M/s ABCI Infrastructures Pvt. Ltd. v. Union of India and Others

Case / Petition Number:
Civil Appeal No. 2546 of 2025
Neutral Citation:[2025] 3 S.C.R. 128

Case Synopsis & Summary

This is a Civil Appeal arising from a bid for design and construction of two-lane twin tunnels at Shinkun La Pass in Himachal Pradesh, with an estimated project value of Rs. 15,04,64,00,000. The appellant, M/s ABCI Infrastructures Pvt. Ltd., was declared L-1 with a quoted price of Rs. 1,569, reportedly Rs. 1,569 crores, but the appellant contends the price appeared as Rs. 1,569 due to a system error. The appellant promptly informed BRO about the alleged mistake, but BRO insisted on requiring a detailed price analysis and ultimately proceeded to forfeit the bid security of Rs. 15.04 crores and encash the bank guarantee. The writ petition before the Himachal Pradesh High Court was dismissed. The Supreme Court examined whether the bid error could be treated under Section 20 of the Indian Contract Act, 1872, noting that the explanation to Section 20 excludes errors of value as a matter of fact. The Court recognized that while the error was self-evident, relief in equity for bid mistakes is available in certain circumstances, citing West Bengal State Electricity Board v Patel Engineering and other authorities. The Court held that the appellant was at fault for not adding zeros and that a practical approach should have been adopted. It directed the appellant to pay Rs. 1 crore to BRO, and upon payment, BRO was to return the bank guarantee within a week; the impugned judgment was set aside and the appeal allowed with no costs.

Precedent Explorer

Find Cases Like This

Explore other judgments dealing with similar legal situations, facts, or statutory provisions.

Case Details & Bench

Court
Supreme Court of India
Hon'ble Judges
  • Sanjiv Khanna
  • Sanjay Kumar
  • K.V. Viswanathan
Judgment Date
2025-02-14
Court Decision / Holding
The impugned judgment of the High Court is set aside. The Supreme Court allows the appeal. The appellant is directed to pay Rs. 1 crore to BRO; upon receipt, BRO shall return the original bank guarantee of Rs. 15.04 crores within one week. There would be no order as to costs. The contract is not reaffirmed; instead, the remedy involves financial adjustment and return of security, with the bid process subsequently continuing via a fresh tender.
Final Disposition
Appeal allowed. No costs. Appellant to pay Rs. 1 crore to BRO and receive return of Rs. 15.04 crores bank guarantee within one week after payment; impugned judgment set aside.

Parties to the Case

Appellants / Petitioners

  • M/s ABCI Infrastructures Pvt. Ltd.

Respondents

  • Union of India
  • Border Road Organisation

Legal Representation & Advocates

Counsels for Petitioners

  • • Mukul Rohatgi
  • • Gaurav Khanna
  • • Ms. Natasha Sahrawat
  • • Ms. Deepali Bhanot
  • • Gautam Barnwal
  • • Rudraksh Pandey
  • • Ms. Alisha Roy

Counsels for Respondents

  • • Ms. Archana Pathak Dave
  • • A.S.G.
  • • Dr. N. Visakamurthy
  • • Yashraj Singh Bundela
  • • Raman Yadav
  • • Hitarth Raja
  • • Udit Dedhiya
  • • Mukesh Kumar Maroria
  • • Sanjay Kapur
  • • Surya Prakash
  • • Arjun Bhatia
  • • Ms. Shubhra Kapur
  • • Ms. Mahima Kapur

Provisions of Law Cited

Indian Contract Act, 1872, Section 20 (and its Explanation)

Legal Doctrines & Maxims

  • Equitable relief in cases of mistake in bids on public contracts
  • Relief in equity for mistake (Section 20)
  • Proportionality doctrine in judicial review
  • Self-evident / patent error in bid price
  • Minds of the parties having not met (when contract not formed)
  • Rectification/withdrawal before contract as recognized in relevant precedent

Submissions & Arguments

Contentions of Appellants / Petitioners

The appellants argued that the Rs.1,569 crore figure was a patent and self-evident error, likely a system glitch or typographical mistake, and was discovered on 24.08.2023 after bids opened. They assert prompt notice to withdraw and seek relief in equity under Section 20 of the Indian Contract Act, contending that a practical, corrective approach should have been adopted by BRO rather than forfeiture of bid security. They emphasize that delays were not solely attributable to the appellant and that the error was addressed promptly; a lower-cost, re-tendered outcome later occurred. They contend that the bank guarantee should be returned and that waiver of forfeiture would uphold transparency and fairness in bidding, avoiding unjust enrichment or punitive results for an obvious, clerical error.

Contentions of Respondents

The respondents argued that the quoted Rs.1,569 breached the contract’s scale, being unrealistically low for a project exceeding Rs.1,500 crore. They maintained that the error was not a mere misprint but a significant self-evident mistake that could not be corrected after bids, and that the appellant forfeited the bid security due to delay and non-compliance. They relied on ongoing procurement rules and the necessity to preserve transparency and accountability in public contracting, asserting that the bank guarantee was enforceable and that a fresh tender process, or alternate award, was appropriate. They argued for strict application of contractual and statutory provisions, resisting relief by way of correction or withdrawal after bid opening.

Legal Doctrine & Issue Explorer

Explore This Legal Issue

Find relevant judgments and authoritative positions on the legal questions discussed here.

Cited Precedents (6)

Case NameCitationTreatmentExplanation
West Bengal State Electricity Board v. Patel Engineering Company Limited and Others[2001] 1 SCR 352 : (2001) 2 SCC 451PositiveCited as the controlling authority for equitable relief in bid-mistake scenarios and for outlining the exceptions to Section 20 relief, including prompt action and reasonable care by the bidder.
M/s Omsairam Steels & Alloys Pvt. Ltd. v. Director of Mines and Geology, BBSR & Ors.2024 INSC 520PositiveCited to illustrate that relief may be granted in equitable terms when a bidder promptly informs the authority after discovering a mistake, before contract enters, aligning with exceptions to general rule.
Coimbatore District Central Cooperative Bank v. Coimbatore District Central Cooperative Bank Employees Association and Another[2007] 5 SCR 430 : (2007) 4 SCC 669Mentioned OnlyReferenced in discussion of related principles but not adopted as the controlling rule in this case.
Moffett, H. and C. Co. v. Rochester178 U.S. 373 (1900)Mentioned OnlyCited for comparative background on mistake/recovery before contract formation; not treated as controlling authority in the domestic judgment.
Hearne v. New England Marine Ins. Co.22 L. Ed. 395Mentioned OnlyCited for historical perspective on errors and relief; not treated as binding precedents in the decision.
Spina Asphalt Paving Excavating Contractors, Inc. v. Borough of Fairview304 NJ Super 425Mentioned OnlyReferenced in context of bid-price error rectification discussions; not applied as binding precedent in the judgment.
Case Applicability Diagnostic

Apply This to My Facts

Share your situation and test whether this judgment governs, supports, or challenges your case.

Official Judgment Record
•3,116 words•~15 min read

In The Court Record

M/s ABCI Infrastructures Pvt. Ltd. v. Union of India and Others

[2025] 3 S.C.R. 128 : 2025 INSC 215 # **M/s ABCI Infrastructures Pvt. Ltd.** ## **v.** # **Union of India and Others** (Civil Appeal No. 2546 of 2025) 14 February 2025 # **[Sanjiv Khanna,* CJI, Sanjay Kumar and K.V. Viswanathan, JJ.]** ## **Issue for Consideration** Whether BRO-Border Road Organisation was justified in accepting the bid of Rs.1,569/-, and on the failure of the appellant-L1 bidder to execute the agreement asking for forfeiture vide encashment of bank guarantee of Rs.15,04,64,000/-. ## **Headnotes[†]** **Contract Act, 1872 – s.20 – Mistake of fact – Tender dispute – Forfeiture of bank guarantee/bid security on default – Respondent no.2- Border Road Organisation invited bids for the construction of tunnels and appellant ranked as L-1 bidder – When financial bids opened, the appellants discovered their mistake that instead of appellant’s bid price of Rs.1569 Crores, the quoted amount appeared to be just Rs.1569/- – Next day, the appellant informed the authorities regarding the mistake but respondent no.2 called upon the appellant to justify the quoted amount of Rs.1569/- – Respondent no.2, stating that the appellant had been declared a defaulter, and their bid security was to be forfeited, asked the appellant’s bank to encash the bank guarantee and remit Rs.15,04,64,000 to respondent no.2 – Writ petition by the appellant – Dismissed by the High Court – Correctness:** **Held:** As per explanation to s.20, an erroneous opinion as to the value of the thing which forms the subject matter of an agreement is not deemed to be a mistake as a matter of fact – Instant case does not fall under any exception to the general principle on a person seeking relief in equity on account of mistake, for the error or mistake in quoting a price of Rs.1,569/- is self-evident – Contract for an * Author [2025] 3 S.C.R.  129 ## **M/s ABCI Infrastructures Pvt. Ltd. v. Union of India and Others** estimated value of more than Rs.1,500 crores requiring construction of roads and tunnels in a hilly terrain can never be executed for a mere Rs.1,569/- – Appellant was at fault and had made the mistake, of having failed to add the required zeros in the financial bid – Plea of a system glitch cannot be accepted, as others had successfully uploaded their bids without problem – Claim of BRO that delay was entirely due to the appellant’s mistake is flawed, ignoring its own lapses – Mistakes, including by authorities, to be resolved through corrective steps – Practical approach could have avoided the delay, which was caused by BRO’s refusal to acknowledge appellant’s genuine error and unwarranted cancellation of the bid – Alleged two-month delay by appellant is incorrect – Appellant promptly acknowledged the mistake – Appellant directed to pay Rs.1 crore to BRO, as a consequence of their error – Upon receiving this payment, BRO to return the appellant’s original bank guarantee or demand draft of Rs.15.04 crores – Impugned judgment set aside. [Paras 5, 10, 13-17] ## **Case Law Cited** _West Bengal State Electricity Board v. Patel Engineering Company Limited and Others_ **[2001] 1 SCR 352 : (2001) 2 SCC 451;** _M/s Omsairam Steels & Alloys Pvt. Ltd. v. Director of Mines and Geology, BBSR & Ors.,_ **2024 INSC 520;** _Coimbatore District Central Cooperative Bank v. Coimbatore District Central Cooperative Bank Employees Association and Another_ **[2007] 5 SCR 430 : (2007) 4 SCC 669 – referred to.** _Moffett, H. and C. Co. v. Rochester,_ **178 U.S. 373 (1900);** _Hearne v. New England Marine Ins. Co.,_ **22 L. Ed. 395;** _Spina Asphalt Paving Excavating Contractors, Inc. v. Borough of Fairview,_ **304 NJ Super 425 – referred to.** ## **List of Acts** Contract Act, 1872. ## **List of Keywords** Tenders; Mistake of fact; Delay; Online technical and financial bids; Bank guarantee; System error; Typographical mistake; Patent error; Forfeiture of bid security; Bid specifications; Relief in equity; Defaulter of bid; Cancellation of bid. [2025] 3 S.C.R. 130 ## **Digital Supreme Court Reports** ## **Case Arising From** CIVIL APPELLATE JURISDICTION: Civil Appeal No. 2546 of 2025 From the Judgment and Order dated 07.10.2023 of the High Court of Himachal Pradesh at Shimla in CWP No. 6658 of 2023 ## **Appearances for Parties** Mukul Rohatgi, Sr. Adv., Gaurav Khanna, Ms. Natasha Sahrawat, Ms. Deepali Bhanot, Gautam Barnwal, Rudraksh Pandey, Ms. Alisha Roy, Advs. for the Appellant. Ms. Archana Pathak Dave, A.S.G., Dr. N. Visakamurthy, Yashraj Singh Bundela, Raman Yadav, Hitarth Raja, Udit Dedhiya, Mukesh Kumar Maroria, Sanjay Kapur, Surya Prakash, Arjun Bhatia, Ms. Shubhra Kapur, Ms. Mahima Kapur, Advs. for the Respondents. ## **Judgment / Order of the Supreme Court** ## **Judgment** ## **Sanjiv Khanna, CJI** Leave granted. 2. This is an avoidable litigation. No doubt, there was a mistake on the part of the Appellant – M/s ABCI Infrastructure Private Limited, _albeit,_ instead of taking a pragmatic approach, Respondent No. 2 - Border Road Organisation[1] under the Ministry of Defence, Union of India, adopted an obdurate and overly legalistic stance, causing a delay in the project’s execution. 3. We begin by briefly discussing the facts of the case: - On 23.02.2023, BRO invited bids for the design and construction of two-lane twin tunnels, approximately 4.1 kilometres long, at Shinkun La Pass, including civil, electrical, and mechanical work, with approaches connecting the Darcha-Padam Highway to NHDL specifications in Himachal Pradesh and Ladakh. The estimated cost of the project was Rs.15,04,64,00,000/- 1 Hereinafter, “BRO.” [2025] 3 S.C.R.  131 ## **M/s ABCI Infrastructures Pvt. Ltd. v. Union of India and Others** (Rs. 1,504.64 crores). The project was to be completed within 48 months. The bid security amount was Rs.15,04,64,000/(Rs. 15.04 crores) - Ten bidders, including the Appellant, had submitted their online Technical and Financial Bids on 03.06.2023. The Appellant, like others, had furnished a bank guarantee of Rs.15,04,64,000/-. - On 05.06.2023, technical bids were opened and seven bidders, including the Appellant, were declared technically qualified. - On 24.08.2023, the financial bids of seven bidders, including the Appellant, were opened and the results were declared. - The Appellant was ranked as L-1 bidder, with the bid price of Rs.1,569/- (Rupees One thousand five hundred and sixty-nine only). According to the Appellant, they had quoted a bid price of Rs.1,569 crores. However, due to what they claim was a system error, the quoted amount appeared as just Rs.1,569. - The Appellant claims that they discovered the mistake on 24.08.2023 when the financial bids were opened and announced, and therefore, on the next day, 25.08.2023, they informed the authorities that their actual bid was Rs.1,569 crores, not Rs.1,569. They attributed the error to a typographical mistake or a critical technical issue with the server. While we would not accept the plea of system error, the figure quoted was clearly unrealistic, a patent error and a mistake given the scale and nature of the work tendered. Though the mistake was baldfaced, what followed is incomprehensible, with BRO, insisting on accepting the bid, in spite of letters from the Appellant wanting to withdraw from the tender. - BRO, guided by the Evaluation Committee, instead of accepting the obvious, _vide_ letter dated 26.08.2023, called upon the Appellant to justify the quoted amount of Rs.1,569 by providing a detailed price analysis, including the scope of work, completion schedule, risk allocation, safety requirements, and proof of capability to complete the project, by 31.08.2023. - On 30.08.2023, the Appellant reiterated that their intended bid was Rs.1,569 crores, not Rs.1,569, attributing the error to a technical or typographical mistake. [2025] 3 S.C.R. 132 ## **Digital Supreme Court Reports** - On 07.09.2023, the Appellant sent another letter stating they should not be considered the L1 bidder, and the bank guarantee of Rs.15,04,64,000 may be returned to them without encashment. - On 12.09.2023, the Appellant again wrote emphasizing that the bid was an error and that the bid security should not be forfeited. - _Vide_ letter 16.09.2023, BRO, unmoved, wrote to the Appellant’s bank, the State Bank of India, stating that the Appellant had been declared a defaulter, and their bid security was to be forfeited. The bank was asked to encash the bank guarantee and remit Rs.15,04,64,000 to BRO. - The Appellant filed a writ petition before the High Court of Himachal Pradesh at Shimla, which stands dismissed by the impugned judgment dated 07.10.2023. 4. The short question before us is whether BRO was justified in accepting the bid of Rs.1,569, and on the failure of the Appellant to execute the agreement asking for forfeiture _vide_ encashment of bank guarantee of Rs.15,04,64,000. 5. A mistake may be unilateral or mutual, but it is always unintentional. If it is intentional, it ceases to be a mistake. Mistakes or errors, though avoidable, are committed inadvertently. They have varied consequences in law. As per Section 20 of the Indian Contract Act, 1872[2] whereby both parties to an agreement are under a mistake as to matter of fact essential to an agreement, the agreement is void. The explanation to Section 20 says that an erroneous opinion as to the value of the thing which forms the subject matter of an agreement is not deemed to be a mistake as a matter of fact. This will not be a case covered by Section 20 of the Contract Act. However, this is not the first time that this question has arisen either before this Court or Courts outside of India. In _**West Bengal State Electricity Board**_ v. _**Patel Engineering Company Limited and Others[3]**_ , this Court referred to paragraph 84 of _American Jurisprudence_ (2[nd] Edition, Volume 64 at page 944), which reads: > 2 Hereinafter, “Contract Act.” > 3 (2001) 2 SCC 451 [2025] 3 S.C.R.  133 ## **M/s ABCI Infrastructures Pvt. Ltd. v. Union of India and Others** “As a general rule, equitable relief will be granted to a bidder for a public contract where he has made a material mistake of fact in the bid which he submitted, and where, upon the discovery of that mistake, he acts promptly in informing the public authorities and requesting withdrawal of his bid or opportunity to rectify his mistake particularly when he does so before any formal contract is entered into.” 6. Thereafter, reference was made to two decisions of the Supreme Court of the United States in _**Moffett, H. and C. Co.**_ v. _**Rochester[4]**_ and _**Hearne**_ v. _**New England Marine Ins. Co.**_ **[5]** wherein it is observed that where the mistake is apparent and the party promptly informs the other as soon as it is discovered but before entering into a contract, equitable orders may be passed. However, the mistake should be clear, explicit, and undisputed. Further, a mistake on one side may be a ground for rescinding but not for reforming a contract where the minds of the parties have not met, yet there is no contract and hence none to be rectified. Relief may not be granted where it is inequitable. While accepting this legal position, this Court in _**West Bengal State Electricity Board**_ (supra) has propounded the following exceptions to the general principle on a person seeking relief in equity on account of mistake: “ **27.** …….. (1)Where the mistake might have been avoided by the exercise of ordinary care and diligence on the part of the bidder; but where the offeree of the bid has or is deemed to have knowledge of the mistake, he cannot be permitted to take advantage of such a mistake. (2) Where the bidder on discovery of the mistake fails to act promptly in informing to the authority concerned and request for rectification, withdrawal or cancellation of bid on the ground of clerical mistake is not made before opening of all the bids. (3) Where the bidder fails to follow the rules and regulations set forth in the advertisement for bids as to the time when > 4 178 U.S. 373 (1900) > 5 22 L. Ed. 395 [2025] 3 S.C.R. 134 ## **Digital Supreme Court Reports** bidders may withdraw their offer; however where the mistake is discovered after opening of bids, the bidder may be permitted to withdraw the bid.” 7. This judgment also refers to a decision of the Superior Court of New Jersey in _**Spina Asphalt Paving Excavating Contractors, Inc.**_ v. _**Borough of Fairview**_ .[6] The said case is related to the rectification of mistakes in the bid specifications. Relief granted in the said case was upheld by the Superior Court with the caution that generally an error in the statement of a price would not be treated as immaterial and it is only when the case of error was patent and the true intent of the bidder obvious that such an error might be disregarded. 8. In _**West Bengal State Electricity Board**_ (supra), the private party, the bidder did not succeed for several reasons, including the factum that the error was not obvious and self-evident. Further, the correction of such mistakes after one and a half months after the opening of the bids would have violated the express clauses relating to the computation of the bid amount. Thus, waiver of the rule or conditions in favour of the one bidder would have created unjustifiable doubts in the minds of others impairing the rule of transparency and fairness and providing room for manipulation for awarding contracts. 9. The decision in _**West Bengal State Electricity Board**_ (supra) was referred to and followed where a relief to the bidder was apparent before this Court in _**M/s Omsairam Steels & Alloys Pvt. Ltd.**_ **v.** _**Director of Mines and Geology, BBSR & Ors**_ .[7] This decision observes that while the Court must exercise a lot of restraint in exercising the power of judicial review in contractual commercial matters, the doctrine of proportionality nevertheless applies when the error or mistake is writ large and equity merits the grant of some relief. Reference was made to the decision in _**Coimbatore**_ _**District Central Cooperative Bank**_ v. _**Coimbatore District Central Cooperative Bank Employees Association and Another[8]**_ where discussing the question of proportionality or punishment imposed on the striking workmen it is observed: > 6 304 NJ Super 425 > 7 2024 INSC 520 > 8 (2007) 4 SCC 669 [2025] 3 S.C.R.  135 **M/s ABCI Infrastructures Pvt. Ltd. v. Union of India and Others** “ **18.** “Proportionality” is a principle where the court is concerned with the process, method or manner in which the decision-maker has ordered his priorities, reached a conclusion or arrived at a decision. The very essence of decision-making consists in the attribution of relative importance to the factors and considerations in the case. The doctrine of proportionality thus steps in focus true nature of exercise—the elaboration of a rule of permissible priorities. **19.** de Smith states that “proportionality” involves “balancing test” and “necessity test”. Whereas the former (balancing test) permits scrutiny of excessive onerous penalties or infringement of rights or interests and a manifest imbalance of relevant considerations, the latter (necessity test) requires infringement of human rights to the least restrictive alternative. [ _Judicial Review of Administrative Action_ (1995), pp. 601-05, para 13.085; _see also_ Wade & Forsyth: _Administrative Law_ (2005), p. 366.] **20.** In _Halsbury’s Laws of England_ (4th Edn.), Reissue, Vol. 1(1), pp. 144-45, para 78, it is stated: “The court will quash exercise of discretionary powers in which there is no reasonable relationship between the objective which is sought to be achieved and the means used to that end, or where punishments imposed by administrative bodies or inferior courts are wholly out of proportion to the relevant misconduct. The principle of proportionality is well established in European law, and will be applied by English courts where European law is enforceable in the domestic courts. The principle of proportionality is still at a stage of development in English law; lack of proportionality is not usually treated as a separate ground for review in English law, but is regarded as one indication of manifest unreasonableness.” [2025] 3 S.C.R. 136 ## **Digital Supreme Court Reports** Accordingly, in the said case the Appellant was directed to make a payment of Rs.3 crores within the stipulated period and on the said payment the security deposit in the form of a bank guarantee of over Rs.9 crores was directed to be refunded. 10. The present case does not fall under any exception, for the error or mistake in quoting a price of Rs.1,569/-, does not require any argument and cannot be debated as it is self-evident. A contract of this nature for an estimated value of more than Rs.1,500 crores spread over 48 months requiring construction of roads and tunnels of the length of more than 4 kilometres in a hilly terrain can never be executed for a mere Rs.1,569/-. 11. At the same time, we agree with BRO, that the Appellant was at fault and had made the mistake, of having failed to add the required zeros in the financial bid. The plea of a system glitch should not be accepted, as others had successfully uploaded their bids without a problem. 12. BRO justified encashing the bank guarantee by citing delays caused by issuing a second notice inviting bids. This claim is baseless, as BRO was aware of the Rs.1,569/- error. Instead of declaring the bid _non est_ due to the clear mistake, BRO asked the appellant to justify the bid, cancelled the notice, declared the Appellant a defaulter, invoked the bank guarantee, and issued a fresh notice inviting bids. 13. Thus, BRO’s claim that the delay was entirely due to the Appellant’s mistake is flawed, ignoring BRO’s own lapses. Mistakes, including by authorities, should be resolved through corrective steps. A practical approach could have avoided the delay, which was caused by BRO’s refusal to acknowledge the Appellant’s genuine error and the unwarranted cancellation of the bid. 14. The alleged two-month delay by the Appellant is incorrect. The error, submitted on 03.06.2023, became apparent only when financial bids were opened on 24.08.2023. The Appellant promptly acknowledged the mistake on 25.08.2023. 15. A fresh tender was issued, and financial bids opened on 09.01.2024 revealed the lowest bid of Rs.1,290 crores, lower than the earlier Rs.1,351 crores. Thus, while delayed, the contract was awarded at a lower cost. [2025] 3 S.C.R.  137 ## **M/s ABCI Infrastructures Pvt. Ltd. v. Union of India and Others** 16. In view of the aforesaid discussion, we direct the Appellant to pay Rs.1 crore to BRO, as a consequence of their error. Upon receiving this payment, BRO shall return the Appellant’s original bank guarantee or demand draft of Rs.15.04 crores within one week. 17. The impugned judgment is set aside, and the appeal is allowed in the aforesaid terms. There would be no order as to costs. _Result of the case:_ Appeal allowed. - _†Headnotes prepared by:_ Nidhi Jain
End of Judgment Record
Browse All Supreme Court of India (2025) Decisions
2025-01-03

Krishna Devi @ Sabitri Devi (Rani) M/s S.R. Engineering Construction v. Union of India & Ors.

Krishna Devi @ Sabitri Devi (Rani) approaches the Supreme Court seeking pronouncement of judgment in terms of an arbitral award under Section 17 of the Arbitration Act, 1940. The appellant’s husband secured a favourable award on 31 May 2022 in a dispute over a Tezpur work contract. Although the award was not published due to outstanding arbitrator fees, a district court order dated 21 September 2022 directed the respondents to clear the balance and stated that once paid, the award would be furnished. The appellant filed a Section 17 application on 10 November 2022 seeking the court to pronounce judgment in terms of the award. The trial court and the Gauhati High Court held the application premature, because it was filed before the expiry of the 30-day objections window under Article 119(b) of the Limitation Act, calculated from 18 November 2022 (alleged formal notice). The Supreme Court, however, held that the start of limitation is not tied to a formal notice but to awareness of the award’s existence. It relied on earlier decisions establishing that Section 14(2) only requires awareness that an award exists; a court’s order directing payment of fees can constitute such notice. Consequently, the 30-day limitation expired by 20 October 2022, rendering the Section 17 application timely. The appeal is allowed, and directions are issued to dispose of the related matter expeditiously with no costs.

2025-03-04

Saranga Anilkumar Aggarwal v. Bhavesh Dhirajlal Sheth & Ors.

This Civil Appeal concerns whether execution of penalty orders imposed by the National Consumer Disputes Redressal Commission (NCDRC) can be stayed under the interim moratorium provisions of Section 96 of the Insolvency and Bankruptcy Code, 2016 (IBC), while insolvency proceedings are pending under Section 95 of the IBC. The appellant, a real estate developer, sought a stay of 27 penalties levied for deficiency in service and delay in possession of residential units, arguing that an application under Section 95 of the IBC had triggered an interim moratorium. The NCDRC had rejected the stay, holding that consumer-claims and penalties are not “debts” within the moratorium’s ambit. The Supreme Court affirmed that the damages awarded in consumer disputes arise to compensate home-buyers and deter malpractice, and are not ordinary contractual debts susceptible to IBC restructuring; such damages fall within the category of “excluded debts” under Section 79(15) of the IBC, and their enforcement remains unaffected by insolvency proceedings. The Court emphasized the essential distinction between debt-recovery proceedings and regulatory/penal actions under consumer protection laws, rejected reliance on contrary authorities (notably Sheetal Gupta per incuriam), and held that criminal penalties under the CP Act do not automatically fall within the moratorium. The appeal was dismissed; the appellant was directed to comply with the NCDRC penalties within eight weeks.

2025-04-09

Serious Fraud Investigation Office v. Aditya Sarda

This batch of sixteen interconnected criminal appeals arises from SFIO's complaint against multiple respondents including Aditya Sarda for serious economic offences under the Companies Act, 2013 and the IPC. The Special Court at Gurugram took cognizance of the offences and issued bailable warrants to the accused, who allegedly concealed themselves or otherwise obstructed the process. Non‑bailable warrants were issued, and some proclamations under CrPC Section 82 were initiated against certain respondents. The High Court granted anticipatory bail to several respondents, notwithstanding the cognizance, warrant proceedings, and proclamations, leading to a series of challenges before the Supreme Court. The Court emphasises that anticipatory bail is an extraordinary remedy not available as a routine in cases involving serious economic offences, and that the twin mandatory conditions in Section 212(6) of the Companies Act, 2013 must be considered: (i) Public Prosecutor must be given an opportunity to oppose; and (ii) where opposed, the court must be satisfied of reasonable grounds to believe the accused is not guilty and unlikely to commit an offence while on bail. It reasons that respondents who evade process by concealing themselves after cognizance and after non‑bailable warrants were issued should not receive anticipatory bail. Accordingly, the High Court orders granting anticipatory bail are set aside, and the respondents are directed to surrender within one week to the Special Court, with subsequent bail determinations to be made in accordance with law. The judgment reiterates that economic offences require a cautious, exception‑based approach to bail and underscores the importance of ensuring due process and the unobstructed progress of judicial proceedings.

2025-03-04

K.S. Mehta v. M/s Morgan Securities and Credits Pvt. Ltd.

This is a Supreme Court decision under Criminal Appeal No. 1105 of 2025 arising from quashing under Section 482 CrPC of criminal proceedings instituted under Section 138 read with Section 141 of the Negotiable Instruments Act, 1881. The appellants, K.S. Mehta and Basant Kumar Goswami, were non-executive directors of M/s Blue Coast Hotels & Resorts Ltd., chosen to meet SEBI’s governance requirements (Clause 49 of Listing Agreement). They were not present at the 09.09.2002 board meeting that approved an Inter-Corporate Deposit (ICD) of ₹5 crores nor signatories to the ICD agreement or related instruments. Later, two cheques issued to discharge the debt were dishonored, leading to criminal proceedings against the directors. The High Court of Delhi dismissed petitions under Section 482 CrPC seeking quashing. The Supreme Court held that non-executive and independent directors cannot be fastened with vicarious liability under Section 141 NI Act unless the record demonstrates their direct involvement in the company’s affairs at the relevant time. Here, there was no evidence of their involvement, no signatory status, and mere attendance at board meetings cannot establish liability. The Court emphasized the need for specific averments showing the director was in charge of and responsible for the company’s conduct. Consequently, the proceedings against the appellants were quashed and the appeals allowed.