Uttar Haryana Bijli Vitran Nigam Ltd. & Anr. v Adani Power Ltd. & Ors.
Case Synopsis & Summary
This Supreme Court judgment, delivered by a Division Bench, consolidates two Civil Appeals (5865/2018 and 6190/2018) involving the Haryana Discoms (UHBVNL and DHBVN) and Gujarat Urja Vikas Nigam Ltd. (GUVNL) against Adani Power Ltd. and others, arising from power purchase arrangements for an SEZ-based coal-fired plant. The core issue is whether the parties are entitled to carrying costs in the wake of withdrawal of exemptions under the SEZ Act and related tax/duty exemptions, following notifications in 2015–2016. The PPAs contain Article 13 on Change in Law, with a restitutionary objective: restore the affected party to the economic position it would have occupied had the Change in Law not occurred. The MoC&I approved the project; subsequent government notifications withdrew exemptions, triggering a Change in Law. The CERC initially allowed carrying costs, and the Appellate Tribunal affirmed, while the Commission had concluded there was no provision for carrying costs in the PPAs. The Supreme Court, after examining Articles 13.2 (restitution) and 13.4.1 (effective date for tariff adjustment) held that restitutionary principles apply and the adjustment must be effected from the date of withdrawal of exemptions—subject to the thresholds and the construction/operation-period formulas—and affirmed the lower tribunal’s approach. The appeals are dismissed in terms of the signed reportable judgment, upholding the restitutionary basis for carrying costs under the PPAs.
Find Cases Like This
Explore other judgments dealing with similar legal situations, facts, or statutory provisions.
Case Details & Bench
- Court
- Landmark Cases
- Hon'ble Judges
- R. F. Nariman
- Navin Sinha
- Judgment Date
- 2019-02-25
- Court Decision / Holding
- The appeals are dismissed in terms of the signed reportable judgment.
- Final Disposition
- Appeals dismissed.
Parties to the Case
Appellants / Petitioners
- Uttar Haryana Bijli Vitran Nigam Ltd.
- Dakshin Haryana Bijli Vitran Nigam Ltd.
- Gujarat Urja Vikas Nigam Ltd.
Respondents
- Adani Power Ltd.
- Others
Legal Representation & Advocates
Counsels for Petitioners
- • Mr. Rakesh K. Sharma (AOR)
- • Mr. G. Umapathy
- • Mr. Nishant
Counsels for Respondents
- • Mr. Mukul Rohatgi
- • Mr. P. S. Narsimha
- • Mr. Mahesh Agarwal
- • Ms. Neeha Nagpal
- • Ms. Poonam Verma
- • Mr. Abiha Zaidi
- • Ms. Aparajita Upadhyay
- • Ms. Devanshi Singh
- • Mr. Malav Deliwala
- • Ms. Aditi Pathak
- • Mr. Arshit Anand
- • Mr. E. C. Agrawala (AOR)
Provisions of Law Cited
Legal Doctrines & Maxims
- Restitutionary principle under Article 13.2 (restore to the same economic position)
- Carrying costs under Change in Law as recognized in the PPAs and subsequent case law
- No Consequential or Indirect Losses (Article 18.17)
Submissions & Arguments
Contentions of Appellants / Petitioners
The appellants argued that carrying costs are not part of the PPAs in question and that restitutionary or equity-based recovery cannot override the express terms of the PPAs; they contended that no provision in the PPAs obliges payment of carrying costs and that adjustments should be governed strictly by the PPA’s terms.
Contentions of Respondents
The respondents contended that Article 13 embodies a restitutionary principle intended to restore the injured party to its pre-Change in Law economic position; they argued that the Commission and Appellate Tribunal were correct in recognizing carrying costs under Article 13, with the period and quantum to be determined by the PPA and the appropriate Commission; they relied on prior jurisprudence supporting restitution under Change in Law.
Explore This Legal Issue
Find relevant judgments and authoritative positions on the legal questions discussed here.
Cited Precedents (5)
| Case Name | Citation | Treatment | Explanation |
|---|---|---|---|
| National Thermal Power Corporation Ltd. v. Madhya Pradesh State Electricity Board | (2011) 15 SCC 580 | Distinguished | The Court/docket distinguished this judgment; reasoned that its facts and the PPAs’ restitutionary framework differ, leading to different application under Article 13. |
| South Eastern Coalfields Ltd. v. State of Madhya Pradesh and Ors. | (2003) 8 SCC 648 | Distinguished | The judgment was said to have no application to the present facts due to the Contractual (PPA) context and Article 18.17 limitations. |
| Indian Council for Enviro-Legal Action v. Union of India & Ors. | (2011) 8 SCC 161 | Mentioned Only | Not applicable to the facts; cited for restitution context but held not to apply to PPA Article 13 circumstances. |
| All India Power Engineer Federation and Ors. v. Sasan Power Ltd. and Ors. | (2017) 1 SCC 487 | Mentioned Only | Not applicable to facts; referenced but distinguished due to differences in the PPA framework. |
| Energy Watchdog v. Central Electricity Regulatory Commission and Ors. | (2017) 14 SCC 80 | Positive | Affirmed restitutionary principle under Article 13.2 and used to support the approach that restitution is integral to the tariff adjustment under Change in Law. |
Apply This to My Facts
Share your situation and test whether this judgment governs, supports, or challenges your case.
In The Court Record
Uttar Haryana Bijli Vitran Nigam Ltd. & Anr. v Adani Power Ltd. & Ors.
Related Decisions & Precedents from Landmark Cases
State of Himachal Pradesh & Anr. v. Pinju Ram & Others; State of Himachal Pradesh & Ors. v. Ganesh Dutt & Anr.
This batch of appeals concerns regularisation and monetary benefits of part‑time employees in Himachal Pradesh who were converted to daily‑wage status. The State had issued a policy on 27 February 2004: part‑time Class‑IV employees who had completed ten years of continuous service as on 31 December 2003 would be made daily wagers with prospective effect, and posts vacated by such employees would stand abolished; Education and Ayurveda were excluded from the policy. Revenue Chowkidars, engaged by Panchayats, were not covered by that policy and received separate treatment. Following writ petitions and an order of the Himachal Pradesh High Court and in light of later developments, the State drew‑up directions in 2011 (22 September) to give seniority to Revenue Chowkidars on the basis of ten years of service, but with wages from the date of actual appointment and without back‑dated monetary benefits; 7 July 2012 further instructions reiterated this stance for remaining part‑time employees, with monetary benefits not guaranteed in the interregnum. The respondents pressed for back wages dating from 1 January 2007 and broader coverage. The Supreme Court held that the 2007 back‑pay direction was unsustainable, clarified that seniority would count from ten years without past benefits, and that the 2011 policy and Moti Singh principle should guide the approach. The appeals are allowed; no costs. The related writ petitions are to be disposed of consistent with these directions.
Union Bank of India and Others v. C.G. Ajay Babu and Anr.
This is a Supreme Court of India appeal concerning the forfeiture of gratuity under the Payment of Gratuity Act, 1972. The respondent was a branch manager of the appellant bank and was dismissed on 3 June 2004 after disciplinary proceedings. A show-cause notice sought to forfeit gratuity due to misconduct involving moral turpitude, which was ordered on 20 April 2004. The High Court upheld the dismissal but held that gratuity could be paid since there was no financial loss to the bank, and that a bipartite settlement between the bank and employees permitted forfeiture only where misconduct caused financial loss. The Division Bench, however, held that forfeiture under Section 4(6) must be read together with Section 4(5) and that no loss was proven, thus entitling the employee to gratuity in accordance with the bipartite settlement. The Supreme Court agreed with the High Court that forfeiture is not automatic; it is controlled by Sections 4(5) and 4(6) of the Act and by the bipartite settlement, which requires loss to justify forfeiture. The Court emphasized that an act must constitute an offence involving moral turpitude and that conviction is generally required for forfeiture under 4(6)(b)(ii). The appeal is dismissed with no costs.
Reema Salkan v. Sumer Singh Salkan
This is a Supreme Court of India criminal appeal under the Criminal Appellate Jurisdiction arising from a maintenance dispute under Section 125 Cr.P.C. The parties, married in 2002, had a protracted litigation history. The Family Court granted maintenance to the wife from 17 July 2003 to 8 December 2010, and held no maintenance thereafter. The High Court, in revision, partly allowed the application, directing Rs.9,000 per month from 9 December 2010 onward, while upholding the earlier period’s Rs.10,000 per month. This Court had earlier granted interim maintenance of Rs.20,000 per month in 2014 (Criminal Appeal Nos. 2347-2349 of 2014). The appellant contends there has been no change in circumstances since the interim order and that the respondent’s substantial assets, education, and overseas earnings establish the capacity to pay higher maintenance. The respondent defends the High Court’s reasoning, arguing that the Family Court’s assessment, demeanor observations, and the principle that maintenance should not be perpetual require careful scrutiny, and that the notional minimum wage approach used by the High Court is flawed. The overarching issue is the quantum of monthly maintenance payable to the appellant and whether the interim amount should be augmented beyond the period up to 2010.”
M/s Embassy Property Developments Pvt. Ltd. v State of Karnataka & Ors.
This judgment concerns three Civil Appeals filed by a Resolution Applicant, the Corporate Debtor (through its Resolution Professional) and the Committee of Creditors, challenging an Interim Order of the Karnataka High Court staying an NCLT order in proceedings under the Insolvency and Bankruptcy Code, 2016. The NCLT Chennai had admitted an application under Section 7 of the IBC against M/s Tiffins Barytes Asbestos & Paints Ltd. and directed a moratorium under Section 14. The Interim Resolution Professional then sought a deemed extension of a mining lease under MMDR Act, 1957 and the Government of Karnataka rejected it. The NCLT, by an order dated 11.12.2018, set aside the Government’s order and directed execution of Supplement Lease Deeds for the period up to 31.03.2020. The Government of Karnataka challenged this in a High Court writ petition, which stayed the impugned NCLT order. The core issues were: (i) whether the High Court may interfere under Article 226/227 with an NCLT order in IBC when an appeal lies to the NCLAT, and (ii) whether fraud can be inquired into by NCLT/NCLAT in CIRP. The Court reiterates that IBC is a complete, umbrella code with a three‑tier mechanism (NCLT, NCLAT, Supreme Court) and that public‑law disputes arising from MMDR Act obligations lie outside IBC. It ultimately holds that while NCLT/NCLAT may inquire into fraud, they cannot adjudicate MMDR‑related public legal disputes; and the High Court’s writ jurisdiction in public‑law contexts remains permissible. The appeals are dismissed.