator to grant prereference, pendente lite, and post-award interest on the rationale that a person who has been deprived of the use of money to which he is legitimately entitled has a right to be compensated for the same. When the agreement does not prohibit the grant of interest and a party claims interest, it is presumed that interest is an implied term of the agreement, and therefore, the arbitrator has the power to decide the same._ _23.2. Under the 1940 Act, this Court has adopted a strict construction of contractual clauses that prohibit the grant of interest and has held that the arbitrator has the power to award interest unless there is an express, specific provision that excludes the jurisdiction of the arbitrator._ _23.3. Under the 1996 Act, the power of the arbitrator to grant interest is governed by the statutory provision in Section 31(7). This provision has two parts. Under clause (a), the arbitrator can award interest for the period between the date of cause of action to the date of the award, unless otherwise agreed by the parties. Clause (b) provides that unless the award directs otherwise, the sum directed to be paid by an arbitral award shall carry interest @ 2% higher than the current rate of interest, from the date of the award to the date of payment._ _23.4. The wording of Section 31(7)(a) marks a departure from the Arbitration Act, 1940 in two ways : first, it does not make an explicit distinction between pre-reference and pendente lite interest as both of them are provided for under this sub-section; second, it sanctifies party autonomy and restricts the power to grant pre-reference and pendente_ [2025] 4 S.C.R. 538 ## **Digital Supreme Court Reports** _lite interest the moment the agreement bars payment of interest, even if it is not a specific bar against the arbitrator._ _23.5. The power of the arbitrator to award pre-reference and pendente lite interest is not restricted when the agreement is silent on whether interest can be awarded or does not contain a specific term that prohibits the same._ _23.6. While pendente lite interest is a matter of procedural law, pre-reference interest is governed by substantive law. Therefore, the grant of pre-reference interest cannot be sourced solely in Section 31(7)(a) (which is a procedural law), but must be based on an agreement between the parties (express or implied), statutory provision (such as Section 3 of the Interest Act, 1978), or proof of mercantile usage._ ” (emphasis supplied) 11. At this stage, we find it necessary to deal with Ms. Pathak’s submission that _Reliance Cellulose_ (supra) relies on _Engineers-De-Space-Age_ (supra), which was later read down and clarified by a 3-judge bench in the _First Ambica_ case. Upon reading _Reliance Cellulose_ (supra), it is clear that this Court undertook a comprehensive survey of the case-law on the issue of payment of interest on arbitral awards, including a detailed discussion of the _First Ambica_ case,[12] before formulating the legal position extracted hereinabove. 12. In the _First Ambica_ case (supra), the issue before this Court was whether _Engineers-De-Space-Age_ (supra) and _Madnani Construction_[13] were correctly decided.[14] After taking note of the interpretation of various contractual clauses barring payment of interest in this Court’s decisions under the 1940 Act and the 1996 Act, it summarised their rulings as follows: “ _28. It is apparent from various decisions referred to above that in G.C. Roy the Constitution Bench of this Court has laid down that where the agreement expressly provides_ > 12 _Reliance Cellulose_ (supra), paras 19-21. > 13 _Madnani Construction Corpn. (P) Ltd. v. Union of India_ , (2010) 1 SCC 549. - 14 _First Ambica_ case (supra), para 1. [2025] 4 S.C.R.  539 ## **M/s Ferro Concrete Construction (India) Pvt. Ltd. v. The State of Rajasthan** _that no interest pendente lite shall be payable on amount due, the arbitrator has no power to award interest. In N.C. Budharaj a Constitution Bench has observed that in case there is nothing in the arbitration agreement to exclude jurisdiction of the arbitrator to entertaining claim for interest, the jurisdiction of the arbitrator to consider and award interest in respect to all periods is subject to Section 29 of the Act. In Hindustan Construction Co. Ltd. this Court has followed the decision in G.C. Roy and laid down that on the basis of principles of Section 34 the arbitrator would have the power to award pendente lite interest also. In B.N. Agarwalla, this Court has again followed G.C. Roy and Hindustan Construction Co. Ltd. with respect to the power of the arbitrator to award pendente lite interest and it was held that the arbitrator has the power to award interest. In Harish Chandra this Court interpreted Clause 1.9 which provided that no claim for interest or damages will be entertained by the Government in respect to any monies or balances which may be lying with the Government. It was held that there was no provision which could be culled out against the contractor not to claim interest by way of damages before the arbitrator on the relevant items placed for adjudication. In Ferro Concrete Construction (P) Ltd. this Court considered Clause 4 containing a stipulation that no interest was payable on amount withheld under the agreement. It was held that Clause 4, which dealt with rates, material and workmanship, did not bar award of interest by the arbitrator on claims of the contractor made in the said case. In Sayeed Ahmed this Court has emphasised that award of interest would depend upon nature of the clause in the agreement. In Bright Power Projects (India) (P) Ltd. this Court has considered the expression “unless otherwise agreed by parties” employed in Section 31(7)(a) of the 1996 Act and laid down that in case contract bars claim of interest the contractor could not have claimed interest. The provision of Section 31(7) (a) of the 1996 Act is binding upon the arbitrator. In Sree Kamatchi Amman Constructions similar view has been taken._ ” [2025] 4 S.C.R. 540 ## **Digital Supreme Court Reports** The Court then took note of the doubts expressed regarding the correctness of _Engineers-De-Space-Age_ (supra) and _Madnani Construction_ (supra) in _Sayeed Ahmed_ (supra) and _Tehri Hydro Development Corpn. Ltd. v. Jai Prakash Associates Ltd._[15] , on the ground that they allow the arbitrator to grant interest by ignoring an express bar in the contract.[16] In order to resolve the discordant note, this Court in the _First Ambica_ case (supra) held as follows: “ _32. In para 4 in Engineers-De-Space-Age this Court has observed that bar under the contract will not be applicable to the arbitrator cannot be said to be observation of general application. In our opinion, it would depend upon the stipulation in the contract in each case whether the power of the arbitrator to grant pendente lite interest is expressly taken away. If answer is “yes” then the arbitrator would have no power to award pendente lite interest._ _33. The decision in Madnani Construction Corpn. has followed the decision in Engineers-De-Space-Age. The same is also required to be diluted to the extent that express stipulation under contract may debar the arbitrator from awarding interest pendente lite. Grant of pendente lite interest may depend upon several factors such as_ _phraseology used in the agreement, clauses conferring power relating to arbitration, nature of claim and dispute referred to arbitrator and on what items power to award interest has been taken away and for which period._ _34. Thus, our answer to the reference is that if the contract expressly bars the award of interest pendente lite, the same cannot be awarded by the arbitrator. We also make it clear that the bar to award interest on delayed payment by itself will not be readily inferred as express bar to award interest pendente lite by the Arbitral Tribunal, as ouster of power of the arbitrator has to be considered on various relevant aspects referred to in the decisions of this Court, it would be for the Division Bench to consider the case on merits._ ” (emphasis supplied) 15 (2012) 12 SCC 10. 16 _First Ambica_ case (supra), paras 29-31. [2025] 4 S.C.R.  541 ## **M/s Ferro Concrete Construction (India) Pvt. Ltd. v. The State of Rajasthan** 13. From the above extracted paragraphs, the decision of the 3-judge bench in the _First Ambica_ case (supra) can be stated as follows. The arbitrator’s power to grant interest would depend on the contractual clause in each case, and whether it _expressly takes away the arbitrator’s power to grant pendente lite interest_ . This would have to be determined based on the phraseology of the agreement, clauses conferring powers relating to arbitration, the nature of claim and dispute referred to the arbitrator, and on what items the power to award interest is contractually barred and for which period. Further, a bar on award of interest for delayed payment would not be readily inferred as an express bar to the award of _pendente lite_ interest by the arbitrator. 14. We find that the position of law laid down in paragraph 24 of _Reliance Cellulose_ (supra) is in line with the position of law laid down in the _First Ambica_ case. Both decisions emphasise the need for an express contractual bar on the payment of _pendente lite_ interest to create a bar on the arbitrator from awarding interest. They also emphasise that a bar on the arbitrator’s power would depend on the phraseology of the contractual clause in that case. In this light, Ms. Pathak’s submission regarding the correctness of _Reliance Cellulose_ (supra) ought to be rejected. We do not find any reason to unsettle the position of law, when it has been clearly enunciated and followed. It is not sufficient to lay down a precedent, but it is equally important to follow and apply them as well. 15. Now that we have stated the law applicable to this case, we will consider the terms of Clause 22 of the contract to determine whether it bars the arbitrator from awarding _pendente lite_ interest on the arbitral award. Clause 22 prohibits the appellant (contractor) from claiming interest on _any payment, arrears or balance_ , which may be found due to him _at any time_ . Applying the above-stated law, we find that this clause does not expressly bar the award of _pendente lite_ interest in the event of disputes, differences, or misunderstandings between the parties, or on delayed payment, or in any other respect whatsoever. Under the 1940 Act, this Court has not readily inferred a bar on the arbitrator from clauses that merely bar the contractor from claiming interest, and the same will apply to this case as well. 16. In view of the above discussion, we allow the present appeal and set aside the impugned judgment of the High Court in SBCMA No. [2025] 4 S.C.R. 542 ## **Digital Supreme Court Reports** 3175/2006 dated 06.01.2023. Considering that the arbitrator entered reference in 1991 and the award was made in 1995, along with the passage of time in litigation as well as the amounts already paid by the respondent including post-award interest @ 9%, we deem it appropriate to grant 9% _pendente lite_ interest, instead of 15% as granted by the arbitral tribunal, from 18.12.1991 till 07.03.1995 (date of the arbitral award) within a period of 60 days.[17] 17. No order as to costs. 18. Pending applications, if any, stand disposed of. _Result of the case:_ Appeal allowed. - _†Headnotes prepared by:_ Ankit Gyan > 17 As these proceedings arise under the 1940 Act, the scope and jurisdiction of the Court to modify or vary the award is larger than that of the court exercising jurisdiction under Section 34 of the 1996 Act.
End of Judgment Record
Browse All Supreme Court of India (2025) Decisions
2025-01-03

Krishna Devi @ Sabitri Devi (Rani) M/s S.R. Engineering Construction v. Union of India & Ors.

Krishna Devi @ Sabitri Devi (Rani) approaches the Supreme Court seeking pronouncement of judgment in terms of an arbitral award under Section 17 of the Arbitration Act, 1940. The appellant’s husband secured a favourable award on 31 May 2022 in a dispute over a Tezpur work contract. Although the award was not published due to outstanding arbitrator fees, a district court order dated 21 September 2022 directed the respondents to clear the balance and stated that once paid, the award would be furnished. The appellant filed a Section 17 application on 10 November 2022 seeking the court to pronounce judgment in terms of the award. The trial court and the Gauhati High Court held the application premature, because it was filed before the expiry of the 30-day objections window under Article 119(b) of the Limitation Act, calculated from 18 November 2022 (alleged formal notice). The Supreme Court, however, held that the start of limitation is not tied to a formal notice but to awareness of the award’s existence. It relied on earlier decisions establishing that Section 14(2) only requires awareness that an award exists; a court’s order directing payment of fees can constitute such notice. Consequently, the 30-day limitation expired by 20 October 2022, rendering the Section 17 application timely. The appeal is allowed, and directions are issued to dispose of the related matter expeditiously with no costs.

2025-03-04

Saranga Anilkumar Aggarwal v. Bhavesh Dhirajlal Sheth & Ors.

This Civil Appeal concerns whether execution of penalty orders imposed by the National Consumer Disputes Redressal Commission (NCDRC) can be stayed under the interim moratorium provisions of Section 96 of the Insolvency and Bankruptcy Code, 2016 (IBC), while insolvency proceedings are pending under Section 95 of the IBC. The appellant, a real estate developer, sought a stay of 27 penalties levied for deficiency in service and delay in possession of residential units, arguing that an application under Section 95 of the IBC had triggered an interim moratorium. The NCDRC had rejected the stay, holding that consumer-claims and penalties are not “debts” within the moratorium’s ambit. The Supreme Court affirmed that the damages awarded in consumer disputes arise to compensate home-buyers and deter malpractice, and are not ordinary contractual debts susceptible to IBC restructuring; such damages fall within the category of “excluded debts” under Section 79(15) of the IBC, and their enforcement remains unaffected by insolvency proceedings. The Court emphasized the essential distinction between debt-recovery proceedings and regulatory/penal actions under consumer protection laws, rejected reliance on contrary authorities (notably Sheetal Gupta per incuriam), and held that criminal penalties under the CP Act do not automatically fall within the moratorium. The appeal was dismissed; the appellant was directed to comply with the NCDRC penalties within eight weeks.

2025-04-09

Serious Fraud Investigation Office v. Aditya Sarda

This batch of sixteen interconnected criminal appeals arises from SFIO's complaint against multiple respondents including Aditya Sarda for serious economic offences under the Companies Act, 2013 and the IPC. The Special Court at Gurugram took cognizance of the offences and issued bailable warrants to the accused, who allegedly concealed themselves or otherwise obstructed the process. Non‑bailable warrants were issued, and some proclamations under CrPC Section 82 were initiated against certain respondents. The High Court granted anticipatory bail to several respondents, notwithstanding the cognizance, warrant proceedings, and proclamations, leading to a series of challenges before the Supreme Court. The Court emphasises that anticipatory bail is an extraordinary remedy not available as a routine in cases involving serious economic offences, and that the twin mandatory conditions in Section 212(6) of the Companies Act, 2013 must be considered: (i) Public Prosecutor must be given an opportunity to oppose; and (ii) where opposed, the court must be satisfied of reasonable grounds to believe the accused is not guilty and unlikely to commit an offence while on bail. It reasons that respondents who evade process by concealing themselves after cognizance and after non‑bailable warrants were issued should not receive anticipatory bail. Accordingly, the High Court orders granting anticipatory bail are set aside, and the respondents are directed to surrender within one week to the Special Court, with subsequent bail determinations to be made in accordance with law. The judgment reiterates that economic offences require a cautious, exception‑based approach to bail and underscores the importance of ensuring due process and the unobstructed progress of judicial proceedings.

2025-03-04

K.S. Mehta v. M/s Morgan Securities and Credits Pvt. Ltd.

This is a Supreme Court decision under Criminal Appeal No. 1105 of 2025 arising from quashing under Section 482 CrPC of criminal proceedings instituted under Section 138 read with Section 141 of the Negotiable Instruments Act, 1881. The appellants, K.S. Mehta and Basant Kumar Goswami, were non-executive directors of M/s Blue Coast Hotels & Resorts Ltd., chosen to meet SEBI’s governance requirements (Clause 49 of Listing Agreement). They were not present at the 09.09.2002 board meeting that approved an Inter-Corporate Deposit (ICD) of ₹5 crores nor signatories to the ICD agreement or related instruments. Later, two cheques issued to discharge the debt were dishonored, leading to criminal proceedings against the directors. The High Court of Delhi dismissed petitions under Section 482 CrPC seeking quashing. The Supreme Court held that non-executive and independent directors cannot be fastened with vicarious liability under Section 141 NI Act unless the record demonstrates their direct involvement in the company’s affairs at the relevant time. Here, there was no evidence of their involvement, no signatory status, and mere attendance at board meetings cannot establish liability. The Court emphasized the need for specific averments showing the director was in charge of and responsible for the company’s conduct. Consequently, the proceedings against the appellants were quashed and the appeals allowed.