Vijay Constructions, Engineers & Contractors v. The Governor of the State of Kerala represented by the Secretary to Government, Public Works Department, Government Secretariat, Trivandrum & The Project Director (S.E.), National Highway (ADB) Circle, Edappally, Cochin

Case / Petition Number:
AR.No.18 of 2003
Neutral Citation:/

Case Synopsis & Summary

This is an application under Section 11(6) and (8) of the Arbitration and Conciliation Act, 1996, seeking the appointment of an arbitrator to resolve disputes arising out of the NH 49 Madhura–Kochi Road – Special Repairs project. The applicant, Vijay Constructions, was awarded the contract in 2000 and completed the work by 30 April 2001, with the final bill paid on 23 January 2002. The applicant issued Annexures 1 and 2 (19 August 2002 and 26 October 2002) outlining claims, but there was no response from the respondents. In January 2002, the respondents directed the execution of a stamped undertaking (Annexure R2(f)) promising not to claim further amounts, in exchange for payment of the final bill at original rates; the undertaking was furnished on 23 January 2002, and the applicant later protested on 2 February 2002. The respondents contend the undertaking was given voluntarily and there is no arbitrable dispute; the applicant contends it was obtained under coercion due to financial duress. The court examined Apex Court precedents on arbitrability and accords-and-satisfaction, including disputes about no-claim certificates, and ultimately held there was no arbitrable dispute, dismissing the arbitration request. The judgment reflects the court’s view on the voluntariness of no-claim undertakings and the limit of arbitration when accord-and-satisfaction is invoked.

Precedent Explorer

Find Cases Like This

Explore other judgments dealing with similar legal situations, facts, or statutory provisions.

Case Details & Bench

Court
High Court of Kerala
Hon'ble Judges
  • Antony Dominic
Judgment Date
2010-01-06
Court Decision / Holding
The Arbitration Request will, therefore, stand dismissed.
Final Disposition
Arbitration Request dismissed

Parties to the Case

Appellants / Petitioners

  • Vijay Constructions, Engineers & Contractors, Mykulangara, Kinginimattom P.O., Kolenchery - 682 311

Respondents

  • The Governor of the State of Kerala represented by the Secretary to Government, Public Works Department, Government Secretariat, Trivandrum
  • The Project Director (S.E.), National Highway (ADB) Circle, Edappally, Cochin

Legal Representation & Advocates

Counsels for Petitioners

  • • Sri Rajiv Abraham George
  • • Sri Eapen Abraham George

Counsels for Respondents

  • • Mr. K.R. Ganesh, Sr. Government Pleader

Provisions of Law Cited

Section 11(6) & Section 11(8) of the Arbitration and Conciliation Act, 1996

Legal Doctrines & Maxims

  • Accord and satisfaction
  • Economic duress / coercion
  • No claim certificate (NCC)
  • Arbitration agreement doctrine

Submissions & Arguments

Contentions of Appellants / Petitioners

The applicant contended that the undertaking (Annexure R2(f)) furnished while receiving final payment was obtained under coercion due to financial duress. They argued that the absence or validity of an arbitration agreement is not the sole determinant; rather, the question is whether an arbitrable dispute survives in light of accord and satisfaction and any coercive conduct in obtaining a discharge. They relied on Apex Court precedents on no-claim certificates and arbitrability to demonstrate that disputes can persist even after execution of a discharge voucher in certain circumstances.

Contentions of Respondents

The respondents argued that the undertaking R2(f) was voluntary and not coerced; the contractor accepted the original contract rates due to financial pressures, and the final payment was made accordingly. They asserted that there is no arbitrable dispute as the contractor, by signing R2(f) and accepting payment, discharged all claims. They relied on the conceded letters R2(d) and R2(e) to show consent and abandonment of enhanced claims, and invoked doctrinal illustrations (from Boghara) to argue accord and satisfaction may bar arbitration where the discharge is voluntary.

Legal Doctrine & Issue Explorer

Explore This Legal Issue

Find relevant judgments and authoritative positions on the legal questions discussed here.

Cited Precedents (4)

Case NameCitationTreatmentExplanation
S.B.P. & Co. v. Patel Engineering Ltd.2005(8) SCC 618Mentioned OnlyCited as background authority on the maintainability of writ petitions and the posture of Section 11 petitions, but not controlling the present decision.
M.K. Abraham & Co. v. State of Kerala2009(7) SCC 636PositiveApex Court held there is an arbitration agreement between the parties; cited to support the existence of arbitration machinery in the dispute.
M/s. Associated Construction v. Pawanhans Helicopters Pvt. Ltd.AIR 2008 SC 2911DistinguishedFacts involved a no-claim certificate demanded by the awarder; distinguished from the present case where no coercion is established.
National Insurance Co. Ltd v. Boghara Polyfab Pvt. Ltd.AIR 2009 SC 170Mentioned OnlyIllustrates illustrations of when claims are arbitrable after accord and satisfaction; the judge notes paragraph 28(v) as more apt but finds it not helping the applicant.
Case Applicability Diagnostic

Apply This to My Facts

Share your situation and test whether this judgment governs, supports, or challenges your case.

Official Judgment Record
•2,997 words•~14 min read

In The Court Record

Vijay Constructions, Engineers & Contractors v. The Governor of the State of Kerala represented by the Secretary to Government, Public Works Department, Government Secretariat, Trivandrum & The Project Director (S.E.), National Highway (ADB) Circle, Edappally, Cochin

## **IN THE HIGH COURT OF KERALA AT ERNAKULAM** **PRESENT :** **THE HONOURABLE MR. JUSTICE ANTONY DOMINIC** **WEDNESDAY, THE 6TH JANUARY 2010 / 16TH POUSHA 1931** **AR.No. 18 of 2003()** - **-------------------** **APPLICANT (S):** ## **--------------------** **VIJAY CONSTRUCTIONS, ENGINEERS & CONTRACTORS, MYKULANGARA, KINGINIMATTOM.P.O., KOLENCHERY - 682 311.** **BY ADV. SRI.RAJIV ABRAHAM GEORGE SRI.EAPEN ABRAHAM GEORGE** ## **RESPONDENT(S):** **---------------** **1. THE GOVERNOR OF THE STATE OF KERALA REPRESENTED BY THE SECRETARY TO GOVERNMENT, PUBLIC WORKS DEPARTMENT, GOVERNMENT SECRETARIAT, TRIVANDRUM.** **2. THE PROJECT DIRECTOR (S.E.), NATIONAL HIGHWAY (ADB) CIRCLE, EDAPPALLY, COCHIN - 682 024.** ## **MR.K.R.GANESH, SR. GOVERNMENT PLEADER** **THIS ARBITRATION REQUEST HAVING BEEN FINALLY HEARD ON 06/01/2010, THE COURT ON THE SAME DAY DELIVERED THE FOLLOWING:** ## ANTONY DOMINIC, J. ------------------------- ## A.R. No.18 of 2003 --------------------------------Dated, this the 6[th] day of January, 2010 ## O R D E R This is an application filed under Section 11(6) & (8) of the Arbitration and Conciliation Act, 1996 praying for the appointment of an Arbitrator to arbitrate on the disputes raised by the applicant against the respondents. 2. Briefly stated, the facts of the case are that the work of “NH 49 Madhura-Kochi Road - Special Repairs Crash Programme - improving riding quality and strengthening the BT surface by providing 50 mm BM and 25 mm SDBC between km 184/000 to 194/000” was awarded to the applicant by letter of acceptance dated 07/09/2000 from the 2[nd] respondent. Thereafter a formal agreement was entered into between the parties on 26/09/2000, the relevant clause of which providing for settlement of dispute by Arbitration is Annexure 3. The PAC of the contract was Rs.1,29,74,355/- and the work should have been completed before 31/12/2000. A.R.No.18/2003 -2- 3. The applicant commenced work and though belatedly completed the work on 30/04/2001. Payment in terms of part bills were made and the final bill was paid on 23/01/2002. Thereafter Annexure 1 notice was issued by the applicant on 19/08/2002 raising certain claims against the respondents and demanding payment of the amount mentioned therein. There was no response, and thereupon, the applicant issued Annexure 2 notice dated 26/10/2002 to the Director General requesting for the appointment of an Arbitrator to resolve the disputes raised by them. There was no response to Annexure 2 as well. It was thereupon that this application was filed invoking the power of this Court under Section 11(6) and (8) of the Arbitration and Conciliation Act, 1996 for appointment of an Arbitrator. Parties entered appearance, the matter was heard and by order dated 19/12/2003, the application was dismissed upholding the contention of the respondents that there was no arbitration clause in the agreement between the parties. The other contentions raised by the respondents were not gone into. 4. Aggrieved by the said order, a writ petition was filed before this Court. During the pendency of the writ petition, a A.R.No.18/2003 -3- Constitution Bench of the Apex Court rendered judgment in S.B.P.& Co. v. Patel Engineering Ltd. and another (2005(8) SCC 618), holding the writ petition not maintainable. In view of the above judgment, the writ petition was dismissed reserving the right of the applicant to move the Apex Court. Accordingly, the applicant filed SLP No.11119/2006. Leave was granted and the appeal was numbered as Civil Appeal No.4155/2009. By judgment in M.K.Abraham & Co. v. State of Kerala (2009(7) SCC 636) rendered on 07/07/2009, the Apex Court held that there is an arbitration agreement between the parties. However, taking note of the other disputes raised by the respondents in the Civil Appeal, the Apex Court held as follows:- “15. We find from the record that the respondent, apart from contending that there was no arbitration agreement at all, had also contended that the appellants had given full and final settlement receipt with a no claim undertaking in regard to the respective contract and therefore no dispute much less arbitral disputes can exist. On the other hand, appellants had contended that such certificates have been obtained by coercion and pressure. Whether no claim certificate were obtained by coercion or by applying pressure is a question of fact that will have to be considered in the proceedings under Section 11 of the Act. The High Court while deciding the petitions under Section 11, considered only the question whether there is an arbitration A.R.No.18/2003 -4- agreement or not. As it held that there was no arbitration agreement, it did not examine the further objection of the respondents that there was a full and final settlement and consequently there is no arbitral dispute. In the absence of any material on that issue, we are not in a position to decide the same. 16. We therefore allow these appeals and set aside the order of the High Court, holding that there is an arbitration agreement between the parties in both appeals. We remand the matter to the High Court to consider and decide the other objections raised by the respondents in accordance with law.” 5. It is accordingly that the matter is coming up again for consideration. When the matter was taken up for hearing, arguments raised by both sides were confined to the question as to whether there was any arbitrable dispute, in view of Annexure R2(f), the undertaking given by the applicant while receiving final payment. 6. The facts which led to Annexure R2(f) undertaking, according to the applicant, are that after completing the work on 30/04/2001, in terms of the agreement, though they were entitled to be paid the final bill amount within one month thereafter, payment was not made. It is stated that in view of the non-payment explaining their financial crisis and the necessity for immediate payment, Annexure 4 to 8 letters produced along with the reply A.R.No.18/2003 -5- affidavit were issued, requesting for immediate payment. It is stated that finally, the 2[nd] respondent issued Annexure 9 communication to the Executive Engineer, which inter alia reads as under : “Considering the directions of the court and the Contractor's grievances he may be paid the final bill at his agreed rates without any loss to Government. It may be noted that if the new rates proposed for the BM and SDBC are approved by Chief Engineer the total cost of the work executed based on the revised rate would be at a stage requiring a Revised Estimate which would further delay the payment to the Contractor. An undertaking from the contractor in stamp paper to the effect that he will not be claiming any additional amount on account of this work also may be obtained.” 7. It is stated that as the applicant was facing severe financial crisis and under economic duress, Annexure R2(f) undertaking was furnished on 23/01/2002. It is stated that immediately thereafter on 02/02/2002, the applicant issued Annexure 10 notifying the respondents that the undertaking furnished was under coercion, that the same is of no legal effect and reserving their right to raise their legitimate claims in accordance with law. It is in this background, the applicant seeks to avoid Ext.R2(f) undertaking furnished by them. A.R.No.18/2003 -6- 8. On the other hand, in the counter affidavit filed by the respondents, what they contended is that though the contractor, completed the work on 30/04/2001, final bill was raised by the contractor only on 24/10/2001. It is stated that the delay has occurred on account of the fact that the final levels had to be taken manually for the entire stretch of 10 KM. It is stated that in the meanwhile, the contractor had demanded revised rate of BM and BC due to change in the mix design and that complaining that payment was not effected, he moved this Court by filing O.P.No.38819/01. That original petition was disposed of by judgment dated 21/12/2001 with a direction to the respondents to pay the admitted amount due in accordance with the priority laid down by the Full Bench of this Court. It is stated that after the judgment was rendered, on 21/01/2002 the Contractor voluntarily issued Annexure R2(d) letter demanding payment at the original agreement rate, and giving up his demand for the revised rate due to change in the mix design. It is stated that on 21/01/2002 itself, again on his own, the Contractor issued Annexure R2(e) letter, where he reiterated his plea for payment at the original rate. It is stated that on receipt of these letters, which were voluntarily written by the A.R.No.18/2003 -7- contractor, Annexure 9 letter dated 23/01/2002 was issued by the Project Director directing the Executive Engineer to obtain an undertaking in the manner stated therein. It is stated that on 23/01/2002 itself, Annexure R2(f) undertaking in stamp paper of Rs.50/- was furnished by the applicant and on its receipt, cheque for Rs.13,97,248/- was delivered to the applicant on 23/01/2002. According to the respondents, it was thereafter that by Annexure 10 letter dated 02/02/2002, the applicant conveyed his belated protest. According to the respondents, there was no coercion or duress from their side enabling the applicant to wriggle out of Annexure R2(f) undertaking and therefore, the claim of the applicant having been settled as demanded by them entirely to their satisfaction, there is no dispute requiring the appointment of an Arbitrator. On this basis, they seek dismissal of the Arbitration Request. 9. As already seen, the direction of the Apex Court as contained in paragraph 15 of the judgment referred to above, requires this Court to decide whether the no claim certificate was obtained by coercion or pressure, which is a question of fact. Both sides have not requested for adducing any oral evidence and A.R.No.18/2003 -8- therefore, this question of fact will have to be decided based on the documents produced by the parties. 10. As already stated, the work was completed by the applicant on 30/04/2001. Thereafter he approached this Court by filing O.P.No.38819/2001 complaining of non-payment of the bill amount. That original petition was disposed of by judgment rendered on 21/12/2001 directing that admitted amount be paid in terms of the priority as laid down by the Full Bench of this Court. Subsequently, he wrote Annexures 4 to 8 letters explaining his financial crisis and requesting for payment. It was thereafter that he wrote Annexure R2(d) & R2(e) letters, both dated 21/01/2002. Annexure R2(d) letter, to the extent it is relevant, reads as under:- “As the revised rate of BM and SDBC is not yet finalised and supplementary agreement is not executed, the revised rate finalisation takes further time. To avoid further delay in payment of the bill, I request you to kindly settle my final bill with the original agreement rate though it is heavy loss to me to the extent of Rs.2 lakhs (approx.). However, considering the interest on the amount blocked up, and the pressure from my suppliers, I have no other alternative other than to accept original contract agreement rate. Hence, I request you to kindly give directions to the Executive Engineer, N.H., Muvattupuzha, to close my final bill with the original contract agreement rate.” Annexure R2(e) also reads as under: A.R.No.18/2003 -9- “As the revised rates of BM and SDBC is not yet finalised and supplementary agreement not executed, I request you to kindly issue necessary direction to the Executive Engineer to settle my final bill at the rates provided in the original agreement which is acceptable to me.” 11. Even the applicant has no case that either Annexures R2 (d) or R2(e) was issued on account of any threat, coercion or duress exerted by any of the respondents. A reading of these two letters, which were voluntarily written, show that despite its claim for revised rate, the applicant has voluntarily given up its claim for enhanced rate and agreed for original agreement rate, in view of their pressing needs. It was acting upon Annexures R2(d) and R2(e), the claim of the applicant was processed and Annexure 9 requiring the applicant to give an undertaking was issued. On receipt of Annexure 9, without expressing any protest or raising any challenge either before the respondents themselves or any legal forum, the applicant willingly furnished Annexure R2(f) undertaking, which again is a voluntary act on its behalf. Acting upon the undertaking so furnished, on the same date, they were paid the amount that was due. It was thereafter that, for the first time, the applicant expressed its protest by Annexure 10 dated 02/02/2002. In my ## A.R.No.18/2003 -10- view, by any stretch of imagination can this Court, on the materials produced, conclude that Annexure R2(f) undertaking was obtained by coercion or duress, enabling the applicant to avoid the consequences. 12. The learned counsel for the applicant relied on the judgments of the Apex Court in M/s.Associated Construction v. Pawanhans Helicopters Pvt.Ltd. (AIR 2008 SC 2911) and National Insurance Co.Ltd v. M/s.Boghara Polyfab Pvt.Ltd. (AIR 2009 SC 170). 13. A reading of the judgment in M/s.Associated Construction v. Pawanhans Helicopters Pvt.Ltd. (AIR 2008 SC 2911) shows that unlike in this case, the awarder had demanded for a No Claim Certificate, even for entertaining the request made by the contractor for payment. Therefore, the facts of the case dealt with by the Apex Court is totally different and can have no assistance to the applicant. 14. In the decision in National Insurance Co.Ltd v. M/s.Boghara Polyfab Pvt.Ltd. (AIR 2009 SC 170) the Apex Court has, in paragraph 28 thereof, illustrated certain circumstances when claims are arbitrable inspite of giving a No Claim Certificate. A.R.No.18/2003 -11- ## Paragraph 28 reads as under :- “28. Some illustrations (not exhaustive) as to when claims are arbitrable and when they are not, when discharge of contract by accord and satisfaction are disputed to round up the discussion on this subject: (i) A claim is referred to a conciliation for a pre-litigation Lok Adalat. The parties negotiate and arrive at a settlement. The terms of settlement are drawn up and signed by both the parties and attested by the Conciliator or the members of the Lok Adalat. After settlement by way of accord and satisfaction, there can be no reference to arbitration. (ii) A claimant makes several claims. The admitted or undisputed claims are paid. Thereafter negotiations are held for settlement of the disputed claims resulting in an agreement in writing settling all the pending claims and disputes. On such settlement, the amount agreed is paid and the contractor also issues a discharge voucher/no claim certificate/full and final receipt. After the contract is discharged by such accord and satisfaction, neither the contract nor any dispute survives for consideration. There cannot be any reference of any dispute to arbitration thereafter. (iii) A contractor executes the work and claims payment of say Rupees Ten Lakhs as due in terms of the contract. The employer admits the claim only for Rupees six lakhs and informs the contractor either in writing or orally that unless the contractor gives a discharge voucher in the prescribed format acknowledging receipt of Rupees Six Lakhs in full and final satisfaction of the contract, payment of the admitted amount will not be released. The contractor who is hard pressed for funds and keen to get the admitted amount released, signs on the dotted line either in a printed form or otherwise, stating that the amount is received in A.R.No.18/2003 -12- full and final settlement. In such a case, the discharge is under economic duress on account of coercion employed by the employer. Obviously, the discharge voucher cannot be considered to be voluntary or as having resulted in discharge of the contract by accord and satisfaction. It will not be a bar to arbitration. (iv) An insured makes a claim for loss suffered. The claim is neither admitted nor rejected. But the insured is informed during discussions that unless the claimant gives a full and final voucher for a specified amount (far lesser than the amount claimed by the insured), the entire claim will be rejected. Being in financial difficulties, the claimant agrees to the demand and issues an undated discharge voucher in full and final settlement. Only a few days thereafter, the admitted amount mentioned in the voucher is paid. The accord and satisfaction in such a case is not voluntary but under duress, compulsion and coercion. The coercion is subtle, but very much real. The 'accord' is not by free consent. The arbitration agreement can thus be invoked to refer the disputes to arbitration. (v) A claimant makes a claim for a huge sum, by way of damages. The respondent disputes the claim. The claimant who is keen to have a settlement and avoid litigation, voluntarily reduces the claim and requests for settlement. The respondent agrees and settles the claim and obtains a full and final discharge voucher. Here even if the claimant might have agreed for settlement due to financial compulsions and commercial pressure or economic duress, the decision was his free choice. There was no threat, coercion or compulsion by the respondent. Therefore, the accord and satisfaction is binding and valid and there cannot be any subsequent claim or reference to arbitration.” 15. The facts of this case, as explained in the foregoing A.R.No.18/2003 -13- paragraphs, will show that the illustration pointed out by the Apex Court in paragraph 28(v) is more appropriate to the facts of this case. Therefore, I do not think that this judgment will help the applicant in any manner. It may be that the applicant was acting foolishly in having furnished Ext.R2(f) undertaking, but on the materials available, there is nothing to conclude that the undertaking was involuntary and as the applicant has acted with full comprehension of what they were doing, this Court cannot interfere the exercise of their volition. Since the applicant has not succeeded in establishing that Ext.R2(f) undertaking was issued under coercion or duress, I should uphold the objection raised by the respondents that the applicant has voluntarily given the undertaking, received payment and therefore, no case has been made out for appointment of an Arbitrator. The Arbitration Request will, therefore, stand dismissed. ## (ANTONY DOMINIC, JUDGE) jg
End of Judgment Record
Browse All High Court of Kerala (2010) Decisions
2010-09-09

T.K. Biju and Gangaprasad S. v. State of Kerala and The Director, Institute of Human Resources Development (IHRD)

This batch of writ petitions challenges the Institute of Human Resources Development’s (IHRD) recruitment process for the Last Grade Service under notification RECT/03/09/HRD (dated 21.1.2009). The core questions concern the validity of the 23.8.2009 written test, the 23.10.2009 short list (main and supplementary) drawn therefrom, and the 19.3.2010 rank list published after interviews. Petitioners—mostly former daily wage/ad hoc employees—also pursue regularisation, arguing that the selection framework and weightage for past service were either discriminatory or inadequately applied. Ext.P4 had disposed of earlier petitions by directing IHRD to finalise recruitment under a resolution dated 9.7.2007, and Ext.P5 laid down the recruitment rules: an objective written test (70 marks) and an interview (30 marks) with category-wise cut-offs (Rule 5.3) and a rank list valid for three years (Rule 5.4). The court holds that deviations such as clause 8 in the hall ticket do not render the process void in the absence of prejudice, and upholds the short-list’s legality to a large extent. However, drawing on Umadevi (3) and Satya Prakash, the court ultimately directs a limited revisiting of the rank list to grant weightage under Rule 5.2 to those petitioners who would have been included, while denying general regularisation. All petitions are disposed with these directions.

2010-01-21

State of Kerala and District Collector, Kollam v. K. Raghavan

This is a review petition filed by the State of Kerala and the District Collector, Kollam, challenging the High Court’s 23 March 2009 judgment in W.P.(C).29695 of 2005, which directed the Government to consider a freedom fighter’s pension claim and to grant pension from the date of application. The petition traces a long history: the applicant, aged about 75 at the time of filing on 29.12.1995, faced earlier adverse orders in 1987 and 1989; after litigation, the 2005 judgment directed reconsideration and culminated in a 2009 order granting pension in December 2009 but from the date of sanction rather than from the date of application. The review petition contends that the Supreme Court’s decision in State of M.P. and Another v. Devkinandan Maheshwari (2003) and a Division Bench decision followed in W.A. Nos.1419/2006 & 1818/2006 require pension from the date of sanction, not the application date, and thus the judgment should be recalled. It also relies on Dokka Samuel v. Dr. Jacob Lazarus Chelly (1997) to assert that omitting authorities is not a ground for review. The Court, however, finds that omission to cite authorities cannot ground a review and that the government’s delay in compliance violates the Court’s directions, warranting dismissal of the review petition with costs.

2010-02-23

Anitha Rajan v. Revenue Divisional Officer, Thrissur; Thasildar, Chavakkad; Village Officer, Nattika; Sub Registrar, Thriprayar

Anitha Rajan, the petitioner, purchased 50 cents of land in Re-Survey No.166/1, Nattika village, Thrissur district, from the legal heirs of late Gangadharan via Ext.P3 sale deed registered at Triprayar. The conveyance, through power of attorney documents Ext.P1 (executed by Ajayan in Dubai in favor of his mother Rathnabhai) and Ext.P2 (executed by Usha in India), prompted mutation proceedings before the Revenue Divisional Officer (RDO). The RDO refused to effect mutation unless the original Ext.P1 POA was produced for adjudication of stamp duty under the Kerala Stamp Act, 1959, claiming non-compliance with stamping and the need to determine stamp duty under sections 31 and 32. The petitioner contends that it is not mandatory to submit every PoA executed outside India for adjudication; only instruments chargeable with duty which cannot be stamped by private persons must be taken to the Collector under section 18(2). Ext.P1, though executed abroad, is on Indian stamp paper and was presented at registration, having been stamped Rs.150 under Article 44(f). The court analyzed sections 18(1), 18(2), 31 and 32 and held that section 18 applies to instruments executed outside India; since Ext.P1 is duly stamped, Section 18 has no application and Sections 31-32 cannot be invoked to compel production. Relying on Madras High Court decisions Manoharan v. Velu and R.B.K. Rajeswari Nachiar, the court held the Village Officer erred in requiring Ext.P1 before the RDO, quashed Exts.P4 and P6, and directed mutation actions to be completed within two months of certified judgment copy.

2010-03-23

V. Mohanan Nair v. Babu Pillai and others

This writ petition arises from a complex land dispute in Nedumangad where the petitioner, V. Mohanan Nair, challenged a trial court order that set aside a commissioner's report and remitted for a fresh report. In O.S. 380/2005 the plaintiff sought a permanent injunction; in O.S. 542/2005 the second respondent sought declaration of title and possession based on deeds executed in 2005. To resolve the location of the plaint schedule property, a commission was appointed, and Ext. P2 report and plan were filed. Subsequently, I.A. 4808/2009 was filed by the second respondent seeking to set aside the commission report and plan and remit for a fresh report. The trial court remitted the matter; Ext.P8 records the order, which the petitioner challenged in this Writ Petition. The respondents relied on a decision in Sarojini v. Karthiyani Amma to contend that Article 227 petitions against commission reports are not maintainable, while the petitioner argued lack of justification for remitting and the undue delay in filing the petition. The Kerala High Court, while recognizing the normal reluctance to exercise visitorial jurisdiction, held that exceptional circumstances permit interference under Article 227 and remanded the matter for fresh consideration, directing that the trial court assess sufficiency of Exts. C1, C1(a), C1(b) and allow further inspection if needed. The result is a remand to ensure a fair adjudication on the commission report."