Tenetowl LogoTenetowl
Supreme Court of IndiaSupreme Court · 2001Division BenchAppeals dismissed.

Union of India v National Hydroelectric Power Corporation Ltd & Ors

Case / Petition Number:
Civil Appeal Nos. 2885/2000; 4659-4668/2000; 4516/2000; 4517/2000

Case Synopsis & Summary

The key issue in these Civil Appeals was whether a valid levy could be imposed under the Water (Prevention and Control of Pollution) Cess Act, 1977 on hydroelectric power generating units. When the Act was enacted, hydro projects were not included in Schedule I. To bring them within the levy, a notification under Section 16(1) purportedly added hydroelectric power to Schedule I, and the notification was laid before Parliament as required by Section 16(2). The critical question was whether the amendments would take effect only with Parliament’s positive approval, and whether mere laying of the notification before Parliament sufficed. In the Himachal Pradesh High Court, it was held that Section 16(2) requirements had not been fulfilled because no resolution moving the approval was ever moved in Parliament, rendering the Schedule I amendment invalid and the levy unlawful. The Supreme Court examined affidavits and record, concluding that no parliamentary resolution was moved within the prescribed period, and that merely laying the notification does not constitute valid compliance. Consequently, the levy based on the purported amendment was not in accordance with the law. The appeals were dismissed with no costs. The decision underscores that Schedule I amendments require actual Parliamentary approval, not merely procedural laying of notices, for environmental levies to be lawful.

Precedent Explorer

Find Cases Like This

Explore other judgments dealing with similar legal situations, facts, or statutory provisions.

Case Details & Bench

Court
Supreme Court of India
Hon'ble Judges
  • B.N. Kirpal
  • N. Santosh Hegde
  • K.G. Balakrishnan
Judgment Date
2001-07-25
Court Decision / Holding
Appeals dismissed.
Final Disposition
Appeals dismissed.

Parties to the Case

Appellants / Petitioners

  • Union of India

Respondents

  • National Hydroelectric Power Corporation Ltd.
  • Ors.

Legal Representation & Advocates

Counsels for Petitioners

  • • G D.S. Mehra
  • • K.K. Venugopal
  • • Ms. B. Sunita Rao
  • • Ms. Sushma Suri
  • • Satish K. Agnihotri
  • • Ms. Yogmaya Agnihotri
  • • Anil K. Pandey
  • • Naresh K. Sharma
  • • Dhruv Mehta
  • • N.S. Bawa
  • • N.D. Kalra
  • • Ms. Karan Nehra
  • • Ms. Shobha
  • • Anil Nag
  • • Ashok Kumar Gupta
  • • Ajit Pudussery
  • • Sushil Kr. Jain
  • • Ms. Jayshree Anand
  • • Jagjit S. Chura
  • • V.K. Shailendra
  • • Krishnan Venugopal
  • • R.S. Suri
  • • H Mahabir Singh
  • • S.B. Upadhyay
  • • Rajiv Nanda

Counsels for Respondents

  • • G D.S. Mehra
  • • K.K. Venugopal
  • • Ms. B. Sunita Rao
  • • Ms. Sushma Suri
  • • Satish K. Agnihotri
  • • Ms. Yogmaya Agnihotri
  • • Anil K. Pandey
  • • Naresh K. Sharma
  • • Dhruv Mehta
  • • N.S. Bawa
  • • N.D. Kalra
  • • Ms. Karan Nehra
  • • Ms. Shobha
  • • Anil Nag
  • • Ashok Kumar Gupta
  • • Ajit Pudussery
  • • Sushil Kr. Jain
  • • Ms. Jayshree Anand
  • • Jagjit S. Chura
  • • V.K. Shailendra
  • • Krishnan Venugopal
  • • R.S. Suri
  • • H Mahabir Singh
  • • S.B. Upadhyay
  • • Rajiv Nanda

Provisions of Law Cited

Water (Prevention and Control of Pollution) Cess Act, 1977 - Section 3Water (Prevention and Control of Pollution) Cess Act, 1977 - Section 16(1)Water (Prevention and Control of Pollution) Cess Act, 1977 - Section 16(2)Water (Prevention and Control of Pollution) Cess Act, 1977 - Schedule IWater (Prevention and Control of Pollution) Cess Act, 1977 - Section 2(c)

Submissions & Arguments

Contentions of Appellants / Petitioners

The Union of India contends that under Section 16 of the Water Act the Central Government can add an industry to Schedule I by notification, but the amendment becomes operative only upon obtaining Parliament’s approval. Merely laying the notification before Parliament is not sufficient; no resolution moving approval was ever placed in Parliament, which constitutes non-compliance with Section 16(2). Consequently, the purported amendment to Schedule I is void and the levy based on it cannot be regarded as law.

Contentions of Respondents

The respondents contend that laying the notification before Parliament and referring it to a Parliamentary Committee demonstrates compliance with Section 16(2), and that the amendment to Schedule I should be regarded as duly incorporated; therefore, the levy would be legally payable under the amended Schedule I.

Legal Doctrine & Issue Explorer

Explore This Legal Issue

Find relevant judgments and authoritative positions on the legal questions discussed here.

Case Applicability Diagnostic

Apply This to My Facts

Share your situation and test whether this judgment governs, supports, or challenges your case.

Official Judgment Record
•1,463 words•~7 min read

In The Court Record

Union of India v National Hydroelectric Power Corporation Ltd & Ors

A UNION OF INDIA ETC. ETC. _v._ NA TJONAL HYDROELECTRIC POWER CORPN. LTD. AND ORS. ETC. ETC. B JULY 25, _'.LOO_ I [B.N. KIRPAL, N. SANTOSH HEGDE AND K.G. BALAKRISHNAN, JJ.) ## _Water (Prevention and Control of Pollution) Cess Act, 1977 :_ c S. _I 6(2)-Amendment of Schedule I-Units causing pollution--Levy and collection of cess from industries specified in Schedule I-Initially hydropower generating industry not included in Schedule I-Notification No. GSR 377(£) dated 16.4.1998 issued imposing cess on hydro-power generating industry-Challenged-High Court holding that provisions of Section 16 had_ D _not been complied with while purporting to amend Schedule I-Held, High Court was right in holding that levy of cess was not in accordance with law-Though the Notification was laid before the Parliament, steps leading to passing of resolution were not even commenced, and as such it cannot be said that there was a valid amendment of Schedule I to the Act-Legislation-Amendment of an Act-Environmental law._ E CIVIL APPELLATE JURISDICTION _:_ Civil Appeal No. 2885 of 2000. From the Judgment and Order dated 11.10.99 of the HimachaI Pradesh High Court in C.W.P. No. 403 of 1997. F ## AND C.A. Nos. 4659-4668 of 2000 With C.A. No. 4516/2000 and 4517 _I_ 2000. ·- G G D.S. Mehra, K.K. Venugopal, Ms. B. Sunita Rao, Ms. Sushma Suri, Satish K. Agnihotri, Ms. Yogmaya Agnihotri, Anil K. Pandey, Naresh K. Sharma, Dhruv Mehta, N.S. Bawa, N.D. Kalra, Ms. Karan Nehra, Ms. Shobha, Anil Nag, Ashok Kumar Gupta, Ajit Pudussery, Sushi! Kr. Ja!n, Ms. Jayshree Anand, Jagjit S. Ch'.~ura, V.K. Shailendra, Krishnan Venugopal, R.S. Suri, H Mahabir Singh, S.B. Upadhyay and Rajiv Nanda for the appearing parties. 14 15 U.0.1. _v._ NATIONAL HYDROELECTRIC POWER CORPN. LTD. _A_ The following Order of the Court was delivered : Civil Appeal Nos. 2885/2000 and 4659-4668/2000 The short question which arises for consideration in these cases is : Whether there can be a valid levy under the provisions of the Water (Prevention and Control of Pollution) Cess Act, I977 (hereinafter referred to as "the said B Act") on the hydro power generating industry? The aforesaid Act was promulgated with a view to levy and collect cess from the units which were thought to cause pollution and the funds so realised were to be entrusted to appropriate authorities, _inter a/ia,_ for remedial measures. c According to Section 3 of the side Act, the cess was payable by every person carrying on any specified industry and by every local authority. The expression 'specified industry' is defined in Section 2(c) to mean any industry specified in Schedule I. D When the Act was promulgated, hydel power generating industry was not included in Schedule I. In order to be able to impose cess on this industry, a notification No. GSR 377(E) dated 16th April, 1993 was purported to be issued under Section 16 of the Act. The respondent filed writ petitions challenging the imposition of cess E on the hydro power generating industry. Amongst other grounds which were raised, it was contended on behalf of the respondents that there had' been no valid amendment of Schedule I of the Act and, therefore, no cess could be imposed. This was one of the contentions which was accepted by the High Court which came to the conclusion that the provisions of Section 16 had not F been complied with while purporting to amend Schedule I of the Act. In these appeals, it has been contended by the learned Additional Solicitor General that a notification had been issued as contemplated by Section I 6 and the matter had been referred to a Parliamentary Committee and this shows that there had been sufficient compliance with the provisions G of Section 16 and the amendment should be regarded as having been duly incorporated in Schedule I. Section 16 reads as follows : "16. Power to amend Schedule I. - ( 1) The Central Government H 16 SUPREME COURT REPORTS [2001] SUPP. I S.C.R. A may, by notification in the Official Gazette add to Schedule I any industry having regard to the consumption of water in the carrying on of such industry and the consequent discharge thereof resulting in pollution of any stream and thereupon Schedule I shall, subject to the provisions of sub-section (2), be deemed to be amended accordingly. B c (2) Every such notification shall be laid before each House of Parliament, if it is sitting, as soon as may be after the issue of the notification, and if it is not sitting, within seven days of its re-assembly and the Central Government shall seek the approval of Parliament to the notification by a resolution moved within a period of fifteen days beginning with the day on which the notification is so laid before ~he House of the People, and if Parliament makes any modification in the notification or directs that the notification should cease to have effect, the notification shall thereafter have effect only in such modified form or be of no effect, as the case may be, but without prejudice to the validity of anything previously done thereunder." ## D > Sub-section (I) gives power to the Central Government to add to Schedule I any industry, but the procedure which is to be followed is provided by sub-section (2). When a notification is issued with a view to making an addition to Schedule I, the same is required to be laid before each House of Parliament if it is sitting and if the Parliament is not in session then a time E limit of seven days is prescribed from the re-assembly of the Parliament within which the notification must be so place. Sub-section (2) further requires that after the notification has been so place, then within fifteen days of the > placing of the notification, the Central Government has to seek approval of the Parliament to the issuance of the notification. Mere perusal of sub-section F (2) shows that there has to be a positive act of approval by the Parliament to the issuance of the notification before it can be held that Schedule I has been amended. Merely laying the notification before each House of Parliament is not sufficient compliance within the provisions of Section 16(2). There is of course no time limit within which the Houses of Parliament are required to pass a resolution once the Central Government has sought approval as G contemplated by sub-section (2), but in the present case the pleadings disclose that no such approval was in fact sought for. During the hearing of the writ petitions before the Himachal Pradesh High Court, an affidavit dated 19th July, 1999 was filed by one Dr. Jag Ram Additional Director in the Ministry of Environment & Forests, Government H of India. In paragraph 4 of the said affidavit, he states as follows : 17 U.0.1 _v._ NATIONAL HYDROELECTRIC POWER CORPN. LTD. __ ..-->·_ "4. That during the course of hearing on 5-7 July, I 999 before A this Hon'ble Court reference was made to the averments made in paragraph 5 of the aforementioned affidavit (dated 9.12.98) by this respondent. In this connection, this respondent submits that the requisite records and bulletins of the Parliament have been further exam in ed. It was found that no resolution relating to the above B notification dated 16.4.93, had been moved." We see no reason to disbelieve the correctness of the averment so made in the said affidavit. The averment made is categorical and unequivocal, namely, that no resolution relating to the notification dated 16.4.1993 had been moved in the Parliament. If no resolution had been moved, the question C of the Parliament giving approval does not arise. Though the first step of placing the notification in each House of Parliament had been taken, subsequent steps leading to passing of the resolution were not even commenced with the moving of the resolution. It is not necessary for us to consider what is the effect of not moving the resolution within the time frame of 15 days as prescribed by sub-section (2) as the present case is not where there has been D a delay in moving the resolution. There has been in fact a non-compliance with the said requirement. With resolution not having been moved at all, it cannot be held that there was a valid amendment of Schedule I to the Act. The High Court,. in our opinion, was, therefore, right in coming to the conclusion that this levy and the purported realisation of the cess was not in E accordance with law. The appeals are, accordingly, dismissed, but with no order as to costs. Civil Appeal Nos. 4516 and 4517 of 2000. In view of the above order, these appeals are also dismissed, but with no order as to costs. F R.P. Appeals dismissed.
End of Judgment Record
Browse All Supreme Court of India (2001) Decisions
2001-08-07

Sajan Abraham v. State of Kerala

On 7 August 2001, the Supreme Court rendered its judgment in Sajan Abraham v. State of Kerala arising from a Narcotic Drugs and Psychotropic Substances Act case. The appellant was charged under Section 21 for possession of Buprenorphine and three syringes near Palluruthy, after information from a Head Constable led to seizure by a Special Squad and arrest following an on-site search. The Trial Court acquitted due to inconsistencies; the Kerala High Court, on reappraisal, convicted and sentenced the appellant to ten years’ rigorous imprisonment and a Rs 1 lakh fine. The prosecution contended violations of Sections 42, 50 and 57: failure to record information in writing and communicate it to the immediate superior before arrest; failure to inform the accused in writing of the right to be searched in the presence of a Magistrate or Gazetted Officer; and non-submission of a full report within 48 hours. The Supreme Court adopted a pragmatic approach to mandatory provisions in the NDPS Act, recognizing the stringent nature of the statute but allowing substantial compliance to suffice when it results in no prejudice and promotes timely action to prevent escape. It held that the information was conveyed promptly, the Section 50 right was validly communicated orally, and that copies of FIR and seizure records were sent to the superior, satisfying substantial compliance with Section 57. Citing State of Punjab v Baldev Singh and Balbir Singh, the Court dismissed the appeal, upholding the conviction and sentence.

2001-08-08

P. C. Joshi v. State of U.P. and ORS.

This Supreme Court appeal concerns a judicial officer challenged termination following disciplinary proceedings. The Allahabad High Court had dismissed a writ petition filed by the appellant after the Enquiry Officer held him guilty of several charges, including missteps in bail orders. The central issue was whether initiation of disciplinary action is warranted where an order is faulty or where a different action could have been taken. The Court emphasized that a bona fide erroneous exercise of judicial powers cannot be treated as misconduct and warned against a chilling effect on judicial independence: if every faulty judgment triggered a disciplinary inquiry, subordinate judges would fear writing judgments. It relied on established constitutional principles that safeguard the independence of the judiciary and prevent routine harassment through disciplinary machinery over minor or non-mala fide errors. The Court referred to the tests laid down in Union of India v. A.N. Saxena and Union of India v. K.K. Dhawan for determining when disciplinary action may be initiated. In evaluating the bail-related charges, the Court found that the Enquiry Officer’s conclusions rested on inferences rather than legally tenable evidence, rendering substantial parts of the findings vitiated. Consequently, the judgment of the High Court was set aside and the appellant was reinstated with continuity of service and arrears of salary, with no costs.

2001-04-09

Bank of India v. Secretary, Bank of India Staff Union and Anr.

Bank of India v. Secretary, Bank of India Staff Union and Anr. concerns entitlement to special 'Special Assistant' allowances for staff serving as clearing-house representatives. The Industrial Tribunal-cum-Labour Court at Kanpur held that the concerned workmen were entitled to special assistant allowances for the number of days they worked at various collection centres and clearing-house duties, with payment to be made for the days actually worked from the date of reference. The Bank challenged the award on two fronts: first, that the duties performed by the workers did not require the greater skill and responsibility of a Special Assistant, being largely clerical in nature; and second, that the Special Assistant duties were defined by the Bipartite Settlements (1966 and its modifications, including 1984) and awards (Sastry and Desai). The workers contended that they performed duties as authorised representatives at clearing houses of RBI and State Bank of India and carried out routine bank duties connected with clearing. On appeal, the Supreme Court found that the Tribunal had not adjudicated the precise duties and responsibilities with reference to the parties’ contentions and evidence, and there was no concrete finding that the workers discharged duties warranting Special Assistant status. The Court set aside the Tribunal’s award and remitted the matter for fresh consideration, directing examination of the exact duties in light of the Bipartite Settlements and Sastry/Desai framework.

2001-09-13

KANHAIYALAL AGRAWAL AND ORS. v. THE FACTORY MANAGER, GWALIOR SUGAR CO. LTD.

These cross-appeals arise from termination of employees by the Gwalior Sugar Company. The Labour Court held that three workmen—Kanhaiyalal Agrawal and two others—had contravened prescribed procedures and, on the basis of evidence, found loss of confidence in them, denying reinstatement and awarding half salary with full retirement benefits. The Industrial Court, by contrast, held that the employees had not committed misappropriation of money but were negligent in performing their duties, and directed reinstatement without back wages. A Single Judge of the Madhya Pradesh High Court upheld the Industrial Court’s order. A Division Bench of the High Court dismissed the writ appeals on the ground that they arose under Article 227 (revisional jurisdiction) and were not maintainable. The present appeals before the Supreme Court, by management and workmen, focus on whether loss of confidence can be reversed and whether back wages should be payable. The Supreme Court held that the Industrial Court was correct in reversing the Labour Court’s finding of loss of confidence since such loss must be based on objective facts rather than subjective managerial belief. It affirmed the permissibility of reinstatement without back wages and declined to disturb the earlier orders, dismissing the appeals with no costs.