Tenetowl LogoTenetowl
Landmark CasesDivision BenchAppeals allowed; Award set aside; High Court’s ...

Union of India v M/s. Varindera Constructions Ltd. Etc.

Case / Petition Number:
Civil Appeal Nos. 3994-3995 of 2018

Case Synopsis & Summary

This Civil Appeals arise from disputes overContractual escalation for labour wages in a housing project at Hisar. Union of India floated tenders, awarded to M/s. Varindera Constructions Ltd. (the Contractor). Under the contract, two arbitration references were made; the Arbitrator granted several claims but rejected some, including escalating wages, while the High Court upheld the Award. The core issue is whether an increase in minimum wages declared by the State Government of Haryana can be reimbursed to the Contractor where the contract contains an escalation bar. Clause 19 of the special conditions expressly provides that no escalation or reimbursement shall be made for any increase in wages, price variation, or other inputs, and requires the contractor to quote rates accordingly. Clause 6.3 provides that the contractor shall have no claim if, due to local factors or regulations, he is required to pay wages in excess of the described minimum. Clause 25 is interpreted in the High Court to be an exception to Clause 19, enabling reimbursement of minimum wage increases. The Supreme Court, however, held that Clause 19 cannot be read with Clause 25 as they address distinct issues, and Clause 6.3 reinforces the no-claim principle. The Court emphasized objective contract interpretation and limited judicial interference in arbitration matters, ultimately allowing the appeals and setting aside the arbitral Award and the High Court’s decision, with parties bearing their own costs.

Precedent Explorer

Find Cases Like This

Explore other judgments dealing with similar legal situations, facts, or statutory provisions.

Case Details & Bench

Court
Landmark Cases
Hon'ble Judges
  • R.K. Agrawal
  • Ashok Bhushan
Judgment Date
2018-04-19
Court Decision / Holding
Appeals allowed; the arbitral Award and the High Court’s decision are set aside; the parties to bear their own costs.
Final Disposition
Appeals allowed; Award set aside; High Court’s decision set aside; Costs borne by the parties

Parties to the Case

Appellants / Petitioners

  • Union of India

Respondents

  • M/s. Varindera Constructions Ltd. (and associated parties)

Provisions of Law Cited

Clause 19 (Reimbursement/Refund of Variation in Prices)Clause 25 (Exception to Clause 19)Clause 6.3 (Minimum Wages Payable)Condition 51 of DG MAP general conditions of contractsMinimum Wages Act, 1948Arbitration and Conciliation Act, 1996 (Section 34)Arbitration and Conciliation Act, 1996 (Section 5)

Legal Doctrines & Maxims

  • Interpretation of contracts must be based on the intention of the parties and read harmoniously.
  • The terms of the contract should be construed by the courts after considering the intention of the parties.
  • Arbitration awards are subject to limited judicial review under Section 34 of the Act; courts should not disturb a plausible interpretation.
  • Primary object of arbitration is to achieve a speedy, effective, inexpensive and expeditious disposal.

Submissions & Arguments

Contentions of Appellants / Petitioners

The contract is clear that no escalation or reimbursement is permissible for any increase in wages, and the contractor had to quote rates accordingly (Clause 19). Clause 6.3 supports that the contractor shall have no claim if he is required to pay wages in excess of the minimum wages. The Haryana government notification increasing minimum wages cannot alter the contractual risk allocation. The High Court erred by reading Clause 19 in light of Clause 25 and by relying on the arbitrator’s interpretation. Section 34 of the Arbitration and Conciliation Act, 1996 does not permit this challenge. The court should thus interfere and set aside the arbitral award and the High Court’s judgment; the clause hierarchy and intention of the parties mandate upholding the no-escalation clause.

Contentions of Respondents

The contractor sought escalation for minimum wage increases under the contract’s clauses, especially Clause 25 (read as an exception to Clause 19) and Clause 6.3. The High Court held that Clause 19 and Clause 25 must be read harmoniously, allowing reimbursement for minimum wage increases mandated by law. The arbitration award granted some relief to the contractor; the respondents argued that interpretation of contract is within the arbitrator’s remit and that the court should not disturb a plausible interpretation in a Section 34 challenge. The respondents maintained that the statutory wage increase should be reimbursed under the contract’s terms and that the High Court’s interpretation aligns with the substance of the contract and statutory obligations.

Legal Doctrine & Issue Explorer

Explore This Legal Issue

Find relevant judgments and authoritative positions on the legal questions discussed here.

Case Applicability Diagnostic

Apply This to My Facts

Share your situation and test whether this judgment governs, supports, or challenges your case.

Official Judgment Record
•2,121 words•~10 min read

In The Court Record

Union of India v M/s. Varindera Constructions Ltd. Etc.

## **REPORTABLE** ## **IN THE SUPREME COURT OF INDIA** ## **CIVIL APPELLATE JURISDICTION** **CIVIL APPEAL NOS. 3994-3995 of 2018 (Arising out of Special Leave Petition Nos. 9743-9744 OF 2013)** Union of India ….Appellant(s) Versus M/s. Varindera Constructions Ltd. Etc. …. Respondent(s) ## **J U D G M E N T** ## **R.K. Agrawal, J.** 1) Leave granted. 2) These two appeals are preferred against the impugned common judgment and order dated 28.05.2012 passed by the High Court of Delhi at New Delhi in FAO (OS) Nos. 238 and 239 of 2012 whereby the Division Bench of the High Court dismissed the appeals filed by the appellant herein while upholding the decision of learned single Judge of the Signature Not Verified Digitally signed byASHA SUNDRIYAL High Court. Since the moot question is same in these two Date: 2018.04.19 17:26:37 IST Reason: 1 appeals, both would be disposed off by this common judgment. ## 3) **Brief facts:-** (a) The appellant herein is the Union of India and the respondent herein is the Contractor. On 30.10.2006, the appellant floated two tenders for the construction of the residential accommodations at Hissar. Pursuant to that, the appellant received tenders of various companies. (b) Being the lowest quotation of the respondentContractor, its tender was accepted by the appellant. The lump sum amount of these two contracts were Rs. 39,09,80,362.61 and Rs. 35,21,99,854.30 respectively. Consequently, the appellant and the respondent-Contractor entered into formal contract and laid down terms and conditions of the contract by which it was decided that both would be bound and also added the clause of arbitration in case of dispute. 2 (c) As per the terms of the contract, respondent started the work of construction as per the schedule on 20.03.2007 and finally completed the work within the stipulated extended time period of completion. At this juncture, respondent submitted the final bill along with some additional claims. The claim of additional amount was rejected by the appellant. As a result, the respondent invoked the arbitration clause and the dispute was referred to learned Arbitrator Shri Sunil Chopra, Chief Engineer (Contract) as provided under the Contract. (d) Learned Arbitrator made the Award dated 24.08.2011. It is pertinent to note here that the respondent referred total 12 claims in the arbitration proceeding. Out of these claims, two were rejected by learned Arbitrator and one claim is partly withdrawn by the respondent and the remaining claims were decided in favour of the respondent. (e) Feeling aggrieved, the appellant filed OMP Nos. 890 and 891 of 2011 before the High Court of Delhi. Learned single Judge of the High Court, vide common order dated 3 16.03.2012, dismissed both the petitions and upheld the Award passed by learned Arbitrator. (f) Being aggrieved with the said order, the appellant preferred two separate first appeals being FAP (OS) Nos. 238 and 239 of 2012 respectively. However, the same two appeals also got dismissed by the Division Bench of the High Court _in limini_ vide judgment and order dated 28.05.2012. (g) As a result, the appellant has filed these two appeals by way of special leave before this Court. 4) We have given our thoughtful consideration to the submissions of learned senior counsel for the parties and perused the material on record placed before us. ## **Point(s) for consideration:-** 5) The present case is confined only to the extent as to whether the Award of the arbitrator and the findings of the High Court are contrary to the express provision of Clause 19, according to which no escalation is permissible to the contractor for, _inter alia_ , increase in wages of labour due to 4 statutory hike, which the contractor may have to incur during the execution of the work on any account? ## **Rival contentions:-** 6) At the outset, learned senior counsel for the appellant-Union of India contended that the relationship of the appellant and respondent is governed by the terms and conditions of the contract and as per Clause 19 of the special conditions, it is clearly mentioned that “ _No escalation, reimbursement whatsoever shall be made to the contractor for increase in, inter-alia, wages of the labor during the execution of the contract”._ Hence, the Notification issued by the State of Haryana which increased the minimum wages of the labour during the subsistence of the contract does not vest any right to the contractor to claim any extra amount on account of labour wages. Hence, the impugned decision of the High Court is liable to be set aside. 5 7) _Per contra_ , learned counsel for the respondent submitted that this Court need not interfere with the order passed by the High Court and the arbitral Award under the question as the challenge in the instant appeal does not fall within the contours of Section 34 of the Arbitration and Conciliation Act, 1996 (for brevity “the Act”). The alleged challenges pertain to certain claims relating to interpretation of the contract which falls within the jurisdiction of the Arbitrator and findings of facts which are final and binding between the parties, hence, this Court ought not to interfere if the interpretation taken is plausible one and does not shocks the conscience of this Court. Further, it was submitted that the impugned decision of learned single Judge as well as the Division Bench of the High Court is well-reasoned and based on the cannon of laws which does not call for interference by this Court. Therefore, these appeals being devoid of merits and deserve to be dismissed. ## **Discussion:-** 6 8) The primary object of the arbitration is to reach a final disposition in a speedy, effective, inexpensive and expeditious manner. In order to regulate the law regarding arbitration, legislature came up with legislation which is known as Arbitration and Conciliation Act, 1996. In order to make arbitration process more effective, legislature restricted the role of courts in case where matter is subject to the arbitration. Section 5 of the Act specifically restricted the interference of the courts to some extent. In other words, it is only in exceptional circumstances, as provided by this Act, the court is entitled to intervene in the dispute which is subject matter of arbitration. Such intervention may be before, at or after the arbitration proceeding, as the case may be. In short, court shall not intervene with the subject matter of arbitration unless injustice is caused to either of the parties. 9) It is well-settled cannon of law that parties are free to decide their own terms and conditions in case of a contract. In the instant case, Clause 19 of the special conditions deal 7 with issue of bar on reimbursement of certain payments on account of escalation. It is apt to re-produce the said clause 19 herein below: “ **19. Reimbursement/Refund of Variation in Prices:-** No escalation, reimbursement what so ever shall be made to the contractor for increase in price of materials and fuels and wages of labour which the contractor may have to incur during execution of the work on any account. The contractor shall quote their rates accordingly.” On a plain reading of abovementioned clause, _prima facie,_ it appears that the appellant made it clear that the contractor shall quote their rate after having regard to this clause that no reimbursement regarding any escalation whatsoever be made to the contractor if any such escalation takes place during the subsistence of the contract which the respondent with open eyes had agreed. The word _“whatsoever”_ as used in Clause 19 suggests that even any escalation takes place due to the action of the government would also not be reimbursed. 10) At this juncture, we would also like to mention that Clause 6.3 of special conditions, particularly, deals with the 8 present issue. For the sake of convenience, it is reproduced herein below: ## **“Minimum Wages Payable:** 6.1. Refer condition 51 of DG MAP general conditions of contracts. The Contractor shall not pay wages lower than minimum wages of labour as fixed by the Govt of India/State Govt/Union Territory whichever is higher. 6.2 The fair wage referred to in condition 51 of DG MAP general conditions of contracts will be deemed to be the same as the minimum wages payable as referred to above. ## 6.3. **The contractor shall have no claim whatsoever, if on account of local factor and /or regulations he is required to pay the wages in excess of minimum wages as ” described above during the execution of work.** **(Emphasis supplies by us)** On a plain reading of Clause 6.3 read with Clause 19, it is evident that it was particularly made clear that no escalation would be reimbursed even in the case of Regulation. Hence, in the presence of such clauses, which respondent voluntarily agreed before accepting the contract, any departure cannot be allowed. In other words, now the respondent cannot claim reimbursement of excess of minimum wages on account of hike due to the Notification of the Government of Haryana. If any departure would be allowed from the terms and conditions of the contract, then it 9 would destroy the basic purpose of the contract provided such conditions shall not be arbitrary. 11) In the impugned decision, the Division Bench of the High Court, at Para 6 & 7 held as under: “6. Suffice would it be to state that clause 19 and 25 have to be read harmoniously. Whereas Clause 19 prohibits escalation to be paid with respect to the wages of labour, Clause 25 requires minimum wage increase to be reimbursed to the contractor upon there being an impact thereon by a law declared by the State Government. The minimum wages, as we all know, are statutorily notified under the Minimum Wages Act, 1948. We note that the learned arbitrator has granted the benefits under the said head, but not fully recompensing the contractor the 37.46% increase in minimum wages. The reasoning given by the learned arbitrator is that the contractor could have envisaged that there would be some increase in wages during the period of contract. 7. The interpretation by the learned arbitrator, if at all is faulty, is to the detriment of the contractor, for the reason Clause 25, which commences with the expression? However? is required to be read as an exception to Clause 19 and, if so read, the entire increase in minimum wages which was result of a government notification was required to be recompensed.” 12) It is a settled law that the process of interpretation is based on the objective view of a reasonable person, given the context in which the contracting parties made their agreement. On a perusal of the said two paragraphs of the impugned judgment, we fail to understand that on what 10 parameters the High Court has interpreted Clause 19 in light of Clause 25 of the Contract. Both the clauses stand on different footing. Clause 19 deals, _inter alia_ , with the matter of wages whereas Clause 25 deals with the matter of Octroi Sales Tax and other Duties. Such interpretation adopted by the High Court is against the cardinal principle of law which says that the terms of the contract shall be construed by the courts after having regard to the intention of the parties. Courts ought not to take any hypothetical view as it may cause prejudice to either of the parties. 13) It is pertinent to note here that Clause 19 does not start with any word _“Subject to”._ Moreover, there is no other provision in the contract which specifically allow the reimbursement of wages in case of escalation. In the absence of these things, we are of the considered view that it is not permissible in law that Clause 19 ought to be interpreted in light of Clause 25. Also in the impugned judgment, the High Court without having regard to the title and first part of 11 Clause 25, interpreted Clause 19, along with the second part of Clause 25, which is against the cannons of law. 14) To sum up, Clause 19 cannot be read in the light of second Part of Clause 25 as both stands on different footing i.e., deal with separate issues. Hence, the respondent-Contractor in the present case is not entitled to claim any escalation in minimum wages as it would be against the condition of Clause 19 read with Clause 6.3. 15) In view of the above detailed discussion, we are of the considered view that the High Court erred in law. Accordingly, we are inclined to allow these appeals and set aside the decision of the courts below as also the Award. Parties to bear their own cost. ...…………….………………………J. ## **(R.K. AGRAWAL)** .…....…………………………………J. ## **(ASHOK BHUSHAN)** NEW DELHI; APRIL 19, 2018. 12
End of Judgment Record
Browse All Landmark Cases Judgments
2019-01-22

State of Himachal Pradesh & Anr. v. Pinju Ram & Others; State of Himachal Pradesh & Ors. v. Ganesh Dutt & Anr.

This batch of appeals concerns regularisation and monetary benefits of part‑time employees in Himachal Pradesh who were converted to daily‑wage status. The State had issued a policy on 27 February 2004: part‑time Class‑IV employees who had completed ten years of continuous service as on 31 December 2003 would be made daily wagers with prospective effect, and posts vacated by such employees would stand abolished; Education and Ayurveda were excluded from the policy. Revenue Chowkidars, engaged by Panchayats, were not covered by that policy and received separate treatment. Following writ petitions and an order of the Himachal Pradesh High Court and in light of later developments, the State drew‑up directions in 2011 (22 September) to give seniority to Revenue Chowkidars on the basis of ten years of service, but with wages from the date of actual appointment and without back‑dated monetary benefits; 7 July 2012 further instructions reiterated this stance for remaining part‑time employees, with monetary benefits not guaranteed in the interregnum. The respondents pressed for back wages dating from 1 January 2007 and broader coverage. The Supreme Court held that the 2007 back‑pay direction was unsustainable, clarified that seniority would count from ten years without past benefits, and that the 2011 policy and Moti Singh principle should guide the approach. The appeals are allowed; no costs. The related writ petitions are to be disposed of consistent with these directions.

2018-08-14

Union Bank of India and Others v. C.G. Ajay Babu and Anr.

This is a Supreme Court of India appeal concerning the forfeiture of gratuity under the Payment of Gratuity Act, 1972. The respondent was a branch manager of the appellant bank and was dismissed on 3 June 2004 after disciplinary proceedings. A show-cause notice sought to forfeit gratuity due to misconduct involving moral turpitude, which was ordered on 20 April 2004. The High Court upheld the dismissal but held that gratuity could be paid since there was no financial loss to the bank, and that a bipartite settlement between the bank and employees permitted forfeiture only where misconduct caused financial loss. The Division Bench, however, held that forfeiture under Section 4(6) must be read together with Section 4(5) and that no loss was proven, thus entitling the employee to gratuity in accordance with the bipartite settlement. The Supreme Court agreed with the High Court that forfeiture is not automatic; it is controlled by Sections 4(5) and 4(6) of the Act and by the bipartite settlement, which requires loss to justify forfeiture. The Court emphasized that an act must constitute an offence involving moral turpitude and that conviction is generally required for forfeiture under 4(6)(b)(ii). The appeal is dismissed with no costs.

2018-09-25

Reema Salkan v. Sumer Singh Salkan

This is a Supreme Court of India criminal appeal under the Criminal Appellate Jurisdiction arising from a maintenance dispute under Section 125 Cr.P.C. The parties, married in 2002, had a protracted litigation history. The Family Court granted maintenance to the wife from 17 July 2003 to 8 December 2010, and held no maintenance thereafter. The High Court, in revision, partly allowed the application, directing Rs.9,000 per month from 9 December 2010 onward, while upholding the earlier period’s Rs.10,000 per month. This Court had earlier granted interim maintenance of Rs.20,000 per month in 2014 (Criminal Appeal Nos. 2347-2349 of 2014). The appellant contends there has been no change in circumstances since the interim order and that the respondent’s substantial assets, education, and overseas earnings establish the capacity to pay higher maintenance. The respondent defends the High Court’s reasoning, arguing that the Family Court’s assessment, demeanor observations, and the principle that maintenance should not be perpetual require careful scrutiny, and that the notional minimum wage approach used by the High Court is flawed. The overarching issue is the quantum of monthly maintenance payable to the appellant and whether the interim amount should be augmented beyond the period up to 2010.”

2019-12-03

M/s Embassy Property Developments Pvt. Ltd. v State of Karnataka & Ors.

This judgment concerns three Civil Appeals filed by a Resolution Applicant, the Corporate Debtor (through its Resolution Professional) and the Committee of Creditors, challenging an Interim Order of the Karnataka High Court staying an NCLT order in proceedings under the Insolvency and Bankruptcy Code, 2016. The NCLT Chennai had admitted an application under Section 7 of the IBC against M/s Tiffins Barytes Asbestos & Paints Ltd. and directed a moratorium under Section 14. The Interim Resolution Professional then sought a deemed extension of a mining lease under MMDR Act, 1957 and the Government of Karnataka rejected it. The NCLT, by an order dated 11.12.2018, set aside the Government’s order and directed execution of Supplement Lease Deeds for the period up to 31.03.2020. The Government of Karnataka challenged this in a High Court writ petition, which stayed the impugned NCLT order. The core issues were: (i) whether the High Court may interfere under Article 226/227 with an NCLT order in IBC when an appeal lies to the NCLAT, and (ii) whether fraud can be inquired into by NCLT/NCLAT in CIRP. The Court reiterates that IBC is a complete, umbrella code with a three‑tier mechanism (NCLT, NCLAT, Supreme Court) and that public‑law disputes arising from MMDR Act obligations lie outside IBC. It ultimately holds that while NCLT/NCLAT may inquire into fraud, they cannot adjudicate MMDR‑related public legal disputes; and the High Court’s writ jurisdiction in public‑law contexts remains permissible. The appeals are dismissed.