Union of India v. M/s. Concrete Products & Construction Co. Ltd. & Ors.

Case / Petition Number:
Civil Appeal Nos. 2950-2951 of 2014
Neutral Citation:[2014] 3 S.C.R. 535

Case Synopsis & Summary

This case concerns recovery of excess payments made by the Railways under escalation clauses in contracts for supply of mono block concrete sleepers. The Railway Board found excess payments made between 1989 and 1994 and issued recoveries against two contractors. The contracts contained Clauses 2401 and 2403, allowing the Railways to withhold and lien security deposits or sums due under the contract, and to recover such amounts, with an explicit bar that the contractor would have no claim for interest or damages for such withholdings once duly notified. An arbitrator awarded interest at 18% on the amounts recovered, and the High Court upheld this, prompting the Union of India to challenge the award. The central issue was whether contractors are entitled to interest for amounts withheld and recovered in terms of the contract. The Supreme Court held that the sole arbitrator erred by awarding interest without properly applying Clauses 2401 and 2403 and the relevant statutory provisions. It reiterated that Section 31(7) of the Arbitration Act bars interest up to the date of award where the contract itself prohibits it, and that interest, if any, could only arise from the date of the award until the amount is deposited, with the contract limiting such payments. The Court ultimately allowed the appeals, directing that the contractors shall not be entitled to any interest on the amount recovered up to the award and from the award to the date of deposit in court. The decision emphasizes strict adherence to the contract terms governing withholdings and liens when computing any interest on recovered sums.

Precedent Explorer

Find Cases Like This

Explore other judgments dealing with similar legal situations, facts, or statutory provisions.

Case Details & Bench

Court
Supreme Court of India
Hon'ble Judges
  • Surinder Singh Nijjar
  • Fakkir Mohamed Ibrahim Kalifullla
Judgment Date
2014-03-03
Court Decision / Holding
Appeals allowed. The Supreme Court directed that the respondents shall not be entitled to any interest on the amount recovered by the appellant till the date of award and thereafter till the date when the amount awarded was deposited in the High Court. It clarified that the arbitrator had failed to consider Clauses 2401 and 2403 and the statutory constraints, and that interest could not be awarded from the date of recovery to the date of award. The decision reinforces adherence to contractual lien provisions and limits on post-recovery interest.
Final Disposition
Appeals allowed

Parties to the Case

Appellants / Petitioners

  • Union of India

Respondents

  • M/s Concrete Products & Construction Co. Ltd.
  • M/s Kottukulam Engineers Private Limited

Legal Representation & Advocates

Counsels for Petitioners

  • • Mohan Jain, ASG
  • • D.S. Thakur
  • • Prachi Bajpai
  • • Shreekant A N. Terdal

Counsels for Respondents

  • • C.S. Vaidyanathan
  • • G. Umapathy
  • • Rakesh K. Sharma

Provisions of Law Cited

Arbitration and Conciliation Act, 1996 - Section 37(1)Arbitration and Conciliation Act, 1996 - Section 31(7)Arbitration and Conciliation Act, 1996 - Section 33Indian Railways Standard Conditions of Contract - Clause 2401Indian Railways Standard Conditions of Contract - Clause 2403

Submissions & Arguments

Contentions of Appellants / Petitioners

The Union of India contended that the arbitrator had no authority to award interest in view of the explicit restrictions in the contract and in light of Section 31(7) of the Arbitration Act, and that Clauses 2401 and 2403 authorize withholding with lien but deny any interest on retained sums, especially if such withholdings are due to overpayments. It was argued that the contract does not permit interest on amounts recovered in excess of dues, and that the arbitrator failed to consider these contractual provisions and the bar to prejudgment interest. The Union relied on precedents such as Sayeed Ahmed, Sree Kamatchi Amman Construction, and other cases to support strict contractual interpretation and the non-award of pre-award interest, while emphasizing that any interest could only be payable from the date of the award if at all.

Contentions of Respondents

The respondents argued that the Railways had the right to withhold amounts and exercise lien under Clauses 2401 and 2403 and to recover overpayments. They asserted that the 30% deduction and earlier withholdings were agreed upon and that the arbitrator’s award of interest was contemplated by practice under the contract. They contended that interest on withheld amounts should be considered, subject to the contract terms and the contractor’s notification, and that the High Court correctly upheld the arbitrator’s power to award interest in certain circumstances. They also argued that the decision to withhold and recover was valid and that any limitation on interest must be strictly construed in light of the contracts and relevant judicial precedents.

Legal Doctrine & Issue Explorer

Explore This Legal Issue

Find relevant judgments and authoritative positions on the legal questions discussed here.

Cited Precedents (6)

Case NameCitationTreatmentExplanation
Sayeed Ahmed & Company v. State of Uttar Pradesh & Ors.2009 (10) SCR 841PositiveUsed to support the proposition that Section 31(7) bars interest up to the date of award where the contract prohibits it, including pre-reference and pendente lite periods.
Sree Kamatchi Amman Construction v. Divisional Railway Manager (Works), Palghat & Ors.2010 (10) SCR 487PositiveThe Court cited this case to reinforce that Section 37(1) of the Arbitration Act binds the arbitrator to the contract terms regarding the award of interest.
Himachal Pradesh Housing and Urban Development Authority & Anr. v. Ranjit Singh Rana2012 (2) SCR 427PositiveCited in support of strict construction of contractual provisions regarding interest.
Union of India v. Krafters Engineering and Leasing Private Limited2011 (8) SCR 196PositiveUsed to support the proposition that deprivation of money entitles the claimant to compensation by interest, subject to contract constraints.
Executive Engineer, Dhenkanal Minor Irrigation Division, Orissa & Ors. v. N. C. Budharaj (Deceased) by LRs. & Ors.2001 (1) SCR 264PositiveCited for the principle that interest can be payable on deprivation of money, subject to contractual terms.
Secretary, Irrigation Department, Government of Orissa & Ors. v. G. C. Roy1991 (3) Suppl. SCR 417PositiveCited as authority on related principle of compensation for deprivation of money.
Case Applicability Diagnostic

Apply This to My Facts

Share your situation and test whether this judgment governs, supports, or challenges your case.

Official Judgment Record
•5,236 words•~24 min read

In The Court Record

Union of India v. M/s. Concrete Products & Construction Co. Ltd. & Ors.

[2014] 3 S.C.R. 535 A ## UNION OF INDIA _v._ MIS. CONCRETE PRODUCTS & CONST. CO. ETC. (Civil Appeal Nos. 2950-2951 of 2014) B ## MARCH 3, 2014 ## **[SURINDER SINGH NIJJAR AND FAKKIR MOHAMED IBRAHIM KALIFULLA, JJ.]** _Arbitration and Conciliation Act, 1996: s.37(1)_ - _Interest_ C - _for the amount withheld by the railway administration Grant_ - _of Held: Arbitrator passed an award directing the railway administration to refund the amount along with interest and subsequent interest_ @ _18% PA._ - _Arbitrator in awarding interest to the contractors failed to take into ac.count the_ D _provisions contained in Indian Railways Standard Conditions of Contract which disentitled the contractors from claiming any interest or damages for withholding or retention under lien by railway administration_ - _Also,_ as _per s.37(1), the arbitrator could not have awarded any interest from the date when the_ E - _recovery_ was _made till the award_ was _made Interest would have been payable from the date when the award_ was _made till the money_ was _deposited in the court_ - _Upon the amount being deposited, no further interest could be paid to the contractors_ - _Interest._ **F** E **F** . **The appellant-Railway administration and the contractor-respondents entered into contract for supply of concrete sleepers. By letter dated 12 July 1997, appellant-Railway administration informed the respondents that the excess payments had been made** G **to the respondents and, therefore, certain amount was recoverable from the respondents and that said amount would be recovered from sum due or payable from** 535 H 536 SUPREME COURT REPORTS (2014] 3 S C.R A running contract. This gave rise to dispute which was referred to arbitrator. The arbitrator passed an award directing the appellant to refund the amount along with interest and subsequent interest @ 18% PA. The respondents filed an application seeking direction to the B appellant to pay amount awarded from the amount deposited by the appellant with the High Court along with the accrued interest as on date on the said amount. The application was allowed. The appellant filed intra court appeals challenging the order of the single judge c principally on the ground that the appellant was not liable to pay any interest for the period subsequent to the deposit of the principal amount into the court. The Division Bench of the High Court dismissed the appeal holding that appellant had not questioned the power of 0[the sole arbitrator to award interest; that the said issue ] was also not raised before the single judge and a pie.a was raised for the first time before the Division Bench that the award of interest was contrary to Clause No. 2401 of the Indian Railways Standard Conditions of Contract. E The question which arose for consideration in the instant appeals was whether the contractors are entitled to interest for the amount withheld. ## Allowing the appeals, the Court F HELD: 1.1. Clause 2401 provides that the railways shall be entitled to withhold and also have a lien to retain any amount deposited as security by the contractor to satisfy any claims arising out of or in the contract. In such circumstances, the railways can withhold the amount G deposited by the contractors as security and also have lien over the same pending finalization or adjudication of the claim. In case, the security deposit is insufficient to cover the claim of the railways, it is entitled to withhold and have lien to the extent of the amount claimed from H any sum payable for any works done by the contractor UNION OF INDIA _v. MIS._ CONCRETE PRODUCTS & 537 CONST. CO. ETC. thereafter under the same contract or any other contract. A This withholding of the money and the exercise of the lien is pending finalization or adjudication of any claim. This clause further provided that the amount withheld by the railways over which it is exercising lien will not entitle the contractor to claim any interest or damages for such B withholding or retention under lien by the railways. [Para 15) [548-D-G] 1.2. Clause 2403 provides that any sum of money due and payable to the contractor under the contract may be C withheld or retained by way of lien by the railway authorities or the Government in respect of payment of a sum of money arising out of or under any other cont~act made by the contractor with the railway authority or the Government. Clause 2403(b) further provides that it is an agreed term of the contract that against the sum of D money withheld or retained under lien, the contractor shall have no claim for interest or damages whatsoever provided the claim has been duly notified to the contractor. [paras 16, 17) [548-H; 549-A-B] E 2. The sole arbitrator in awarding interest to the contractors has failed to take into account the provisions contained in the said two clauses. The award of interest at-least from the date when the amount was deposited in Court was wholly unwarranted. Therefore, the High Court as well as the arbitrator have committed an error of jurisdiction in this respect. As per section 37(1), the arbitrator could not have awarded any interest from the date when the recovery was made till the award was made. However, interest would have been payable from the date when the award was made till the money was deposited in the High Court and thereafter converted to fixed deposit receipts. Upon the amount being deposited in the High Court, no further interest could be paid to the respondents. The respondents shall not be entitled to any F G H SUPREME COURT REPORTS [2014] 3 S.C.R. 538 A interest on the amount which was recovered by the appellant, till the date of award and thereafter till the date when the amount awarded was deposited in the High Court. [paras 18, 20, 21] [549-C-D; 550-8-E] 8 _Sayeed Ahmed_ & _Company v. State of Uttar Pradesh_ & _Ors._ (2009) 12 SCC 26: 2009 (10). SCR 841; _Sree Kamatchi Amman Construction v. Divisional Railway Manager (Works}, Pa/ghat_ & _Ors._ (2010) 8 SCC 767: 2010 (10) SCR 487 - relied on. C C _Himachal Pradesh Housing and Urban Development Authority_ & _Anr. v. Ranjit Singh Rana_ (2012) 4 SCC 505: 2012 (2) SCR 427; _Union of India v. Krafters Engineering and Leasign Private Limited_ (2011) 7 SCC 279: 2011 (8) SCR 196; _Executive Engineer, Dhenkanal Minor Irrigation_ D _Division, Orissa_ & _Ors. v. N._ C. _Budharaj (Deceased) by LRs._ & _Ors._ (2001) 2 SCC 721: 2001 (1) SCR 264; _Secretary, Irrigation Department, Government of Orissa_ & _Ors. v._ G. C. _Roy_ (1992) 1 SCC 508: 1991 (3) Suppl. SCR 417 - referred to. E ## Case Law Reference: F G ||Case Law Reference:|Case Law Reference:|| |---|---|---|---| |2012|2012(2)SCR427|referred to|Para10| |2010|2010(10)SCR487|relied on|Para11| |2009|2009(10)SCR841|relied on|Para11| |2011|(8)SCR196|referred to|Para11| |2001|(1)SCR264|referred to|Para12| |1991|(3)Suppl. SCR417|referred to|Para12| CIVIL APPELLATE JURISDICTION : Civil Appeal No. 2950-2951 of 2014. From the Judgment & Order dated 21.03.2012 of the High H Court of Madras in OSA No. 44 and 45 of 2012. UNION OF INDIA _v._ M/S. CONCRETE PRODUCTS & 539 CONST. CO. ETC. Mohan Jain, ASG, D.S. Thakur, Prachi Bajpai, Shreekant A N. Terdal for the Appellant. C.S. Vaidyanathan, G. Umapathy, Rakesh K. Sharma for the Respondents. The Judgment of the Court was delivered by B **SURINDER SINGH NIJJAR, J.** 1. Leave. granted. 2. These appeals impugn the final judgment and decree dated 21st March, 2012 passed by the High Court of C Judicature at Madras in OSA No. 44 & 45 of 2012 and M.P. No. 1 of 2012, whereby the letters patent appeals of the Union of India were dismissed. The appellant had entered into agreements with the respondents on 30th January, 1983 and 30th March, 1984 for supply of mono block concrete sleepers (in short "Sleepers"). The agreements were renewed from time D to time under which the Union of India agreed to pay specified rates for supply of each sleeper. The agreements/contracts also provided that the rates payable shall be based on certain standard rates of principal raw materials, such as cement, High Tensile Steel (HTS) wires, molded steel, etc. The contracts E further provided that whenever the cost of the principal raw materials increased or decreased, the contract price for sleepers shall also correspondingly be increased or decreased with effect from the date of such increase or decrease. The agreements/contracts also provided for escalation, subject to F certain conditions prescribed under Clause 11 of the Contract. The contracts/agreements further provided that the respondents must exercise utmost economy in the purchase of raw materials and that the escalation will be admitted on the basis of actual price paid for the respective raw material. This was subject to G the ceiling on the price. As per Clause 12.2(c), ceiling was fixed "in the case of raw materials not covered by either of the above, the lowest price (for destination) arrived at on the basis of at least three quotations obtained by the Contractor for each supply from various established sources of supply of the H D E F G H 540 SUPREME COURT REPORTS [2014] 3 S.C.R. . ## A respective raw materials". 3. The respondents/contractors purchased HTS wires from established sources in terms of the various clauses of the contract. The material was used in the manufacture of sleepers. B Payment for the sleepers was made by the contractors at the lowest price quoted by the suppliers. The quotation was also scrutinized alongwith the supporting documents. The Railway authorities release the payment to the respondent contractors only upon their satisfaction, upon scrutiny of all the relevant documents. ## c 4. A new contract was entered into between the parties in May, 1997. The railway administration changed the policy and allowed the respondents/contractors to purchase the HTS wires, subject to escalation as noticed above. By letter dated D 12th July, 1997, the railways administration informed the respondents that the Railway Board had found that excess payments had been made between 1989 and November, 1994 under escalation clause for HTS wires. It was stated that the amounts paid to the contractors were more than the prevalent E market price. Therefore, a sum of Rs. 1,80,92,462/- was recoverable from M/s Concrete Products and Construction Company, respondent in C.A. No. (arising,.out of SLP(C) No. 5384 of 2013) and a sum of Rs.1,78,09,789/was recoverable from Mis. Kottukulam Engineers Private F Limited, respondent in C.A. No. (arising out of SLP(C) No. 5385 of 2013). It was also pointed out that the aforesaid sums would be recoverable from the sums due and payable to them in the current/running contracts. 5. The contractors (respondents herein) challenged the G aforesaid recovery by filing Writ Petition No. 11805 and 10814 of 1999, before the High Court of Madras. The railway administration took up the preliminary objection, pleading that the writ petition is not maintainable as the dispute has to be referred to arbitration. The objection of the appellant was H UNION OF INDIA _v._ MIS. CONCRETE PRODUCTS & 541 CONST. CO. ETC. [SURINDER SINGH NIJJAR, J.] accepted. The High Court appointed a Former Judge of the A Madras High Court as the arbitrator to adjudicate the dispute. The contractors/respondents herein challenged the aforesaid order of the learned Single Judge by filing Writ Appeal Nos. 251 and 2.52 of 2000, on the plea that the arbitrator had to be appointed in terms of the agreement. By order dated 22nd B March, 2000, the writ appeals were allowed, and the order of the learned Single Judge was set aside. The matter was remanded back to the Single Judge for disposal in terms of the agreement. On remand, the learned Single Judge, instead of referring matter to arbitration in terms of the contract between the parties allowed the writ petitions filed by the respondents herein and direct~d the railway authorities to refund the sum of . Rs.1,69, 78,883/- and Rs.1, 78,09, 789/- to the respondent firms, respectively with interest thereon from the date of withholding till the date the same is refunded. The order was directed to be complied within a period of 4 week from the date of the receipt of the order. This order was again challenged by the railway administration by filing, first of all, Writ Appeal Nos. 2822 and 2823 of 2001. Subsequently, writ appeal miscellaneous petition No. 21103 and 21104 of 2001 were also filed in the aforesaid two writ appeals, seeking stay of the judgments under appeal. On 30th April, 2004, the Division Bench dismissed the writ appeals as well as the miscellaneous petitions. c D E F 6. The railway administration challenged the aforesaid order of the Division Bench, before this Court by filing SLP No. 18244 and 18245 of 2004. Special leave was granted in both the special leave petitions and the same were converted to Civil Appeal Nos. 2999 and 3000 of 2005. By a short order passed on 2nd May, 2005, the disputes between the parties were referred by this court for adjudication by an Arbitration Tribunal consisting solely of Mr. Justice K. Venkataswami, a former Judge of this Court. This order was passed without going into G H 542 SUPREME COURT REPORTS [2014] 3 S.C.R. - A the merits of the disputes and the submissions made by the learned Solicitor General on behalf of the railways, that in view of the specific condition contained in the contract, the dispute cannot be referred to an arbitrator other than the authority referred to in the contract. This Court directed that the matter - B shall be referred to Mr. Justice Venkataswami. It was, however, made clear that the order shall not be treated as a precedent. Pursuant to the aforesaid order of this Court, the matter ultimately reached the arbitrator. At the conclusion of the arbitral proceedings, the final award was rendered on 24th June, 2006. - c The sole arbitrator directed the appellants to refund the amount awarded as follows:- - "In the result I direct the Respondents to refund a sum of Rs.1, 78,09, 789/- recovered from the Claimants and interest of Rs.2,38,28,960/- and subsequent interest at - D 18% P:A from 1.9.2005 on Rs. 1, 78,09, 789/- till date of payment in Kottukulam Engineers Pvt. Ltd. matter. Ana a sum of Rs.1,69, 78,883/- and interest of Rs.2,25,25,513/and subsequent interest at 18% P .A from 1.09.2005 till date of payment in m/s Concrete Product & Construction - E Company Trivalam." The counter claims made by the appellants were dismissed. The railway administration challenged the common arbitration award in O.P. No. 142 & 143 of 2007 under Section F 33 of the Arbitration and Conciliation Act, 1996 before High Court of Madras. The learned Single Judge dismissed the arbitration petitions filed by the railway administration by its order dated 30th November, 2010. Thereafter the contractors filed applications before the High Court for direction to the G railways to make payments of the amount. Thereafter Application Nos. 780 & 781 of 2011 were filed in the O.P. Nos. 142 & 143 of 2007 by the contractors seeking a direction from the Court directing that the amounts awarded by the learned Sole Arbitrator be paid from the amount deposited by the railway administration with the High Court along with the H UNION OF INDIA _v._ MIS. CONCRETE PRODUCTS & 543 CONST. CO. ETC. [SURINDER SINGH NIJJAR, J.] accrued interest as on date on the aforesaid amount. These A applications were allowed by order dated 24th February, 2011. The High Court directed that the awarded amount deposited by the railways in the Court for satisfying the outcome of the original petitions which was subsequently converted into fixed deposit receipts, be dispersed to the respondent contractors. B 7. Again the railway administration filed intra court appeals challenging the order of the learned Single Judge principally on the ground that the railway administration was not liable to pay any interest for the period subsequent to the deposit of the principal amount into Court. The appeals filed by the railway administration were dismissed by the High Court by the impugned order dated 21st March, 2012. The High Court held that railway administration had not questioned the power of the sole arbitrator to award interest. The issue with regard to the award of interest was also not raised before the learned Single Judge. For the first time before the Division Bench, a plea was raised that the award of interest was contrary to Clause No. 2401 of the Indian Railways Standard Conditions of Contract. The Division Bench of the High Court came to the conclusion that the aforesaid clause has no application at all as it applies only to amounts, which have been withheld or retained under lien. The amounts having already been paid were sought to be illegally recovered from the contractors. The sole arbitrator found that such order of recovery can not be sustained in law and the recoveries affected were illegal. The High Court, however, concluded that Clause No. 2401 would have application only in respect of amounts which had not been paid to the contractors. The railway administration can not exercise lien over the amounts already paid to the contractors. Therefore, award of the arbitrator did not suffer from any error apparent. It was further held that the learned Single Judge having upheld the award, the appeals deserve to be dismissed. C D E F G 8. The appeals having been dismissed, the Union of India has approached this Court in these Civil Appeals. H 544 SUPREME COURT REPORTS [2014] 3 S.C.R. A 9. We have heard Mr. Mohan Jain, learned Additional Solicitor General, appearing for the appellants. 10. It is submitted that the only question which arises for consideration of this Court is whether the contractors are 8[entitled ][to ][interest ][for ][the ][amount ][withheld ][and ][if ][so ][at ][what ][rate. ] The contractors had claimed interest @18 per cent from the date of recovery till payment. Mr: Jain submitted that the High Court has wrongly held that the appellant had no authority to exercise lien on the current payments in relation to the amount already released to the contractors. It is submitted by Mr. Jain C that the arbitrator had no authority to award interest in view of the prohibition contained under Section 31 (7) of the Arbitration Act, 1996. Learned Additional Solicitor General pointed out that the contract entered into between the parties did not provide for any payment of interest. Mr. Jain also pointed out that under D Clause 2403, the railway administration has a lien on all the amounts of money that may be due to the contractors, _in praesenti_ or _in the futuro._ °Therefore, when the contractors were paid in excess of the amounts actually due, the appellants were fully justified in recovering the amount from the respondents by E exercising the _lien_ over the future bills in terms of Clause No. 2403. He submits that the sole arbitrator was wholly unjustified in awarding interest, as under Clause No. 2403(b), it is specifically provided that the contractors shall have no claim for interest or damages whatsoever, for the amount so retained F even in case the arbitration award or any other legal proceeding subsequently holds that the amount was withheld illegally. Mr. Jain submits that the learned Single Judge erred in holding that the award did not suffer from an error apparent on this short ground. In support of the submission, he relies on G judgment of this Court in the case of _Himachal Pradesh Housing and Urban Development Authority_ & _Anr. Vs. Ranjit Singh Rana[1] •_ H 1. c2012) 4 sec 505. UNION OF INDIA _v._ MIS. CONCRETE PRODUCTS & 545 CONST. CO. ETC. [SURINDER SINGH NIJJAR, J.] 11. Mr. Jain further submitted that the principal amount A awarded was deposited in Court in 2007. This amount was released to the contractors on 24th April, 2011 alongwith the interest, but 30 per cent of the amount was duly withheld. This was in agreement with the respondents. He also pointed out that in fact the recovery of the amount was deferred after B discussions with the respondents. In view of the agreements, the respondents had no justification for claiming any interest and the award granting such relief suffer from an error apparent as it was contrary to the contract. In support of this submission, he relies on judgment of this Court in Sree _Kainatchi Amman_ c. _Construction Vs. Divisional Railway Manager (Works), Pa/ghat_ & _Ors._[2 ] He also relied on _Sayeed Ahmed_ & _Company Vs. State of Uttar Pradesh_ & _Ors._[3 ] and _Union of India Vs. !<rafters Engineering and Leasign Private Limited._[4 ] 12, Mr. C.S. Vaidyanathan, learned senior counsel D appearing for the respondents, on the other hand, submitted that the payments have been made to the contractors from 1989 till November, 1994. The High Court judgment in the writ petitions challenging the recovery notice were set aside by the High Court. The respondents had agreed to the deduction of E 30 per cent only because the contractors required the money for execution of further works. He submitted that the appellants can not possibly be permitted to claim that the respondents had agreed to the deduction of 30 per cent of the amount due. He pointed out that the recovery was made against the supplies F made under the agreements of 9th December, 1991 in relation to the contracts which were being performed in the year 1996. In such circumstances, the appellants had no authority to exercise lien on the amounts that accrued due to the works performed subsequent to 9th December, 1991 under Clause(s) G 2401 or 2403 of the Contract. Mr. Vaidyanathan emphasized that such recovery of the time barred claims is clearly without D E 2. (201d) a sec 767. 3. (2009) 12 sec 26. 4. c2011) _1_ sec 279. H [2014] 3 S.C.R. ## 546 SUPREME COURT REPORTS A any justification. The appellants having failed to notify that 30 per cent of the amount due had been withheld, the invocation of Clause No. 2401 or 2403 would be wholly illegal. Learned senior counsel further submitted that the appellant can not justify the recovery on the basis of the letter dated 22nd October, 1997 a as it was written without prejudice to the rights of the contractors. The counter claims made by the appellant were clearly time barred and hence, disallowed by the sole arbitrator. Mr. Vaidyanathan relied on a Constitution Bench decision of this Court in _Executive Engineer, Dhenkanal Minor Irrigation_ c _Division, Orissa_ & _Ors. Vs. N.C. Budharaj (Deceased) by LRs._ & _Ors._[5 ] Reliance was also placed upon _Secretary, Irrigation_ • _Department, Government of Orissa_ & _Ors. Vs._ G.C. _Roy6_ in support of the submission that a person deprived of his money is entitled to be compensated by way of interest, therefore, any provision in the contract which seeks to take away such a right . 0 has to be strictly construed. The ratio in the aforesaid judgment has been subsequently reiterated, according to Mr. Vaidyanathan, in the case of _Sree Kamatchi Amman Construction_ (supra). Mr. Vaidyanathan submitted that the railway administration had no authority either under Clause E 2401 or 2403 of the contract to recover the amounts allegedly overpaid for the work done prior to 1991 from the amounts due to the contractors for the works done subsequently. 13. We have considered the submissions made by the F learned counsel for the parties. 14. Clause Nos. 2401 and 2403 are as under:- - **"2401.** Whenever any claim or claims for payment of a sum of money arises out of or under the contract against the - G Contractor, the Purchaser shall be entitled to withhold and also have a lien to retain such sum or sums in whole or in part from the security, if any, deposited by the Contractor 5. c2001) 2 sec 721. - H 6. (1992) 1 sec 5oa. - UNION OF INDIA _v._ M/S. CONCRETE PRODUCTS & 547 CONST. CO. ETC. [SURINDER SINGH NIJJAR, J.] - and for the purpose aforesaid, the Purchaser shall be A entitled to withhold the said cash security deposit or the security, if any, furnished as the case may be and also have a lien over the same pending finalization or adjudication of any such claim. In the event of the security being insufficient to cover the claimed amount or amounts B or if no security has been taken from the Contractor, the Purchaser shall be entitled to withhold and have lien to retain to the extent of the such claimed amount or amounts referred to supra, from any sum or sums found payable or which at any time-thereafter may become payable to the c Contractor under the same contract or any other contract with the Purchaser or the Government pending finalization or adjudication of any such claim. It is an agreed term of the contract th.at the sum of money or moneys so withheld or retained under the lien referred to above, by the Purchaser will be kept withheld or retained as such by the Purchaser till the claim arising out of or under the contract is determined by the Arbitrator (if the contract is governed by the arbitration clause) or by the competent court as prescribed under Clause 2703 hereinafter provided, as the case may be, and that the Contractor will have no claim for interest or damages whatsoever on any account in respect of such withholding or retention under the lien referred to supra and duly notified as such to the contractor." D E F; - **"2403.** Lien in respect of Claims in other Contracts: - (a) Any sum of money due and payable, to the Contractor (including the security deposit, returnable to him) under the contract may withhold or retain by G way of lien by the Purcha~er or Government against any claim of the Purchaser or Government in respect of payment of a sum of money arising out of or under any other contract\ made by the Contractor with the Purchaser or Government. H 548 SUPREME COURT REPORTS [2014] 3 S.C.R. - A (b) It is an agreed term of the contract that the sum of money so withheld or retained under this clause by the Purchaser or Government will be kept withheld or retained as such by the Purchaser or Government till his claim arising out of the same - B contract or any other contract is either mutually settled or determined by the arbitrator, if the contract is governed by the arbitration clause or by the competent court under Clause 2703 hereinafter provided, as the case may be, and that the - c Contractor shall have no claim for interest or damages whatsoever on this account or on any other ground in respect of any sum of money withheld or retained under this clause and duly notified as such to the Contractor." A D 15. Clause 2401 provides that the railways shall be entitled to withhold and also have a lien to retain any amount deposited as security by the contractor to satisfy any claims arising out of or in the contract. In such circumstances, the railways can withhold the amount deposited by the contractors as security E and also have lien over the same pending finalization or adjudication of the claim. In case, the security deposit is insufficient to cover the claim of the railways, it is entitled to withhold and have lien to the extent of the amount claimed from any sum payable for any works done by the contractor thereafter F under the same contract or any other contract. This withholding of the money and the exercise of the lien is pending finalization or adjudication of any claim. This clause further provided that the amount withheld by the railways over which it is exercising lien will not entitle the contractor to claim any interest or G damages for such withholding or retention under lien by the railways. H 16. Clause 2403 again provides that any sum of money due and payable to the contractor under the contract may be withheld or retained by way of lien by the railway authorities or UNION OF INDIA _v._ M/S. CONCRETE PRODUCTS & 549 CONST. CO. ETC. [SURINDER SINGH NIJJAR, J.] the Government in respect of payment of a sum of money A _arising out of or under any other contract_ made by the contractor with the railway authority or the Government. 17. Clause 2403(b) further_pr.ovides that it is an agreed term of the contract that against the sum of money withheld or retained under lien,,the contractor shall have no claim for interest or damages ~hatsoever provided the claim has been duly notified to the contractor. 8 18. We are of the opinion that the sole arbitrator in awarding interest to the contractors has failed to take into account the provisions contained in the aforesaid two clauses. We find merit in the submission made by learned Additional Solicitor General that award of interest at-least from the date when the amount was deposited in Court was wholly unwarranted. Therefore, the High Court as well as the arbitrator, in our opinion, have committed an error of jurisdiction in this respect. This view of ours will find support from the judgment of this Court in the case of Sayeed _Ahmed_ & _Company_ (supra), wherein it has been held as follows:- "16. In view of clause (a) of sub-section (7) of Section 31 of the Act, it is clear that the arbitrator could not have awarded interest up to the date of the award, as .the agreement between the parties barred payment of interes.t. The bar against award of interest would operate not only during the pre-reference period, that is, up to 13-3-1997 but also during the pendente lite period, that is, from 143-1997 to 31-7-2001." C D E F 19. This view has been reiterated by this Court in _Sree Kamatchi Amman Construction_ (supra), wherein it has been G held as follows:- "19. Section 37(1) of the new Act by using the words "unless otherwise agreed by the parties" categorically clarifies that the arbitrator is bound by the terms of the H 550 SUPREME COURT REPORTS [2014] 3 S.C.R. A contract insofar as the award of interest from the date of cause of action to the date of award. Therefore, where the parties had agreed that no interest shall be payable, the Arbitral Tribunal cannot award interest between the date when the cause of action arose to the date of award." ## B 20. From the aforesaid it becomes apparent that the arbitrator could not have awarded any interest from the date when the recovery was made till the award was made. However, interest would have been payable from the date when the award was made till the money was deposited in the High C Court and thereafter converted to fixed deposit receipts. Upon the amount being deposited in the High Court, no further interest could be paid to the respondents. 21. In view of the aforesaid, the appeals are allowed and D it is directed that the respondents shall not be entitled to any interest on the amo.unt which was recovered by the appell~nt, till the date of award and thereafter till the date when the amount awarded was deposited in the High Court, i.e. from 12th July, 1997. E 22. The appeals are allowed in the aforesaid terms. D.G. Appeals allowed.
End of Judgment Record
Browse All Supreme Court of India (2014) Decisions
2014-07-01

Duryodhan Rout v. State of Orissa

These appeals challenge a common judgment convicting Duryodhan Rout of rape and murder of a 10-year-old girl, Subhasini Bhoi. The trial court convicted him under IPC sections 376(f), 302, and 201 and sentenced him to death; on reference, the High Court remitted the death sentence for the 302 offence to life imprisonment while keeping the other sentences unchanged. The prosecution's case rested solely on circumstantial evidence. PW-1 and PW-2 saw the accused with the victim on a bicycle around 4 p.m. and returning alone about an hour later; PW-5 (father) and PW-6 (mother) testified that the child was taken on the pretext of talking on the phone. In custody, the accused confessed before PW-3 and PW-4, and under Section 27 of the Evidence Act the recovery of the body and the underwear was recorded; the autopsy by PW-9 indicated throttling and injuries consistent with rape. The chain of circumstances — last-seen with the victim, recovery of the corpse in the jungle, and the forensic findings — formed a robust basis for conviction. The central legal issue was whether sentences for multiple offences should run consecutively. The Court held that life imprisonment is the remainder of a convict's natural life, and the proviso to Section 31(2) Cr.P.C. prevents aggregation beyond fourteen years, thus consecutive sentences cannot be imposed where life imprisonment is one of the terms. Consequently, all IPC sentences should run concurrently; the death sentence for the 302 offence was replaced by life imprisonment, and the appeal was allowed in part.

2014-12-16

Nand Kishore v. State of Madhya Pradesh

This is a criminal original jurisdiction writ petition under Article 32 challenging the continued incarceration of a convict under Section 302 IPC, with the petitioner contending entitlement to the Juvenile Justice (Care and Protection of Children) Act, 2000 (JJC Act) protections on the ground that he was a juvenile at the time of the offence (born 14 April 1980; incident on 18 June 1997). The Court scrutinized documentary and oral evidence from the Juvenile Justice Board indicating the petitioner’s true date of birth and concluded that on the date of occurrence he was 17 years 2 months 4 days old, thereby satisfying the juvenile criteria. The judgment clarifies a central legal question: whether the protections and benefits under the JJC Act, enacted in 2000, can be extended to those convicted before its coming into force if they were juveniles at the time of the offence. Relying on earlier decisions such as Hariram v. State of Rajasthan and Ajay Kumar v. State of Madhya Pradesh (and others), the Court held that a person who had not completed 18 years on the date of offence is entitled to the Act’s benefits as if the provisions had always existed, effectively retroactively applying the protective regime. The petition was allowed; the petitioner is to be released forthwith, with bail bonds and sureties discharged, reflecting the Court’s protective stance for juveniles in criminal proceedings.

2014-04-24

Vishal Goyal & Ors. v. State of Karnataka & Ors.

This batch of writ petitions under Article 32 concerns admissions to Post Graduate Medical and Dental courses in government medical/dental colleges and the state quota in private colleges in Karnataka for the 2014-2015 academic year. The petitioners, who completed MBBS/BDS in Karnataka, challenged sub-clause (a) of clause 2.1 of two National Board of Examinations Information Bulletins (PGET-2014) which defined “Karnataka Origin” to permit admission only to those who satisfy certain criteria, effectively excluding many who studied in Karnataka institutions. They argued this violates Article 14 (equality before law and equal protection of laws) and undermines merit-based selection for postgraduate courses. They invoked Dr. Pradeep Jain & Others v. Union of India (1984) to contend that institutional preference may be permissible but must conform to equality; Magan Mehrotra v. Union of India (2003), Saurabh Chaudhri v. Union of India (2003), and Nikhil Himthani v. State of Uttarakhand (2013) were cited to support the continuing emphasis on merit and equality. The State countered that Article 371J allows reservation for the Hyderabad-Karnataka region and argued that the Pradeep Jain framework applies only to government or state-instrumentality institutions and not to private colleges. The Court held sub-clause (a) ultra vires Article 14, directed fresh Information Bulletins, and ordered admissions in accordance with the law on the basis of existing entrance test results, with the general counselling schedule from Dr. Fraz Naseem & Ors. not applying for 2014-2015 Karnataka admissions.

2014-08-21

SINGH RAM (D) THR. L.Rs. v. SHEO RAM & ORS.

This is a Supreme Court of India decision on the limit of time within which a usufructuary mortgagee can seek relief, and the corresponding equity of redemption for the mortgagor. The appellants challenged the Punjab and Haryana High Court Full Bench’s view that there is no fixed time for redemption in a usufructuary mortgage and that the right to seek redemption arises on payment/deposit of mortgage money, irrespective of the mortgage date. The HP High Court’s decision was later reversed by a larger bench of this Court in the context of reconciling conflicting precedents such as Sampuran Singh, Prabhakaran and Jayasingh Dhyanu Mhoprekar, Parichhan Mistry and Harbans etc., emphasizing that Section 62 of the Transfer of Property Act confers a special right on the usufructuary mortgagor to recover possession, which begins only when the mortgage money is paid out of rents and profits or when paid/deposited by the mortgagor. Article 61 of the Limitation Act governs the period for redeeming or recovering possession (30 years from accrual of the right, unless restricted). The Court reaffirms the principle ‘once a mortgage, always redeemable’ and rejects a blanket 30-year extinguishment rule for usufructuary mortgages, upholding the Full Bench view of the Punjab and Haryana High Court and dismissing the appeals. The decision emphasizes equity, statutory recognition under Section 62, and the distinctive treatment of usufructuary mortgages.