UNION OF INDIA & ANR. v. PREMCO-DKSPL (JV) & ORS.

Case / Petition Number:Civil Appeal No. 6179 of 2016
Neutral Citation:[2016] 3 S.C.R. 484

Case Details & Bench

Court
High Court
Hon'ble Judges
  • Shiva Kirti Singh
  • R. Banumathi
Judgment Date
2016-07-25
Court Decision / Holding
Appeal allowed. The impugned Gauhati High Court order is set aside. If the respondent desires continuation, a fresh notice for arbitration should be served within one month, and on receipt of the notice the Railways shall send a panel of the requisite number of names within 60 days so that the Arbitral Tribunal can be constituted in terms of the Agreement. If the Railways default in sending the panel within the stipulated time, the contractor will be at liberty to pursue its remedies under the Act. The appeal is allowed but without any order as to costs.
Final Disposition
Appeal allowed

Parties to the Case

Appellants / Petitioners

  • Union of India
  • Anr.

Respondents

  • Premco-DKSPL (JV) & ORS

Legal Representation & Advocates

Counsels for Petitioners

  • • Ms. Kiran Suri
  • • N. K. Kashail
  • • Ms. Sadhna Sandhu
  • • Shreekant N. Terdal

Counsels for Respondents

  • • Anil Kumar Mishra

Case Synopsis & Summary

Union of India and Anr. (the appellants) challenged a Gauhati High Court order under Section 11 of the Arbitration and Conciliation Act, 1996, appointing a former judge as arbitrator in a contractual dispute with Premco-DKSPL (JV) and others arising from a railway project. The arbitration clause in the contract required the Railways to furnish within 60 days a panel of more than three gazetted railway officers from which the contractor would nominate at least two for appointment as the arbitrator; the contractor must respond within 30 days of the panel's dispatch. The contractor demanded arbitration on 12 June 2013 (served 14 June 2013) and filed a Section 11 application on 23 July 2013, before expiry of the 60-day window. The Railways sent a panel of four names on 30 July 2013, within the 60-day period, and the contractor submitted its nominations accordingly. The designated Gauhati High Court judge held that the Railways had defaulted and forfeited its right to appoint, appointing a retired judge as arbitrator. The Supreme Court reversed, holding that the contract terms must be read in their entirety and that the 60-day period for sending a panel and the 30-day period for the contractor to suggest names are part of the agreement’s binding terms; the 11(6) application was premature. The Court distinguished Datar Switchgears and held that the Railways’ default did not occur; it remanded with directions for a fresh arbitration process.

Provisions of Law Cited

Arbitration and Conciliation Act, 1996, Section 11Arbitration and Conciliation Act, 1996, Section 11(6)Arbitration and Conciliation Act, 1996, Section 11(8)(a)Arbitration and Conciliation Act, 1996, Section 11(8)(b)

Legal Doctrines & Maxims

  • Due regard to qualifications and independence of the arbitrator under Section 11(8)(a)-(b) (as per Patel Engineering principle)
  • The terms of the arbitration agreement bind the parties unless they have repudiated them

Submissions & Arguments

Contentions of Appellants / Petitioners

The impugned order misread the arbitration clause (64(3)(a)(ii)) by overlooking the 60-day window for Railways to respond with a panel and the contractor’s 30-day window to suggest two names. The 11(6) application was premature; Datar Switchgears (on time limits) is distinguishable because the contract itself prescribes timelines and does not permit automatic forfeiture. The agreement’s terms bind the parties and cannot be treated as forfeiture without proper justification. The court should not appoint a non-technical arbitrator; the proper course is to adhere to the contract’s terms and consider fresh arbitration with a compliant process.

Contentions of Respondents

The Railways were entitled to rely on the contract terms, including the 60-day panel provision and the contractor’s obligation to nominate within 30 days. The Section 11(6) application was filed within the permissible window, and the Railways’ obligation to send a panel was triggered by the contractor’s demand; failure to timely comply could constitute default/forfeiture. The decision to appoint an arbitrator honoring the contract’s terms, consistent with Patel Engineering, should be affirmed; the respondent sought to ensure a fair, independent, and impartial appointment within the agreement’s framework.

Cited Precedents (2)

Case NameCitationTreatmentExplanation
Datar Switchgears Ltd. v. Tata Finance Ltd. & Anr.(2008) 8 SCC 151DistinguishedThe present case involves a contractual 60-day panel process, which the court found to differ from Datar Switchgears; hence the precedent is distinguished rather than followed.
Northern Railway Administration, Ministry of Railways v. Patel Engineering Company Limited—PositiveUsed to support the proposition that due regard must be given to qualifications and independence under Section 11(8)(a)-(b) for appointing an arbitrator, and to secure an independent and impartial appointment.

Diagnostic Tool

Beta

Does this judgment govern your specific facts?

Don't risk relying on a distinguishable precedent. Enter your facts or proposition below. We will test it against UNION OF INDIA & ANR. v. PREMCO-DKSPL (JV) & ORS. and instantly map out authorities that support, challenge, or govern your position.

Extracted Judgment Text

Exact text extracted from official judgment records.

[2016] 3 S.C.R. 484 A ## UNION OF INDIA & ANR. v. B PREMCO-DKSPL (JV) & ORS. (Civil Appeal No. 6179 of2016) JULY25,2016 ## **[SHIVA KIRTI SINGH AND R. BANUMATHI, JJ.]** - _Arbitration and Conciliation Act. 1996: s.11 -Appointment_ - _of arbitrator_ - _Stipulation in the agreement that on the request of respondent-contractor for arbitration. Railways shall send them a_ - c _panel of more than 3 names of railway officers within 60 days whereafter the contractor would suggest at least two names out of that panel for appointment of contractors nominee_ - _Such suggestion from contractor was required to be made within 30 days from the dispatch of request by Railway_ - _Contractor sent a notice_ - **D** _demanding arbitration on 12.6.2013 which was served on Railways on J.I. 6.2013_ - _Instead of waiting for 60 days, the contractor preferred application u/s.11 on 23. 7.2013_ - _Railways sent a panel of 4 names to the contractor on 30. 7.2013, well within 60 days_ - _Whether Railway had forfeited its right to appoint railway officers as arbitrators in terms of agreement_ - _Held: Railway had not_ - **E** _forfeited its right to appoint arbitrator_ - _Rather the application ul s.11 (6) was premature_ - _Notice of appointment was served on 14. 06. 2013_ - _Contractor ought to have waited for a period of at least 60 days before s.11 application could be filed_ - _Instead of waiting for 60 days, the contractor/respondent preferred such application_ - **F** _prematurely on 23.07.2013_ - _Thus, Railways had not committed default and had not forfeited their right to appoint arbitrators as per terms of the agreement._ ## **Allowing the appeal, the Court** - **HELD: 1. In the facts and circumstances, it did not lie in** - G **the mouth of the respondent contractor that the appellants had committed a default and had forfeited their right to appoint arbitrators as per terms of the agreement. The Judge failed to read the relevant clause of the agreement properly and therefore wrongly placed reliance upon judgment in the case of** - **H Datar Switchgears. In that case this Court had extracted the** 484 UNION OF INDIA & ANR. v. PREMCO-DKSPL (JV) & ORS. 485 A relevant terms of agreement which showed that there was no A stipulation of any time limit like that of 60 days in the present case. The terms of the Agreement bind the parties unless they have chosen to repudiate the same. Relevant terms, if provided, will be material for deciding when the right of a party to appoint the arbitrator will suffer forfeiture and when the other party would B be entitled to give notice and on failure, move application under Section 11(6) of the Act. Such terms deserve respect of the parties and attention of the Court. In case the respondent contractor is still desirous of pursuing its claim through arbitration in terms of the agreement, it is given the option to serve a fresh notice for arbitration within a month and on receipt of the same the c appellants/railways shall be at liberty to send a panel of requisite number of names to the respondents within 60 days of receipt of the notice so that Arbitral Tribunal is constituted in terms of the Agreement. It goes without saying that ifthe Railways default in sending the panel within the stipulated time; the contractor D will be at liberty to pursue its further remedies as per provisions of the Act and law. [Paras 6, 7) (488-B-G) _Datar Switchgears Ltd. v. Tata Finance Ltd. & Anr._ (2008) 8 sec 151 - referred to. ## Case Law Reference E (2008) 8 sec 151 referred to Para3 CIVIL APPELLATE JURISDICTION : Civil Appeal No. 6179 of2016. From the Judgment and Order dated 25.02.2014 of the High Court ofGauhati in Arbitration Petition No. 14 of2013. F Ms. Kiran Suri, Sr. Adv., N. K. Kashail, Ms. Sadhna Sandhu, Shreekant N. Terdal, Advs. for the Appellants. Anil Kumar Mishra, Advs. for the Respondents. The Judgment of the Court was delivered by G SHIVA KIRTI SINGH, J. I. The appellants have assailed the legality and correctness of final order dated 25.02.2014 passed in Arbitration Petition No.14 of2013 by an Hon'ble Judge ofGauhati High Court designated by the Chief Justice of that Court to de9ide respondents' applications under Section 11 of the Arbitration and Conciliation Act, H 486 [2016] 3 S.C.R. SUPREME COURT REPORTS - A 1996 (hereinafter referred to as 'the Act'). By the impugned order the designated Judge allowed the application under Section 11 of the Act and appointed a former Judge of that Cow1 as the Arbitrator after holding that the appel I ants had forfeited their right to appoint railway officers as arbitrators in terms of clause 64(3)(a)(ii) of the agreement. - B 2. According to Ms. Kiran Suri, learned senior counsel for the appellants the impugned order suffers from apparent error of fact on account of misreading or non-reading of the relevant clause of the Agreement, i.e., clause 64(3)(a)(ii) which requires the contractor/ respondent to make a written demand for arbitration and permits 60 days' time to the Railways from the date of receipt of the demand, to - c send a panel of more than three names of eligible gazetted railway officers so that the contractor may suggest to General Manager at least two names out of that panel for appointment of the contractor's nominee. Such suggestion from the contractor should come within 30 days from the dispatch of the request by Railways. According to learned senior - D counsel, the relevant clause though indicated in paragraph 4 of the impugned order has been misread leading to an erroneous inference in the following words : - " .... This Clause permits the respondents to nominate a railway officer, provided of course, the nomination is made - E within 30 days of receipt of the demand letter from the petitioner. But since there was no reaction from the rai I ways side within the permissible 30 days and since in the meantime the contractor has approached the High Court under Section I I (6) of the Arbitration Act, having regard to the decision in Datar Switchgears Ltd. (supra) it is apparent that the - F respondents have forfeited their right to appoint a railway officer as the arbitrator." 3. It has been further contended on behalf of the appellants that the law laid down in the case of Datar Switch~ears Ltd. v. Tata Finance Ltd. &Anr.[1 ] has not been correctly appreciated by the learned G Judge because in that case failure to meet the demand to appoint an arbitrator was apparent on account of expiry of the notice period of 30 days indicated in the demand. Even then the Court held that since the application was under Section I I (6)(a) of the Act and since that Section does not prescribe any time limit rather gives an unfettered discretion to H 1 <2000) s sec 151 UNION OF INDIA & ANR. v. PREMCO-DKSPL (JV) & ORS. 487 [SHIVA KIRT! SINGH, J.] appoint an arbitrator without any time limit, such power will stand forfeited only after the party making the demand has moved the Court under Section 11 and not on mere expiry of the notice period of30 days. It is appellants' stand that in view of stipulations in the relevant clause providing for arbitration, the respondent-contractor admittedly sent a notice demanding arbitration on 12.06.2013 which was served on the appellants on 14.06.2013 and hence it had to wait for 60 days for receipt of a panel of more than three names. Thereafter the contractor had to suggest two names for appointment of his nominee arbitrator within 30 days. The cause of action for sending a notice of30 days or any reasonable period, in view of clear terms in the Arbitration Agreement which has not been repudiated, can arise only after 60 days. Hence according to learned senior counsel for the appellants, the learned Judge erred in holding that the appel I ants had forfeited their right to appoint arbitrators. Instead, the finding should have been that the application under Section 11 ( 6) of the Act was premature. 4. On behalf ofappellants reliance has been placed upon judgment of this Court by a three Judges Bench in the case of **Northern Railway Administration, Ministry ofRaihvay v. Patel Engineering Company** Limited~ in support of the proposition that in the appointment of arbitrator by court under Section 11 (6), the Chief Justice or the designated person shall have "due regard to the two conditions in Section 11 (8)(a) and (b) relating to qualifications required for the arbitrator by the agreement of the parties; and other considerations relevant to secure the appointment of an independent and impartial arbitrator''. Hence, in any event appointment of a non-technical person, a former judge as arbitrator was unwarranted. S. On behalf of respondent contractor the relevant facts have not been disputed and hence on facts it is beyond any doubt that the learned Judge has misread or omitted to read the relevant clause of the agreement which allows 60 days' time to the Railways to respond to the demand of the contractor by sending a panel containing more than three names out of which the contractor has to suggest at least two names to the Railways which has to appoint one out of them as the contractor's nominee. The relevant dates are also not in dispute~ Since the notice for appointment ofarbitrators dated 12.06.2013 was served on the railways on 14.06.2013, the contractor had to respect the terms of the agreement which was A B c D E F G 2 (2008) 1 o sec 240 H 488 SUPREME COURT REPORTS [2016) 3 S.C.R. - A unrepudiated and to wait for a period of at least 60 days before Section 11 application could have been filed. Instead of waiting for 60 days the contractor/respondent preferred such application prematurely on 23.07.2013. The Railways sent a panel of 4 names to the respondent on 30.07.2013, well within 60 days limit. - B 6. In the aforesaid facts and circumstances it did not lie in the mouth of the respondent contractor that the appellants had committed a default and had forfeited their right to appoint arbitrators as per terms of the agreement. The learned Judge failed to read the relevant clause of the agreement properly and therefore wrongly placed reliance upon judgment in the case of **Datar** Switchgears (supra). In that case this - c Court had extracted the relevant terms of agreement in paragraph 9 which showed that there was no stipulation of any time limit like that of 60 days in the present case. The terms of the Agreement bind the parties unless they have chosen to repudiate the same. Relevant terms, if provided, will be material for deciding when the right of a party to - D appoint the arbitrator wi II suffer forfeiture and when the other party would be entitled to give notice and on failure, move application under Section 11 ( 6) of the Act. Such terms deserve respect of the parties and attention of the Court. 7. In view of aforesaid discussions we find no option but to set E aside the impugned order under appeal. We order accordingly. In case the respondent contractor is still desirous of pursuing its claim through arbitration in terms of the agreement, it is given the option to serve a fresh notice for arbitration within a month and on receipt of the same the appellants/railways shall be at liberty to send a panel of requisite number of names to the respondents within 60 days of receipt of the notice so F thatArbitral Tribunal is constituted in terms of the Agreement. It goes without saying that if the Railways default in sending the panel within the stipulated time, the contractor will be at liberty to pursue its further remedies as per provisions o(the Act and law. The appeal is al lowed in aforesaid terms but without any order as to costs. G Devika Gujral Appeal allowed.