UNION OF INDIA v. TECCO TRICHY ENGINEERS & CONTRACTORS

Case / Petition Number:
Civil Appeal No. 1784 of 2005

Case Synopsis & Summary

This judgment addresses the interpretation of ‘party’ and ‘party making the application’ for setting aside an arbitral award under the Arbitration and Conciliation Act, 1996 in a dispute arising from a railways work contract. The matter was referred to arbitration by the Southern Railway and the award was delivered to the office of the General Manager on 12 March 2001; the Chief Engineer of the relevant department received a copy on 19 March 2001. The applicant filed an application under Section 34 on 10 July 2001 along with a delay-condonation petition arguing that the limitation period should commence from the date the department head received the award, given the organizational structure of Railways where the General Manager cannot independently assess the award’s merits. The respondent contends that limitation starts from 12 March 2001, allowing only a 30-day condonation window under the proviso to Section 34(3) and that a 34-day delay cannot be condoned. The Supreme Court clarifies that, in large State organizations, ‘party’ must be construed as the person directly connected with and in control of the proceedings. The copy must be received by the appropriate departmental head (Chief Engineer) for the limitation period to run, making 19 March 2001 the starting point. The 27-day delay is condonable, the appeal is allowed, and the matter is remitted to the High Court for merits evaluation.

Precedent Explorer

Find Cases Like This

Explore other judgments dealing with similar legal situations, facts, or statutory provisions.

Case Details & Bench

Court
Supreme Court of India
Hon'ble Judges
  • R. C. Lahoti
  • G. P. Mathur
  • P. P. Naolekar
Judgment Date
2005-03-16
Court Decision / Holding
Appeal allowed. The Supreme Court held that the starting point for limitation is 19 March 2001 (date Chief Engineer received the copy). The delay of 27 days is condonable, and the application under Section 34(1) filed on behalf of the appellant shall stand restored in the High Court for decision on merits. No order as to costs.
Final Disposition
Appeal allowed. The High Court’s order is set aside; the application under Section 34(1) is restored to be heard on merits in the High Court. No order as to costs.

Parties to the Case

Appellants / Petitioners

  • Union of India

Respondents

  • Tecco Trichy Engineers & Contractors

Legal Representation & Advocates

Counsels for Petitioners

  • • K. Radhakrishnan
  • • T.A. Khan
  • • S.N. Terdal
  • • Mrs. Anil Katiyar

Counsels for Respondents

  • • Arvind Kumar
  • • Ms. Poonam Prasad
  • • Ms. Laxmi Arvind

Provisions of Law Cited

Arbitration and Conciliation Act, 1996Section 2(h)Section 31(5)Section 34(1)Section 34(3)34(3) provisoSection 33(1)Section 33(4)Section 32

Submissions & Arguments

Contentions of Appellants / Petitioners

The applicants contend that in a large State organization like the Railways, the term 'party' in Section 2(h) read with Section 34(3) and the role of the 'party making the application' must be understood as a person directly connected with and in control of the proceedings. Since the Chief Engineer represents the Union of India in the arbitral proceedings and is directly concerned with the subject matter, he must receive the copy of the arbitral award for it to be effective and for limitation to commence. Delivery to the General Manager cannot alone trigger the limitation clock; receipt by the departmental head is the crucial starting point (19 March 2001). The copy delivered to the Chief Engineer on 19.3.2001 makes the 27-day delay until 10.7.2001 condonable under the proviso to Section 34(3). The High Court erred in treating 12.3.2001 as the starting date and in rejecting condonation; the matter should be decided on merits by the High Court.

Contentions of Respondents

The respondents argued that the limitation begins on 12 March 2001, the date the copy of the award was delivered to the General Manager’s office, and thus the delay of 34 days should be considered; the proviso to Section 34(3) permits condonation only for a further 30 days, so the delay cannot be condoned. They maintained that the recipient of the award must be the party, or person acting in place of the party, with knowledge of the proceedings. The High Court’s view that the limitation clock started earlier was correct, and the appellant’s application under Section 34(1) should be barred by limitation."},

Legal Doctrine & Issue Explorer

Explore This Legal Issue

Find relevant judgments and authoritative positions on the legal questions discussed here.

Case Applicability Diagnostic

Apply This to My Facts

Share your situation and test whether this judgment governs, supports, or challenges your case.

Official Judgment Record
•3,171 words•~15 min read

In The Court Record

UNION OF INDIA v. TECCO TRICHY ENGINEERS & CONTRACTORS

# UNION OF INDIA v. # TECCO TRICHY ENGINEERS & CONTRACTORS MARCH 16, 2005 [R.C. LAHOTI, CJ., G.P. MATHUR AND P.P. NAOLEKAR, JJ.] _Arbitration and Conciliation Act, 1996 :_ _ss. 2(h), 31(5), 34(1) read with s.34(3) proviso-Limitation for filing application for setting aside the award-Delivery of copy of award to "party"-_ C _"Party" making application for setting aside award-Arbitration proceedings between Railways and contractor-Copy of award delivered in office of General Manager, Railways-Later, copy of award delivered by arbitral tribunal to Chief Engineer concerned-Chief Engineer filing application for setting aside the award alongwith an application for condonation of delay-Application_ D · _contested as being beyond the period of limitation from the date of receipt of copy of award in Office of General Manager-Held, in the context of State or a department of Government, more so, a large organization like Railways, "party" as referred to in s.2(h) read with s.31(5) and s.34(3) has to be construed to be a person directly connected with and involved in the proceedings and who is in control of the proceedings before the arbitrator-_ E _On facts, the Chief Engineer was representing the Union of India and notices of the proceedings were served on him-Subject matter of arbitration was related to his department-He was directly concerned with the arbitrationDelivery of copy of award within the meaning of s. 31 (5) shall be deemed :o have taken place on the date Chief Engineer received copy of the award as_ F _that date would be the starting point of limitation to challenge the awardThus calculated, the delay in filing application uls 34(1) deserves to be condoned-Judicial Notice._ In a disputed claim arising out of a work contract between appellantRailways and respondent-contractor, the General Manager, Southern G Railways referred the matter to an arbitral tribunal, which gave its award, a copy of which was delivered in the office of the General Manager, Southern Railways on 12.3.2001. The Chief Engineer of the department concerned received the copy of the award from the arbitral tribunal on H 983 [2005] 2 S.C.R. 984 SUPREME COURT REPORTS A 19.3.2000, and presented an application on 10.7.2001 for setting aside the said award under s.34 of the Arbitration and Conciliation Act, 1996, alongwith an application for condo nation of 27 days delay calculated from 19.3.2001, the date on which he received the copy of the award. The contractor contested the application for condonation of delay on the B ground that limitation was to be calculated from 12.3.2001, the date on which copy of the award was delivered in the office of the General Manager, Southern Railways, and thus calculated, there being 34 days' delay, the proviso appended to sub-s.(3) of s.34 of the Act did not permit any delay beyond 30 days' to be condoned by the Court. The single Judge of the High Court accepted the stand of the contractor. In appeal, the C Division Bench of the High Court upheld the decision. Aggrieved, the Railways filed the present appeal. ## Allowing the appeal, the Court HELD : 1.1. In the instant case, it is to be seen as to what is the D meaning to be assigned to the term "party" and "party making the application" for setting the award in the context of the State or a department of the Government, more so, a large organization like the Railways. In such organizations "party" as rei'erred to in s.2 (h) read with s.34 (3) and sub-s. (5) ofs.31 of the Arbitration and Conciliation Act, 1996 has to be construed to be a person directly connected with and involved E in the proceedings and who is in control of the proce..:dings before the arbitrator. 1987-E; 988-D-El 1.2. Court can take judicial notice of it that there are several arbitration proceeaings pending consideration concerning affairs of the F Railways before arbitration. The General Manager, with executive workload of entire Division cannot be expected to know all the niceties of the case pending before the arbitral tribunals or for that matter the arbitral award itself and to take a decision as to whether the arbitral award deserves challenge, without proper assistance of the departmental head who is directly concerned with the subject matter as well as arbitral G proceedings. (988-B-CI 1.3. The delivery of an arbitral award under sub-s.(5) of s.31 is not a matter of mere formality. It is a matter of substance. The delivery of arbitral award to the party, to be effective, has to be "received" by the party. In the context of a huge organization like Railways, the copy of the H award has to be received by the person who has knowledge of the U.0.1. _v._ TECCO TRICHY ENGINEERS & CONTRACTORS [NAOLEKAR, J.] 985 proceedings and who would be the best person to understand and A appreciate the arbitral award and also to take a decision in the matter of moving an application under sub-s. (I) or (5) of s.33 or under sub-s.(1) of s.34. (988-E-F; 989-AI 1.4. In the present case, the Chief Engineer had signed the agreement on behalf of Union of India entered into with the respondent. In the B arbitral proceedings the Chief Engineer represented the Union of India and the notices, during the proceedings of the Arbitration, were served on the Chief Engineer. The Chief Engineer is directly concerned with the Arbitration, as the subject matter of Arbitration relates to the department of the Chief Engineer and he has direct knowledge of the arbitral C proceedings and the question involved before the arbitrator. The delivery of the copy of the award within the meaning of sub-s. (5) of s.31 shall be deemed to have taken place on the date the Chief Engineer received the copy of the award. (989-B-G) 1.5. The High Court erred in holding the application under s.34 filed D on behalf of the appellant as having been filed beyond a period of 3 months and 30 days within the meaning of sub-s.(3) of s.34. There was a delay of 27 days only and not of 34 days as held bY, the High Court. In the facts and circumstances of the case, the delay in filing the application deserves to be condoned and the application under sub-s. (1) of s.34 of the Act filed on behalf of the appellant deserves to be heard and decided on merits.. E E [989-H; 990-A-B] CIVIL APPELLATE JURISDICTION : Civil Appeal No. 1784 of 2005. From the Judgment and Order Dated 19.6.2002 of the Madras High Court in O.S.A. No. 195 of 2002. F K. Radhakrishnan, T.A. Khan, S.N. Terdal and Mrs. Anil Katiyar for the Appellant. Arvind Kumar, Ms. Poonam Prasad and Ms. Laxmi Arvind for the Respondent. G The Judgment of the Court was delivered by P.P. NAOLEKAR, J. Leave granted. The Southern Railway entered into a contract with respondent No. I for gauge conversion from Madras Beach to Trichchirappalli Villupuram Section H 986 [2005] 2 S.C.R. ## SUPREME COURT REPORTS A - construction of a bridge being agreement No. 136/Cn/95 dated 29.9.95. On behalf of the Southern Railway, the contract was signed by the then Chief Project Manager, presently, the Chief Engineer. Disputes arose touching the claims arising out of the execution of works under the contract and in exercise of the power conferred by the arbitration clause contained in the contract, the General Manager, Southern Railway appointed an arbitrator as also a Presiding B Arbitrator, while respondent No. I nominated its arbitrator. The arbitral tribunal so constituted gave its award on 10/11.03.2001 and signed the same. A copy of the award was delivered in the office of the General Manager, Southern Railway on 12.3.2001. The receipt seems to have been acknowledged by someone in the office, probably the inwards clerk. The Chief Engineer received C the copy of the award from the tribunal on 19.3.2001. > On 10.7.2001, the Chief Engineer presented an application for setting aside the arbitral award under Section 34 of the Arbitration and Conciliation Act, 1996 (hereinafter 'the Act' for short). An application seeking condonation of delay under sub-Section (3) of Section 34 was also filed. The delay sought D to be condoned was of 27 days only based on an assumption that the copy of the awarg was received on 19.3.2001. The application for condonation of delay was contested by respondent No. 1 on the ground that arbitral award was delivered on 12.3.2001 and calculated from that date there was a delay of 34 days in filing the application beyond the period of limitation prescribed E by sub-Section (3) of Section 34 of the Act while the proviso appended to > the said provision does not permit any delay beyond the period of 30 days being condoned by the Court. The objection raised by respondent Ne 1 has > found favour with the learned Single Judge of the High Court, who rejected the application holding it as barred by limitation. The decision has been > upheld by the Division Bench of the High Court. Feeling aggrieved, the F appeal has been filed by specia: leave. The short question which arises for decision in this appeal is : which is the effective date on which the appellant was delivered with and received the arbitral award as that would be the date wherefrom the limitation within the meaning of sub-Section (3) of Section 34 of the Act shall be calculated. G Sub-sections (I) and (3) of Section 34 a~e relevant for our purpose and are reproduced hereunder : 34. _Application for setting aside arbitral award.-_ ( 1) Recourse to a Court against an arbitral award may be made only by an application for setting aside such award in accordance with sub- H U.0.1. _v._ TECCO TRI CHY ENGINEERS & CONTRACTORS [NAOLEKAR. J.] 987 A section (2) and sub-section (3). xxx xxx xxx xxx (3) An application for setting aside may not be made after three months havP. elapsed from the date on which the party making that application had received the arbitral award or, if a request B had been made under section 33, from the date on which that request had been disposed of by the arbitral •rib.;nal : Provided that if the Court is satisfied that the applicant was prevented by sufficient cause from making the application within the said period of three months it may entertain the application C within a further period of thirty days, but not thereafter." Fonn and contents of arbitral award are provided by Section 31 of the Act. The arbitral award drawn up in the manner prescribed by Section 31 of the Act h3:s to be signed and dated. According to sub-Section (5), "after the arbitral award is made, a signed copy shall be delivered to each party". The D term "party" is defined by clause {h) of Section 2 of the Act as meaning 'a party to an arbitration agreement'. The definition is to be read as given unless the context otherwise requires. Under sub-Section (3) of Section 34 the limitation of 3 months commences from the date on which "the party making that application" had received the arbitral award. We have to see what is the meaning to be assigned to the tenn "party" and "party making the application" E for setting aside the award in the context of the State or a department of the Government, more so a large organization like the Railways. It is well-known that the Ministry of Railways has very large area of operation covering several Divisions, having different Divisional Heads and _p_ various departments within the Division, having their own Departmental Heads. The General Manager of Railways is at the very apex of the Division with a responsibility of taking strategic decisions, laying down policies of the Organisation, giving administrative instructions and issuing guidelines in the organisation. He is from elite managerial cadre which runs entire Organisation of his Division with different Departments, having different Departmental G Heads. The day to day management and operations of different departments rests with different Departmental Heads. Departmental Head is directly connected and concerned with the departmental functioning and is alone expected to know the progress of the matter pending before the arbitral Tribunal concerning his department. He is the person who knows exactly H 988 [2005] 2 S.C.R. ## SUPREME COURT REPORTS A where the shoe pinches, whether the arbitral award is adverse to Department's interest. Departmental Head would naturally be in a position to know whether the Arbitrator has committed a mistake in understanding Departmental's line of submissions and the grounds available to challenge the award. He is aware of the factual aspect of the case and also the factual and legal aspects of the B questions involved in the arbitration proceedings. It is also a known fact and Court can take judicial notice of it that there are several arbitration proceedings pending consideration concerning affrtirs of the Railways before arbitration. The General Manager, with executive work load of entire Division cannot be expected to know all the niceties of the case pending before the arbitral tribunal or for that matter the arbitral award itself and to take a decision as C to whether the arbitral award deserves challenge, without proper assistance of the Departmental Head. General Manager, being the head of the Division, at best is only expected to take final decision whether the arbitral award is to be challenged or not on the basis of the advise and the material placed before him by the person concerned with arbitration proceedings. Taking a final D decision would be possible only if the subject matter of challenge namely, the arbitral award is known to the Departmental Head, who is directly concerned with the subject matter ~s well as arbitral proceedings. In the large organizations like Railways, "party" as referred to in Section 2(h) read with Section 34(3) of the Act has to be construed to be a person directly connected with and involved in the proceedings and who is in control of the proceedings E before the Arbitrator. > The delivery of an arbitral award under sub-Section (5) of Section 31 is not a matter of mere fonnality. It is a matter of substance. It is only after the stage under Section 3 I has passed that the stage of tennination of arbitral F proceedings within the meaning of Section 32 of the Act arises. The delivery of arbitral award to the party, to be effective, has to be "received" by the > party. This delivery by the arbitral tribunal and receipt by the party of the award sets in motion several periods of limitation such as an application for correction and interpretation of an award within 30 days under Section 33(1 ), > an application for making an additional award under Section 33(4) and an G application for setting aside an award under Section 34(3) and so on. As this delivery of the copy of award has the effect of conferring certain rights on the party as also bringing to an end the right to exercise those rights on expiry of the prescribed period of limitation which would be calculated from > that date, the delivery of the copy of award by the tribunal and the receipt H thereof by each party constitutes an important stage in the arbitral proceedings. B ## U.0.1. _v._ TECCO TRICHY ENGINEERS & CONTRACTORS [NAOLEKAR, J.] 989 In the context of a huge organization like Railways, the copy of the A award has to be received by the person who has knowledge of the proceedings and who would be the best person to understand and appreciate the arbitral award and also to take a decision in the matter of moving an application under sub-Section (I) or (5) of Section 33 or under sub-Section (I) of Section 34. In the present case, the Chief Engineer had signed the agreement on behalf of Union of India entered into with the respondent. In the arbitral proceedings the Chief Engineer represented the Union oflndia and the notices, during the proceedings of the Arbitrati~n, were served on the Chief Engineer. Even the arbitral award clearly mentions that the Union of India is represented C by Deputy Chief Engineer/Gauge Conversion, Chennai. The Chief Engineer is directly concerned with the Arbitration, as the subject matter of Arbitration relates to the department of the Chief Engineer and he has direct knowledge of the arbitral proceedings and the question involved before the arbitrator. The General Manager of the Railways has only referred the matter for arbitration as required under the contract. He cannot be said to be aware of D the question involved in the arbitration nor the factual aspect in detail, on the basis of which the arbitral tribunal had decided the issue before it unless they are all brought to his notice by the officer dealing with that arbitration and who is in-charge of those proceedings. Therefore, in our opinion, service of arbitral award on the General Manager by way of receipt in his inwards E office cannot be taken to be sufficient notice so as to activate the Department to take appropriate steps in respect of and in regard to the award passed by the arbitrators to constitute starting point of limitation for the purposes of Section 34(3) of the Act. The service of notice on the Chief Engineer on 19.3.200 l would be the starting point of limitation to challenge the award in the Court. F We cannot be oblivious of the fact of impersonal approach in the Government departments and organizations like Railways. In the very nature of the working of Government departments a decision is not taken unless the papers have reached the person concerned and then an approval, if required, of the competent authority or official above has been obtained. All this could G not have taken place unless the Chief Engineer had received the copy of the award when only the delivery of the award within the meaning of subsection (5) of Section 31 shall be deemed to have taken place. > The learned Single Judge of the High Court as also the Division Bench H 990 [2005] 2 S.C.R. ## SUPREME COURT REPORTS - A have erred in holding the application under Section 34 filed on behalf of the appellant as having been filed beyond a period of 3 months and 30 days within the meaning of sub-Section (3) of Section 34. There was a delay of 27 days only and not of 34 days as held by the High Court. In the facts and circumstances of the case, the delay in filing the application deserves to be - B condoned and the application under sub-Section (1) of Section 34 of the Act filed on behalf of the .appellant deserves to be heard and decided on merits. The appeal is allowed. The application under Section 34(1) filed on behalf of the appellant shall stand restored in the High Court, to be heard and decided In accordance with law by the learned Single Judge. No order as to C costs, R.P. Appeal allowed.
End of Judgment Record
Browse All Supreme Court of India (2005) Decisions
2005-09-29

Ram Bhual v. Ambika Singh

Ram Bhual v. Ambika Singh concerns the Uttar Pradesh Legislative Assembly election of 2002 from the 166, Kauriram constituency. The appellant Ram Bhual’s election was challenged under Section 100(1)(c) of the Representation of the People Act, 1951, on the ground that the Returning Officer wrongly rejected the nomination of an independent candidate, Sita Ram, during scrutiny. Sita Ram had to be proposed by at least ten qualified persons; the ninth proposer, Sant Lal, was shown as Serial No. 392 in Part 91 of the Voters’ list, while his name actually appeared as Serial No. 352 on the same page. The Returning Officer rejected Sita Ram’s nomination on the basis of this serial-number discrepancy, asserting the ninth proposer was not a voter. The independent candidate and the election petitioner contended that this was merely a clerical error and a minor defect that could be overlooked or corrected under Sections 33(4) and 36(4) of the Act and the proviso thereto. The Allahabad High Court held that the rejection was improper and declared the appellant’s election void under Section 100(1)(c). The Supreme Court, in a Division Bench, upheld the High Court’s view, holding that the defect was minor and that the Returning Officer could have corrected it under the statutory proviso; the petition should not have been dismissed on such a ground. The appeal was dismissed, affirming the High Court’s judgment and voiding the appellant’s election.

2005-10-18

V. Hutcheswaran v. Madras Hardware Mart

This Supreme Court judgment concerns a partition suit in which a final decree directed the sale of certain co-shares to empower the other parties. The 2nd defendant (Hutcheswaran) did not sell his share despite the decree. The 6th defendant, who eventually became the owner of a 4/5th share, sought to execute the decree and obtain possession. An execution petition by the decree holder was filed in 1990 but dismissed as time-barred under Article 136 of the Limitation Act. The decree holder then sought relief in Civil Revision Petitions before the Madras High Court, which condoned the delay and remanded. Subsequently, another execution petition was allowed, and a sale deed in favor of the decree holder was executed, with delivery of possession. Hutcheswaran filed a Special Leave Petition (SLP) to challenge the High Court orders, which was withdrawn by him, resulting in the High Court order becoming final. Hutcheswaran then prayed for restitution to the position before the execution petition. The Supreme Court held that once the SLP was withdrawn, the question of restitution could not arise, as the order had become final. The Court distinguished the precedents cited by Hutcheswaran (Hameed Joharan and Prasanna Kumar Roy Karmakar) and dismissed the appeals. There will be no order as to costs.

2005-03-31

V.M. SALGAOCAR v. BOARD OF TRUSTEES OF PORT OF MORMUGAO

This is an appeal from the Goa-Port case dealing with rebate claims under the Mechanised Ore Handling Plant regime at Mormugao Port and the interplay of limitation and statutory notice under the Major Port Trusts Act, 1963. The Port Board levied a surcharge and later offered a partial rebate to the appellant exporting iron ore. The appellant claimed a larger rebate, computed on turnover, totaling Rs. 62,46,584.10, while the Board offered Rs. 7,09,835 as admitted. The suit, filed on 11.06.1986, sought the balance and damages, but the Board contended that the suit was time-barred under Section 120 of the Major Port Trusts Act, which prescribes a six-month filing window from accrual of cause of action, and requires one month prior written notice. The Trial Court passed a decree on admission for Rs. 7,09,835, while dismissing the main suit for want of notice and limitation. The High Court upheld, and the Supreme Court dismissed the appeals. Key issues: whether Section 120’s provisions must be read conjunctively (notice and six-month limit), whether the notice letter of 12.04.1984 could suffice as a statutory notice, and whether the shorter limitation violates constitutional guarantees. The Court affirmed the constitutionality and applied the conjunctive readings, concluding the suit was barred by time, and that waiver was not established.

2005-07-28

T.N. Rajasekar v. N. Kasiviswanathan

Facts: The suit property belonged to late T.N. Ganapathy, who died unmarried and issueless. Rajasekar (appellant) and the respondents—his brothers and sister—succeeded as Class-II heirs under the Hindu Succession Act, 1956. The appellant filed a civil suit for partition claiming a 1/5th share and sought ancillary reliefs. The initial Single Judge passed a preliminary decree directing the respondents to remit Rs. 37,68,000 into court and render accounts. The Division Bench held that the respondents must deposit only 1/5th of that amount (Rs. 7,53,000) and that accounts were to be rendered only for the properties existing on the date of the owner's death, excluding those acquired later under a Power of Attorney. Subsequently, the Single Judge passed a final decree valuing the properties at Rs. 2,98,79,569; the appellant was allotted Item No. 6 (the house) valued at Rs. 1,50,00,000, against which his 1/5th share amounted to Rs. 59,75,914. The owelty amount of Rs. 90,24,086 was directed to be adjusted from the land acquisition compensation due to the appellant. The Division Bench later set aside the direction to adjust owelty against compensation but otherwise confirmed the decree. The appellant deposited Rs. 60,00,000 in court. The matter proceeded to Special Leave petitions and appeals to the Supreme Court. The Court ultimately confirmed the Division Bench’s judgment subject to directions, directing the appellant to deposit the remaining Rs. 30,24,086 with interest, and on deposit, the respondents would hand over peaceful possession of the suit property to the appellant. The appeals were disposed of with no costs ordered.