U.P. Electricity Board, Lucknow & Ors. v. City Board, Mussoorie & Ors.

Case / Petition Number:
Civil Appeal Nos. 814 and 815 of 1974
Neutral Citation:1985 SCR (2) 816

Case Synopsis & Summary

This appeal concerns the fixation and subsequent enhancement of grid tariffs for electricity in the Ganga–Sarda Grid under the Electricity (Supply) Act, 1948. The City Board, Mussoorie—a local licensee—challenged the validity of the tariff fixed by the Uttar Pradesh Electricity Board in 1962 (under section 46) and the 1967 enhancement (by two notifications), contending that no regulations under section 79(h) had been framed, rendering the tariff arbitrary and invalid under Article 226 of the Constitution. The High Court dismissed the petition; the Division Bench later allowed the appeal in part, holding that while the Act provides ample guidance, the additional charge of 7.5% and the 20% enhancement were illegal; it directed afresh consideration of tariffs for the period up to July 1, 1968. The Supreme Court analyzed whether section 46(1) requires regulations before fixing a Grid Tariff. It held that although tariffs must be fixed in accordance with regulations, framing regulations under section 79(h) cannot be a condition precedent for fixing tariffs, and a Grid Tariff may be fixed in the absence of such regulations if guided by the Act, with non-discrimination and government oversight. The Court affirmed that a common Grid Tariff for an area is permissible and left certain questions open for recalculation. The appeals were disposed of with no costs; the Electricity Board may reconsider the specified periods as directed by the High Court’s Division Bench.

Precedent Explorer

Find Cases Like This

Explore other judgments dealing with similar legal situations, facts, or statutory provisions.

Case Details & Bench

Court
Supreme Court of India
Hon'ble Judges
  • Chinnappa Reddy
  • E. S. Venkatramiah
  • Sabyasachi Mukharji
Judgment Date
1985-02-08
Court Decision / Holding
Appeals disposed of; no costs; matter remanded to Electricity Board for reconsideration in line with the High Court’s directions for the specified periods.
Final Disposition
Appeals disposed of; no costs; matter to be reconsidered by the Electricity Board for the specified periods as directed by the Division Bench of the High Court.

Parties to the Case

Appellants / Petitioners

  • U.P. Electricity Board, Lucknow & Ors.

Respondents

  • City Board, Mussoorie & Ors.

Legal Representation & Advocates

Counsels for Petitioners

  • • D. N. Kackar
  • • Gopal Subramaniam
  • • Mrs. Shobha Dikshit

Counsels for Respondents

  • • U. R. Lalit
  • • B. S. Chauhan

Provisions of Law Cited

Electricity (Supply) Act, 1948, s.46Electricity (Supply) Act, 1948, s.58Electricity (Supply) Act, 1948, s.79(h)Constitution of India, Art. 226

Legal Doctrines & Maxims

  • No undue preference / Non-discrimination
  • Rationalisation of production and supply of electricity
  • Unjust enrichment doctrine

Submissions & Arguments

Contentions of Appellants / Petitioners

City Board contended that the impugned grid tariffs under section 46 were void for lack of regulatory guidance under section 79(h); no regulations existed when the notifications were issued, making the tariff arbitrary. It also attacked the 1967 enhancement and the subsequent charges as unauthorized, seeking relief for the period prior to the writ petition.

Contentions of Respondents

UP Electricity Board argued that grid tariffs could be fixed even in the absence of regulations, and that the Act provides ample guidance; fixation of a common Grid Tariff for the area is permissible to promote uniform development, subject to government control and non-discrimination. It contended that the levy of the additional charges and the later directives should be reconsidered within the scope of tariff policies, and that the City Board cannot challenge the grid tariff for the pre-petition period since the writ was filed after the period in question.

Legal Doctrine & Issue Explorer

Explore This Legal Issue

Find relevant judgments and authoritative positions on the legal questions discussed here.

Cited Precedents (2)

Case NameCitationTreatmentExplanation
Maharashtra State Electricity Board v. Kalyan Borough Municipality and Anr.[1968] 3 S.C.R. 137PositiveThis Court’s reasoning and guidance on tariffs and regulatory framework were followed.
Mysore State Road Transport Corporation v. Gopinath Gundachar Char[1968] 1 S.C.R. 767PositiveUsed to illustrate that regulations under a statute need not be framed before operational provisions are applied; tariffs can be fixed with available guidance.
Case Applicability Diagnostic

Apply This to My Facts

Share your situation and test whether this judgment governs, supports, or challenges your case.

Official Judgment Record
•4,441 words•~21 min read

In The Court Record

U.P. Electricity Board, Lucknow & Ors. v. City Board, Mussoorie & Ors.

_>_ The U .P. Electricity Board under a notification dated 24 April 1962, **fixed the tariff payable** **by** **licensees** **who** **used to get bulk supply** **of electric** **tnergy.** **The** **tariff** **so** **fixed** **was** **enhanced** **by** **another notification** **dated** **September** **30,** **1967 by** **20%** **which came into force** **on** **December,** **l, 1967.** **The** **City** **Board,** **a licensee,** **moved** **the State Government on September** **13,** **1966** **for** **permission to** **enhance** **the rates for supply; but no such sanction** **was given** till March 23, 1968. The City Board questioned the validity of the tariff fixed and its subsequent enhancement under Art. 226 on the grounds: (I) that the notifica· lion dated April 24, 1962 was not in conformity Y'ilh s. 46, and (2) that it had **not been permitted** **to enhance correspondin@'ly** **the** **rates chargeable** **by it. The** **petition was,** **however,_** **dismissed.** U.P. STATE ELECTRICITY BOARD. LUCKNOW & ORS. A _v._ CITY BOARD, MUSSOORIE & ORS. ETC. (AND VICE VERSA) _February 8,_ _1985_ [0. CHINNAPPA REDDY, E.S. VBNKATARAMIAH AND SABYASACHI MUKHARJI, JJ.] _E/ectriclty (Supply) Act,_ _1948,_ _sections 46_ _and_ _56-Grid tariif-Flxa1ion_ _**of-Framing of Regulations under section 79(h)--Whether**_ _**condition**_ _**precedent-**_ _A_ _common_ _tariff for all_ _licensees_ _in_ _an_ _area_ _servtd by the grid-Whether_ _permlssibl•._ **B** c Section 46 of the Electricity (Supply) Act 1948 prov id•s that a '"if 'r **be** **known** **as** **the Grid Tariff shall,** **in accordance with** **any-regulations made,** be fixed from time to time by the Electricity Board. Section 58 enables a local **authority to implement** th~ **directions issued by** **the Electricity Board** **or** **the** **D** **Government with regard to** **amortisation** **and tariffs** **policies.** On appeal the Division Bench partly allowed the app.al, holding : (i) **1-rt1t** **ample guidance** **is available** **in** **the** **Act,** **and** **that** **the rates fixed** **are subject** **to the control of the** **State** **Government** **: (ii)** **that** **the** **levy** **of** **an** **additional** **7.1/2** **%** **as an** **aC.diticnal** **charge and subsequent** **enhancement** **under** **the** **two** **notifications** **was** **illegal;** **(iii) that** **it** **was open** **to the Electricity Board to** **make** **an** **additional** **charge** **to** **the** **e:ii:tent** **of the** **actual** **expenditure** **incurred by** supplying energy at 6600 volts, and (iv) that the Electricity Board should consider afresh rates at which electric energy could be supplied, E **F** G Both the City Board and the Electricity Board filed appeals to this Court. It was contended on behalf of the City Board that in the absence of any re'ulations layin$ down the principles for fixins the tariff under s. 79, the **H** A B c D F G H (2) Th• Electricity (Supply) Act 1948 had been enaoted to provide for the rationalisation of the production of supply of electricity and generallyfor taking measures conducive to electrical development. It is, therefore, permissible for the Electricity Board to fix a common Grid Tariff for an area so that there may be a reasonably uniform development of the area by the supply of electric energy to all licensees or consumers in the area at a uniform rate with such reasonable variations as may be permissible in law subject to the condition that no undue preference is shown to any of them. The Act also furnishes ample guidance regardina: the determintioo of tariffs by an Electricity Board. [823A-CJ _Maharashtra Stal• El•ctricity Board v._ _Ka/ya11 Boro•gh_ _MU11icipa/ity_ _alld_ _Anr .._ [1968] 3 S.C.R. 137, followed. (3) The validity of the levy of additional char11es could not be questioned by the City Board under Article 226 of the Constitution in respect of the period prior to the filing of the writ petition. The additional charec of 7.1/2% was levied in 1962,and the City Board did not questicn it before tho Court till March 23, 1968 when it filed the Writ Petition. Moreover, the City Board had not stated that it had not collected charges from the consumers of electric energy supplied by it at the rates which would cover the additional 7.1/2%.and had not recouped itself by collecting the charges from the consumers. The presun1ption in this situation would be that the City Board had not suffered any loss by the levy of 7.1/2% by way of additional charges. [823 G-H 824 A-Bl In the instant case, the City Board has been given directions from time to time by the Government regarding the charges it may collect from the consumers in the light of the charges it has to pay to the Electricity Board and its own investment expenditure on the undertakina:. The City Board cannot question the Grid Tariff only without at the same time questioning the directions pursuant to which it has been collecting charges from its consumers. No satisfactory material has been placed before the Court showing that the charges which were being collected by the City Board from the consumers were µneconomic•I and di4 not satisfy th~ r~asoqable standards which should 816 SUPREME COURT REPORTS (1985] 2 S.C.R. two Notifications issued under s. 46 of the Act were void as they had been issued without any guidance and were, therefore, arbitrary. On the question whether the grid tariff fixed suffered from vice of arbitrariness, I _'r_ HELD: (1) Whiles. 79(h) of the Act authorises the Electricity Board to make regulations laying down the principles governing the fixirg of Grid Tariffs, s. 46(1) of the Act does not say that no Grid Tariff can be fixed until such regulations are made. It only provid~s that the Grid Tariffs shall be fixed _Y--_ in accordance with any regulations made in this behalf. The framing of regulation under s. 79(h) of the N:t cannot, therefore, be a condition precedent for fixing the Grid Tariff. In the instant case, the Grid Tariff fixed did not suffer from the vice of arbitrariness. [82JE-G; 822E] _Mysore State Road Transport_ _CorPQration_ _v._ _Gopinath Gundachar Char_ (1968] 1 S.C.R. 767, followed. ##### • _')_ U.P ... ELECTlUCITY BOARD _v._ CITY BOARD _(Venkataramiah,_ _J.)_ 817 **govern** **the** **directions issued by the** **Electricity Board or** **the Government** **from** **time to time regarding the** **tariff's** **policies** **of the City Board. Therefore.** **it** **would not be** **proper to reopen the claims of the City Board** **in** **regard** **to the** **period prior to** **the filing** **of the** **writ** **petition arising** **on** **the.basis of the alleged**, invalidity of the notification dated April 24, 1962. The deci1ion of the High **Court** **on** **the above point** **is** **allowed** **to** **remain only for** **the period between** **March** **23,** **1968 and** **July** **1,** **1968.** **No opinion on its correctness** **is** **expressed** **bccallse** **the** **period** **is** **sman** **one and the Electricity Board has not** in~isted upon a decision on thi1 question. The relief granted by the High Court with regard to the levy of additional charge _of_ 20% with effect from December!, !967 till July I, 1968 i1 also not disturbed for the same reason1; [824D·H; 825Al. **The** **matter may** **be reconsidered by the** **Electricity Board as** **directed** **by** the High Court on the other points in regard to the above specified periods. [824B] C1viL APPELLATE JURISDICTION : Civil Appeal Nos. 814 and 815 of 19.74. _U._ _R. La/it_ and _B._ S. _Chauhan_ for the Respondent in CA. No. 814 and Appellant in CA. No. 815. - The Judgment of the Court was delivered by VENKATARAMIAH, J. These two appeals by special leave are filed against the judgment dated August 13, 1970 of the High Court of Allahabad in Special Appeal No. 34 of 1969 _(City_ _Board,_ _Mussoorle_ v _State Electricity B-Oard_ _&_ Ors.)(') by the Uttar Pradesh Electricity Board (hereinafter referred to as 'the Electricity Board') constituted under the Electricity (Supply) Act, 1948 (hereinafter referred to as 'theAct')and the CityBoard,Mussoorie, a local authority (hereinafter referred to as 'the City Board') respectively. The City Board as a licensee under the Indian Electricity Act, 1910 used to get bulk supply of electric energy from the Electricity Board from the Ganga·Sarda Grid and in its turn was distributing it to the consumers within its jurisdiction. In the year 1962, under a (I) A.J.R. _1911_ Allahabad 2j9, A **B** c From the Judgment and Order dated 13. 8. 1970 of the High Court of Allahabad in Special Appeal No. 34 of 1969. **D** s. _N._ _Kackar, Gopa/ Subramaniam_ and _Mrs._ _Shobha Dikshit_ for the Appellant in CA. No. 814 and respondent in CA. No. 815. E F G _y-_, ·• ###### \' A B ##### _c_ D F G H 318 SUPREMB COURT REPORTS (1985] 2 S.C.R notification dated April 24, 1962 issued under section 46 of the Act, the tariff payable by the City Board and other licensees in the GangaSarda Grid was fixed by the Electricity Board. The relevant portion of the Tariff was as follows: "I. _Applicability-This_ rate schedule is applicable to all licensees situated in Ganga Sarda Grid area and taking supply in bulk from the Board. 2. _Character of service-A._ C., 3, Phase, 50 cycles, 11,000 volts, Alternatively, the supply can be given at a voltage lower than 11 KV in which case an additional charge at 7. 1/2 per cent on the total amount of the bill will be levied. If the consumer takes supply at a standard voltage above 11 KV, a rebate of 5% will be allowed to him by the Board on the total amount of the bill calculated at the rates prescribed for supply at KV. 3. _Rate:-_ (a) _Demand Charges-_ I "" #### • First 500 KVA of Chargeable demand during the month at the rate of ...... Ne:i:t 1500 KVA of the chargedemand during the month at the rate of· ...... All above 2000 KV A of the chargeable demand during the month at the rate of ...... _PLUS_ (b) _Energy Charges-_ ... Rs. 12.75 per KVA ... Rs. 10.00per KVA ... Rs. 8.50 per KVA First 170 Kwh, per KVA of Charge· able demand consumed during the month at the rat~ of ... ·•"., .. ·•·· SP· per Kwh A #### • ## # U.P. ELECTRICITY BOARD _v._ CITY BOARD _(Venkataramiah,_ _J.)_ 819 Next 170 Kwh. per KVA of chargeable demand consumed during the month at the rate of .............................. ..4P. per Kwh . 4. (i) _Chargeable_ _Demand-The_ chargeable demand for the month shall be defined as the actual demand during the month or 60 per cent of the contracted demand or 75 per cent of the highest demand which occurred during the preceding 11 months, whichever is the highest. (ii) _Coal-Clause-The_ above rates shall be subject to a coal price adjustment at the rate of 0.001 per Kwh. increase or decrease for every one P. of variation .above or below Rs. 40 per tonne of coal delivered at the bunkers in the Harduaganj Generating Station ........................ .. Remaining Kwh. per KVA of the chargeable demand consumed during the month B at the rate of ....................................... 3P. per KWh c D 5. _Determination of Demand:-Demand_ measurement shall be made by suitable instruments at the point of deli very. The demand for any month shall be defined at the E highest average load measured in Kilovolt-amperes during any 30 consecutive n;iinutes period of the month." The tariff so fixed was enhanced by another notification dated September 30, 1967 by twenty per cent and the enhanced rate come into force on December I, 1967. Under section 58 of the Act, the F Electricity Board or where no snch Board was constituted, the State Government had the power to direct the amortisation and tariffs policies of any licensee, being a local authority, with respect to its licensed undertaking in such manner as the Electricity Board or the State Government, as the case may be, after giving the local authority a reasonable opportunity of being heard, considered expedient for the purposes of the Act. The licensee, being a local authority, G the provisions of any other law or of any rules made or dir.:ctions given thereunder notwithstanding, was bound to give effect to any such directions of the Electricity Board, or the State Government, as the case may be. The Electricity Board however, could not issue any directions under section 58 of the Act except after obtaining the prior approval of the State Government. The City Board had H A B c D E G 820 SUPl.BJA! CQUl.T,ll~O&TS (1985) 2 s.c.1.. moved the State Government on September 13, lt66 for permission to enhance the rates for aupply of electric energy to Consumera, No llUch san.ction was aiven till March 23, IP68. The City Board, therefore, filed a petition under Article 226 of the Constitution questio· ning the validity of the tariff ~ed under the notification dated April 24, 1962 a,nd the enh1111cemc11t made under the notification da. . ' ted September 30, ' . - . ' . 1967. It may, ho.wever, be stated here that . subsequently on April 20, 1P68, the City Board was permitted to raise tJle c~rg~~ for light aµd f11n by two paise per unit which came to 6% \l.r 7% of~he origi11al ra~es aJ)d bY 10% for el,ectric energy supplied for otl!cr purposes. The City Board challenged the notification issued on April 24, 1962 on the ground that it was not in conformity with aection 46 ofth.e A,ct. ~qi,uest.ion~d the enhanceiµent ma.de on September 30, 1967 on th,e ·around t~t it !l~d Q9t been penn\\ted to. ephance correspondingly th~ rat~s chargeabl,e by it to tile coµsuw.~rs even though in i~s vid.ni,ty t~e Electri,city Board. itself was suRplying electric energy to consumers at a much higher rate. The petition was contested by the Electriciiy Board. The Writ Petition was heard by a Single Judge of the High Court. He dismissed the petition. The City Board, thereafter filed an appeal before ihe Division Bench of the High Court. The Divi· sion Bench allowed the appeal in part. Aggrieved by th~ judgment of the Division ·Bench, the City Board and the Electricity Board have filed the above appeals by special leave. The m.aterial part or aection 46 of the Act reads thus: "46. (I) A tariff to be ~nown as the Grid Tariff shall in accordance with any regulations made in this b~half, be fixed from time to time by the Board in respect of each. ar~a for which a scheme is in force, and tariffs fixed under this section !)lay, fr th.e Board thinks fit, differ for different . "' . ax:eu. (2) WitJlout prejudice to the provisions o( se~~ion 47, tile tjrid Tariff shall &J?ply ~o s11le"s. of el~~tnc1ty by.the Board to. licensees wberQ .~o ~eq\lir~d \l!ld.er a?y of the F1~~t, Seco'nd and Third Schedul~s, !l)ld slulll, subJect ~s he~em • .. I "" I ##### • ) '" _',,>_ regulations laying down the principks Emerning the fixing of _Ori_ Tariffs. But section 46 (I) of the Act does not say tha.t nQ Grid Tar ff can be fixed until such regulations are made. It only provi· des that the Grid Tariff shall be in accordance with any regulations . . ### . made in this behalf. That means that if there were any regulations the Grid Tariff should be fixed in accordance with such regulations and nothing more. We are of the view that the framing of regulations under section 79 (h) of the Act cannot be a condition precedent for fixing the Grid Tariff. A similar contention was rejected ·by this Court in _Mysore_ _State Road Transport_ _Corporation_ v. _G_opilJa!h_ _Gwzdachar_ _Char(_ _[1]_ _)_ which was a case arising under the Road Tra11~port Corporation Act, 1950. Under section 14 of that Act a Road Trans· port Corporation was entitled to appoint officers and servants as cit considered necessary for the efficient performance of its sa~ctions. u.P. ELBCTl.iCITY BOARD _v._ _CITY_ IIOUD _(Venkataramlalt,_ J.) 821 after provided, also be applicable to sales of electricity by the Board to licensees in other cases: Provided that _if_ in any such other case _it_ appean to the Board that, having regard to the extent of the supply required, the transmission expenses involved in affording the supply are higher than those allowed in fixing the Grid Tariff, the Board may make such additional charges as _it_ considers appropriate,. ................................................ " The first contention urged before us by the City Board is that in the absen~e of any regulations framed by the Electri~ity Board under section 79 of the Act regarding the principles go\'erniiig tb,e fixing of Grid Tariffs, _it_ was not open to the Electricity Board to issue, the ill)pq~ed notjficat.ions. T~.is contentiq17 is ba~ed on subsection (1) of sectio.n 46 of the Act which provides that a t!lrilf to be known as the Grid Tariff shall _in_ _accordance_ _with_ _any_ _regulationJ._ _made_ _In_ _this behalf,_ be fixed from tiD1e to time by th.c Electricity Board. It is urged that in the absence of any regulationt laying down the principles for fixing the tariaff, the impugned notifications were void as they had been issued without any guidelines and were,. therefore, arbitrary. It i.s admitted that no such regulations hadt been made by the Electricity Board by the time the impugd ned notifications were issued. The Division Bench b .. s nega lived the above plea and according to u_s, rightly. It is. ti:ue tha section 79 (h) of the Act authorises the Electricity Board to ~-ke c D F G Under section 34 (I) of the Road Transport Corporation Act, 1950 (1l [1968) 1 S.C.R. 767, A B c D E 822 SUPREMB COURT REPORTS (1985) 2 S.C.R. the Slate Government had been empowered _inter alia_ to issue directions to the Road Transport Corporation regarding recruitment, conditions of service and training of its employees.. Under section 45 (2) (c) of that Act, the Road Transport Corporation was empowered to make regulations regarding the conditions of appointment and service and the scales of pay of officers and servants of the Corporation other than the Chief Executive Officer, General Manager and the Chief Accounts Officer. Admittedly no regulations had been framed under section 45 (2) (c) of that Act. It was contended that the Corporation could not appoint officers and servants referred to therein or make any provision regarding their conditions of service until such regulations were made. This Court rejected the said plea with the following observation at page 770: "The conjoint effect ofss. 14 (3) (b), 34 and 45 (2) (c) is that the appointment of officers and servants and their conditions of service must conform to the directions, if any given by the State Government under s. 34 and the regulations, if any, framed under s. 45 (2) (c ). But until such regulations are framed or directions are given, the Corporation may appoint such officers or servants as may be necessary for the efficient performance of its c;luties on such terms and conditions as it thinks fit." We do not also find any merit in the submission that the Grid TariJf lixed in this case suffered from the vice '. of arbitrariness. As observed by the Division Bench of the High Court, there is ample guidance available in the various provisions of the Act and F that the rates fixed are subject to the col)tr9l of the State Government. We do not find it necessary to repeat what is stated by the Division Bench except observing that we respectfully agree with the reasons given by it for rejecting the said plea. In _Maharashtra_ _State Electricity Board_ v. _Ka/yan Borough Municipality_ & _Anr.,\_ ') this Court has. discussed the relevant' provisions of the Act while dealing G with section 49 thereof which show that the Act furnishes ample guidance generally regarding the. determination of tariffs by an Electricity Board functioning under the Act. There is also no merit in the submission that there cannot be a common tariff for all licensees in an area served· by a Grid and.that there should be a separate rate .... ' ll (I) [1968] 3 s.c.R. 137. A B c D E F G H _,>· ' tJ.P. ELllCtRICtTY llOAllD _v._ CITY BOARD _We11kataramiah,_ J.) 823 of charge for each licensee. While it.may not be objectionable to have a reasonable tariff fixed in the case of a particular licensee without offending the rule of non-discrimination, fixation of a common Grid Tariff is in consonance with the spirit of the Act. The preamble to the Act says that it had been enacted to provide for the rationalisation of th> production and supply of electricity and generally for taking measures conducive to electrical development. Looked at against this background, it is permissible for the Electricity Board to fix a common Grid Tariff for an area so that there may be a reasonably uniform development of the area by the supply of electric energy to all licensees or consumers in the area at a uniform rate with such reasonable variations as may be permissible in law subject to the condition. that no undue preference is shown to any of them. The Division Bench, however, held that the levy of an additional 7. I _!2_ % as an additional charge- made by the Electricity Board under the first para of clause (2) of the impugned notifications dated April 24, 1962 and September 30, 1967 was illegal and therefore liable to be quashed because according to it the adpitional charge of 7.1/2% could be imposed under the proviso to section 46 (2) of the Act to cover extra expenses only and not for supplying electric energy at a lower voltage of 6600 volts when the Grid Tariff had fixed rates for supplying electric energy at 11000 volts. It however, held that it was open to the Electricity Board to make an additional charge only to the extent of the actual expenditure incurred by supplying electric energy at 6600 volts. It also quashed the Government order dated April 20, 1968 by which the City Board was permitted to increase the charges payable by the consumers in some respects and the subsequent action taken on the above basis. The Division Bench directed the respondents to consider afresh the question of the rates at which electric energy could be supplied. We do not propose to go into the correctness of this part of the decision of the Division Bench because we are of the view that this case can be dispesed of in a different way. The contention relating to the validity of the levy of additional charges could not be raised by the City Board under Article 226 of the Constitution in respect of the period prior to the filing of the writ petition. The above additional charge of 7. t /2 % was levied in 1962 and the City Board did not question it before the Court till March 23, 1968 when it filed the writ petition. It is further seen that it has not stated that it had not collected charges from the consumers cf electric energy supplied by it at th~ I .,., c D' E F G H (l98S} :! s.c.R. rates Wnich w6uld cover the additional 7.1/2%. The learned counsel for the City Board was not able to state that the City Board bad nt>t recouped itself by collecting the charges from the consumers. In thi~ sitliation we have to presume that the City Board had not suffered any loss by the levy of 7. I /2 % by way of additional charges. We are of the view that in cases of this nature where there is little or 110 pOssilillity of refunding the excess amount collected from the ultifuate consumer to him and the granting of the relief to the petitioiler would result in his unjust enrichment, the Court should not otl!inarily direct any refund in exercise of its discretion under Artie!~ 226 of the Constitution. Moreover in this case the City Board woke up nearly 6 years after the issue of the first notification attd ibat too only after an enhancement by 20% was made under . the second nohfication. In the case of the City Board, which is a local authority, there is an additional reason. Under section _58_ of tlib A'ct whicb is already referred to above a local anthority is bound t<i implement the directions Issued by the Electricity Board or the Gove'tinileiit, as !he case may be, with regard to the amortisation an'd tariffs policies. The City Board bas been given directions from time to time by the Government regarding the charges it may collect fr'6nl the consumers in the light of the charges it bas to pay to the ElectriCity Board and its own investment and expenditure on the umfortaking. The City Board cannot question the Grid Tariff only withnul .at the same time questioning the directions pursuant to which it bas been collecting charges from its consumers. No satisfactory material is placed before the Court showing that the charges which Were being collected by the City Board from the consumers were uneconomical and did not satisfy the reasonable standards w'blch should govern the directions issued by the Electricity Board or t'tie Government from time to time regarding the tariffs policies· of the City Board. In this situation, we feel that it would not be proper to reopen the claims of the City Board in regard to the period prior to to the filing of the writ petition arising on the basis of the alleged invalidity of the notification dated April 24, 1962. Hence we refuse to grant any relief in this regard to the City Board for the periOd. up to the date of the writ petition, that is, till March 23, 1968. The Grid Tariff was revised in this case on July I, 1968. The decision or tlie High Court on the above point is, however, allowed to remain only for the period between March 23, 1968 and July I, 1968 without expressing any opinion on its correctness because the period is a small one and the Electricity Board does not insist upon a deCisioii on this question in this case. The question is left open by , I > I, tl.P. ELl!CTRiCITY BOAIID _v._ CITY BOARD _(Penkataramiah,_ J.) ru us. Similarly, the relief granted by the High Court with regard to the levy of additional charge of 2 % with effect from December I, 1967 till July I, 1968 is not disturbed by us for the same reason without expressing any opinion on its correctness. This judgment shall not be construed as affirming the decision of the High Court in so far as the above points are concerned. The matter may be reconsidered by the Electricity Board - '•' . ' ~ as directed by the Division -Bench of the High Court but with regard to the periods specified above . The appeals are accordingly disposed of. There shall be no order as to costs. A.P.J. A B c
End of Judgment Record
Browse All Supreme Court of India (1985) Decisions
1984-09-28

Gurpal Tuli and Ors. v. State of Punjab and Ors.

This Supreme Court decision concerns pay scales for teachers in the Punjab government schools in light of circulars issued in 1967, 1979, and 1957. The appellants—Masters and Mistresses holding M.A., M.Sc., B.T. or B.Ed. degrees—petitioned for the higher Lecturer’s grades set out in paragraph 2 of the Government Circular Letter dated July 29, 1967 (Rs. 300-25-450/25-600 for those with first and second division Master’s degrees; Rs. 250-25-400/25-550 for those with third-class Master’s degrees). They argued that they perform the same work as Lecturers and, under the principle of equal pay for equal work, are entitled to those higher grades; reliance was placed on Randhir Singh v. Union of India. The Punjab and Haryana High Court dismissed the writ petitions, and the Division Bench affirmed. The Court held that paragraph 2 of the July 29, 1967 circular creates a Lecturer’s Grade, and the number of Lecturer posts is limited; entitlement to those grades is contingent on holding Lecturer posts, not merely possessing postgraduate qualifications. The decision distinguishes Randhir Singh and notes that the July 29, 1967 circular operates on a different plane from the 1957 circular. Kirpal Singh Bhatia’s case is deemed of no assistance. Consequently, the appeals are dismissed, preserving the distinction between Lecturer posts and other teaching posts while acknowledging earlier clarifications remain applicable to the relevant posts.

1984-12-11

Goa Sampling Employees' Association v. General Superintendence Co. of India Pvt. Ltd. & Ors.

These appeals address whether the Central Government is the "appropriate Government" to refer five industrial disputes under Section 10(1)(d) of the Industrial Disputes Act, 1947, in the Union Territory of Goa, Daman and Diu. The Goa Sampling Employees' Association contended that iron ore samplers employed at Mormugao Port fall within the Dock Workers (Regulation of Employment) Act, 1948 as "dock workers" and, being in a major port within a Union Territory, the Central Government is the appropriate authority to refer the disputes. They also argued that in a Union Territory there is no State Government and thus the Central Government should perform functions of the State Government for the UT. The Central Government’s references were initially upheld by the Tribunal, but the Bombay High Court quashed them, holding the Central Government not to be the appropriate Government, since Goa, Daman and Diu is administered by an Administrator under Article 239, with the Administrator treated as the State Government for purposes of the Act. The Supreme Court reversed, holding that the General Clauses Act definitions and Constitutional provisions treat the Union Territory administration separately from a State Government; the Central Government is the appropriate Government for UTs in relation to industrial disputes. The Court directed expeditious disposal of the merits and awarded costs against the respondents.

1985-04-23

V. J. THOMAS AND ORS. v. UNION OF INDIA AND ORS.

This is a Supreme Court appeal by Junior Engineers challenging the constitutionality of the Note appended to clause (4) of Appendix I to the Telegraphic Engineering Service (Group B Posts) Recruitment Rules, 1981. The dispute traces to earlier rules: the 1966 Telegraphic Engineering Service (Class II) Recruitment Rules required promotion to Assistant Engineer entirely by promotion through a qualifying departmental examination, with a list prepared by a Departmental Promotion Committee. Sub-clause (4) allowed those recruited and absorbed in that grade against vacancies in a given year (five years prior to the year of announcement) to be eligible for the department exam. The 1981 Rules superseded the 1966 Rules and introduced a qualifying-cum-competitive examination, with a Note stating that the first two examinations would be competitive only for officers who had already qualified in the qualifying examination held before the 1981 Rules. Appellants, recruited in 1973, argued that this Note discriminates against 1973 and later batches by denying them a fair opportunity to contest promotions, despite five years’ service. The Kerala High Court found the Note ultra vires, but the Division Bench disagreed. The Supreme Court ultimately held that the appeal is infructuous due to time and that the Note is not ultra vires, while directing future scheduling of qualifying and competitive examinations, and promotions in light of vacancies. The appeal is disposed of with no costs.

1985-03-27

T. Venkata Reddy v. State of Andhra Pradesh

These writ petitions challenge the constitutional validity of the Andhra Pradesh Abolition of Posts of Part-time Village Officers Ordinance, 1984 (Ordinance No. 1 of 1984), which abolishes part-time village posts and creates Village Assistants. The Governor promulgated the Ordinance under Article 213, arguing administrative reform and expediency in a divided Andhra Pradesh (Andhra Area and Telangana Area) with a long history of hereditary and semi-hereditary village offices governed by pre-constitutional and colonial statutes. The petitions raised three main contentions: (i) lack of mind by the Governor in promulgating the Ordinance, (ii) the Ordinance lapsed due to absence of a replacement Act and thus the abolished posts should be revived, and (iii) the abolition infringed Article 21. The petitioners relied on earlier judgments upholding gubernatorial ordinances and the proposition that an Ordinance should have the same force as an Act, yet require constitutional limits. The Court reviews the constitutional framework (Articles 123 and 213) and explains that Ordinance power is a plenary legislative function exercisable to meet emergencies when the legislature is not in session, with the Ordinance having the force of an Act but subject to six-week or six-month disallowance provisions. It also clarifies that abolition and the creation of Village Assistants are two independent, sequential actions and that disapproval cannot revive completed, already-implemented changes. The Court ultimately dismisses the petitions, noting that the State may create new posts under Article 162 as long as not pre-empted by a statute or rule.