Union of India and Ors. v. Pra Veen Gupta and Ors.

Case / Petition Number:
Civil Appeal No. 13228 of 1996

Case Synopsis & Summary

This Supreme Court appeal arises from a Delhi High Court order in a land acquisition matter relating to shifting the timber market from the walled city of Delhi to timber depots outside. The notification under Section 4(1) of the Land Acquisition Act, 1894 was issued in 1989 for 1328 bighas in Siraspur and Libaspur; declaration under Section 6 was published in 1990, while Section 5A enquiry was dispensed with. The writ petition challenged the urgency clause under Section 17(4) and the quashing of the Section 6 declaration. The High Court had dismissed the LPA on grounds of delay and quashed the declaration; the Division Bench of the High Court concurred, leading to special leave. In hearing the appeal, the Court examined whether urgency can be established on record to dispense with Section 5A, noting that urgency is an administrative, subjective decision. The respondent Union argued that shifting the timber market is a public purpose justifying urgency, while the respondent contended there was no real urgency and urged adherence to the principles in Dora Phalavli and Gurdial Singh, and Narayan Govind Gavate. The Court ultimately held that mere mention in the notification that land is likely to be needed does not negate urgency under Section 17(4). The appeal is allowed; the declaration under Section 6 stands restored and the LAO must pass the award within three months, with no costs.

Precedent Explorer

Find Cases Like This

Explore other judgments dealing with similar legal situations, facts, or statutory provisions.

Case Details & Bench

Court
Supreme Court of India
Hon'ble Judges
  • K. Ramaswamy
  • S. P. Kurdukar
Judgment Date
1996-10-04
Court Decision / Holding
Appeal allowed. The order of the learned Single Judge and the Division Bench of the High Court are set aside. The declaration under Section 6 stands restored. The Land Acquisition Officer is directed to pass the award after issuing notice to the respondents within three months from the receipt of this order. No costs.
Final Disposition
Appeal allowed; High Court orders set aside; Section 6 declaration restored; award to be passed within three months; no costs.

Parties to the Case

Appellants / Petitioners

  • Union of India
  • Ors.

Respondents

  • Pra Veen Gupta
  • Ors.

Legal Representation & Advocates

Counsels for Petitioners

  • • N. N. Goswami
  • • B. K. Prasad
  • • S. P. Singh

Counsels for Respondents

  • • G. L. Sanghi
  • • Subhash Mittal
  • • M. K. Garg
  • • V. B. Saharaya
  • • R. K. Maheshwari

Provisions of Law Cited

Land Acquisition Act, 1894 - s.4(1)Land Acquisition Act, 1894 - s.5ALand Acquisition Act, 1894 - s.6(1)Land Acquisition Act, 1894 - s.17(4)

Submissions & Arguments

Contentions of Appellants / Petitioners

The appellants contended that urgency under Section 17(4) is a valid, administrative decision grounded on material on record and that delaying the project would defeat the public purpose of relocating the timber market and relieving congestion in the walled city. They argued that MPD-2001 master plan and the notice of likely public necessity justify dispensing with the Section 5A inquiry, citing precedents that permit urgency in planned development projects. They emphasized that a large number of similar cases warranted decision on merits rather than remittance to the High Court, and that the shifting of the timber market constitutes urgent public purposes.

Contentions of Respondents

The respondents argued that there was no real urgency and that the State could have afforded a full opportunity to challenge the public necessity. They relied on Dora Phalavli and Gurdial Singh to caution against cavalier dispensing with Section 5A, while Narayan Govind Gavate was distinguished. They stressed that urgency is a subjective administrative decision requiring careful scrutiny of material on record and statutory purposes, and argued that the entire land acquisition involved more than the urgent necessity claimed. They pointed to delays and questioned the necessity of broad land acquisition under the MPD-2001 framework.

Legal Doctrine & Issue Explorer

Explore This Legal Issue

Find relevant judgments and authoritative positions on the legal questions discussed here.

Cited Precedents (4)

Case NameCitationTreatmentExplanation
Jai Narain & Ors. v. Union of India & Ors.[1996] 1 SCC 9PositiveSupported urgency in dispensing with 5A under Section 17(4) for the public purpose in the broad context of planned development and related cases.
Narayan Govind Gavate & Ors. v. State of Maharashtra & Ors.[1977] 1 SCC 133DistinguishedCourt distinguished this decision in the present judgment; not controlling the outcome here.
Dora Phalavli v. State of Punjab & Ors.[1979] 4 SCC 485Mentioned OnlyCited and discussed; used to illustrate cautions about dispensing with 5A, but not followed as a blanket rule.
State of Punjab & Anr. v. Gurdial Singh & Anr.[1980] 2 SCC 471Mentioned OnlyCited and discussed in the context of cautions about urgency and 5A enquiry; not adopted as controlling precedent here.
Case Applicability Diagnostic

Apply This to My Facts

Share your situation and test whether this judgment governs, supports, or challenges your case.

Official Judgment Record
•2,428 words•~12 min read

In The Court Record

Union of India and Ors. v. Pra Veen Gupta and Ors.

# UNION OF INDIA AND ORS. _v._ PRA VEEN GUPTA AND ORS. OCTOBER 4, 1996 [K RAMASWAMY AND S.P. KURDUKAR, JJ.) ## _Land Acquisition Act, 1894 :_ _Ss. 4(1), SA, 6(1) and 17(4)-Acquisition of land for shifting timber market under Master Plan of Delhi- 2001-Dispensing with the inquiry u/s._ c _5-A-Exercise of power of urgency u/s. 17(4)-Held, the acquisition is valid in law and dispensing with the inquiry u/s. 5-A was justified-Mere mention in notification that land is likely to be needed for public purpose does not take away the power of the appropriate government to exercise the power of urgency under s. 17(4)-Declaration u/s. 6 stands restored._ D ## _Limitation :_ _Land Acquisition proceedings-Notifications under ss. 4( 1) and 6( 1) of Land Acquisition Act, 1894_ publishe~Writ _petitions by land owners challenging the Notifications allowed by Single Judge of High Court-Delay in filing L.P A. by State before Division Bench of High Court-Division Bench_ E _dismissing LP A, on the ground of delay-Delay caused due to inappropriate legal opinion-Held, delay was properly explained-High Court not justified in refusing to condone delay-Delay in filing the appeal condoned._ _Jai Narain & Ors._ v. _Union of India & Ors.,_ [1996] 1 sec 9, relied on. p _Narayan Govind Gavate & Ors._ v. _State of Maharashtra & Ors.,_ [1977] 1 sec 133, distinguished. _Dora Phalavli_ v. _State of Punjab & Ors.,_ [1979] 4 sec 485 and _State of Punjab & Anr._ v. _Gurdial Singh & Anr.,_ [1980] 2 sec 471, referred to. CIVIL APPELLATE JURISDICTION: Civil Appeal No. 13228 of 1996. From the Judgment and Order dated 14.7.92 of the Delhi High Court in L.P.A. No. 36/92 in W.P. No. 963 of 1989. H 201 A 202 SUPREME COURT REPORTS [1996] SUPP. 7 S.C.R. N.N. Goswami, B.K. Prasad and S.P. Singh for the Appellants. G.L. Sanghi, Subhash Mittal, M.K. Garg, V.B. Saharaya and R.K. Maheshwari for the Respondents. The following Order of the Court was delivered : B Leave granted. We have heard learned counsel on both sides. This appeal by special leave arises from the judgment of the Division C Bench of the Delhi High Court made on July 14, 1992 in L.P.A. No 36/92 dismissing the L.P.A. The learned single Judge had allowed the Writ Petition No. 936/89 on the ground that there was no justification for invoking the urgency clause in Section 17( 4) of the Land Acquisition Act, 1894 (1 of 1894) (for short, the 'Act'). Accordingly, the learned Single D Judge quashed the declaration under Section 6. The Division Bench dismissed the L.P A. on the ground that there was inordinate delay of more than 200 days in filing the appeal. Thus, this appeal by special leave. When the matter had come up before us and the respondents pointed out that the land involved is only two bighas and, therefore, it is E not a case warranting interference. We directed the learned counsel for the Union of India to find out as to why they are insisting upon decision on merits. A statement was made by Shri K.T.S. Tulsi, learned Additional Solicitor General that there are number of cases of the similar nature pending in the High Court awaiting the decision of this Court and, therefore, decision on merits was necessary. We accordingly set the case for F hearing on merits. The learned counsel for the parties have· filed their written submissions. We have heard Shri N.N. Goswami, learned senior counsel for the appellants and Shri G.L. Sanghi, learned senior counsel for the responG dents. The admitted position is that the notification under Section 4(1) of the Act was published on February 9, 1989 acquiring 1328 Bighas of land situated in Siraspur & Libaspur. The enquiry under Section _SA_ was dispensed with. Declaration under Section 6 was published on February 7, 1990. The writ petition was filed on March 5, 1990. Two awards No. 8 and 9 of 1991 came to be made on February 7, 1992 in respect of the land H except these two bighas of land which are subject matter in this case. Since U.0.1. _v._ P. GUPTA 203 the learned Judge had quashed the notification, two questions have been A raised and argued by the learned counsel for the parties. The first question relates to the delay in filing the L.P.A. It is seen that learned single Judge passed the order on March 5, 1990 and certified copy of the judgment was obtained by the counsel appearing for the Government on July 12, 1990 ; and a letter was addressed immediately on July 31, 1990 directing the B Government pleader to file the appeal. Instead of filing the appeal, he had given the opinion two months thereafter on November 4, 1990 that it was not a fit case. Accordingly, he did not file the appeal. When the matter was re-examined since a large number of cases were involved, new Government pleader opined on April 16, 1992 that it was a fit case for filing the appeal. Accordingly, L.P.A. came to be filed. Shri Sanghi learned senior counsel C for the respondents, contended that delay has not been properly explained. The question is : whether delay on the_ part of the appellants in filing the appeal has been explained? It is seen that as soon as the copy of the judgment of the learned single Judge was received by the Government within 18 days from the date of the receipt of the judgment, letter was · written to the Government pleader to file the appeal. He had no business D to give opinion at that stage that it is not a fit case for filing the appeal. After the lapse of two months, he sent the letter. Obviously, relying upon that opinion, no further action was taken. When the matter reached the Government of India, it got the same re-examined and the Government pleader gave his opinion. Unless this matter is challenged, all the other cases would follow the suit and law being laid down in the appeal would be E applicable and the notification would get quashed. Resultantly, the decision was taken to file the appeal. Under these circumstances, we are of the view that though there is considerable delay in filing the appeal, the Division Bench of the High Court was not justified in refusing to condone the delay and examine the matter on merits. Accordingly, we condone the delay in filing the F appeal. Two courses are open to be considered are whether it is a fit case for remitting the matter for consideration by the·High Court or whether this Court could decide the matter on merits. Having regard to the facts that more than 200 cases are pending disposal in the High Court, remitting G the matter again after years for decision of the High Court would not be justified and we feel it expedient to avoid any further delay that the matter could be decided on merits in this Court. Accordingly, we requested the learned counsel for the parties to argue the case on merits. We have considered the written submissions and heard the arguments elaborately H SUPREME COURT REPORTS [1996] SUPP. 7 S.C.R. 204 A addressed by the counsel. Shri Sanghi, learned Senior Counsel has pointed out that there is no real urgency in this matter and the respondents could have been given an opportunity to contend that land is not needed for any public purpose. In B support thereof, he placed strong reliance on the judgments in _Narayan Govind Gavate & Ors._ v. _State of Maharashtra & Ors.,_ [1977] 1 SCC 133; _Dora Phalavli_ v. _State of Punjab & Ors.,_ [1979] 4 SCC 485 and _State of Punjab & Anr._ v. _Gurdial Singh & Anr.,_ [1980] 2 SCC 471. The decision in _Narayan Govind's_ case, has been distinguished by this Court in several cases. In the light of the ratio in catena of decisions, this Court has C consistently held that acquisition of the property for the planned development of the housing accommodation is an urgent for acquisition and, therefore, dispensing with the enquiry under Section 5A, exercising power under Section 17(4) has been held to be valid. It is true that in _Dora Phalavli and Gurdial Singh's_ cases, the two Judge Bench of this Court in D each of the cases held that enquiry under Section 5A may not be dispensed with in .a cavalier manner denying the opportunity to file the objections unless real urgency is shown. Each case has to be considered on its own facts. The very object of enquiry under Section 5A, is whether the land proposed to be acquired is needed or is likely to be needed for the public purpose mentioned in the notification and whether any other suitable land E other than the acquired land is needed for the said public purpose. In this case, the entire land in two villages was acquired. It is seen that timber business is being carried on in the walled city of old Delhi. It has become a source of traffic congestion and that it requires to be shifted urgently from the existing place to relieve the congestion by acquiring the concerned p land for the public purpose, namely establishment of timber depots. It is true that a mention was also made that unauthorised construction has been made in that area proposed to be acquired. If the enquiry was conducted, delay would defeat the very public purpose of acquisition for shifting of timber business from the walled city and establishment of the timber depots outside the walled city. Therefore, the urgency mentioned in exercising the G power under Section 4(1) was justified. Shri Goswami, learned senior counsel for the Union of India, has relied upon the judgment of this Court in _Jai Narain & Ors._ v. _Union of India & Ors.,_ [1996) 1 SCC 9. It is true, as pointed out by Shri Sanghi, that the acquisition in this reported decision was made for the establishment of sewerage plan as per the direction of H this Court and, therefore, there was urgency. U.0.I. _v._ P. GUPTA 205 But, as stated earlier, since the acquisition is for shifting of timber A business from the walled city to the outskirts of the city, shifting itself is for urgent purpose, viz., to relieve the traffic congestion in the walled city. Under those circumstances, the exercise of the power under Section 17( 4) cannot be said to be unwarranted in this case. It is true that there was a delay, from the date of the notification under Section 4(1) of the Act in B publication of the declaration under Section 6. When it was pointed out that no counter-affidavit was filed in the High Court explaining the delay, we directed the learned counsel for the State to produce the record. An averment has been made in the special leave petition that the delay was due to enquiry being conducted into the objections filed before Lt. Governor in this behalf and until the objections were over-ruled, declaration C under Section 6 could not be published. The note in the office file and the running file do indicate that certain persons kept on making representations right from 1983 and a~ far as present notification is concerned, objections had been received on April 25, 1990 and, thereafter, they have been considered after the Lt. Governor directed to enquire into the matter D and submit the report. Consequently, they conducted the enquiry and submitted the report. It is now settled legal position that decision on urgency is an administrative decision and is a matter of subjective satisfaction of the appropriate Government on the basis of the material available on record. E Therefore, there was no need to pass any reasoned order to reach the conclusion that there is urgency so as to dispense with the enquiry under is Section 5A in exercise of power under Section i 7( 4). It is then contended by Shri Sanghi that as per the revised Master Plan, only 37 hectares of land was needed for establishment of timber depots, though extensive land was F sough to be acquired. When that objection was taken, we passed the order directing the competent officer to file an affidavit. By our proceedings dated August 24, 1995, it was observed as under : "In view of the specific averments made in the written submissions of the respondents regarding the location of the timber depots in G terms of the master plan, it requires clarification by the Delhi Administration whether the lands in Siraspur & Libaspur are still required for the purpose mentioned in the notification, namely, planned development of Delhi and shifting of the timber depots from the Teliwara area into the new places". H 206 A ## SUPREME COURT REPORTS (1996] SUPP. 7 S.C.R. A On G.S. Meena, Under Secretary (L & B) of the Government of National Capital Territory of Delhi has filed the affidavit. Therein, he has stated that the acquisition of the land in the said village for shifting of the timber market is still under existence as per the provisions scheme of MPD-2001, as notified by the DDA. Under these circumstances, the public purpose still subsists. Even under the revised Master Plan, the acquisition B is valid in law and dispensing with the enquiry under Section _5A_ was justified. The learned single Judge, therefore, was not right in quashing the declaration under Section 6. Shri Sanghi, learned senior counsel, further contended that the notification discloses that the land is likely to be needed which would indicate that there is no real urgency. The language of the C notification is not conclusive but the Court is required to consider the material whether there is any urgency to exercise the power under Section 17(4) of the Act. The same view taken by this Court in _Jai Narain's_ case referred to earlier. B Accordingly, we are of the view that mere mention in the notification D that the land is likely to be needed for the public purpose does not take away the power of the appropriate Government to exercise the power of urgency clause under Section 17(4). The appeal is accordingly allowed. The order of the learned single E Judge as well as of the Division Bench of the High Court are set aside. The declaration under Section 6 stands restored. The Land Acquisition Officer is directed to pass the award after issue of the notice to the respondents within a period of three months from the receipt of the order. No costs. R.P. Appeal allowed.
End of Judgment Record
Browse All Supreme Court of India (1996) Decisions
1996-08-16

Pfizer Ltd. v Mazdoor Congress and ors.

Pfizer Ltd. v Mazdoor Congress and ors is a Supreme Court appeal arising from writ petitions under Article 227 challenging the Bombay High Court’s reversal of Labour Court and Industrial Court findings that Pfizer had not committed an unfair labour practice in terminating two security staff, Waman S. Surve and R.B. Sail. The matter centers on the terminations of Surve and Sail after arrests in a theft case involving Pfizer property and the company’s loss of confidence in their suitability as watch and ward personnel. The Labour Court dismissed the complaints under Section 28 of the MRTU & PULP Act, and the Industrial Court upheld that dismissal; the High Court, however, intervened in a petition under Article 227, allowing an unfair labour practice claim under Item 1(1) of Schedule IV on the grounds of undue haste and ordering reinstatement with back wages. The apex court reverses, holding that undue haste is a question of fact to be determined on evidence and that no case under Item 1(1) was pleaded or proven before the lower fora or the High Court. It stresses that new arguments cannot be introduced at the Article 227 stage absent prior pleadings and evidence. The Court restores the Labour Court’s and Industrial Court’s decisions and allows Pfizer’s appeals, clarifying the evidentiary and pleading boundaries for unfair labour practices in industrial relations law.

1996-01-09

Union of India v. S.S. Uppal and Anr.

This appeal concerns the fixation of seniority for an officer absorbed into the Indian Administrative Service (IAS) from a state civil service quota. Respondent No.1, S.S. Uppal, a Development Officer in Madhya Pradesh’s Commerce and Industry Department, was considered for IAS absorption under Rule 8(2) of the IAS (Recruitment) Rules, 1954. A panel of four officers was prepared for vacancies arising up to 1 February 1989, with Uppal placed at serial No.4, making him eligible only for the February 1989 vacancy. Although the vacancy arose earlier, he was not appointed until 15 February 1989, and on 3 February 1989 the IAS (Regulation of Seniority) Rules were amended to introduce a weightage-based method for determining Year of Allotment (YOA) for those appointed by selection. Uppal challenged Rule 2 of the 1989 Amendment Rules as ultra vires and argued his seniority should be determined by the rules in force on 1 February 1989. The Central Administrative Tribunal accepted that the vacancy occurred before the amendment, so unamended rules should apply. The Supreme Court held that seniority in the IAS is determined by the rules in force on the date of appointment, not the date of vacancy, and that weightage cannot be retrospective unless provided. It emphasized that mere inclusion in a panel does not guarantee appointment and that the Central Government may amend seniority rules from time to time. The appeal was allowed, and the Tribunal’s order set aside.

1996-03-29

Thimmappa v. Siddaramakka

Thimmappa v. Siddaramakka concerns a deed of reconveyance attached to a sale of land. The reconveyance deed provided that if the respondent vendor repaid Rs. 5,000 within eight years from the sale date (July 20, 1968), the sale deed would be executed and registered in her favor. The respondent contended she offered payment before the eight-year period expired and sought specific performance through reconveyance; the appellant allegedly refused. The trial court accepted the respondent's evidence of offer within the period; the appellate court reversed, holding time was the essence of the contract and thus the suit was barred by limitation. The Karnataka High Court then set aside the appellate decree and restored the trial court’s decree. The Supreme Court held that, unless the deed of agreement of sale fixes a date for performance, time is not necessarily the essence of the contract. It found that Thimmappa had agreed to reconveyance conditioned on repayment within eight years, and that the respondent offered payment before expiry while the appellant refused to reconvey. The cause of action arose on expiry of eight years from July 20, 1973, but the suit was filed on July 20, 1976, within the period from the date of refusal (July 19, 1976). The Court concluded the suit was not barred by limitation, dismissed the appeal, and upheld the High Court’s restoration of the trial court’s decree.

1996-11-19

STATE OF UTTAR PRADESH AND ORS. v. V.K. JAIN

State of Uttar Pradesh and Ors. v. V.K. Jain concerns the regulation of compounded entertainment tax for cinema theatres under the Uttar Pradesh Entertainments and Betting Tax Act, 1979 and related Rules. The respondent cinema proprietor sought to reduce seating capacity from 540 to 450 for the 1995-96 year and to opt for the compounded tax system under Rule 24-A. The District Magistrate rejected both applications; the Allahabad High Court quashed that rejection, holding that the District Magistrate had no power to ignore or alter the seating capacity indicated in the option application. The State appealed to the Supreme Court. The Court held that a proprietor cannot enter into a composite agreement indicating a reduced seating capacity from the maximum stated in the licence, and the District Magistrate cannot adopt any seating capacity other than the maximum in the licence for Rule 24-A purposes. To reduce seating capacity, the proprietor must approach the licensing authority under Rule 14 of the U.P. Cinematograph Rules, 1951 to amend the licence, and only then can the amended capacity be used for Rule 24-A calculations. The decision emphasizes that the maximum seats fixed in the licence, not ad hoc figures, determine the governing base for taxation and that post-composition adjustments require proper licensing amendments. The Government suggests a clarifying recast of sub-rule (4) for the post-composition period to avoid litigation.