- Court Decision / Holding
- Writ appeal disposed of with a direction to Additional Respondent-3 to reconsider the matter afresh after affording an opportunity of hearing to the 2nd respondent-consumer, after supplying all relevant materials relied on by the Board, and to take a final decision within three months. Exts. P2, P4, P6 and the learned Single Judge’s order were set aside.
- Final Disposition
- Writ appeal disposed of with directions to reconsider afresh; the Additional Respondent to hold hearing and decide within three months; prior orders setting aside are quashed to enable fresh action consistent with natural justice.
Parties to the Case
Appellants / Petitioners
- The Deputy Chief Engineer, Electrical Circle, Kerala State Electricity Board Limited, Harippad
- The Special Office (Revenue) Kerala State Electricity Board Limited, Vydhyuthi Bhavanam, Pattom, Thiruvananthapuram
Respondents
- Consumer Grievance Redressal Forum for Kerala State Electricity Board Limited, Central Region, Power House Building, Cemetery Mukku Junction, Ernakulam, Kochi
- M/S. Central Travancore, Specialist Hospital Limited, Mulakkuzha, Chengannoor-689 505
- Additional Respondent 3 (Impleaded): Executive Engineer, TMR Division, Pallom
Legal Representation & Advocates
Counsels for Petitioners
- • Sri Raju Joseph (Sr.)
- • Sri Georgekutty Mathew, SC, KSEB
Counsels for Respondents
- • Adv. Jai Mohan (for Adv. M. Gopikrishnan Nambiar, R2)
- • M. Gopikrishnan Nambiar, Advocate (R2)
- • Adv. Jai Mohan (for R1)
Case Synopsis & Summary
This writ appeal arises from an order of the Consumer Grievance Redressal Forum (CGRF) for Kerala State Electricity Board Limited, Central Region, which set aside a demand for Rs. 23,15,304 raised against the 2nd respondent for alleged undercharging of electricity consumption. The appellants, being the petitioners in WP(C) No.19153 of 2015, challenged Ext.P6, the CGRF’s order, in the High Court of Kerala. The factual matrix centers on a high-tension consumer with contract demand of 360 KVA; July 2010 readings showed a dramatic drop in consumption, while the consumer’s activity continued normally. An inspection on 06.12.2011 revealed that the LT fuse on the R phase of the PT was blown, causing under-recording. After the fuse was replaced, data were downloaded, and the Board proceeded to quantify undercharging by applying an arithmetical adjustment (40-50% enhancement was discussed in the proceedings) under Regulation 24(5) of the Kerala Electricity Supply Code, 2005, issuing Ext.P4. The Forum’s Ext.P6 order cancelling the demand and the learned Single Judge’s order refusing to interfere prompted the appeal. The Division Bench ultimately disposed of the writ appeal by directing the Additional Respondent-3 (Executive Engineer, TMR Division, Pallom) to reconsider the matter afresh, after supplying all relied materials and providing an opportunity of hearing to the 2nd respondent, with a final decision to be recorded within three months. The decision underscores adherence to natural justice in civil consequences and the need for due process in recovery actions."
Provisions of Law Cited
Legal Doctrines & Maxims
- Principles of natural justice
Submissions & Arguments
Contentions of Appellants / Petitioners
The appellants contend that the meter did not record correctly due to a blown fuse in the R phase of the PT. After rectification, data were downloaded showing the period 08.07.2010 to 06.12.2011. Since the three phases are equally balanced, an arithmetical calculation should suffice to determine any undercharging. Therefore, Ext.P4 demand is perfectly legal and valid. They argue that the method does not require any new initiation of proceedings and that the Board’s reliance on Regulation 24(5) is proper. The contention is that the Forum’s scrutiny and the court’s earlier orders were misapplied, and that fresh computation should proceed with proper materials and due process.
Contentions of Respondents
The respondents submit that Ext.P2/Ext.P4 were issued without giving any notice and without providing the materials relied upon. They argue that without due process, including notice and opportunity to be heard, the decision constitutes arbitrary action. They rely on Section 126 of the Electricity Act, 2003 and on decisions like State of Orissa v. Dr (Miss) Binapani Dei, D.K. Yadav v. J.M.A. Industries Ltd, and Sahara India (Firm) v. Commissioner of Income Tax to contend that the procedures were not properly followed and natural justice requires hearing and disclosure of relied materials.
Cited Precedents (3)
| Case Name | Citation | Treatment | Explanation |
|---|---|---|---|
| State of Orissa v. Dr (Miss) Binapani Dei and others | AIR 1967 SC 1269 | Mentioned Only | Cited by respondents to support natural justice; the judgment relies on natural justice principles but does not adopt the holding. |
| D.K. Yadav v. J.M.A. Industries Ltd | (1993) 2 SCC 259 | Mentioned Only | Cited to illustrate need for fair procedure; not expressly followed or distinguished in the decision. |
| Sahara India (Firm), Lucknow v. Commissioner of Income Tax, Central-I and another | (2008) 14 SCC 151 | Mentioned Only | Cited as supporting the natural justice principle; not treated as binding for the present case. |
Diagnostic Tool
Does this judgment govern your specific facts?