Union of India & Anr. v. Dr. Asket Singh & Ors.

Case / Petition Number:
Civil Appeals Nos. 1636-1637 of 2016
Neutral Citation:/

Case Synopsis & Summary

This is a Civil Appeal in the Supreme Court arising from land acquisition under the Requisitioning and Acquisition of Immovable Property Act, 1952. The respondents owned lands acquired by the Central Government; the vesting occurred on 3rd April 1964 after a notification under Section 7 of the 1952 Act. Compensation was to be determined under Section 8; if no agreement on value, an arbitrator is to be appointed. The government offered compensation belatedly in August 1976; the arbitrator fixed market value at Rs.150 per Marla in 1998. The High Court enhanced the value to Rs.350 per Marla, following decisions in similar cases and holding that there was gross delay in arbitral proceedings, warranting solatium and interest. The appellants argued that solatium and interest have been granted only where delays occurred in appointment of arbitrators, not in disposal of proceedings, and that this case involves substantial delay in disposal, not necessarily appointment. The Court examined prior precedents (Harbans Singh Shanni Devi v. Union of India; Union of India v. Chajju Ram; Dilawar Singh v. Union of India; Hari Krishan Khosla) and found them distinguishable on timing but supportive of the underlying principle that compensation for delay may carry solatium and interest. Ultimately, the Court dismissed the appeals, noting that respondents had already received compensation years earlier and refraining from costs. The decision upholds the High Court’s awards for solatium and interest.”

Precedent Explorer

Find Cases Like This

Explore other judgments dealing with similar legal situations, facts, or statutory provisions.

Case Details & Bench

Court
Landmark Cases
Hon'ble Judges
  • Abhay S. Oka
  • Ujjal Bhuyan
Judgment Date
2024-05-01
Court Decision / Holding
Hence, the appeals are dismissed.
Final Disposition
Appeals dismissed with no costs to be imposed on the parties.

Parties to the Case

Appellants / Petitioners

  • Union of India & Anr.

Respondents

  • Dr. Asket Singh & Ors.

Provisions of Law Cited

Section 7 of the Requisitioning and Acquisition of Immovable Property Act, 1952Section 8 of the Requisitioning and Acquisition of Immovable Property Act, 1952Clause (a) of sub-section (1) of Section 8Clause (b) of sub-section (1) of Section 8Article 300A of the Constitution of IndiaArticle 14 of the Constitution of India

Legal Doctrines & Maxims

  • Arbitrariness prohibited by Article 14 of the Constitution of India
  • Right to property under Article 300A of the Constitution of India
  • Delay in payment of compensation may attract solatium and interest despite lack of express provision in the 1952 Act
  • Principle of reasonable time for payment of compensation after vesting

Submissions & Arguments

Contentions of Appellants / Petitioners

The appellants submitted that the relief of solatium and interest has been granted in earlier cases where there was delay by the Central Government in appointing an Arbitrator for determining compensation, and that in this case the delay is mainly in disposal of arbitral proceedings. They contended that the High Court ought not to have awarded both solatium and interest, especially since there was already a substantial delay attributable to the government but not necessarily to the arbitral process itself.

Contentions of Respondents

The respondents contended that, following earlier decisions, solatium and interest are warranted in delay scenarios, and that the government’s protracted actions necessitated such relief. They highlighted that the respondent had already received compensation about seven years prior to this hearing and argued for upholding the awards as proper under the evolving constitutional framework and case law.

Legal Doctrine & Issue Explorer

Explore This Legal Issue

Find relevant judgments and authoritative positions on the legal questions discussed here.

Cited Precedents (4)

Case NameCitationTreatmentExplanation
Harbans Singh Shanni Devi v. Union of India[1]PositiveCited to justify solatium and interest in cases involving delay; used as a basis for applying the principle in later decisions.
Union of India v. Chajju Ram[2]PositiveCited as precedent supporting compensation adjustments in delay scenarios.
Dilawar Singh & Ors. v. Union of India & Ors.[3]PositiveFollowed to reinforce the approach of awarding solatium/interest due to delays in proceedings.
Hari Krishan Khosla[4]PositiveQuoted for its observation on delay and the corresponding awards of solatium and interest; used to justify the Court’s reasoning on the impact of delay.
Case Applicability Diagnostic

Apply This to My Facts

Share your situation and test whether this judgment governs, supports, or challenges your case.

Official Judgment Record
•1,594 words•~8 min read

In The Court Record

Union of India & Anr. v. Dr. Asket Singh & Ors.

2024 INSC 409 **REPORTABLE** **==> picture [72 x 72] intentionally omitted <==** ## **IN THE SUPREME COURT OF INDIA CIVIL APPELLATE JURISDICTION** ## **CIVIL APPEAL NOS.1636-1637 OF 2016** **UNION OF INDIA & ANR. ... APPELLANT(S) VS. DR. ASKET SINGH & ORS. ... RESPONDENT(S)** **JUDGMENT** **Abhay S.Oka, J.** **Heard the learned counsel appearing for the parties.** **2. The facts of the case are glaring. The respondents are the owners of the lands subject matter of these appeals. At the instance of the Ministry of Defence, acquisition proceedings were initiated under the Requisitioning and Acquisition of Immovable Property Act, 1952 (for short "the 1952 Act"). A notice of acquisition under Section 7 of the 1952 Act was issued on 26[th ] March, 1964 which was published in the State Government Gazette on 3[rd ] April, 1964. The vesting of the acquired property** Signature Not Verified **was complete on publication of the notice in the official** Digitally signed by Anita Malhotra Date: 2024.05.13 18:11:18 IST Reason: **gazette.** 1 **3. The provisions for grant of compensation in respect of the acquired land are found in Section 8 of the 1952 Act. The first option provided therein is to fix the compensation by an agreement between the acquiring body and the owners. if there is no such agreement, under clause (b) of sub-section (1) of Section 8, the Central Government is required to appoint an arbitrator for determining the amount of compensation payable. An offer for payment of compensation was made by the appellants belatedly after 12 years on 16[th] August, 1976. The respondents declined to accept the said offer. Therefore, the Land Acquisition Officer addressed a letter to the Government on 8[th] October, 1976 to appoint an arbitrator. Accordingly, the Additional District Judge, Gurdaspur was appointed as the Arbitrator. Nearly 22 years thereafter on 8[th] May, 1998, the award was declared by the Arbitrator by which he came to the conclusion that the market value of the acquired land was Rs.150/- per Marla.** **4. An appeal was preferred by the first respondent as well as by the present appellants for challenging the award of the Arbitrator. By the impugned judgment, the High Court held that the market value ought to be Rs.350/- per Marla which was determined in the cases of** 2 **similarly situated acquired lands. As there was a gross and inordinate delay in completing the arbitral proceedings for determination of the market value, relying upon the decisions of this Court in the cases of** _**Harbans Singh Shanni Devi**_ **v.** _**Union of India[1]**_ **and** _**Union of India**_ **v.** _**Chajju Ram[2]**_ **which were followed by this Court in a decision in the case of** _**Dilawar Singh & Ors.**_ **v.** _**Union of India & Ors.[3] ,**_ **the High Court granted solatium at the rate of 30% of the market value and interest on the compensation amount at 9% and 15%.** **5. The submission of the learned counsel appearing for the appellants is that the relief of solatium and interest has been granted in earlier cases by this Court where there was a delay on the part of the Central Government in appointing an Arbitrator for determination of compensation. In this case, the delay is mainly in disposal of the arbitral proceedings. He, therefore, submitted that the High Court ought not to have awarded both solatium and interest. The learned counsel appearing for the first respondent pointed out that in terms of the impugned judgment, the first respondent has received the entire compensation amount about 7 years** 1. **decided on 11[th ] February, 1985 in Civil Appeal No.470-471 of 1985** 2. **(2003) 5 SCC 568** 3. **(2010) 14 SCC 357** 3 ## **back.** **6. It will be useful to refer to paragraphs 9 and 10 of the decision of this Court in the case of** _**Dilawar Singh[3]**_ **which reads thus:** **"9. It is common ground that the provisions of the Requisitioning and Acquisition of Immovable Property Act, 1952 do not make any provision for the grant of solatium or interest to the expropriated landowners. The absence of any such provision in the said act was in fact made a basis for a challenge to the constitutional validity of the enactment which was repelled by this Court in** _**Union of India**_ **v.** _**Hari Krishan Khosla[4] .**_ **This Court pointed out that any comparison between acquisition made under the Requisitioning and acquisition Act would be odious in view of the dissimilarities between the two enactments. That decision was followed in subsequent pronouncements of this Court in** _**Union of India**_ **v.** _**Chajju Ram[2]**_ **where a similar attack was mounted against the constitutional validity of the Defence of India Act, 1971 but repelled by this Court relying upon the decision in** _**Hari Krishan Khosla[4] .**_ **10. What is noteworthy is that in both these matters this Court had made a distinction between cases in which there was inordinate delay in the appointment of an arbitrator and consequent delay in the determination of the amount of compensation payable to the owners and other case** 4. 1993 Supp (2) SCC 149 4 **where there was no such delay. In para 79 of the judgment of this Court in** _**Hari Krishan Khosla[4] ,**_ **this Court observed:** **"79. This is a case in which for 16 years no arbitrator was appointed. We think it is just and proper to apply the principle laid down in** _**Harbans Singh Shanni Devi**_ **v. Union of India[1] . The Court held as under: Having regard to the peculiar facts and circumstances of the present case and particularly in view of the fact that the appointment of the arbitrator was not made by the Union of India for a period of 16 years, we think this is a fit case in which solatium at the rate of 30% of the amount of compensation and interest at the rate of 9% per annum should be awarded to the appellants. We are making this order having regard to the fact that the law has in the meanwhile been amended with a view to providing solatium at the rate of 30% and interest at the rate of 9% per annum."** **7. As noted in the said decision, there is no provision for grant of solatium and interest under the 1952 Act.** 5 **8. It is true that the right to hold immovable property is no longer a fundamental right but it is a right under Article 300A of the Constitution of India. Considering the peculiar provisions of the 1952 Act, the land owned by the first respondent stood vested in the Central Government on 3[rd] April, 1964. Therefore, the compensation ought to have been paid to the first respondent within a reasonable time from 3[rd ] April, 1964. Under clause (a) of sub-section (1) of Section 8, there is a provision to decide the amount of compensation by an agreement. Such agreement could have been arrived at, provided the Central Government had submitted their proposal or offer to the first respondent. However, the offer was actually made by the Collector in August, 1976. Thus, there was no attempt made by the Central Government to bring about the consensus on the market value for a period of more than 12 years. Inordinate time of 12 years was taken by the Government to offer compensation to the first respondent. We must record here that this delay of more than 12 years is attributable solely to the Central Government. After the Arbitrator was appointed on 8[th ] October, 1976, it took slightly less than 20 years to conclude the proceedings. There is nothing placed on record to show that the proceedings were delayed due to** 6 **any conduct attributable to the first respondent. The delay in appointing the arbitrator must be attributed to the Central Government, as the Central Government took 12 years to offer compensation. In effect, market value prevailing on the date of acquisition was paid to the owners after lapse of more than 30 years from the date of vesting.** **9. After having perused the aforesaid decisions of this Court, we find that as there are no provisions under the 1952 Act to compensate the owner for the delay in making payment of compensation, a direction was issued by this Court that in such cases, solatium and interest must be paid by the Central Government. The main reason for taking the said view is that the compensation must be paid to the owner of the acquired property within a reasonable time from the date on which the acquired property vested in the acquiring body. The requirement of making payment of compensation within a reasonable time from the date of vesting must be read into the 1952 Act. In fact, such a long delay of 12 years even in offering compensation will attract arbitrariness which is prohibited by Article 14 of the Constitution of India. The first respondent had an option of even seeking quashing of the acquisition on the ground of this** 7 **arbitrariness which may have violated his rights under Article 300A of the Constitution of India.** **10. Considering the huge delay involved in payment of compensation, the High Court has rightly granted solatium and interest in terms of the decisions of this Court. In fact, we are surprised to note that the appellants have dragged the first respondent to this Court. There is absolutely no merit in these appeals. As the first respondent has been paid compensation 7 years back, we are refraining from imposing costs.** **11. Hence, the appeals are dismissed.** **..........................J. (ABHAY S.OKA) ..........................J. (UJJAL BHUYAN)** **NEW DELHI; May 01, 2024.** 8
End of Judgment Record
Browse All Landmark Cases Judgments
2019-01-22

State of Himachal Pradesh & Anr. v. Pinju Ram & Others; State of Himachal Pradesh & Ors. v. Ganesh Dutt & Anr.

This batch of appeals concerns regularisation and monetary benefits of part‑time employees in Himachal Pradesh who were converted to daily‑wage status. The State had issued a policy on 27 February 2004: part‑time Class‑IV employees who had completed ten years of continuous service as on 31 December 2003 would be made daily wagers with prospective effect, and posts vacated by such employees would stand abolished; Education and Ayurveda were excluded from the policy. Revenue Chowkidars, engaged by Panchayats, were not covered by that policy and received separate treatment. Following writ petitions and an order of the Himachal Pradesh High Court and in light of later developments, the State drew‑up directions in 2011 (22 September) to give seniority to Revenue Chowkidars on the basis of ten years of service, but with wages from the date of actual appointment and without back‑dated monetary benefits; 7 July 2012 further instructions reiterated this stance for remaining part‑time employees, with monetary benefits not guaranteed in the interregnum. The respondents pressed for back wages dating from 1 January 2007 and broader coverage. The Supreme Court held that the 2007 back‑pay direction was unsustainable, clarified that seniority would count from ten years without past benefits, and that the 2011 policy and Moti Singh principle should guide the approach. The appeals are allowed; no costs. The related writ petitions are to be disposed of consistent with these directions.

2018-08-14

Union Bank of India and Others v. C.G. Ajay Babu and Anr.

This is a Supreme Court of India appeal concerning the forfeiture of gratuity under the Payment of Gratuity Act, 1972. The respondent was a branch manager of the appellant bank and was dismissed on 3 June 2004 after disciplinary proceedings. A show-cause notice sought to forfeit gratuity due to misconduct involving moral turpitude, which was ordered on 20 April 2004. The High Court upheld the dismissal but held that gratuity could be paid since there was no financial loss to the bank, and that a bipartite settlement between the bank and employees permitted forfeiture only where misconduct caused financial loss. The Division Bench, however, held that forfeiture under Section 4(6) must be read together with Section 4(5) and that no loss was proven, thus entitling the employee to gratuity in accordance with the bipartite settlement. The Supreme Court agreed with the High Court that forfeiture is not automatic; it is controlled by Sections 4(5) and 4(6) of the Act and by the bipartite settlement, which requires loss to justify forfeiture. The Court emphasized that an act must constitute an offence involving moral turpitude and that conviction is generally required for forfeiture under 4(6)(b)(ii). The appeal is dismissed with no costs.

2018-09-25

Reema Salkan v. Sumer Singh Salkan

This is a Supreme Court of India criminal appeal under the Criminal Appellate Jurisdiction arising from a maintenance dispute under Section 125 Cr.P.C. The parties, married in 2002, had a protracted litigation history. The Family Court granted maintenance to the wife from 17 July 2003 to 8 December 2010, and held no maintenance thereafter. The High Court, in revision, partly allowed the application, directing Rs.9,000 per month from 9 December 2010 onward, while upholding the earlier period’s Rs.10,000 per month. This Court had earlier granted interim maintenance of Rs.20,000 per month in 2014 (Criminal Appeal Nos. 2347-2349 of 2014). The appellant contends there has been no change in circumstances since the interim order and that the respondent’s substantial assets, education, and overseas earnings establish the capacity to pay higher maintenance. The respondent defends the High Court’s reasoning, arguing that the Family Court’s assessment, demeanor observations, and the principle that maintenance should not be perpetual require careful scrutiny, and that the notional minimum wage approach used by the High Court is flawed. The overarching issue is the quantum of monthly maintenance payable to the appellant and whether the interim amount should be augmented beyond the period up to 2010.”

2019-12-03

M/s Embassy Property Developments Pvt. Ltd. v State of Karnataka & Ors.

This judgment concerns three Civil Appeals filed by a Resolution Applicant, the Corporate Debtor (through its Resolution Professional) and the Committee of Creditors, challenging an Interim Order of the Karnataka High Court staying an NCLT order in proceedings under the Insolvency and Bankruptcy Code, 2016. The NCLT Chennai had admitted an application under Section 7 of the IBC against M/s Tiffins Barytes Asbestos & Paints Ltd. and directed a moratorium under Section 14. The Interim Resolution Professional then sought a deemed extension of a mining lease under MMDR Act, 1957 and the Government of Karnataka rejected it. The NCLT, by an order dated 11.12.2018, set aside the Government’s order and directed execution of Supplement Lease Deeds for the period up to 31.03.2020. The Government of Karnataka challenged this in a High Court writ petition, which stayed the impugned NCLT order. The core issues were: (i) whether the High Court may interfere under Article 226/227 with an NCLT order in IBC when an appeal lies to the NCLAT, and (ii) whether fraud can be inquired into by NCLT/NCLAT in CIRP. The Court reiterates that IBC is a complete, umbrella code with a three‑tier mechanism (NCLT, NCLAT, Supreme Court) and that public‑law disputes arising from MMDR Act obligations lie outside IBC. It ultimately holds that while NCLT/NCLAT may inquire into fraud, they cannot adjudicate MMDR‑related public legal disputes; and the High Court’s writ jurisdiction in public‑law contexts remains permissible. The appeals are dismissed.