Upendra Choudhury v. Bulandshahar Development Authority & ORS.
Case Synopsis & Summary
This writ petition, filed under Article 32 of the Constitution, concerns a home buyer’s challenge to the Sushant Megapolis real estate project developed by Bulandshahar Development Authority and others. The petitioner seeks directions including cancellation of all agreements with the developers and refund of money, or in the alternative, that the project be completed and handed over within a reasonable time. He also prays for the constitution of a monitoring committee headed by a retired Supreme Court judge, a detailed forensic audit of all projects under the flagship, and investigations by agencies such as the CBI and ED. The Court recognises the petitioner’s genuine grievance but emphasizes that Article 32 relief would entail adjudication of issues that are better resolved within statutory frameworks. It highlights the existence of robust statutory remedies under the Consumer Protection Act 1986 (and successor legislation), the Real Estate (Regulation and Development) Act 2016 (RERA), and the Insolvency and Bankruptcy Code 2016 (IBC), and notes that criminal investigations are available under the Code of Criminal Procedure 1973. Relying on prior rulings such as Shelly Lal and Devendra Dwivedi, the Court concludes that entertaining a petition under Article 32 in these circumstances would amount to day-to-day supervision of a construction project, contrary to judicial review limits. Accordingly, the petition is declined, while preserving the petitioner’s right to pursue statutory remedies.
Find Cases Like This
Explore other judgments dealing with similar legal situations, facts, or statutory provisions.
Case Details & Bench
- Court
- Supreme Court of India
- Hon'ble Judges
- Dr. Dhananjaya Y. Chandrachud, J.
- M.R. Shah, J.
- Judgment Date
- 2021-02-11
- Court Decision / Holding
- Petition under Article 32 declined. The Court held that there is a statutory framework for relief to home buyers and entertaining an Article 32 petition would entail ongoing day-to-day supervision of a construction project, which is outside the scope of judicial review. The matter is disposed of with the liberty to pursue remedies available under the relevant statutes.
- Final Disposition
- Writ Petition under Article 32 declined; disposed of with liberty to pursue statutory remedies.
Parties to the Case
Appellants / Petitioners
- Upendra Choudhury
Respondents
- Bulandshahar Development Authority
- Ors.
Legal Representation & Advocates
Counsels for Petitioners
- • Manoj V. George
- • Shilpa Liza George
- • Akriti Jai Panmei
- • Manju E. George
Provisions of Law Cited
Legal Doctrines & Maxims
- Calibrated exercise of judicial discretion (as per Devendra Dwivedi v. Union of India)
- Day-to-day supervision of a construction project lies beyond the province of judicial review
- Statutory remedies must be exhausted before invoking Article 32
- Representative consumer complaints under statutory regimes
- Judicial intervention should not flood courts with petitions at the cost of time and resources
Submissions & Arguments
Contentions of Appellants / Petitioners
The petitioner argued for exercise of Article 32 jurisdiction to issue directions canceling contracts, refund money, or ensure completion of the Sushant Megapolis project; he also sought a monitoring committee led by a former Supreme Court judge, a forensic audit, and investigations by CBI/ED, asserting that the court should intervene given the ongoing home buyer grievances.
Contentions of Respondents
The respondents argued that Article 32 assistance is inappropriate in the present factual matrix because there exist explicit statutory remedies under consumer protection, RERA, and IBC; judicial supervision of a construction project is beyond the constitutional function of Article 32 and would crowd courts with matters best handled by statutory bodies and specialized forums.
Explore This Legal Issue
Find relevant judgments and authoritative positions on the legal questions discussed here.
Cited Precedents (5)
| Case Name | Citation | Treatment | Explanation |
|---|---|---|---|
| Shelly Lal v Union of India | Writ Petition (Civil) No 1390 of 2020 | Positive | Cited as precedent supporting non-entertainment of Article 32 petitions in similar circumstances. |
| Pawan Kumar Kushwaha and Ors. v Lucknow Development Authority and Ors. | Writ Petition (Civil) No 1001 of 2020 | Mentioned Only | Cited as a prior related proceeding; not controlling for the current decision. |
| Devendra Dwivedi v. Union of India and Ors. | Writ Petition (Criminal) 272 of 2020 | Positive | Cited for the principle of calibrated judicial discretion and the preference for statutory remedies. |
| Bikram Chatterji v Union of India | ( cited as part of examples of past intervention) | Mentioned Only | Referenced as an example of earlier court intervention in home-buyers’ cases. |
| Bhupinder Singh v Unitech Ltd | ( cited as part of examples of past intervention) | Mentioned Only | Referenced similarly to illustrate prior interventions in analogous real estate matters. |
Apply This to My Facts
Share your situation and test whether this judgment governs, supports, or challenges your case.
In The Court Record
Upendra Choudhury v. Bulandshahar Development Authority & ORS.
Related Decisions & Precedents from Supreme Court of India (2021)
HARI OM @ HERO v. STATE OF U.P.
This is a Supreme Court appeal arising from six accused tried in multiple trials for offences under IPC sections 396 and 412, the SC/ST Act (3(2)(v)) and the Arms Act. The Trial Court convicted Hari Om @ Hero of the 396 IPC offence and awarded death, while other accused received varying outcomes. The High Court confirmed Hari Om’s death sentence and upheld some convictions, while acquitting three co-accused. The Supreme Court, in a Division Bench led by Justice Uday Umesh Lalit, allowed the appeals by Hari Om and others, finding serious infirmities in the prosecution case, especially the testimony of PW5, a five-year-old child witness (Ujjwal). The Court held that corroboration of a child witness is a prudential rule rather than a hard requirement and that, given glaring inconsistencies and lack of reliable corroboration, the evidence could not sustain a conviction under Section 396 IPC against Hari Om. It also highlighted ambiguities in fingerprint evidence—its collection, handling, and interpretation—and noted the absence of robust link evidence connecting the accused to the crime. Consequently, Hari Om, Sanjay @ Sonu and Saurabh @ Sanju were acquitted and ordered to be set at liberty, with the Court emphasizing careful, circumspect evaluation of child-witness testimony and forensic evidence.
INDIAN BANK AND ANOTHER v. MAHAVEER KHARIWAL
This appeal concerns an Indian Bank employee who sought voluntary retirement under the Indian Bank Employees Pension Regulations, 1995 (Regulation 29), including a request for waiver of the three-month notice. The bank rejected the request on the ground that the employee was not eligible under Regulation 29, and initiated departmental proceedings which culminated in penalties. The employee challenged the rejection in a writ petition; the Single Judge dismissed it to the extent challenged here, but the Division Bench quashed the rejection and directed the bank to release retiral dues under the Pension Regulations. The Supreme Court, upholding the employer’s challenge, held that the voluntary retirement application dated 21.01.2004 was absolutely in consonance with Regulation 29 and that the 20.04.2004 rejection was illegal and contrary to Regulation 29. It held that the employee is entitled to all retiral benefits on the basis of voluntary retirement, and that the subsequent departmental enquiry would be non est since there would be no employer–employee relationship after retirement. The Court analyzed Regulation 29, including the three-month notice, the need for acceptance by the appointing authority, and the curtailment mechanism under Sub-Regulation 3, as well as the proviso to Sub-Regulation (1) relating to deputation. The appeal is dismissed with no costs, and the employee’s retiral benefits are secured while any further proceedings are void.
Hasmat Ali v. Amina Bibi & ORS.
This is a Civil Appeal under Section 100 of the Code of Civil Procedure, 1908, arising from a suit in which the plaintiff sought a declaration that the defendant was a tenant up to 31.03.2003, eviction of the defendant from the suit shop, and other reliefs. The Trial Court partly decreed the suit directing the defendant to vacant possession; the Appellate Court dismissed the appeal, and the High Court, in Regular Second Appeal No. 403 of 2017, dismissed the appeal in limine without giving reasons. The essential issue is whether the High Court could dismiss a second appeal in limine without recording reasons and whether the appeal should be admitted for consideration of substantial questions of law under Section 100(1)–(5). The Supreme Court examines the interplay between Section 100 and Order XLII, clarifying that a second appeal lies only if the High Court formulates a substantial question of law under Section 100(4) and that the appeal must be heard on that question under Section 100(5). It reinforces that a dismissal in limine requires explicit reasons and that “so far as may be” in Order XLII indicates procedural alignment with Order XLI. Applying these principles, the Court sets aside the High Court’s order for lack of reasons, allows the appeal, and remits the matter to the High Court for fresh disposal in accordance with law, with no costs. The decision underscores the mandatory requirement of reasoned orders in second-appeal dismissals.
Sudipta Chakrobarty & Anr. v. Ranaghat S.D. Hospital & Ors.
This Civil Appeal concerns the practice of delivering a final operative order without accompanying reasons in proceedings before the National Consumer Disputes Redressal Commission (NCDRC) and the consequences of delaying reasons. The National Commission pronounced the operative order in 2019 but took eight months to issue a reasoned judgment, prompting scrutiny under Article 21 of the Constitution. The Supreme Court recalls established authority that the right of aggrieved parties to challenge an order on its merits is prejudiced when reasons are withheld or delayed, and that due process requires timely, reasoned decisions. Citing State of Punjab & Ors. v. Jagdev Singh Talwandi (1984), Anil Rai v. State of Bihar (2001) and Zahira Habibulla M. Sheikh & Ors. v. State of Gujarat (AIR 2004 SC 3467), among others, the Court reiterates that pronouncing the operative portion without reasons undermines the fruits of litigation and defeats subsequent remedies. In the instant case, there was a hiatus of eight months between the operative order dated 26.04.2019 and the accompanying reasons. The Court orders that the President of the National Commission examine the matter and take steps to discontinue this practice, ensuring that reasoned judgments are delivered together with operative orders. The appeal and pending applications are disposed of.