Tenetowl LogoTenetowl
High Court of KeralaKerala High Court · 2009Division BenchAppeals dismissed

Writ Appeals Nos. 2446, 2447, 2453 & 2475 of 2008 (against WPC 9735/2008)

Case / Petition Number:
WA Nos. 2446, 2447, 2453 & 2475 of 2008

Case Synopsis & Summary

These writ appeals challenge a common judgment of a learned single judge repelling the challenge to land acquisition proceedings for the Infopark project under the Fast Track Project. The notification under Section 4(1) of the Land Acquisition Act was issued for 138 acres in Ernakulam district to acquire land for Infopark's expansion. The petitions contend that the officer issuing the Section 4(1) notification was not the Collector as defined, and therefore the proceedings are invalid, since the Collector must publish a notification under the Act. The respondents rely on Annexure-1 notification dated 21 August 1989, which authorised the Special Tahsildar (Land Acquisition) Cochin Refineries Limited to perform the functions of a Collector within Ernakulam district and to issue Section 4(1) notifications for acquisitions in line with government policy. The court held that the Special Tahsildar, empowered by the 1989 notification and the dedicated Acquisition Unit, qualifies as the 'Collector' under Section 3(c) of the Act (and by implication the Government notification). The decision was heavily supported by Abdul Hussain Tayabali v. State of Gujarat and others, where the scope of Section 3(c) was discussed. The court ruled that public interests justify a liberal approach and declined to interfere with the notification; the appeals were dismissed. The judgment confirms that the Infopark land acquisition proceeds in pursuance of state policy and that the challenged notification stands valid.

Precedent Explorer

Find Cases Like This

Explore other judgments dealing with similar legal situations, facts, or statutory provisions.

Case Details & Bench

Court
High Court of Kerala
Hon'ble Judges
  • J.B. Koshy, Acting Chief Justice
  • P.R. Ramachandra Menon, J.
Judgment Date
2009-01-06
Court Decision / Holding
The impugned judgment dismissing the writ appeals is upheld. The Special Tahsildar (LA) Cochin Refineries Limited, by virtue of the 1989 notification and the established Acquisition Unit, is the ‘Collector’ for purposes of Section 3(c) of the Land Acquisition Act, and thus validly issued the Section 4(1) notification. The appeals are dismissed; the lands for Infopark expansion proceed under the government policy. The court also cites Abdul Hussain Tayabali v. State of Gujarat for supporting the interpretation of the Collector’s scope and endorses a liberal approach in public interest matters.
Final Disposition
Appeals dismissed

Parties to the Case

Appellants / Petitioners

  • E.A. Aboobacker
  • E.A. Nizamuddin
  • K.A. Abdul Kalam

Respondents

  • State of Kerala
  • Land Revenue Commissioner, Kerala
  • District Collector, Ernakulam
  • Special Tahsildar (LA) Kochi Refineries Limited
  • Secretary Information Technology Department, Thiruvananthapuram
  • M/S Infopark
  • Maleril Poulose

Legal Representation & Advocates

Counsels for Petitioners

  • • Sri S. Easwaran
  • • Sri Shinu J. Pillai

Counsels for Respondents

  • • Sri M.P. Sreekrishnan, Government Pleader (for R1-R5)
  • • Sri P.A. Ahammad, SC (for R6)

Provisions of Law Cited

Section 4(1) of the Land Acquisition Act, 1894Section 3(c) of the Land Acquisition Act, 1894Section 15 of the General Clauses Act

Legal Doctrines & Maxims

  • Public interest allows a liberal interpretation when powers are involved.
  • The definition of 'Collector' under Section 3(c) includes officers specially appointed to perform Collector functions (as per LAA, 1894).
  • Abdul Hussain Tayabali v. State of Gujarat and others — interpretation of Section 3(c) and validity of Special Tahsildar acting as Collector.

Submissions & Arguments

Contentions of Appellants / Petitioners

The appellants contended that the 4(1) notification could be issued only by the Collector as defined in the Act. Since the Exts. P1 and P2 notifications were issued by the Special Tahsildar (LA) Cochin Refineries Limited, who is not the Collector, the acquisition proceedings are void ab initio. They argued that the 1989 notification creating a Special Tahsildar unit and authorising him to act as Collector is not a valid basis to issue the Section 4(1) notification, and that the policy considerations do not override statutory requirements.

Contentions of Respondents

The respondents argued that Annexure-1 notification (21 August 1989) authorised the Special Tahsildar to perform Collector functions in Ernakulam district and to issue Section 4(1) notifications for acquisitions within his jurisdiction. They emphasised that the unit created for acquisition purposes remains in existence and that the Collector’s functions could be exercised by the Special Tahsildar in furtherance of government policy, thus validating Exts. P1 and P2.

Legal Doctrine & Issue Explorer

Explore This Legal Issue

Find relevant judgments and authoritative positions on the legal questions discussed here.

Cited Precedents (1)

Case NameCitationTreatmentExplanation
Abdul Hussain Tayabali v. State of Gujarat and othersAIR (55) 1968 Supreme Court 432PositiveThe Supreme Court held that the Special Tahsildar can act as Collector under Section 3(c) and that Section 15 of the General Clauses Act supports such interpretation; this supports the Kerala court’s conclusion in favor of the Special Tahsildar’s status as Collector in this case.
Case Applicability Diagnostic

Apply This to My Facts

Share your situation and test whether this judgment governs, supports, or challenges your case.

Official Judgment Record
•1,496 words•~7 min read

In The Court Record

Writ Appeals Nos. 2446, 2447, 2453 & 2475 of 2008 (against WPC 9735/2008)

## **IN THE HIGH COURT OF KERALA AT ERNAKULAM** **PRESENT :** ## **THE HON'BLE THE ACTING CHIEF JUSTICE MR.J.B.KOSHY** **&** **THE HONOURABLE MR. JUSTICE P.R.RAMACHANDRA MENON** **TUESDAY, THE 6TH JANUARY 2009 / 16TH POUSHA 1930** **WA.No. 2446 of 2008()** **--------------------AGAINST THE JUDGEMENT/ORDER IN WPC.9735/2008 Dated 25/11/2008** **....................** ## **APPELLANT(S): PETITIONERS:** **----------------------------------------------** **1. E.A.ABOOBACKER, ADVOCATE, ELAVAKKAT HOUSE, VAZHAKALA JUNCTION, KAKKANAD WEST PO, KOCHI 682 030.** ## **2. E.A.NIZAMUDDIN, ADVOCATE, ... DO..DO....** **3. K.A.ABDULKALAM, ELAVAKKAT HOUSE, ... DO....DO..** **BY ADV. SRI.S.EASWARAN SRI.SHINU J.PILLAI** ## **RESPONDENT(S): RESPONDENTS:** **-----------------------------------------------------** **1. STATE OF KERALA,REPRESENTED BY THE CHIEF SECRETARY, GOVERNMENT SECRETARIAT THIRUVANANTHAPURAM.** **2. THE LAND REVENUE COMMISSIONER ,KERALA, THIRUVANANTHAPURAM.** **3. THE DISTRICT COLLECTOR, ERNAKULAM AT CIVIL STATION, KAKKANAD.** **4. THE SPECIAL TAHSILDAR (LA) KOCHI REGINERIES LIMITED, NORTH FORT GATE, TRIPUNITHURA.** _Kss_ **...2/-** **....2.....** ## **W.A.NO.2446/2008** **5. SECRETARY** **INFORMATION TECHNOLOGY (A) DEPARTMENT THIRUVANANTHAPURAM.** **6. M/S. INFOPARK, PARK OFFICE, THAPSYA, KAKKANAD, KOCHI 682 030, REPRESENTED BY ITS CHIEF EXECUTIVE OFFICER.** **7. MALERIL POULOSE, S/O. VARKEY** **AGED 63 YEARS, MALERIL GALEELA HOUSE, BRAHMAPURAM P.O.,AMABALAMEDU 682 303, PUTHENCRUZ VILLAGE, KUNNATHUNADU TALUK.** **GOVERNMENT PLEADER SRI. M.P.SREEKRISHNAN FOR R1 TO R5 ADV. SRI. P.A.AHAMMED, SC FOR R6** **THIS WRIT APPEAL HAVING COME UP FOR ADMISSION ON 06/01/2009 ALONG WITH WA NO. 2447 OF 2008 AND CONNECTED CASES, THE COURT ON THE SAME DAY DELIVERED THE FOLLOWING:** _Kss_ ## **J.B. KOSHY, Ag. CHIEF JUSTICE & P.R. RAMACHANDRA MENON, J.** **........................................................................ W.A. Nos. 2446, 2447, 2453 & 2475 OF 2008 ......................................................................... Dated this the 6[th] January, 2009** ## **J U D G M E N T** ## **KOSHY, Ag. CJ. :** All these Writ Appeals are filed against the common judgment passed by the learned single Judge repelling the challenge made against the land acquisition proceedings for expansion of the Infopark. 2. Notification under section 4(1) of the Land Acquisition Act was issued for acquisition of 138 acres for the development of Infopark under the Fast Track Project. No doubt, establishment of Infopark is important for the development of the State. The only question before us is whether “the officer who issued the notification has power to issue Section 4(1) notification”. Exts. P1 and P2 public notices under section 4(1) are seen issued by the Special Tahsildar (LA), Cochin Refineries Limited, Ernakulam. It is contended that he is not the Collector as defined under the Land Acquisition Act and therefore, the entire acquisition proceedings are bad. According to the 6[th] respondent most of the lands covered under the notification were later purchased by the Government on the price fixed on negotiation. ## **W.A. Nos. 2446, 2447, 2453 & 2475 OF 2008** ## **2** It is also stated that though properties of 500 persons were acquired, only 18 have questioned the same on the above ground. Anyhow, since the petitioners have a legal ground,we have to consider it. 3. Section 4(1) of the Land Acquisition Act reads as follows: _“(1) Whenever it appears to the appropriate Government that land in any locality is needed or is likely to be needed for any public purpose or for a company a notification to that effect shall be published in the Official Gazette and in two daily newspapers circulating in that locality of which at least one shall be in the regional language, and the Collector shall cause public notice of the substance of such notification to be given at convenient places in the said locality the last of the dates of such publication and the giving of such public notice, being hereinafter referred to as the date of publication of the notification. ” (emphasis is supplied)._ Section clearly provides that before taking any steps for acquisition, preliminary notice under Section 4(1) has to be issued by the Collector. Section 3(c) of the Act defines the term ' Collector' which reads as follows: _“The expression “Collector” means the Collector of a district, and includes a Deputy_ **3** ## **W.A. Nos. 2446, 2447, 2453 & 2475 OF 2008** _Commissioner and any officer specially appointed by the appropriate Government to perform the functions of a Collector under this Act.”_ 4. Learned Government Pleader points out that by Annexure-1 notification dated 21[st] August, 1989 (Kerala Gazette dated 17[th] October, 1989) Government authorised the Special Tahsildar (Land Acquisition) Cochin Refineries Limited, Ernakulam,Vytilla, Cochin-19 to perform the functions of a Collector under the said Act within the area of Ernakulam district. The lands covered under Exts. P1 and P2 are situated in Ernakulam. It is the case of the petitioners that he is authorised as a collector for acquisition of 320 acres of land for expansion of the Cochin Refineries Limited and not for any other purpose and therefore he cannot be relied on 5. Since the matter centres round the scope of the Notification dated 21[st] August, 1989, we extract the notification including its explanatory note: _“S.R.O.No.1743/89:- In exercise of the powers conferred by clause © of section 3 of the Land Acquisition Act, 1894 (Central Act 1 of 1894),the Government of Kerala hereby appoint the_ **W.A. Nos. 2446, 2447, 2453 & 2475 OF 2008** ## **4** _Special Tahsildar (Land Acquisition ) Cochin Refineries Limited, Ernakulam,Vytilla , Cochin-19 to perfom the functions of a Collector under the said Act within the area of Ernakulam District and under sub section (2) of section 4 of the said act, authorize him, his servants and workmen to exercise the powers conferred by the said subsection in respect of any land within his jurisdiction for the Acquisition of which a notification under subsection (1) of section 4 has been published._ _xx xx xx_ ## _Explanatory Note_ _(This does not form part of the notification that is intended to indicate its general purport.)_ _As per the Government order (MS )No. 71/89/ID dated 25.04.1989 Government have sanctioned the creation of a new special land acquisition Unit with 30 staff for the acquisition of 320 acres of land for the expansion of Cochin Refineries Limited Ambalamugal. In order to perform the functions of a ' collector' under the Land Acquisition Act, the Land Acquisition Officer has to be authorised under section 3(c) of the Land_ **W.A. Nos. 2446, 2447, 2453 & 2475 OF 2008** **5** _Acquisition Act. Hence the Notification. ”_ 6. The said notification shows that the Special Tahsildar,(Land Acquisition) Cochin Refineries Limited is appointed to perform the functions of a Collector under the Land Acquisition Act within the area of Ernakulam district. It is true that at the time of issuance of the said notification, 4(1) notification has already been issued for acquisition of 320 acres of land for the expansion of Cochin Refineries Limited as evidenced from the explanatory note. It is also evidenced from the explanatory note that for the said purpose 30 staff have been appointed. Even after the acquisition of the land for expansion of the Cochin Refineries Limited that Unit exists. We are of the view that even though the main and immediate purpose for issuance of the notification dated 21[st] August,1989 was acquisition of land for expansion of Cochin Refineries Limited, in view of the establishment of the complete Unit for Acquisition purpose, the Special Tahsildar (Land Acquisition) Cochin Refineries Limited is entrusted with specific powers to perform the functions of a Collector under the Land Acquisition Act within the area of Ernakulam district. The said notification still authorises the Special Tahsildar to issue notification under section 4 (1). In our view, when public interests are concerned a liberal view ## **W.A. Nos. 2446, 2447, 2453 & 2475 OF 2008** ## **6** has to be taken and when majority of the lands were acquired or acquisition is in progress, the said progress cannot be stopped on any cryptic hyper technical ground. It is also argued that the Collector has not applied his mind. It was the Government policy to acquire land for the Info Park and the Collector was authorised to issue notification for implementing the Government policy. In that view of the matter, we cannot set aside the notification because the decision to acquire the land was not originated by the Collector. Here notification dated 21[st] August 1989 specifically authorised the Special Tahsildar (LA ) Cochin Refineries Limited, who issued Exts. P1 and P2, to act and perform the functions of Collector in Ernakulam district for land acquisition purpose. Hence he is the 'Collector' in view of the definition of Collector under Section 3(c). 7. The decision of the Supreme Court in _**Abdul Hussain Tayabali v. State of Gujarat and others**_ **( AIR (55) 1968 Supreme Court 432)** wherein the scope of Section 3(c) of the Land Acquisition Act was dealt with, also affirms the view that the Special Tahsildar is the Collector in view of Section 3 (c) of the Land Acquisition Act and Section 15 of the General Clauses Act. In the above circumstances, on the grounds pleaded by the ## **W.A. Nos. 2446, 2447, 2453 & 2475 OF 2008** **7** appellants, the impugned judgment cannot be interfered with. Accordingly, the appeals are dismissed. **J.B. KOSHY, ACTING CHIEF JUSTICE.** **P.R. RAMACHANDRA MENON, JUDGE.** lk
End of Judgment Record
Browse All High Court of Kerala (2009) Decisions
2009-06-26

Nishana Mol.N v Alappuzha Municipality & Secretary, Alappuzha Municipality

This writ petition concerns the registration of a marriage under the Kerala Registration of Marriages (Common) Rules, 2008 (Common Rules). The petitioner Nishana Mol.N, whose marriage was solemnized on 8 March 2009, sought registration of her marriage by the Local Registrar. Her husband was abroad, and she submitted Form No. 1 along with documents; however, the Local Registrar demanded the presence of both spouses for registration, a point contested by the petitioner. The court recalls the apex court’s directions in Seema v. Ashwani Kumar (2006) to frame rules ensuring compulsory registration to protect women and provide evidence of marriage, while noting that registration under the Rules does not itself create a marriage but evidences one solemnized otherwise. The Rules specify that registration is mandatory for marriages solemnized within the state, with various procedural requirements (Rules 5, 6, 9, 10, 11, 13, 16, 17) and mechanisms for correction, appeal, and re-registration. The court clarifies that the presence of both parties is not ordinarily required; the registrar may require appearance only in cases where there is reasonable doubt about identity, and even then as an exception rather than a rule. Ultimately, the court directs that registration and certificate issuance be completed within one month from copy of the judgment, without insisting on joint appearance, provided the memorandum is in order.

2009-07-27

Abdul Majeed Kalathil v. District Collector, Malappuram & Others

This batch of writ petitions concerns the constitutional validity of Section 17 of the Kerala Anti-Social Activities (Prevention) Act, 2007, and the power of District Magistrates to confiscate vehicles used in anti-social activities. The petitions challenge the absence of a substantive prohibition against using vehicles for anti-social activities and the lack of a defined procedure for confiscation or an appellate remedy. In W.P.C. No. 9925 of 2009 (the lead case), Abdul Majeed Kalathil contends that his goods carriage KL 11-B/6651 was seized by the Sub Inspector of Pandikkad Police and reported to the District Collector, Exts.P1–P2. The court scrutinizes Section 17's scope, defining anti-social activity (Section 2(a)) and whether the District Collector’s power to confiscate is constitutionally tenable. It finds Section 17 to be vague and violative of Articles 14, 19(1)(g) and 21, as it rests on subjective police satisfaction with no clear standards or process. It also notes environmental objectives but concludes that fundamental rights must prevail. The court does not sustain confiscation under Section 17; instead, it directs that such vehicles be dealt with under the Kerala Protection of River Banks and Regulation of Removal of Sand Act, 2001 and Rules, with interim release under specified conditions. It further directs initiation of Sand Act proceedings within a month and finalization within another month. The writ petitions are disposed of accordingly, preserving the rule of law and environmental protection.

2009-06-11

WA No. 671 of 2006 (Fertilizers and Chemicals Travancore Ltd v Union of India)

This writ appeal concerns the pay revision and pensionary benefits of employees of the Fertilizers and Chemicals Travancore Ltd (FACT). The long-term settlement covering terms of employment expired on 31 December 1996. A fresh settlement was concluded (notified 28 August 2001) and made retroactive to 1 January 1997, with revisions in wages and benefits. Clause 29 of Ext. P1 provides that arrears relating to wage revision and dearness allowance for the period 1 January 1997 to 30 June 2001 will be reviewed and decided by management/government only when the company earns profits for at least three consecutive years; Clause 33.1 provides that employees who retired on or after 1 January 1997 will be eligible for arrears calculated from 1 January 1997 to the date of retirement, subject to adjustments for interim relief already paid, with any unclaimed amount transferred to a Welfare Fund. The appellants—the retirees who fall in the 1 January 1997 to 1 July 2001 window—argue that they were denied arrears and were paid pensionary benefits at pre-revised rates, creating discrimination. Respondents contend Ext. P1 binds the parties and arrears depend on profits, and that pay revision administered to others does not compel retroactive change. The court held that Ext. P1 terms survive as terms of employment and directed the management to consider terminal benefits at revised rates within two months and to release arrears when paid to current workers, with connected matters following."

2009-05-29

M/S. Palm Fibers & Yars Trading Co. v. State of Kerala & Others

The petitioner, a Small Scale Industrial unit, ran two LT power connections (No.13070 and No.13427) with commercial production starting in July 1994 and July 1995. On 06/02/1992, the Government issued Ext.P1 guaranteeing concessional tariffs (pre-1992 tariff) for five years from the date of commencement or substantial capacity expansion, certified by the District Industries Centre. Ext.P2 certified eligibility for this concession. Subsequently, the petitioner increased power demand to 300 KVA and was reclassified/advised to HT status from 15/05/1998, converting LT supply to HT. The petitioner argued that Ext.P1 benefits should extend for the full five-year period, covering the LT quantities certified in Ext.P2, and that the HT conversion was a mere reclassification directed by the Board, not a cessation of eligibility. The Board argued Ext.P1 targets only those who commenced production during 1992–1996 and that HT conversion from 15/05/1998 falls outside the Ext.P1 window, rendering the petitioner eligible only up to 15/05/1998. Earlier orders (Ext.P3) had set aside a cut-off date for merits, and Ext.P6/Ext.P4 handled appeals. Ultimately, the Court held that the HT conversion was outside Ext.P1’s period, but directed that the LT benefits for the two LT connections be extended only until 23/05/1998 (LT dismantling date) and without reimbursement from the Industries Department, as held in OP No.7622/1998. The petition was disposed of as above.