VIOM NETWORKS LTD. v. THE S.I. OF POLICE, PANOOR POLICE STATION; MANEESH E.K.; KUNHIPURAYIL HOUSE; R2 TO R4; PANNIYANNUR GRAMA PANCHAYAT (5th respondent)

Case / Petition Number:WP(C).No. 26808 of 2011

Case Details & Bench

Court
High Court of Kerala
Hon'ble Judges
  • Pius C.Kuriakose
  • K. Harilal
Judgment Date
2011-11-28
Court Decision / Holding
Writ petition allowed to the limited extent of directing the first respondent to remove physical obstructions, if any, caused by respondents 2 to 4 or persons acting under them for the construction of the BTS on the basis of Ext. P2 permit. It is clarified that protection for energisation of the tower is not granted. The petitioner must comply with any orders that may be issued by the Ombudsman or a final civil court verdict; if the civil court decides in favour of the respondents, the protection directions will stand withdrawn.
Final Disposition
Partial grant of the writ: protection granted for construction with removal of obstructions; energisation protection refused; subject to trial outcome and any Ombudsman orders; if the civil court or Ombudsman orders favor the respondents, the protection directions may be withdrawn.

Parties to the Case

Appellants / Petitioners

  • Viom Networks Ltd.

Respondents

  • The S.I. of Police, Panoor Police Station
  • Maneesh E.K.
  • Kunhipurayil House
  • Panniyannur Grama Panchayath (5th respondent)

Legal Representation & Advocates

Counsels for Petitioners

  • • Sri A. Mohamed Mustaque
  • • Sri K.R. Avinash (Kunnath)

Counsels for Respondents

  • • Sri. M.K. Aboobacker
  • • Sri.C.P. Peethambaran

Case Synopsis & Summary

Viom Networks Ltd., a telecom infrastructure provider, filed WP(C) No. 26808 of 2011 seeking police protection for constructing a base transceiver station (BTS) on a site for which Ext. P2 permit had been issued by the 5th respondent, Panniyannur Grama Panchayat. The petitioner contends that the permit authorizes the construction and that all other licenses and consents are in place, yet respondents 2 to 4 obstruct the work claiming potential health hazards from the tower and its energisation. The respondents filed a counter-affidavit with documents Exts. R2(a)–R2(j). Counsel for the petitioner contended that the health-hazard issue associated with telecom towers has been addressed in the court's earlier rulings in Reliance Infocom v. Chemanchery Grama Panchayat and Essar Telecommunications v. State of Kerala, and that protection directions can be issued for construction while the civil suit and Ombudsman proceedings progress. The respondents urged restraint, noting that the suit is pending and Ombudsman proceedings may resolve the matter; they argued that energisation should be deferred and protection should not be granted beyond trial. After detailed submissions, the court recognised that health-hazard considerations may be examined in trial but held that, at least, protection could be granted for the construction phase. The court directed removal of obstructions hindering construction on the basis of Ext. P2, while emphasising that energisation protection was not granted and that outcomes of the suit or Ombudsman orders could alter or withdraw the order.

Provisions of Law Cited

Article 227, Constitution of India

Submissions & Arguments

Contentions of Appellants / Petitioners

The petitioner contends that Ext.P2 permit and other licenses authorize construction of the BTS and that police protection should be granted to ensure unobstructed work. It relies on previous high court rulings recognizing health-hazard concerns surrounding telecom towers and asserts that protection can be limited to construction pending final resolution of the civil suit and Ombudsman proceedings.

Contentions of Respondents

The respondents submit that a civil suit is pending with prior injunctions and appeal orders, and that protection should not extend beyond trial; energisation should await adjudication. They contend that the Ombudsman proceedings are in process and may determine the matter, and that protection for energisation should be refused.

Cited Precedents (2)

Case NameCitationTreatmentExplanation
Reliance Infocom v. Chemanchery Grama Panchayat2006 (4) KLT 695PositiveThe judgment is cited as supporting health-hazard considerations related to telecom towers and as precedent for limiting protective relief to construction while leaving energisation for later adjudication.
Essar Telecommunications (P) Ltd. v. State of Kerala2011 (2) KLT 516PositiveCited to indicate that later studies on radiation risks may be considered and that the court can restrict protection to the construction phase pending trial and related proceedings.

Diagnostic Tool

Beta

Does this judgment govern your specific facts?

Don't risk relying on a distinguishable precedent. Enter your facts or proposition below. We will test it against VIOM NETWORKS LTD. v. THE S.I. OF POLICE, PANOOR POLICE STATION; MANEESH E.K.; KUNHIPURAYIL HOUSE; R2 TO R4; PANNIYANNUR GRAMA PANCHAYAT (5th respondent) and instantly map out authorities that support, challenge, or govern your position.

Extracted Judgment Text

Exact text extracted from official judgment records.

## **IN THE HIGH COURT OF KERALA AT ERNAKULAM** **THE HONOURABLE MR. JUSTICE PIUS C.KURIAKOSE THE HONOURABLE MR. JUSTICE K.HARILAL** ## **MONDAY, THE 28TH NOVEMBER 2011 / 7TH AGRAHAYANA 1933** **WP(C).No. 26808 of 2011(A) ---------------------------------------** ## **VIOM NET WORKS LTD.,REGISTERED OFfICE AT 5TH FLOOR, GOWRA TRINITY,CHIRAN FORT LANE, BEGUMPET,SECUNDERABAD 500 003 AND CIRCLE OFFICE AT J & CO CHAMBERS, MANIMALA ROAD,EDAPPALLY,COCHIN-24 THROUGH ITS AUTHORISED SIGNATORY MR.M.SANTHOSH KUMAR.** **BY ADVS. SRI.A.MOHAMED MUSTAQUE, SRI.K.R.AVINASH (KUNNATH).** **1. THE S.I OF POLICE, PANOOR POLICE STATION,** ## **NAMATHUPOYYIL HOUSE, CHAMBAD P.O, PANOOR VIA,** **3. MANEESH E.K,ETTUVEETTIL HOUSE, CHAMBAD P.O, PANOOR VIA,** ## **KUNHIPURAYIL HOUSE,** **R1 BY SR. GOVT. PLEADER SRI. M.K. ABOOBACKER, R2 TO R4 BY ADV. SRI.C.P.PEETHAMBARAN.** **THIS WRIT PETITION (CIVIL) HAVING COME UP FOR ADMISSION ON 28/11/2011,THE COURT ON THE SAME DAY DELIVERED THE FOLLOWING:** **W.P.(C).NO.26808/2011-A:** **APPENDIX** ## **PETITIONER'S EXHIBITS:-** ## **EXHIBIT P1. TRUE COPY OF THE AGREEMENT DATED 12.1.2011.** **EXHIBIT P2. TRUE COPY OF THE PERMIT DATED 18.01.2011 ISSUED BY PANNIYANNUR GRAMA PANCHAYAT.** **EXHIBIT P3. TRUE COPY OF THE REQUEST MADE BY THE PETITIONER BEFORE THE IST RESPONDENT DATED 3.10.2011.** **EXHIBIT P4. TRUE COPY OF THE ACKNOWLEDGEMENT OF EXHIBIT P3.** ## **RESPONDENT'S EXHIBITS:-** **EXT.R2.A: COPY OF THE ORDER DTD. 10/06/2011 IN I.A. 1169/2011 IN O.S. 176/2011 OF MUNSIFF COURT, THALASSERY.** **EXT.R2.B: COPY OF THE JUDGMENT DTD. 10/10/2011 IN O.P.(C).NO.3225/2011 OF THIS HON'BLE COURT.** **EXT.R2.C: COPY OF THE MEMORANDUM OF O.P.NO.1386/2011 FILED BY THE R.3. BEFORE THE OMBUDSMAN.** **EXT.R2.D: COPY OF THE APPLICATION DTD. 24/10/2011 SUBMITTED BY THE R.4. TO THE INFORMATION OFFICER OF THE PANNIANNORE GRAMA PANCHAYATH.** **EXT.R2.E: COPY OF THE REPLY DTD. 27/10/2011 ISSUED BY THE SECRETARY, PANNIANNORE GRAMA PANCHAYATH.** **EXT.R2.F: COPY OF THE MINUTES DTD. 02/05/2011 OF THE ACTION COMMITTEE.** **EXT.R2.G: COPY OF THE NOTICE PUBLISHED IN CONNECTION WITH THE PROTEST MARCH OF ACTION COMMITTEE.** **EXT.R2.H: COPY OF THE PAPER REPORT PUBLISHED IN NEW INDIAN EXPRESS DAILY DTD. 13/10/2011.** **EXT.R2.I: COPY OF THE APPLICATION DTD. 19/10/2011 SENT TO THE PUBLIC INFORMATION OFFICER, UNION MINISTRY OF ENVIRONMENT, NEW DELHI.** **EXT.R2.J: COPY OF THE LETTER ISSUED BY THE MINISTRY.** ## **RESPONDENT'S EXHIBITS:NIL.** ## **//TRUE COPY//** ## **P.A. TO JUDGE** **Prv.** ## **PIUS C.KURIAKOSE & K. HARILAL, JJ. -----------------------W.P.(C).No26808 OF 2011 ------------------------** Dated this the 28th day of November, 2011 ## **JUDGMENT** Pius C.Kuriakose, J. The Panniyannur Grama Panchayat , represented by its Secretary is impleaded suo motu as additional 5th respondent. The Registry is directed to carry out corrections in the cause title. 2. The petitioner company, engaged in the business of providing infrastructure for providers of Teli-communication services, has approached this court seeking police protection for the construction of base transceiver station on the basis of Ext.P2 permit issued by the Additional 5th respondent. The petitioner alleges that respondents 2 to 4 are raising obstructions stating that construction of the tower and its energisation will result in serious health hazards to them and to the other inhabitants of the Panchayat. According to the petitioner, they have obtained Ext.P2 permit from the Panchayat and they have all other requisite licences and consents. 3. The party respondents have filed a detailed counter WPC.No.26808/2011 2 affidavit and they have produced Exts. R2(a) to R2 (j) documents. 4. Sri.Mohamed Mustaque learned counsel for the petitioner and C.P.Peethambaran learned counsel for the party respondents have addressed us at length on the basis of the rival pleadings raised by their parties. Our attention was drawn by the learned counsel to the various documents placed on record by the parties. 5. It was submitted by Sri.Mohamed Mustaque that in this case the party respondents approached the Civil Court and filed a suit against the petitioner. Even though in the first instance the court passed an order of injunction against the petitioner, in appeal the above order was vacated subject to certain observations. Even though the party respondents filed writ petition under Article 227 challenging the order in appeal, this court also did not interfere with the order of the Appellate Court vacating injunction. Hence, according to Mr.Mohamed Mustaque there is every justification for granting the protection directions sought for. 6. Sri.C.P.Peethambaran learned counsel for the party WPC.No.26808/2011 3 respondents drew our attention to the order passed by the court of appeal as well as by this court under Article 227. The learned counsel submitted that even the Ombudsman for the Local Self Government Institutions is in seizin of the matter. The suit is likely to be listed for trial immediately. Protection directions may not be issued till the suit is finally decided. In reply, Mr.Mohammed Mustaque submitted that the petitioner is ready and willing to obey any conditions which may be issued by this court. The protection being given can be made subject to the outcome of the suit as well as the petition before the Ombudsman. 7. We have given our anxious consideration to the submissions addressed at the Bar as well as to the rival pleadings raised by the parties apart from the various documents produced. As noticed by this court in Ext.R2(b) judgment, the issue of health hazards resulting from the construction of Telicommunication towers and also from the radiation, which may emanate from such towers upon their energisation, is covered in favour of the petitioner company by the judgment of this court in Reliance Infocom v. Chemanchery WPC.No.26808/2011 4 Grama Panchayat (2006 (4) KLT 695) and Essar Telecommunications (P) Ltd. v. State of Kerala (2011 (2) KLT 516). The argument of Sri.C.P.Peethambaran is that later studies have revealed that the radiation, which will emanate from telecommunication towers, will be injurious to the health of the people residing near to the towers. The learned counsel's further argument was that during the course of trial it will be open to the party respondents to adduce evidence regarding the recent studies. We find from Ext.R2(d) that, in that judgment itself it has been made clear that whether or not the radiation emanating from the proposed tower once it is energised will be hazardous to the health of the people residing nearby is a matter to be considered by the Civil Court in the trial which is yet to commence. The same is the position regarding the proceedings stated to be pending before the Ombudsman for Local Self Government Institutions. But, we are of the view that protection can be given to the petitioner in the matter of construction of the tower alone. Accordingly, we allow this writ petition to the limited extent of directing the first respondent to remove physical obstructions, WPC.No.26808/2011 5 if any caused by respondents 2 to 4 or persons acting under them for the construction of the tower on the strength of Ext.P2 permit. But we make it clear that we have not granted any protection to the petitioners for energisation of the tower. Once, the suit is decided in favour of the petitioner, it is open to the petitioner to approach this court court seeking protection for energisation of the tower. It is clarified further that if, in the meanwhile, the Ombudsman passed any order against the petitioner in the matter of construction or energisation of the tower, the petitioner will be bound by such order. It is needless to mention that if the verdict of the Civil Court comes to be in favour of the party respondents, the protection directions issued herein will stand automatically withdrawn. ## **PIUS C.KURIAKOSE,JUDGE** **K. HARILAL, JUDGE.** dpk WPC.No.26808/2011 6