M/s ABCI Infrastructures Pvt. Ltd. v. Union of India and Others
Case Synopsis & Summary
This is a Civil Appeal arising from a bid for design and construction of two-lane twin tunnels at Shinkun La Pass in Himachal Pradesh, with an estimated project value of Rs. 15,04,64,00,000. The appellant, M/s ABCI Infrastructures Pvt. Ltd., was declared L-1 with a quoted price of Rs. 1,569, reportedly Rs. 1,569 crores, but the appellant contends the price appeared as Rs. 1,569 due to a system error. The appellant promptly informed BRO about the alleged mistake, but BRO insisted on requiring a detailed price analysis and ultimately proceeded to forfeit the bid security of Rs. 15.04 crores and encash the bank guarantee. The writ petition before the Himachal Pradesh High Court was dismissed. The Supreme Court examined whether the bid error could be treated under Section 20 of the Indian Contract Act, 1872, noting that the explanation to Section 20 excludes errors of value as a matter of fact. The Court recognized that while the error was self-evident, relief in equity for bid mistakes is available in certain circumstances, citing West Bengal State Electricity Board v Patel Engineering and other authorities. The Court held that the appellant was at fault for not adding zeros and that a practical approach should have been adopted. It directed the appellant to pay Rs. 1 crore to BRO, and upon payment, BRO was to return the bank guarantee within a week; the impugned judgment was set aside and the appeal allowed with no costs.
Find Cases Like This
Explore other judgments dealing with similar legal situations, facts, or statutory provisions.
Case Details & Bench
- Court
- Supreme Court of India
- Hon'ble Judges
- Sanjiv Khanna
- Sanjay Kumar
- K.V. Viswanathan
- Judgment Date
- 2025-02-14
- Court Decision / Holding
- The impugned judgment of the High Court is set aside. The Supreme Court allows the appeal. The appellant is directed to pay Rs. 1 crore to BRO; upon receipt, BRO shall return the original bank guarantee of Rs. 15.04 crores within one week. There would be no order as to costs. The contract is not reaffirmed; instead, the remedy involves financial adjustment and return of security, with the bid process subsequently continuing via a fresh tender.
- Final Disposition
- Appeal allowed. No costs. Appellant to pay Rs. 1 crore to BRO and receive return of Rs. 15.04 crores bank guarantee within one week after payment; impugned judgment set aside.
Parties to the Case
Appellants / Petitioners
- M/s ABCI Infrastructures Pvt. Ltd.
Respondents
- Union of India
- Border Road Organisation
Legal Representation & Advocates
Counsels for Petitioners
- • Mukul Rohatgi
- • Gaurav Khanna
- • Ms. Natasha Sahrawat
- • Ms. Deepali Bhanot
- • Gautam Barnwal
- • Rudraksh Pandey
- • Ms. Alisha Roy
Counsels for Respondents
- • Ms. Archana Pathak Dave
- • A.S.G.
- • Dr. N. Visakamurthy
- • Yashraj Singh Bundela
- • Raman Yadav
- • Hitarth Raja
- • Udit Dedhiya
- • Mukesh Kumar Maroria
- • Sanjay Kapur
- • Surya Prakash
- • Arjun Bhatia
- • Ms. Shubhra Kapur
- • Ms. Mahima Kapur
Provisions of Law Cited
Legal Doctrines & Maxims
- Equitable relief in cases of mistake in bids on public contracts
- Relief in equity for mistake (Section 20)
- Proportionality doctrine in judicial review
- Self-evident / patent error in bid price
- Minds of the parties having not met (when contract not formed)
- Rectification/withdrawal before contract as recognized in relevant precedent
Submissions & Arguments
Contentions of Appellants / Petitioners
The appellants argued that the Rs.1,569 crore figure was a patent and self-evident error, likely a system glitch or typographical mistake, and was discovered on 24.08.2023 after bids opened. They assert prompt notice to withdraw and seek relief in equity under Section 20 of the Indian Contract Act, contending that a practical, corrective approach should have been adopted by BRO rather than forfeiture of bid security. They emphasize that delays were not solely attributable to the appellant and that the error was addressed promptly; a lower-cost, re-tendered outcome later occurred. They contend that the bank guarantee should be returned and that waiver of forfeiture would uphold transparency and fairness in bidding, avoiding unjust enrichment or punitive results for an obvious, clerical error.
Contentions of Respondents
The respondents argued that the quoted Rs.1,569 breached the contract’s scale, being unrealistically low for a project exceeding Rs.1,500 crore. They maintained that the error was not a mere misprint but a significant self-evident mistake that could not be corrected after bids, and that the appellant forfeited the bid security due to delay and non-compliance. They relied on ongoing procurement rules and the necessity to preserve transparency and accountability in public contracting, asserting that the bank guarantee was enforceable and that a fresh tender process, or alternate award, was appropriate. They argued for strict application of contractual and statutory provisions, resisting relief by way of correction or withdrawal after bid opening.
Explore This Legal Issue
Find relevant judgments and authoritative positions on the legal questions discussed here.
Cited Precedents (6)
| Case Name | Citation | Treatment | Explanation |
|---|---|---|---|
| West Bengal State Electricity Board v. Patel Engineering Company Limited and Others | [2001] 1 SCR 352 : (2001) 2 SCC 451 | Positive | Cited as the controlling authority for equitable relief in bid-mistake scenarios and for outlining the exceptions to Section 20 relief, including prompt action and reasonable care by the bidder. |
| M/s Omsairam Steels & Alloys Pvt. Ltd. v. Director of Mines and Geology, BBSR & Ors. | 2024 INSC 520 | Positive | Cited to illustrate that relief may be granted in equitable terms when a bidder promptly informs the authority after discovering a mistake, before contract enters, aligning with exceptions to general rule. |
| Coimbatore District Central Cooperative Bank v. Coimbatore District Central Cooperative Bank Employees Association and Another | [2007] 5 SCR 430 : (2007) 4 SCC 669 | Mentioned Only | Referenced in discussion of related principles but not adopted as the controlling rule in this case. |
| Moffett, H. and C. Co. v. Rochester | 178 U.S. 373 (1900) | Mentioned Only | Cited for comparative background on mistake/recovery before contract formation; not treated as controlling authority in the domestic judgment. |
| Hearne v. New England Marine Ins. Co. | 22 L. Ed. 395 | Mentioned Only | Cited for historical perspective on errors and relief; not treated as binding precedents in the decision. |
| Spina Asphalt Paving Excavating Contractors, Inc. v. Borough of Fairview | 304 NJ Super 425 | Mentioned Only | Referenced in context of bid-price error rectification discussions; not applied as binding precedent in the judgment. |
Apply This to My Facts
Share your situation and test whether this judgment governs, supports, or challenges your case.
In The Court Record
M/s ABCI Infrastructures Pvt. Ltd. v. Union of India and Others
Related Decisions & Precedents from Supreme Court of India (2025)
Krishna Devi @ Sabitri Devi (Rani) M/s S.R. Engineering Construction v. Union of India & Ors.
Krishna Devi @ Sabitri Devi (Rani) approaches the Supreme Court seeking pronouncement of judgment in terms of an arbitral award under Section 17 of the Arbitration Act, 1940. The appellant’s husband secured a favourable award on 31 May 2022 in a dispute over a Tezpur work contract. Although the award was not published due to outstanding arbitrator fees, a district court order dated 21 September 2022 directed the respondents to clear the balance and stated that once paid, the award would be furnished. The appellant filed a Section 17 application on 10 November 2022 seeking the court to pronounce judgment in terms of the award. The trial court and the Gauhati High Court held the application premature, because it was filed before the expiry of the 30-day objections window under Article 119(b) of the Limitation Act, calculated from 18 November 2022 (alleged formal notice). The Supreme Court, however, held that the start of limitation is not tied to a formal notice but to awareness of the award’s existence. It relied on earlier decisions establishing that Section 14(2) only requires awareness that an award exists; a court’s order directing payment of fees can constitute such notice. Consequently, the 30-day limitation expired by 20 October 2022, rendering the Section 17 application timely. The appeal is allowed, and directions are issued to dispose of the related matter expeditiously with no costs.
Saranga Anilkumar Aggarwal v. Bhavesh Dhirajlal Sheth & Ors.
This Civil Appeal concerns whether execution of penalty orders imposed by the National Consumer Disputes Redressal Commission (NCDRC) can be stayed under the interim moratorium provisions of Section 96 of the Insolvency and Bankruptcy Code, 2016 (IBC), while insolvency proceedings are pending under Section 95 of the IBC. The appellant, a real estate developer, sought a stay of 27 penalties levied for deficiency in service and delay in possession of residential units, arguing that an application under Section 95 of the IBC had triggered an interim moratorium. The NCDRC had rejected the stay, holding that consumer-claims and penalties are not “debts” within the moratorium’s ambit. The Supreme Court affirmed that the damages awarded in consumer disputes arise to compensate home-buyers and deter malpractice, and are not ordinary contractual debts susceptible to IBC restructuring; such damages fall within the category of “excluded debts” under Section 79(15) of the IBC, and their enforcement remains unaffected by insolvency proceedings. The Court emphasized the essential distinction between debt-recovery proceedings and regulatory/penal actions under consumer protection laws, rejected reliance on contrary authorities (notably Sheetal Gupta per incuriam), and held that criminal penalties under the CP Act do not automatically fall within the moratorium. The appeal was dismissed; the appellant was directed to comply with the NCDRC penalties within eight weeks.
Serious Fraud Investigation Office v. Aditya Sarda
This batch of sixteen interconnected criminal appeals arises from SFIO's complaint against multiple respondents including Aditya Sarda for serious economic offences under the Companies Act, 2013 and the IPC. The Special Court at Gurugram took cognizance of the offences and issued bailable warrants to the accused, who allegedly concealed themselves or otherwise obstructed the process. Non‑bailable warrants were issued, and some proclamations under CrPC Section 82 were initiated against certain respondents. The High Court granted anticipatory bail to several respondents, notwithstanding the cognizance, warrant proceedings, and proclamations, leading to a series of challenges before the Supreme Court. The Court emphasises that anticipatory bail is an extraordinary remedy not available as a routine in cases involving serious economic offences, and that the twin mandatory conditions in Section 212(6) of the Companies Act, 2013 must be considered: (i) Public Prosecutor must be given an opportunity to oppose; and (ii) where opposed, the court must be satisfied of reasonable grounds to believe the accused is not guilty and unlikely to commit an offence while on bail. It reasons that respondents who evade process by concealing themselves after cognizance and after non‑bailable warrants were issued should not receive anticipatory bail. Accordingly, the High Court orders granting anticipatory bail are set aside, and the respondents are directed to surrender within one week to the Special Court, with subsequent bail determinations to be made in accordance with law. The judgment reiterates that economic offences require a cautious, exception‑based approach to bail and underscores the importance of ensuring due process and the unobstructed progress of judicial proceedings.
K.S. Mehta v. M/s Morgan Securities and Credits Pvt. Ltd.
This is a Supreme Court decision under Criminal Appeal No. 1105 of 2025 arising from quashing under Section 482 CrPC of criminal proceedings instituted under Section 138 read with Section 141 of the Negotiable Instruments Act, 1881. The appellants, K.S. Mehta and Basant Kumar Goswami, were non-executive directors of M/s Blue Coast Hotels & Resorts Ltd., chosen to meet SEBI’s governance requirements (Clause 49 of Listing Agreement). They were not present at the 09.09.2002 board meeting that approved an Inter-Corporate Deposit (ICD) of ₹5 crores nor signatories to the ICD agreement or related instruments. Later, two cheques issued to discharge the debt were dishonored, leading to criminal proceedings against the directors. The High Court of Delhi dismissed petitions under Section 482 CrPC seeking quashing. The Supreme Court held that non-executive and independent directors cannot be fastened with vicarious liability under Section 141 NI Act unless the record demonstrates their direct involvement in the company’s affairs at the relevant time. Here, there was no evidence of their involvement, no signatory status, and mere attendance at board meetings cannot establish liability. The Court emphasized the need for specific averments showing the director was in charge of and responsible for the company’s conduct. Consequently, the proceedings against the appellants were quashed and the appeals allowed.