Uttar Pradesh Power Transmission Corporation Ltd. & Anr. v. CG Power and Industrial Solutions Limited & Anr.
Case Synopsis & Summary
This Special Leave Petition challenges a Lucknow Bench High Court order that set aside letters demanding labour welfare cess of Rs. 2,60,68,814 from the respondent CG Power and Industrial Solutions Limited (formerly Crompton Greaves). UPPTCL sought to levy cess under the Building and Other Construction Workers Welfare Cess Act, 1996 (Cess Act) read with the Building and Other Construction Workers Welfare Collows Acting (BOCW Act) and the Cess Rules, arguing that the cost of construction included the supply, erection, and civil works within the project for a 765/400 kV substation at Unnao, and that cess should be recovered from the contractor. The Allahabad High Court held that without a levy/assessment under the Cess Act and the Rules, the UPPTCL’s demand was unsustainable, and that CAG audit observations cannot by themselves justify cess recovery. The Supreme Court, in a Division Bench, examined the contractual framework that split the project into four contracts: supply, erection, civil, and operations & maintenance. It held that a pure supply contract is statutorily exempt from cess under the BOCW Act, and that the first contract’s costs, being unrelated to construction, do not attract cess absent a proper assessment. The Court further noted there was no statutory mechanism to withhold payments or recover cess by invoking a bank guarantee outside the prescribed statutory framework. The Special Leave Petition is dismissed, upholding the High Court’s order and the bar on unilateral cess recovery absent statutory assessment.
Find Cases Like This
Explore other judgments dealing with similar legal situations, facts, or statutory provisions.
Case Details & Bench
- Court
- Landmark Cases
- Hon'ble Judges
- Indira Banerjee, J.
- Uday Umesh Lalit, J.
- Judgment Date
- 2021-05-12
- Court Decision / Holding
- The Special Leave Petition is dismissed.
- Final Disposition
- Special Leave Petition dismissed.
Parties to the Case
Appellants / Petitioners
- Uttar Pradesh Power Transmission Corporation Ltd.
- Anr.
Respondents
- CG Power and Industrial Solutions Limited
- Anr.
Provisions of Law Cited
Legal Doctrines & Maxims
- Availability of relief under Article 226 notwithstanding the existence of an alternative remedy (Harbanslal Sahnia v. Indian Oil Corp. Ltd.; Whirlpool Corporation v. Registrar of Trade Marks, Pimpri Chinchwad Municipal Corp. v. Gayatri Construction Co. & Ors)
- CAG reports are subject to scrutiny by Parliament and cannot be the sole basis for relief or recovery (Centre of Public Interest Litigation v. Union of India; Arun Kumar Agrawal v. Union of India; Pathan Mohammed Suleman Rehmatkhan v. State of Gujarat)
- A contractor entering into a pure supply contract is statutorily exempted from levy under the BOCW Act (divisible nature of contract leading to classification as supply vs. civil works)
- Divisible contract concept and single project management do not automatically convert a supply contract into a construction contract for cess purposes
Submissions & Arguments
Contentions of Appellants / Petitioners
The applicants contended that the Cess Act requires levy on the cost of construction for the welfare of building and construction workers, which includes civil works; however, they argued that the contract structure under the Framework Agreement created four distinct contracts, wherein the First Contract (Supply) is a pure supply contract and does not involve construction. Hence, cess under the Cess Act and the BOCW Act cannot be levied on the supply contract. The First Contract’s value, details of payment schedules, and the Special Conditions of Contract (SCC) underscore the separation of supply from civil works. There was no statutory assessment or levy under the Cess Act for the First and Second Contracts, and the reliance on a CAG report alone cannot justify cess collection. They further argued that the High Court correctly held that the exports were not subject to cess and that withholding payments or encashing a bank guarantee without statutory assessment exceeds UPPTCL’s powers. UPPTCL asserted it acted within the contract’s terms and the statutes; the decision to recover cess was invalid.
Contentions of Respondents
The respondents argued that the BOCW Act and the Cess Act were designed to fund welfare schemes for construction workers and apply to building and construction activities. They maintained that the four contracts collectively constitute a single project and that the cost of construction, including supply of equipment and associated works, falls within the definition of construction activities for cess. They highlighted that cess should be collected, assessed, and paid under the statutory framework, and that non-construction portions of the contract should not be treated as exempt automatically. They sought to rely on CAG reports as an objective basis for cess, subject to proper statutory assessment. They argued that the supply component is not entirely exempt in every circumstance and that a proper assessment under the Cess Act is required before recovering cess from payments or bank guarantees. They asserted that UPPTCL’s actions were unlawful for want of statutory authority and proper procedure, and that the High Court correctly annulled the demands in the absence of such assessment.
Explore This Legal Issue
Find relevant judgments and authoritative positions on the legal questions discussed here.
Cited Precedents (8)
| Case Name | Citation | Treatment | Explanation |
|---|---|---|---|
| Dewan Chand Builders and Contractors v. Union of India | (2012) 1 SCC 101 | Positive | Cited to explain the object of the BOCW Act and welfare of construction workers. |
| Lanco Anpara Power Limited v. State of Uttar Pradesh and Ors. | (2016) 10 SCC 329 | Mentioned Only | Cited as not directly applicable; issues in Lanco Anpara were not adjudicated on supply contracts vs. construction costs. |
| Centre of Public Interest Litigation v. Union of India | (2012) 3 SCC 1 | Positive | CAG reports are subject to parliamentary scrutiny and findings cannot be uncritically relied upon. |
| Arun Kumar Agrawal v. Union of India and Others | (2013) 7 SCC 1 | Positive | Further authority on the status and scrutiny of CAG reports within parliamentary processes. |
| Pathan Mohammed Suleman Rehmatkhan v. State of Gujarat and Others | (2014) 4 SCC 156 | Positive | Affirms the need to scrutinize CAG reports and the appropriate forum for such scrutiny. |
| Whirlpool Corporation v. Registrar of Trade Marks, Mumbai and Ors | AIR 1999 SC 22 | Positive | Supports the principle that availability of an alternative remedy does not bar writ petitions. |
| Pimpri Chinchwad Municipal Corporation v. Gayatri Construction Company and Ors | (2008) 8 SCC 172 | Positive | Reiterates the writ relief principle where applicable despite alternative remedies. |
| Harbanslal Sahnia and Ors. v. Indian Oil Corporation Ltd. | (2003) 2 SCC 107 | Positive | Affirms the discretionary nature of writ jurisdiction in contract disputes. |
Apply This to My Facts
Share your situation and test whether this judgment governs, supports, or challenges your case.
In The Court Record
Uttar Pradesh Power Transmission Corporation Ltd. & Anr. v. CG Power and Industrial Solutions Limited & Anr.
Related Decisions & Precedents from Landmark Cases
State of Himachal Pradesh & Anr. v. Pinju Ram & Others; State of Himachal Pradesh & Ors. v. Ganesh Dutt & Anr.
This batch of appeals concerns regularisation and monetary benefits of part‑time employees in Himachal Pradesh who were converted to daily‑wage status. The State had issued a policy on 27 February 2004: part‑time Class‑IV employees who had completed ten years of continuous service as on 31 December 2003 would be made daily wagers with prospective effect, and posts vacated by such employees would stand abolished; Education and Ayurveda were excluded from the policy. Revenue Chowkidars, engaged by Panchayats, were not covered by that policy and received separate treatment. Following writ petitions and an order of the Himachal Pradesh High Court and in light of later developments, the State drew‑up directions in 2011 (22 September) to give seniority to Revenue Chowkidars on the basis of ten years of service, but with wages from the date of actual appointment and without back‑dated monetary benefits; 7 July 2012 further instructions reiterated this stance for remaining part‑time employees, with monetary benefits not guaranteed in the interregnum. The respondents pressed for back wages dating from 1 January 2007 and broader coverage. The Supreme Court held that the 2007 back‑pay direction was unsustainable, clarified that seniority would count from ten years without past benefits, and that the 2011 policy and Moti Singh principle should guide the approach. The appeals are allowed; no costs. The related writ petitions are to be disposed of consistent with these directions.
Union Bank of India and Others v. C.G. Ajay Babu and Anr.
This is a Supreme Court of India appeal concerning the forfeiture of gratuity under the Payment of Gratuity Act, 1972. The respondent was a branch manager of the appellant bank and was dismissed on 3 June 2004 after disciplinary proceedings. A show-cause notice sought to forfeit gratuity due to misconduct involving moral turpitude, which was ordered on 20 April 2004. The High Court upheld the dismissal but held that gratuity could be paid since there was no financial loss to the bank, and that a bipartite settlement between the bank and employees permitted forfeiture only where misconduct caused financial loss. The Division Bench, however, held that forfeiture under Section 4(6) must be read together with Section 4(5) and that no loss was proven, thus entitling the employee to gratuity in accordance with the bipartite settlement. The Supreme Court agreed with the High Court that forfeiture is not automatic; it is controlled by Sections 4(5) and 4(6) of the Act and by the bipartite settlement, which requires loss to justify forfeiture. The Court emphasized that an act must constitute an offence involving moral turpitude and that conviction is generally required for forfeiture under 4(6)(b)(ii). The appeal is dismissed with no costs.
Reema Salkan v. Sumer Singh Salkan
This is a Supreme Court of India criminal appeal under the Criminal Appellate Jurisdiction arising from a maintenance dispute under Section 125 Cr.P.C. The parties, married in 2002, had a protracted litigation history. The Family Court granted maintenance to the wife from 17 July 2003 to 8 December 2010, and held no maintenance thereafter. The High Court, in revision, partly allowed the application, directing Rs.9,000 per month from 9 December 2010 onward, while upholding the earlier period’s Rs.10,000 per month. This Court had earlier granted interim maintenance of Rs.20,000 per month in 2014 (Criminal Appeal Nos. 2347-2349 of 2014). The appellant contends there has been no change in circumstances since the interim order and that the respondent’s substantial assets, education, and overseas earnings establish the capacity to pay higher maintenance. The respondent defends the High Court’s reasoning, arguing that the Family Court’s assessment, demeanor observations, and the principle that maintenance should not be perpetual require careful scrutiny, and that the notional minimum wage approach used by the High Court is flawed. The overarching issue is the quantum of monthly maintenance payable to the appellant and whether the interim amount should be augmented beyond the period up to 2010.”
M/s Embassy Property Developments Pvt. Ltd. v State of Karnataka & Ors.
This judgment concerns three Civil Appeals filed by a Resolution Applicant, the Corporate Debtor (through its Resolution Professional) and the Committee of Creditors, challenging an Interim Order of the Karnataka High Court staying an NCLT order in proceedings under the Insolvency and Bankruptcy Code, 2016. The NCLT Chennai had admitted an application under Section 7 of the IBC against M/s Tiffins Barytes Asbestos & Paints Ltd. and directed a moratorium under Section 14. The Interim Resolution Professional then sought a deemed extension of a mining lease under MMDR Act, 1957 and the Government of Karnataka rejected it. The NCLT, by an order dated 11.12.2018, set aside the Government’s order and directed execution of Supplement Lease Deeds for the period up to 31.03.2020. The Government of Karnataka challenged this in a High Court writ petition, which stayed the impugned NCLT order. The core issues were: (i) whether the High Court may interfere under Article 226/227 with an NCLT order in IBC when an appeal lies to the NCLAT, and (ii) whether fraud can be inquired into by NCLT/NCLAT in CIRP. The Court reiterates that IBC is a complete, umbrella code with a three‑tier mechanism (NCLT, NCLAT, Supreme Court) and that public‑law disputes arising from MMDR Act obligations lie outside IBC. It ultimately holds that while NCLT/NCLAT may inquire into fraud, they cannot adjudicate MMDR‑related public legal disputes; and the High Court’s writ jurisdiction in public‑law contexts remains permissible. The appeals are dismissed.