This Supreme Court decision concerns a self-financing housing scheme in which the Uttar Pradesh Avas Evam Vikas Parishad (Housing Board) allotted flats, but possession could not be delivered as construction lagged and the price escalated. The respondents, allottees, challenged the escalated prices where the High Court had upheld the escalation but held that interest at 18% was excessive and directed the Board’s Commissioner to grant relaxation in interest and penalties. Subsequently, the Board issued a resolution offering concessional terms to those who would withdraw their petitions, including: no interest for three months from the allotment order; simple interest at 14.5% thereafter; 18% penal interest after a year; and a 50% reduction in maintenance charges. The High Court, however, extended these benefits to all petitioners, directing writ petitions and review petitions to receive the same concessions, and also directed a 50% concession in respect of profit and overhead charges. The Board appealed, and some allottees challenged further. The Supreme Court held that extending concessions to all who defaulted would be inequitable if someone who deposited the full amount was treated worse than a defaulter. While the Court upheld extending the利益 concessions on interest as per the July 1990 letter to all petitioners, it found the 50% concession on profit and overhead charges and related concessions to be improper given earlier final decisions. Appeals were allowed in part, with costs borne by the parties.

Precedent Explorer

Find Cases Like This

Explore other judgments dealing with similar legal situations, facts, or statutory provisions.

Case Details & Bench

Court
Supreme Court of India
Hon'ble Judges
  • R. M. Sahai
  • Sujata V. Manohar
Judgment Date
1995-05-02
Court Decision / Holding
Appeals allowed in part. The High Court’s order extending a 50% concession on administrative charges and on profit/overhead charges is set aside. The High Court’s upholding of the concessions in respect of interest and maintenance charges as per the Board’s July 1990 letter to all petitioners is upheld (with the caveat of earlier observations). Costs to be borne by the parties.
Final Disposition
Appeals allowed in part.

Parties to the Case

Appellants / Petitioners

  • U.P. Avas Evam Vikas Parishad
  • Anr.

Respondents

  • Ravi Kumar Anand
  • Others

Legal Representation & Advocates

Counsels for Petitioners

  • • S.B. Sanyal
  • • P.K. Jain

Counsels for Respondents

  • • Aron Jaitley
  • • Ranjan Mukherjee
  • • Rakesh Persad
  • • B.B. Sabarya

Submissions & Arguments

Contentions of Appellants / Petitioners

The appellants contended that the High Court’s extension of concessions to all petitioners—based on the Board’s July 1990 letter—unfairly rewarded those who had deposited the full amount and unsettled prior decisions on profit/overhead charges. They argued that the 50% concession on profit and overhead charges had already been finally decided and should not be reopened by a review petition, and that any relief must be limited to those actually notified and withdrawn in writing.

Contentions of Respondents

The respondents contended that the concessions should extend to all petitioners to mitigate the impact of delays and that the relaxation in interest and penalties, as indicated in the Board’s letter, should apply broadly; they argued equity requires a uniform benefit for all petitioners who sought relief.

Legal Doctrine & Issue Explorer

Explore This Legal Issue

Find relevant judgments and authoritative positions on the legal questions discussed here.

Case Applicability Diagnostic

Apply This to My Facts

Share your situation and test whether this judgment governs, supports, or challenges your case.

Official Judgment Record
•2,045 words•~10 min read

In The Court Record

U.P. Avas Evam Vikas Parishad v. Ravi Kumar Anand and Ors.

A r~ U.P. AVAS EVAM VIKAS PARISHAD AND ANR. _v._ # RA VI KUMAR ANAND AND ORS. MAY 2, 1995 B [R.M. SAHAI AND SUJATA V. MANOHAR, JJ.) _Housing:_ _Housing Board-Allotment of Houses-Price escalation-Writ Chai-_ C. _lenging-High Court upholding escalation but directing Board to grant relaxalion in respect of interest and penalty-Special Leave Petition by al/ottees-DismissaJ-Review Petitions-Writ by some a//ottees claiming benefit granted by High Court ear/ie1"-/Joard's resolution to grant concession to those al/ottees who would withdraw their cases-Issue of notices to defaul-_ D _[ter ][allottees-Letter ][containing ][Board's ][decision ][not ][communicated to ][each ] allottee-Direction by High Court to extend concessional benefit not only to defaulters but to all the petitioners-field justified-But High Court's direction regarding 50% concession in respect of profit and overhead charges held not justified as it was settled in earlier petitions._ E The respondents, who were allotted and given delayed delivery of Oats under a Self Financing Scheme by the appellant- board, filed writ petitions in the High Court challenging the escalated price demanded by the appellant. The High Court upheld the escalation but held that the demand of 18% Interest from the allottees was excessive and directed the F[Board's Commissioner to grant relaxation to allottees in interest and ] penalty: The respondents flied a Special Leave Petition which was dis· missed) Therefore, they Ille review petition before the High Court for claririfation of the Impugned judgment. In the meantime, some of the allottees filed writ petitions claiming the same benefits which were given by the High Court in its earlier order. During the pendency of these G petitions the Board resolved to grant certain concessions with regard to interest and maintenance charges to those allottees who would withdraw their cases from the Court and accordingly directed Its authorities to issue notices for recovery of money from those allottees who had committed default in making the payments. However, the Board's decision was not H[communicated to each individual allottee in writing. On the basis ][of ][the ] 1112 ..._ ,· .. "' ~- 1113 ## U.P.AVAS EVAMVIKASv. RAVI KUMAR ANAND letter dated 20/21 July, 1990 containing the Board's resolution the High A Court directed that the benefits should be extended to every petitioner. The High Court also directed that the demand of administrative and profit charges should be reduced by 50% Against the decision of the High Court Housing Board preferred appeals to this Court. ## Allowing the appeals in part, this Court B HELD : 1. The effect of the resolution passed by the Board and its implementation was to grant concession to those allottees who bad com· milted default that was not fair. If the Board's Commissioner relaxed the conditions in pursuance of the judgment of the High Court then the benefit of it could not be denied to those who were more law abiding and deposited the entire amount demanded by the Board. They could not be made worse then those who were defaulters. Consequently, all those allottees who bad filed the review petitions or writ petitions and to whom no intimation was sent shall also be extended the same concession. The High Court's order in respect of eXtension of concession to all the allottees is upheld. (1116· D·E) .• .A 2. The High Court was not justified in granting the concession of 50% in respect of profit and over-head charges as these aspects bad been finally decided and settled in the earlier writ petitions, Special Leave E Petitions against which bad been dismissed by this Court. The High Court could not have reopened the matter by way of a review petition when it was not permitted by this Court and effect ot which, if permitted, would be to disturb the finality of the ellrller decision. The said order of the High Court is liable to be set aside. [1116-G-H, 1117-A-B) F CIVIL APPELLATE JURISDICTION : Civil Appeal No. 5713 of 1995 Etc. From the Judgment and Order dated 5.11.1993 of the Allahabad High Court in Civil Misc. Writ Petition No. 1179 of 1987. G S.B. Sanyal and P.K. Jain for the Appellants. --' ' Aron Jaitley, Ranjan Mukherjee, Rakesb persad and B.B. Sabarya for the Respondents. The following Order of the Court was delivered : H 1114 [1995] 3 S.C.R. SUPREME COURT REPORTS A The short question that arises for consideration in these appeals filed by the statutory body constituted for constructing and providing houses is whether the High Court was justified, in peculiar facts and circumstances of these cases, to allow review applications and writ petitions filed by various allottees and direct the appellants to grant concession of 50% in profit and administrative charges due to delayed delivery of flats as the B High Court in earlier writ petition had granted such benefit in respect of interest and penalty. For proper appreciation of the controversy, few facts in brief are necessary to be mentioned. In a Scheme known as 'Self Financing Scheme, C 1985' announced sometime in t!J.e month of October/November, 1984 the respondents were allotted flats in 1986 of different types in different income groups. But the possession could not be handed over as constructions were not complete. When possession was delivered the appellant demanded extra amount as the price had escalated in the mean time. It D was challenged by the allottees as the amount demanded was arbitrary and the constructions too were incomplete. The writ petitions were decided in February, 1990. The escalation was upheld. But the demand of interest at 18% was held to be excessive. The High Court further observed that brochure issued by the appellant relating to the scheme empowered the Commissioner to grant relaxation from various conditions for valid reason E or for the delay due to slackness of the official machinery. The High Court directed that since delay was caused as the appellant did not discharge initial responsibility, the Commissioner may consider granting relaxation in interest and penalty. The respondents were not satisfied. They approached this Court by way of Special Leave Petitions. The petitions were dismissed F on 22nd March, 1990. The order reads as under:- "The Special Leave Petitions are without merits and are dismissed. The fate of these SLPs will no(, however, stand in the way of the petitioners moving the High Court for clarification of certain observations in the impugned judgment, which the petitioners contend are in their favour and in regard to which we express no **view".** G A ., In consequence of the observations in the last part of the order of the respondents approached the High Court by way of review petitions. H Some of the allottees filed writ petitions as well claiming same benefit as 1115 U.P. AV AS EV AM VIKAS _v._ RA VI KUMAR ANAND was given by the High Court in its order dated 7th February, 1990. While these petitions were pending the appellant held a meeting to consider the implications of directions issued by the order. The Board resolved:· "The proposal has beeu unanimously approved by the Parishad after discussion. It was further decided by Parishad that this benefit be given to the allottees who withdraw their case from the court". **B** The ietter then gives out the concessions which the Board resolved to grant to allottees. It was as under:- ·- _)._ - "1. After the issuance of the allotment order no interest would be charged from the allottees within a period of three months as indicated in the order dated 22.4.88. • ,._ 2. After the expiry of three months simple interest at the rate of 14.5% will be realised from allottees as indicated in the order dated 29th July, 1988. This period shall reckon from **D** the expiry of three months, but after a lapse of an year 18% interest penal interest would be charged from such allottees. - 3c The· maintenance charges shall be reduced to the extent of **50%."** E In the end it was added:· "Under the above decision of Parishad the Estate management. officer Indira Nagar/Vikas Nagar, Lucknow and Kanpur and Raibarielly be informed that the persons affected be assessed and **F** requisition be sent with the notice enclosed. Please take quick action so that money may be recovered'. This letter was produced before the High Court. Even though the scope of the review petitions or the writ petitions was limited, the allottees attempted once again to raise the issue of escalation. It was rejected. **But G** the High Court after perusing the letter observed that these benefits may be extended to every petitioner" It was further held that since there was no contractual liability about the administrative and profit charges which were sought to be recovered from petitioners the demand was liable to be reduced by 50%. **H** 1116 SUPREME COURT REPORTS [1995] 3 S.C.R. _Y_ -Y A The question that arises for consideration is whether. the High Court was justified in extending the benefits of letter dated 20th/21st July to all those allottees who had approached the High Court since the Board . extended it only to those who agreed to withdraw their petition. It is not necessary to d~cide this larger issue as the allottees could be precluded b from claiming any benefit only if it could be established that the decision of the Board was brought to their notice by written intimation and yet they did not agree to avail of it. The decision of the Board was, it appears, not communicated IQ each individual allottee in writing. The argument of the learned counsel for the Board that when letter was produced before the High Court it should be held to be intimation to the allottees does not C impress. The Scheme was a self-financing scheme. The last part of the letter indicates that some allottees had not made the payment. Therefore, the authorities were directed to issue letters after calculating the amount. The decision was not communicated, therefore, it cannot be argued that those who did avail of it were not entitled to the concession. The effect of D the resolution and its implementation was to grant concession to these allottees who had committed default. That was not fair. If the Commissioner relaxed the condition in pursuance of the judgment of the High Court then the benefit of it could not be denied to those who were more law abiding and deposited the entire amount demanded by the Board. They E could not be made worse than those who were defaulters. Consequently, fill those allottees who had filed the review petitions or writ petitions and to whom no intimation was sent shall also be extended the same concession. b "'- -- The High Court has further held that on the same parity of reasoning F as of maintenance, the allottees should be granted concession of 50 percent in respect of profit and overhead charges. Whether in a 'Self Financing Scheme' the Parishad was entitled to charge profit and overhead charges from those persons who had deposited the entire amount but were not handed over possession and the delay was on part of the Parishad is a debatable issue on which it is not necessary to express any opinion in this G case as it was not open to allottees to raise it and the High Court was not justified in granting the concession as these aspects had been finally decided and settled in the earlier writ petitions, SLPs against which had been dismissed by this Court. The High Court could not have reopened the matter by way of a review petition when it was not permitted by this H Court and effect of which, if permitted, would be to distuob the finality of 1117 U.P.AVAS EVAMVJKASv. RAVI KUMAR ANAND A the earlier decision. In the result, the appeals are allowed in part, the order of the High Court allowing the review petition and directing the Parishad to grant 50% concession on the administrative charges as well as the profit sought to be realised is liable to be set aside. The order in respect of interest and the extension of concession as mentioned in the letter dated 20/2lst July, 1990 B to all the allottees subject to observation made earlier is upheld. The parties shall bear their own costs. T.N.A. Appeals allowed . ... ,l, l
End of Judgment Record
Browse All Supreme Court of India (1995) Decisions
1995-02-23

Inder Singh v. State of Punjab

Inder Singh, convicted under Section 302 IPC for the murder of Amar Singh, questions the High Court’s affirmation of his life-term sentence. The prosecution’s version is that Amar Singh, who had gone to see off a tractor driver, did not return home; on the night of 31 March/1 April 1984, the appellant, armed with a barchha, lay in wait behind a heap of manure and suddenly sprang upon Amar Singh, while PW4 (the deceased’s father) and PW5 (the mother) were trying to intervene. Amar Singh died instantaneously from a fatal neck wound, with the post‑mortem revealing injuries that pointed to a lethal strike. The Trial Court convicted the appellant under Section 302 IPC, while acquitting two co‑accused. In the appeal before the Supreme Court, the defence argued that the appellant’s motive was merely to thrash Amar Singh for suspected theft of cauliflowers, and that lying in wait with a weapon did not necessarily prove an intention to kill. The Court rejects this: the manner of the assault, the weapon used, the location and extent of the injuries, and the fact that PW4 was also injured while trying to save Amar Singh indicate a determined intention to cause fatal injury. The Court also notes the prompt FIR, the medical evidence, and the recovery of the weapon as corroboration, sustaining the conviction. The appeal is dismissed.

1995-03-27

SUBORDINATE SERVICES SELECTION BOARD v. BIR SINGH AND ANR./RAM NIWAS AND ORS.

This Supreme Court decision concerns the interpretation of reservation in Ex-Servicemen posts and the eligibility of dependents of ex-servicemen for clerical posts in A-class offices. The case arose from a dispute over whether dependents of ex-servicemen, who possess Matriculation but do not have First Division in Matriculation or Second Division in Intermediate, could be considered for appointment to A-class clerical posts when ex-servicemen are unavailable and vacancies exist in the reserved quota. The government had reserved A-class posts for ex-servicemen and prescribed stratified qualifications for A-class and B-class offices; in 1979, to avoid lapsing of reserved posts, it was decided that dependent sons and daughters of ex-servicemen who fulfilled all prescribed conditions should be considered on merit for posts reserved for ex-servicemen to the extent of non-availability of suitable ex-servicemen. The respondents, dependents of ex-servicemen, argued that the 7.9.1991 advertisement did not distinguish between A- and B-class posts and that their Matriculation alone made them eligible for A-class posts on par with ex-servicemen. The High Court held them eligible, but the Court reversed, holding that such dependents are not entitled unless they meet the prescribed qualifications (Matric with First Division or Intermediate with Second Division) or are ex-servicemen. The appeals were allowed.

1995-11-01

Yadu Nandan Garg v. State of Rajasthan and Ors.

This appeal concerns a preliminary notification under Section 4(1) of the Rajasthan Land Acquisition Act, 1953 for the 'planned development of Jaipur city' and a declaration under Section 6 issued after the improvement scheme had been finalised. The appellant, Yadu Nandan Garg, had purchased part of the land in 1970 and built a residence there, while Anand Nursery nearby obtained an exemption. The challenge focused on: (i) alleged unexplained delay between the preliminary notification and the declaration, (ii) discriminatory treatment in granting exemption to Anand Nursery but not to the appellant, and (iii) misdescriptions of survey numbers in the Section 9 notice, namely 265 vs 265/1. The Rajasthan High Court had dismissed the challenge, and the Supreme Court, in its division bench, upheld the validity of the acquisition. The Court held that a purchaser cannot acquire title against the State by clinging to an encumbrance after the notification and finalisation of the scheme; under Section 16 the State is entitled to possession with absolute title free from encumbrances. It rejected the contention of inordinate delay, noting the usual administrative time involved in finalising the scheme. It also held that wrong exemptions or mis-stated survey numbers do not invalidate the notification under Section 4(1), provided the main survey number is mentioned, and that discrimination claims fail given lack of a universal benefit. Consequently, the appeal was dismissed without costs.

1995-09-19

Controller of Examination, Utkal University and Anr. v. Paurnamasi Das and Anr.

These two Civil Appeals arise from challenges to the awarding of BA honours by Utkal University under its Regulations for pre-degree and final degree examinations, and the operation of the 1990 Hard Case Rule. Regulation 12 prescribes separate classification in pre-degree and final degree exams, to be shown on the diploma, with specific percentage thresholds for Second Class and First Class honours in both stages. Regulation 16(b) makes the final degree honours list depend solely on marks obtained in the final examination, subject to retaining honours in the pre-degree stage. The Hard Case Rule provides grace marks (up to 0.5%) to enable a candidate to retain honours or attain a higher class, but must be applied per part of the examination. The respondents, in two appeals, were short by 4 marks in their final degree honours papers, seeking to add 4 grace marks (0.5% of 800) by aggregating marks across pre-degree and final degree, an approach the High Court accepted but the University challenged. The Court held that the Hard Case Rule applies separately to each examination part, and that only up to 2 grace marks could be added in the final degree examination (not across parts). The High Court’s view was thus incorrect, and the appeals were allowed with writ petitions dismissed."