Tenetowl LogoTenetowl
Supreme Court of IndiaSupreme Court · 1997Division BenchAppeal allowed; High Court judgment set aside; ...

Union of India and Ors. v Tata Engineering and Locomotive Co., Ltd.

Case / Petition Number:
Civil Appeal No. 7645 of 1997

Case Synopsis & Summary

Union of India and Ors. v Tata Engineering and Locomotive Co., Ltd. concerns the valuation of excisable goods (vehicles) for central excise duty. TELCO submitted price lists for excisable goods for assessment; the Patna High Court directed the Assistant Collector of Central Excise, Jamshedpur, to pass final orders on all price lists and held that the price at the factory gate should be treated as the normal price for value computation. It also held that the price lists of TELCO’s Regional Sales Offices were not relevant for passing final orders on TELCO’s price lists. The Union of India appealed, contending that the writ petition should not have been entertained; that the Assistant Collector has discretion to complete the assessment and call for relevant documents; that the court should not control the mode of assessment; that the two-stage pricing at the factory gate (dealer vs sub-dealer) should be considered. TELCO argued that it was necessary to examine the price at the Regional Sales Offices to account for the two price types charged at the factory gate. The Supreme Court held that the writ petition was not entertainable and that the Assistant Collector is entitled to complete the assessment in his judgment, calling for whatever documents he deems relevant; the court cannot fetter his discretion. It observed that if there is a mistake, remedy lies in appeal or revision. The appeal is allowed; the Patna High Court order is set aside; the Assistant Collector is directed to complete the assessment expeditiously.

Precedent Explorer

Find Cases Like This

Explore other judgments dealing with similar legal situations, facts, or statutory provisions.

Case Details & Bench

Court
Supreme Court of India
Hon'ble Judges
  • Suhas C. Sen
  • M. Jagannadha Rao
Judgment Date
1997-11-10
Court Decision / Holding
Appeal allowed. The High Court’s judgment is set aside. The Assistant Collector is directed to complete the assessment expeditiously as possible. There will be no order as to costs.
Final Disposition
Appeal allowed; High Court judgment set aside; directions to complete the assessment expeditiously.

Parties to the Case

Appellants / Petitioners

  • Union of India and Ors.

Respondents

  • Tata Engineering and Locomotive Co., Ltd. (TELCO)

Legal Representation & Advocates

Counsels for Petitioners

  • • N.K. Bajpai
  • • V.K. Verma

Counsels for Respondents

  • • Soli J. Sorabjee
  • • Ravinder Narain
  • • Sridharan
  • • Amrita Mitra
  • • Amit Bansal
  • • Juhi Singh

Provisions of Law Cited

Constitution of India, 1950 Article 226

Legal Doctrines & Maxims

  • The Assistant Collector is entitled to complete the assessment as he thinks fit in exercise of his judgment.
  • The Court should not try to control the mode and manner in which an assessment should be made.
  • If the Assistant Collector fails to follow any judgment of the High Court or this Court, the assessee has adequate statutory remedies by way of an appeal and revision.
  • Writ petitions in such matters should not be entertained; the High Court should not guide the subordinate authority in the assessment method.

Submissions & Arguments

Contentions of Appellants / Petitioners

The writ petition was wrongly entertained; the Assistant Collector must complete the assessment in his own judgment, calling for relevant documents as needed. The normal price for excisable goods should be the factory-gate price; prices from Regional Sales Offices are not determinative for final orders. The Court should not micromanage the assessment process and should avoid substituting its view for the officer’s expert judgment. If the assessment order deviates from judgments, statutory remedies by appeal/revision remain available.

Contentions of Respondents

TELCO contends that examining the Regional Sales Offices’ price is necessary if two price structures exist (factory-gate dealer vs sub-dealer) and that the High Court’s directions were misapplied. TELCO argues the issue was not adequately raised before the High Court and that continued, indefinite assessments would undermine the statutory process. The replying counsel emphasizes adherence to prior decisions and argues for a reasoned, fact-based evaluation by the assessing officer.

Legal Doctrine & Issue Explorer

Explore This Legal Issue

Find relevant judgments and authoritative positions on the legal questions discussed here.

Case Applicability Diagnostic

Apply This to My Facts

Share your situation and test whether this judgment governs, supports, or challenges your case.

Official Judgment Record
•899 words•~5 min read

In The Court Record

Union of India and Ors. v Tata Engineering and Locomotive Co., Ltd.

# UNION OF INDIA AND ORS. _v._ TATA ENGINEERING AND LOCOMOTIVE CO., LTD. ETC. NOVEMBER IO, 1997 [SUHAS C. SEN AND M. JAGANNADHA RAO, JJ.] _Constitution of India, 1950 : Article 226._ _Excise duty-Computation of-Power of competent authority-Extent of judicial control-Held High Court in exercise of its jurisdiction cannot_ C _give guidance to Assistant Collector about the manner and mode in which the assessment should be made._ _Excise duty-Assessment of-Price list of vehicles sold submitted by respondent company-Assessment made by Assistant Collector of ExciseWrit filed by respondent Company-Direction given by High Court to Assistant_ D _Collector-To pass final order on all the price lists submitted by respondent company-The price at which the Company sold the vehicles at the factOJy gate should be the normal price for the purpose of computation of the value of the excisable goods-Court also held that price lists of Regional Sales Offices of Tata Engineering & Locomotive Co. (TELCO) was not relevant for_ E _passing final orders on the price lists submitted by the company-Appeal preferred by Union of India-Held the writ petition should not have been entertained by the High Court at all-The Assistant Collector is entitled to complete the assessment as he thinks fit in exercise of his judgment-He can cal/ for and examine whatever documents he considers relevant-The Court should not try to control the mode and manner in which an assessment_ F _should be made._ CIVIL APPELLATE JURISDICTION: Civil Appeal No. 7645of1997. From the Judgment and Order dated 27.9.88 of the Patna High Court in C.W.J.C. No. 802of1988 (R). N.K. Bajpai and V.K. Verma for the Appellants. Soli J. Sorabjee, Ravinder Narain,.Sridharan, Ms. Amrita Mitra, Amit Bansal and Ms. Juhi Singh for M/s. J.B.D. & Co. for the Respondent. 109 SUPREME COURT REPORTS [1997) SUPP. _5_ S.C.R. 110 ·--· A The following Order of the Court was delivered : Leave granted. Union of India has come up in appeal against the judgment and order of the Division Bench of the Patna High Court directing the Assistant Collector of Central Excise, Jamshedpur, to pass without delay appropriate final order on all the price lists already submitted by the Company. The Court also held that the price at which the Company sold the vehicles at the factory gate at Jamshedpur should be the normal price for the purpose of computation of the value of the excisable goods. The Court also held that the Assistant Collector of Central Excise could only call for relevant documents for the purpose of assessment of the value of the excisable goods. In .the facts of this case, price lists of Regional Sales Offices of Tata Engineering & Locomotive Co. (TELCO) could not be said to be relevant for passing final orders on the price lists submitted by the company. B c D The appellant has contended that it was necessary for the Excise Officer to examine the price at the Regional Sales Offices because two types of prices were being charged at the factory gate of the Company at Jamshedpur. It has been contended in reply that the bulk of the sales made by the Company was to the dealers; a small portion of sales was effected to sub-dealers directly E for which full particulars were·furnished. Moreover, this point was not raised before that High Court when the writ petition was heard. .,. ' In our view, this writ petition should not have been entertained by the High Court at all. The Assistant Collector is entitled to complete the assessment F as he thinks fit in exercise of his judgment and according to his understanding of the law and facts. For this purpose, he can call for and examine whatever documents he considers relevant. If the Assistant Collector fails to follow any judgment of the High Court or this court, the assessee had adequate statutory remedies by way of an appeal and revision against the assessment order. The G Court should not try to control the mode and manner in which an assessment should be made. If the Assistant Collector is of the view that enquiries are necessary to be made as to the price at which trucks were sold at the Regional Sales Offices, the· Court cannot stop him from making such enquiries. Mr. Sorabjee, appearing on behalf of the respondents, has complained H that the assessments are going on endlessly and without due regard to an U.0.1. _v._ TATA ENGINEERING AND LOCOMOTIVE CO., LTD. 111 - earlier judgment of the Patna High Court in respect of an earlier assessment A year on the very same issues. Whether the controversy raised in this case is covered by an earlier judgment of the High Court is a matter to be decided by the Assistant Collector. He will have to decide all questions of fact and law. He has to make whatever enquiries he thinks necessary for determination of the value of excisable goo1s. The High Court in exercise of its jurisdiction B cannot give guidance to Assistant Collector about the manner and mode in which the assessment should be made. We are of the view that the High Court was in error in entertaining this writ petition. Therefore, the appeal is allowed and the judgment of the High Court under appeal is set aside. There will be no order as to costs. C The Assistant Collector is directed to complete the assessment expeditiously as possible. T.N.A. Appeal allowed.
End of Judgment Record
Browse All Supreme Court of India (1997) Decisions
1997-12-17

Sharad Vasant Kotak and Ors. v. Ramniklal Mohanlal Chawda and Anr.

This Supreme Court judgment concerns the maintainability of a suit for dissolution of partnership and accounts under the Indian Partnership Act, 1932, as amended by the Maharashtra Amendment of 1984 (Section 69(2A)). The Paramount Builders partnership, registered in 1980 with seven partners (Kotak family and Chawda family), underwent changes after the death of partner Mohanlal Chawda in 1986, when his widow was inducted as a partner. A series of deeds (1986, 1992) reconstituted the firm without informing the Registrar of Firms, raising questions about registration and the applicability of Section 69(2A), which restricts suits to registered firms where the suing partner is shown in the Register of Firms. The Bombay High Court Division Bench held that reconstitution does not cancel registration and that amendments to pleadings were permissible; it concluded that Section 69(2A) does not bar the suit. The appellants argued that induction of a new partner dissolves the old firm and requires a fresh registration, while the respondents contended that dissolution and reconstitution are distinct concepts and that registration continues despite changes. The Supreme Court ultimately held that the firm was merely reconstituted, not dissolved; non‑compliance with registration provisions may attract penalties, but does not erase registration. The Special Leave Appeal was dismissed, with no costs.

1997-11-18

National Insurance Co. Ltd. v. Santro Devi and Ors.

National Insurance Co. Ltd. v. Santro Devi deals with a motor-accident compensation claim under the Motor Vehicles Act. A Tribunal found that the offending vehicle was driven by a person who held a valid driving licence, which had been renewed on the date of the accident, and the claimants were accordingly awarded compensation. The Punjab and Haryana High Court affirmed this finding on appeal but then referred the matter to a full Bench to decide a legal question: whether a forged or fake licence, if renewed, would be treated as a valid licence for purposes of liability. The full Bench answered that a forged licence would not become valid under the Motor Vehicles Act and that an insured, bonafide believing in the licence’s validity, would still incur liability toward third parties under the policy; several related conclusions regarding insurer liability were laid down. The Insurance Company challenged these High Court observations. The Supreme Court allowed the appeal in part, holding that the claimants were rightly granted compensation on the facts, and that the High Court’s observations on forged licences were obiter and not binding precedents since there was concurrent factual finding that the driver held a valid licence renewed on the date of the accident. The Court affirmed the substantive order and dismissed the related Special Leave Petition.

1997-02-03

JAIPUR DEVELOPMENT AUTHORITY v. SITA RAM AND ORS.

This appeal concerns the validity of notifications under Section 52 of the Rajasthan Urban Improvement Act, 1959, by which the Jaipur Development Authority sought to continue land acquisition even after the repeal of the 1959 Act, and after a fresh notification was issued in 1984 under the Jaipur Development Authority Act. The Rajasthan High Court had held that unless the master plan scheme under the JDA Act had been properly framed, the notification issued under Section 52 was not valid in law. The appellants challenge this proposition, contending that framing of a scheme is not a mandatory pre-condition for acquisition and that the 1984 notification cannot be quashed solely for lack of a sanctioned scheme. The matter traces several precedents: Pratap v. State of Rajasthan; State of Tamil Nadu v. Mohd. Yousef; Narain v. State of Rajasthan; and Urban Improvement Trust v. State of Rajasthan. The decision ultimately clarifies that framing of a scheme is not a required pre-condition for land acquisition; overruled or distinguished interpretations in earlier decisions, especially Tamil Nadu Yousef, Krishnan’s later formulation and Narain’s approach. The Court endorses the view that the notification for acquisition cannot be invalidated on account of non-framing of a scheme, and thus allows the appeals, setting aside the High Court’s judgment and dismissing the writ petitions, with no costs to either side.

1997-07-07

Delhi Administration (Now Govt. of N.C.T. Delhi) through the Chief Secretary, Delhi and Ors. v. Nand Lal Pant and Anr.

Delhi Administration v. Nand Lal Pant concerns the scope of promotion from the cadre of Trained Graduate Teachers (TGT) to Post-Graduate Teachers (Sanskrit) in the Delhi education cadre, and the remedy when a sanctioned channel does not exist. Pant, appointed as a TGT in 1974 and confirmed, was asked to officiate in the PGT (Sanskrit) post when it became vacant after the retirement of S.N. Sastri, a Sanskrit-qualified officer. He repeatedly sought promotion to the PGT position, which the Delhi High Court granted in 1996, directing promotion with effect from 1986 and ordering payment of consequential benefits. The Delhi Administration appealed on the ground that there was no direct promotional channel from TGT (General) to PGT (Sanskrit), and that the SC caste reservation for the post should be respected. The Supreme Court accepted that there is no direct channel, but noted Pant’s extended officiation in the PGT post since 1986. It held that justice required a workable remedy: creation of a supernumerary PGT (Sanskrit) post in any school or directorate, allowing Pant to continue there until retirement, with pay from the date of creation. The decision clarifies it as a discretionary remedy and not a general precedent, and it disposed of the appeal with no costs.