WAPCOS LTD. v. SALMA DAM JOINT VENTURE & ANR.
Case Synopsis & Summary
This Supreme Court decision concerns the validity and effect of an Amendment of Agreement (AoA) executed on 09.06.2015 between WAPCOS Limited (WAPCOSL) and Salma Dam Joint Venture (SDJV), comprising SSPPL and Angelique International Limited (AIL). The AoA revised rates and expressly stated, through its 1.2 and 1.3 provisions, that balance pending claims would be buried and there would be no arbitration for settlement of claims. SDJV, via SSPPL (the lead partner and authorized to invoke arbitration on behalf of AIL and SDJV), invoked Section 11(6) of the Arbitration and Conciliation Act, 1996 to appoint a sole arbitrator. The High Court of Delhi held that arbitration could proceed, accepting that the AoA did not extinguish the arbitration clause, and thus appointed an arbitrator. The Supreme Court reversed, holding that the AoA superseded the arbitration clause in the Contract Agreement, particularly since the AoA was executed when roughly 97% of the project was complete, with revised costs and terms expressly limiting future claims and arbitration. It held that SSPPL's authority to act for SDJV did not override the AoA’s express terms, and that the arbitration petition filed under Section 11 was not maintainable. The Court allowed the appeals and dismissed the arbitration petition, while permitting other remedies between the parties.
Find Cases Like This
Explore other judgments dealing with similar legal situations, facts, or statutory provisions.
Case Details & Bench
- Court
- Supreme Court of India
- Hon'ble Judges
- A. M. Khanwilkar
- Dinesh Maheshwari, JJ.
- Judgment Date
- 2019-11-14
- Court Decision / Holding
- Appeals allowed. The impugned judgment of the High Court is set aside and the Arbitration Petition (Arb. P. 810/2016) filed on behalf of SDJV through SSPPL stands dismissed. All pending applications are disposed of. The parties are free to pursue other remedies inter se in accordance with law. No order as to costs.
- Final Disposition
- Appeals allowed; High Court judgment set aside; Arbitration Petition dismissed; parties may pursue other remedies as permitted by law.
Parties to the Case
Appellants / Petitioners
- WAPCOS Limited (WAPCOSL)
- Angelique International Limited (AIL)
Respondents
- Salma Dam Joint Venture (SDJV)
- SSPJV Projects Private Limited (SSPPL)
Legal Representation & Advocates
Counsels for Petitioners
- • Mr. Gaurav Panchnanda (Senior Counsel)
- • Mr. Shyam Divan (Senior Counsel)
Counsels for Respondents
- • Mr. Sachin Datta (Senior Counsel)
Provisions of Law Cited
Legal Doctrines & Maxims
- Arbitration clause perishes with the contract when the contract is substituted, rescinded or altered (accord and satisfaction)
- Doctrine of accord and satisfaction terminating arbitration rights when disputes are settled and finalised
- Section 62 of the Indian Contract Act – substitution/alteration of contract extinguishes the original contract and its arbitration clause
Submissions & Arguments
Contentions of Appellants / Petitioners
The AoA (dated 09.06.2015) expressly amended the original Contract Agreement and, via clauses 1.2 and 1.3 of Section-01, buried all pending and future claims and declared that there would be no arbitration for settlement of claims. Execution of AoA at a stage when about 97% of the works were complete and the revised cost/terms reflected a deliberate supersession of the arbitration mechanism. Clause 4.1–4.3 of the Contract Agreement read with CoPA (and Clauses 20 and 20.6) could not resurrect arbitration once the AoA deactivated the arbitration route. The High Court erred by treating the AoA as non-derogatory of the arbitration clause. The law and earlier decisions (Damodar Valley Corp. v. Kar; National Insurance Co. Ltd. v. Boghara Polyfab; Nathani Steels Ltd. v. Associated Constructions) support the proposition that substitution/alteration of a contract ends the arbitration clause and accord and satisfaction may extinguish arbitration rights.
Contentions of Respondents
The AoA did not amount to a total repudiation of the arbitration clause; the Technical Committee’s actions and the process under CoPA did not imply waiver, and the date of AoA was misread. The petition was properly presented under Section 11(6) as the arbitration agreement persisted between SDJV and WAPCOSL; SSPPL had authority to represent SDJV under the JVA and PoA; the consent from AIL to SSPPL’s acts was not properly revoked in a manner that voided the arbitration petition; non-modification of Clause 20 of CoPA by AoA should have left arbitration intact, and the High Court’s reliance on AoA’s terms to extinguish arbitration was erroneous.
Explore This Legal Issue
Find relevant judgments and authoritative positions on the legal questions discussed here.
Cited Precedents (3)
| Case Name | Citation | Treatment | Explanation |
|---|---|---|---|
| Damodar Valley Corporation v. K. K. Kar | [1974] 2 SCR 240 | Positive | Cited to illustrate that when a contract is substituted or altered, the arbitration clause may perish; supports the view that an accord/settlement can extinguish arbitrable rights. |
| National Insurance Company Limited v. Boghara Polyfab Private Limited | (2009) 1 SCC 267; [2008] 13 SCR 638 | Positive | Used to discuss accord and satisfaction and the extinguishment of arbitration rights upon settlement of disputes. |
| Nathani Steels Ltd. v. Associated Constructions | (1995) Suppl. 3 SCC 324 | Positive | On settlement, subsequent invocation of arbitration is not permissible; supports the finding that final settlements can bar arbitration. |
Apply This to My Facts
Share your situation and test whether this judgment governs, supports, or challenges your case.
In The Court Record
WAPCOS LTD. v. SALMA DAM JOINT VENTURE & ANR.
Related Decisions & Precedents from Supreme Court of India (2019)
Uber India Systems Pvt. Ltd. v. Competition Commission of India & Ors.
Uber India Systems Pvt. Ltd. v. Competition Commission of India & Ors. concerns allegations that Uber, in its ride‑hailing network, abused a dominant position under the Competition Act, 2002. The case arose on appeals challenging the Competition Appellate Tribunal’s order in Appeal No. 31 of 2016, which upheld the Director General’s inquiry into whether Uber’s pricing and incentive practices violated Section 4. The Supreme Court analysed whether the information before it sufficed to constitute a prima facie case under Section 26(1) and whether there was abuse of a dominant position in the National Capital Region. It focused on the two ingredients for abuse: the existence of a dominant position and its misuse. The court considered, based on a statement summarizing driver incentives and a period when Uber reportedly paid high incentives to fleet owners, that Uber may have pursued a pricing strategy that would affect its competitors. Under Section 4(2)(a), abuse includes an unfair price, including predatory pricing. The Court accepted that there is a prima facie case for infringement, yet did not itself interfere with the Appellate Tribunal’s order and dismissed the appeals. It directed the Director General to complete the investigation within six months from today.
STATE OF BIHAR & ORS. v. DR. CHAITRAYA KUMAR SINGH & ORS.
This civil appeal concerns the reorganization of the erstwhile Bihar into Bihar and Jharkhand in 2000 and the post-allocation transfer of an employee. The first respondent, Dr. Chaitraya Kumar Singh, was initially allocated to Jharkhand in 2007 as an Ayurvedic Medical Officer and, following Union guidelines permitting transfer after final allocations, was re-allocated to Bihar on 6 September 2010 with mutual consent of both States. Bihar issued formal orders, and the respondent joined Jharkhand in 2007; however, he remained in Jharkhand and continued to work there until his retirement on 30 April 2017. A few days before retirement, he filed a writ petition in Jharkhand seeking relief to join Bihar and to be relieved by Jharkhand so that Bihar could accept joining. The Jharkhand High Court confirmed a Single Judge’s order directing Bihar to absorb him. The appellants contend that after the 2010 allocation there was no vacancy, the respondent did not pursue available remedies promptly, and seven years of service in Jharkhand after allocation render absorption in Bihar inappropriate. The Court agrees, noting the allocation to Bihar continued to hold and the petitioner failed to pursue remedies in time; his superannuation in Jharkhand eliminates the basis for absorption. The relieving order issued post-retirement is irrelevant. The appeal is allowed, the High Court’s order set aside, and there shall be no costs; pending applications are disposed.
PUNJAB FINANCIAL CORPORATION v. M/S PAULBRO LEATHERS PVT. LTD.
Punjab Financial Corporation (lender) filed against Paulbro Leathers Pvt. Ltd. after Paulbro defaulted on a loan. The dispute was settled under the Corporation’s One Time Settlement (OTS) policy on 01.04.2003, and a court-ordered reference to a Chartered Accountant (CA) was made to determine the remaining outstanding balance. After the CA submitted his report, a new dispute arose about the precise liability and how much had been paid, prompting the Corporation to issue a demand for Rs. 49,86,713 which Paulbro disputed in a writ petition before the Punjab and Haryana High Court. The High Court allowed the petition on the ground that the entire exercise had been carried out with consent and no objection had been raised, effectively barring re-opening of the settlement. The appellant challenged these rulings in this Court. The Supreme Court held that the settlement created a fresh dispute arising out of its terms and that the matter must be decided on its merits under the law. It emphasized that the High Court should record how and on what basis Paulbro satisfied the settlement and discharged liability, and if needed, refer the report to another CA. The Court remanded the case to the High Court to decide the writ petition afresh on merits, with a directions to decide expeditiously (preferably within six months).
RAJESH KUMAR DWIVEDI v. STATE OF U.P. & ANR.
Rajesh Kumar Dwivedi challenges the rejection of his candidature for the post of Instructor in Fitter at Government Industrial Training Institutes in Uttar Pradesh. An advertisement of 17 March 2008 required candidates to possess a certificate in the respective trade from the NCVT, in addition to experience. Dwivedi possessed three National Trade Certificates from Model Industrial Training Institute, Haldwani (one-year basic training in Mechanical, six-month Fitter General module, six-month Metrology and Engineering Inspection), but did not hold a two-year NCVT certificate. The High Court had dismissed his writ petition, holding that three separate courses could not be treated as equivalent to the NCVT qualification. Dwivedi relied on (i) the 16 December 1983 circular clarifying equivalence between the Restructured and Conventional patterns of the Craftsmen Training Scheme, and (ii) 1988 and 1992 UP circulars recognizing MITI, Haldwani training as equivalent to NCVT, including a two-year Fitter trade certificate. The State argued that the amended UP ITI Rules require NCVT certification and that the reliance on circulars cannot override the Rules. The Supreme Court held that the eligibility condition is to have a certificate in the respective trade from NCVT, and that if the State had earlier treated certain qualifications as equivalent through its circulars, such equivalence cannot be disregarded. Consequently, the appellant’s candidature could not be validly rejected, and the State was directed to appoint him within two months. The decision underscores how State-issued equivalence can complement or override rigid Rule-based qualifications when consistently recognized.