UHL POWER COMPANY LTD. v. STATE OF HIMACHAL PRADESH

Case / Petition Number:
Civil Appeal No. 10341 of 2011
Neutral Citation:[2022] 1 S.C.R. 1

Case Synopsis & Summary

This Supreme Court decision concerns the 1992 Memorandum of Undertaking (MoU) and the 1997 Implementation Agreement (IA) governing the UHL-III hydroelectric project in Himachal Pradesh. The core issue is whether the MoU merged with the IA, such that disputes arising under the MoU were referable to arbitration under Clause 20 of the IA, and whether an arbitral award could include interest on interest (compound interest) and post-award interest. The High Court of Himachal Pradesh had partly allowed UHL’s Arbitration Appeal and the Single Judge had disallowed pre-claim interest. The Court overruled the earlier view in S. L. Arora (which had held compound interest could not be awarded absent contractual or statutory provision) and endorsed Hyder Consulting (UK) Ltd., recognizing Parliament’s power to empower an arbitral tribunal to award interest on the sum directed to be paid by the award. It held that Appendix A (the MoU) forms part of the IA because the word “Agreement” in Clause 2.2 includes all appendices and annexures, and the second recital confirms the MoU’s inclusion. The Court also found that termination of the IA by the State prior to the expiry period was impermissible. Consequently, the appeals were disposed of: UHL’s appeal partly allowed on the interest issue; the State’s appeal rejected in toto.

Precedent Explorer

Find Cases Like This

Explore other judgments dealing with similar legal situations, facts, or statutory provisions.

Case Details & Bench

Court
Supreme Court of India
Hon'ble Judges
  • N. V. Ramana
  • A. S. Bopanna
  • Hima Kohli
Judgment Date
2022-01-07
Court Decision / Holding
The Court partly allowed UHL’s appeal on the interest issue, holding that post-award interest can be granted by the Arbitral Tribunal on the sum directed to be paid by the award (reversing the impugned judgment on this point). It overruled S.L. Arora on compound interest, endorsing Hyder Consulting’s view that Parliament empowered the arbitral tribunal to award interest on the sum directed to be paid by the award. It also affirmed that the MoU merged with the IA, making MoU-disputes arbitrable, and found the termination of the IA premature. Civil Appeal No. 10341 of 2011 was partly allowed to the extent mentioned; Civil Appeal No. 10342 of 2011 filed by the State was dismissed in toto.
Final Disposition
Appeals disposed of: UHL’s appeal partly allowed on the interest component; HP State’s appeal rejected in toto.

Parties to the Case

Appellants / Petitioners

  • UHL Power Company Limited

Respondents

  • State of Himachal Pradesh

Legal Representation & Advocates

Counsels for Petitioners

  • • Mr. Jaideep Gupta

Counsels for Respondents

  • • Mr. Abhinav Mukerji

Provisions of Law Cited

Arbitration and Conciliation Act, 1996: s.34Arbitration and Conciliation Act, 1996: s.31(7)(b)Arbitration and Conciliation Act, 1996: s.34(2)(b)(ii)Section 37 of the Arbitration ActClause 20 of the Implementation AgreementClause 4 of the Implementation AgreementClause 2.2 of the Implementation Agreement

Legal Doctrines & Maxims

  • Fundamental policy of Indian law
  • Patent illegality
  • Public policy of India
  • Wednesbury reasonableness
  • Two plausible interpretations doctrine in contract interpretation

Submissions & Arguments

Contentions of Appellants / Petitioners

The applicants contended that the Memorandum of Undertaking (MoU) dated 10 February 1992 merged with the Implementation Agreement dated 22 August 1997 (Appendix A), such that disputes under the MoU were arbitrable under Clause 20. They challenged the High Court’s and Single Judge’s treatment of pre-claim interest and argued for award of post-award interest (and interest on interest) in line with the Arbitral Award. They relied on the interpretation that the IA, read with its recitals and Clause 2.2, treats the MoU as part of the Agreement; the arbitration clause thus covered MoU disputes and allowed interest on the principal sum adjudged, including post-award interest.

Contentions of Respondents

The State contended that the MoU did not merge with the IA and that the arbitration clause did not extend to MoU disputes; it argued against compound interest in the absence of contractual or statutory permission and highlighted the limited scope of Section 34. It also defended premature termination of the IA by the State within the prescribed period, arguing it did not breach the contract.

Legal Doctrine & Issue Explorer

Explore This Legal Issue

Find relevant judgments and authoritative positions on the legal questions discussed here.

Cited Precedents (11)

Case NameCitationTreatmentExplanation
State of Haryana v. S.L. Arora and Co.2010 (3) SCC 690; [2010] 2 SCR 297OverruledOverruled by Hyder Consulting (UK) Ltd. v. Governor, State of Orissa through Chief Engineer (2015) 2 SCC 189; held that post‑award interest can be awarded by the arbitral tribunal.
Hyder Consulting (UK) Ltd. v. Governor, State of Orissa through Chief Engineer2015 (2) SCC 189; [2014] 14 SCR 1029PositiveEstablished that Arbitral Tribunal may award interest on the sum directed to be paid by the award (post‑award interest).
MMTC Limited v. Vedanta Limited2019 (4) SCC 163; [2019] 3 SCR 1023PositiveCited to support the narrow, non‑parliamentary review in Section 34 and related public policy considerations.
K. Sugumar v. Hindustan Petroleum Corporation Ltd.2020 (12) SCC 539PositiveCited for the disciplined scope of Section 34’s interference limits.
Dyna Technologies (P) Ltd. v. Crompton Greaves Ltd.2019 (20) SCC 1; [2019] 20 SCC 1PositiveAffirms that two plausible interpretations should not lead to interference; court should show restraint under Section 34.
Parsa Kente Collieries Limited v. Rajasthan Rajya Vidyut Utpadan Nigam Limited2019 (7) SCC 236; [2019] 8 SCR 728PositiveConstructing terms of a contract is for the arbitrator unless perverse.
Rashtriya Ispat Nigam Ltd. v. Dewan Chand Ram Saran2006 (11) SCC 181; [2012] 4 SCR 1PositiveAntecedent articulation on public policy and patent illegality in arbitral awards.
South East Asia Marine Engg. & Constructions Ltd. v. Oil India Ltd.2020 (5) SCC 164; [2020] 5 SCC 164PositiveAffirms deference to arbitral reasoning when two plausible interpretations exist.
NHAI v. ITD Cementation (India) Ltd.2015 (14) SCC 21PositiveSupports limited appellate interference and deference to arbitral reasoning.
Sail v. Gupta Brothers Steel Tubes Ltd.2009 (10) SCC 63PositiveReferenced in the context of contract interpretation and arbitration standards.
McDermott International Inc. v. Burn Standard Co. Ltd. And Others2019 (20) SCC 1PositiveReiterates that courts should not reweigh evidence and should respect arbitral outcomes absent perversity.
Case Applicability Diagnostic

Apply This to My Facts

Share your situation and test whether this judgment governs, supports, or challenges your case.

Official Judgment Record
•6,454 words•~30 min read

In The Court Record

UHL POWER COMPANY LTD. v. STATE OF HIMACHAL PRADESH

[2022] 1 S.C.R. 1 # UHL POWER COMPANY LTD. v. ## STATE OF HIMACHAL PRADESH (Civil Appeal No. 10341 of 2011) ## JANUARY 07, 2022 ## **[N. V. RAMANA, CJI, A. S. BOPANNA AND HIMA KOHLI, JJ.]** _Arbitration and Conciliation Act, 1996: Post award interest on the interest amount awarded – Held: Can be granted by Arbitrator._ _Arbitration and Conciliation Act, 1996: s.34 – Jurisdiction under, Scope – Held: Court does not sit in appeal over the arbitral award and may interfere on merits on the limited ground provided under s.34(2)(b)(ii)._ _Arbitration: If there are two plausible interpretations of the terms and conditions of the contract then no fault can be found if the arbitrator proceeds to accept one interpretation as against the other._ _Arbitration: Arbitral award – Scope of interference by courts – Held: Courts should not interfere with an award merely because an alternate view on facts and interpretation of contract exists._ _Deeds and Documents: Whether in the instant case, the Memorandum of Undertaking (MoU) dated 10[th] February, 1992 merged into the Implementation Agreement dated 22[nd] August, 1997 – Held: As admitted by State, the MoU was mentioned as “Appendix A” in the second recital of Implementation Agreement which itself demolished the plea taken by the State that the Arbitral Tribunal and the Appellate Court have erred in returning a finding that the MoU dated 10th February, 1992 did not merge into the Implementation Agreement dated 22nd August, 1997 – The view is reinforced on a reading of the definition of the word “Agreement” as used in Clause 2.2 of the Implementation Agreement which clearly stated that the word “Agreement” wherever used in the Implementation Agreement, shall include all its appendices and annexures – The MoU having been described by the parties as_ 1 2 SUPREME COURT REPORTS [2022] 1 S.C.R. - A _Appendix A to the Implementation Agreement, would have to be treated as having merged with the Implementation Agreement for all effects and purposes._ ## **Disposing of the appeals, the Court** - **HELD: 1. As the judgment in the case of** _**S.L. Arora**_ **, on** - B **which reliance has been placed by the Division Bench of the High Court of Himachal Pradesh, has since been overruled by a threeJudge Bench of this Court in the case of** _**Hyder Consulting (UK) Ltd.**_ **, the findings returned by the Appellate Court in the impugned judgment to the effect that the Arbitral Tribunal is not empowered** - C **to grant compound interest or interest upon interest and only simple interest can be awarded in favour of UHL on the principal amount claimed, is quashed and set aside. As a result, the findings returned in para 54(a) of the impugned judgment insofar as it relates to grant of the interest component, are reversed while restoring the arbitral award on the above aspect in favour of UHL.** - D **[Para 6][8-E-G]** **2. The very fact that the State admits to having executed** **the MoU with UHL on 10th February, 1992 and the said MoU has been mentioned as “Appendix A” in the second recital of the Implementation Agreement, itself demolishes the plea taken by** E **the State that the Arbitral Tribunal and the Appellate Court have erred in returning a finding that the MoU dated 10th February, 1992 did not merge into the Implementation Agreement dated 22nd August, 1997. The said view is reinforced on a reading of the definition of the word “Agreement” as used in Clause 2.2 of** F **the Implementation Agreement which clearly states that the word “Agreement” wherever used in the Implementation Agreement, shall include all its appendices and annexures. The MoU having been described by the parties as Appendix A to the Implementation Agreement, would have to be treated as having merged with the Implementation Agreement for all effects and** G **purposes. In the light of the said recitals and clauses of the Implementation Agreement, this Court endorses the findings returned in para 47 of the impugned judgment, wherein it has been held that a plain reading of the second recital read with Clause 2.2 of the Implementation Agreement suggested that the** - H 3 UHL POWER COMPANY LTD. v. STATE OF HIMACHAL PRADESH **MoU has merged with the Implementation Agreement and, therefore, the disputes that were referable to arbitration under the Implementation Agreement in terms of Clause 20, were to include disputes arising under the MoU, even though the latter document did contain a separate arbitration clause. [Para 10] [10-B-F]** **3. All the points of dispute between the parties regarding performance of the contractual obligations including claims for damages and expenses incurred by UHL either arising from the MoU dated 10th February, 1992, or under the Implementation Agreement dated 22nd August, 1997, were referable to arbitration in accordance with Clause 20 forming a part of the Implementation Agreement. [Para 11][11-B-C]** **4. The second plea taken by the State is that the Appellate Court has erred in setting aside the order of the Single Judge and restoring the findings of the Sole Arbitrator on the aspect of pre-mature termination of the Implementation Agreement on the part of the State well before expiry of the prescribed period. [Para 12][11-D]** **5. A plain reading of Clauses 4.1(a) and (b) leaves no manner of doubt that UHL was required to commence construction of the project within a period of one year from the effective date only after obtaining a techno-economic clearance from CEA and an environmental clearance from the Government of India, Ministry of Environment and Forests. However, it was agreed by the parties that since obtaining of the relevant clearances referred to above and under Clause 16.8 of the Agreement whereunder the State was required to discharge certain obligations, were not entirely in the hands of UHL, in the event of any delay beyond a period of three months reckoned from the effective date, the stipulated period of one year contemplated in the Implementation Agreement could be extended, but not beyond the additional period of twelve months. In the light of the aforesaid clauses of the Implementation Agreement, the submission made by the State that, under all circumstances, the Implementation Agreement had to be executed within a period of one year and since the provision for extension beyond one** A B C D E F G H 4 SUPREME COURT REPORTS [2022] 1 S.C.R. - A **year was applicable only to the conditions contemplated in Clause 4.1(a) and (b) and not to those stipulated in Clause 4.1(c) to (g), is found to be unmerited and is turned down. When the parties to the Implementation Agreement were ad idem that the period of one year available to UHL to commence the construction activity was to be reckoned after the major requirements prescribed in** - B **Clause 4.1 could be obtained, then any argument sought to be advanced to segregate the obligations under different sub-heads of Clause 4.1 only to lay the blame at the door of UHL when the requisite clearances were to be obtained by the State Government from the Central Government and Centralized Authorities, is** - C **devoid of merits, besides being completely unreasonable and illogical. [Para 13][12-D-H; 13-A]** **6. This Court also accepts as correct, the view expressed by the Appellate Court that the Single Judge committed a gross error in re-appreciating the findings returned by the Arbitral** D **Tribunal and taking an entirely different view in respect of the interpretation of the relevant clauses of the Implementation Agreement governing the parties inasmuch as it was not open to the said Court to do so in proceedings under Section 34 of the Arbitration Act, by virtually acting as a Court of Appeal. [Para 14][13-B-C]** E **7. As it is, the jurisdiction conferred on Courts under Section 34 of the Arbitration Act is fairly narrow, when it comes to the scope of an appeal under Section 37 of the Arbitration Act, the jurisdiction of an Appellate Court in examining an order, setting aside or refusing to set aside an award, is all the more** F **circumscribed. [Para 15][13-C-D]** G _MMTC Limited v. Vedanta Limited_ **(2019) 4 SCC 163 : [2019] 3 SCR 1023;** _K.Sugumar v. Hindustan Petroleum Corporation Ltd._ **(2020) 12 SCC 539;** _Dyna Technologies (P) Ltd. v. Crompton Greaves Ltd._ **(2019) 20 SCC 1;** _Parsa Kente Collieries Limited v. Rajasthan Rajya Vidyut Utpadan Nigam Limited_ **(2019) 7 SCC 236 : [2019] 8SCR 728;** _McDermott International Inc. v. Burn Standard Co. Ltd. And Others_ **(2019) 20 SCC 1;** H 5 UHL POWER COMPANY LTD. v. STATE OF HIMACHAL PRADESH _Rashtriya Ispat Nigam Ltd. V. Dewan Chand Ram Saran_ **(2006) 11 SCC 181 : [2012] 4 SCR 1;** _South East Asia Marine Engg. & Constructions Ltd. [SEAMAC Limited] v. Oil India Ltd._ **2020 (5) SCC 164 : [2020] 5 SCC 164 – relied on.** **8. In the instant case, the interpretation of the relevant clauses of the Implementation Agreement, as arrived at by the Sole Arbitrator, are both, possible and plausible. Merely because another view could have been taken, can hardly be a ground for the Single Judge to have interfered with the arbitral award. In the given facts and circumstances of the case, the Appellate Court has rightly held that the Single Judge exceeded his jurisdiction in interfering with the award by questioning the interpretation given to the relevant clauses of the Implementation Agreement, as the reasons given are backed by logic. [Para 21][17-C-D]** **9. The decision of the Appellate Court is upheld that has restored the findings returned in the arbitral award dated 05th June, 2005 to the effect that the State of Himachal Pradesh had proceeded to terminate the Implementation Agreement before expiry of the prescribed period which could have been extended up to 24 months, reckoned from the “effective date”. In the instant case, the State of H.P. had terminated the Implementation Agreement five months prior to the stipulated period by adopting a distorted interpretation of Clause 4 of the Implementation Agreement, which was impermissible. [Para 22][17-E-F]** _State of Haryana v. S.L. Arora and Co._ **(2010) 3 SCC 690 : [2010] 2 SCR 297 – held overruled.** A B C D E F _Hyder Consulting (UK) Ltd. V. Governor, State of Orissa through Chief Engineer_ **(2015) 2 SCC 189 : [2014] 14 SCR 1029 – followed.** ## **Case Law Reference** |**[2010]**|**2 SCR 297**|**held overruled**|**Para 3**| |---|---|---|---| |**[2014]**|**14 SCR 1029**|**followed**|**Para 4**| |**[2019]**|**3 SCR 1023**|**relied on**|**Para 15**| G H 6 SUPREME COURT REPORTS [2022] 1 S.C.R. |A|**(2020)**|**12 SCC 539**|**relied on**|**Para 16**| |---|---|---|---|---| ||**(2019)**|**20 SCC 1**|**relied on**|**Para 17**| ||**[2019]**|**8 SCR 728**|**relied on**|**Para 18**| ||**(2019)**|**20 SCC 1**|**relied on**|**Para 18**| |B|**[2012]**|**4 SCR 1**|**relied on**|**Para 18**| ||**[2020]**|**5 SCC 164**|**relied on**|**Para 20**| The Judgment of the Court was delivered by ## **HIMA KOHLI, J.** ## C 1. Both the present appeals arise from a common judgment dated 24[th] May, 2011, passed by the High Court of Himachal Pradesh partly allowing Arbitration Appeal No. 2 of 2009 filed by UHL Power Company Limited[1] under Section 37 of the Arbitration and Conciliation Act, 1996[2] . UHL has filed Civil Appeal No. 10342 of 2011 and the State of Himachal D Pradesh[3] has filed Civil Appeal No. 10342 of 2011, as both the parties are aggrieved by the impugned judgment. 2. Though several grounds have been taken by UHL in its appeal to assail the impugned judgment, Mr. Jaideep Gupta, learned senior counsel for UHL has confined his grievance to the disallowance of the E pre-claim interest i.e., interest from the date when expenses were incurred by UHL, till the date of lodging the claim. It may be noted that in terms of the award dated 05[th] June, 2005, the learned Sole Arbitrator had awarded a sum of **¹** 26,08,89,107.35p. (Rupees Twenty six crores eight lakhs eighty nine thousand one hundred and seven and thirty five paise) in favour of UHL towards expenses claimed along with pre-claim interest F capitalized annually, on the expenses so incurred. Further, compound interest was awarded in favour of UHL @ 9% per annum till the date of claim and in the event the awarded amount is not realized within a period of six months from the date of making the award, future interest was awarded @ 18% per annum on the principal claim with interest. G 3. Dissatisfied with the award, when the State of H.P. filed a petition under Section 34 of the Arbitration Act, vide judgment dated 16[th] December, 2008, the learned Single Judge disallowed the entire claim of 1 For short ‘UHL’ 2 For short ‘the Arbitration Act’ H 3 For short ‘the State’ 7 UHL POWER COMPANY LTD. v. STATE OF HIMACHAL PRADESH [HIMA KOHLI, J.] UHL. The said judgment was challenged by UHL in a petition filed under Section 37 of the Arbitration Act that has been decided by the impugned judgment whereunder, the Division Bench of the High Court has awarded a sum of **¹** 9,10,26,558.74 (Rupees Nine crores ten lakhs twenty six thousand five hundred fifty eight and seventy four paise) in favour of UHL, being the actual principal amount along with simple interest @ 6% per annum from the date of filing of the claim, till the date of realization of the awarded amount. For declining payment of compound interest awarded by the learned Sole Arbitrator to UHL, the Division Bench relied on the decision of this Court in _**State of Haryana v. S.L. Arora and Co.[4]**_ , wherein it was held that compound interest can be awarded only if there is a specific contract, or authority under a Statute, for compounding of interest and that there is no general discretion vested in courts or tribunals to award compound interest. It was further held that in the absence of any provision for interest upon interest in the contract, the Arbitral Tribunals do not have the power to award interest upon interest, or compound interest, either for the pre-award period or for the post-award period. 4. By now, the aforesaid aspect has been set at rest by a threeJudge Bench of this Court in _**Hyder Consulting (UK) Ltd. V. Governor, State of Orissa through Chief Engineer[5]**_ , that has overruled the verdict in the case of _**S.L. Arora**_ (supra). The majority view is that post-award interest can be granted by an Arbitrator on the interest amount awarded. Writing for the majority, Justice Bobde (as His Lordship then was) has held thus: “21. In the result, I am of the view that _**S.L. Arora case [State of Haryana v. S.L. Arora and Co**_ . **(2010) 3 SCC] is wrongly decided** in that it holds that a sum directed to be paid by an Arbitral Tribunal and the reference to the award on the substantive claim does not refer to interest pendente lite awarded on the “sum directed to be paid upon award” and that in the absence of any provision of interest upon interest in the contract, the Arbitral Tribunal does not have the power to award interest upon interest, or compound interest either for the pre-award period or for the post-award period. Parliament has the undoubted power to legislate on the subject and provide that the **Arbitral Tribunal may award** A B C D E F G 5 (2015) 2 SCC 189 4 (2010) 3 SCC 690 H 8 SUPREME COURT REPORTS [2022] 1 S.C.R. A **interest on the sum directed to be paid by the award, meaning a sum inclusive of principal sum adjudged and the interest** , and this has been done by Parliament in plain language.” ## _**[emphasis supplied]**_ 5. While giving a concurring opinion in the aforesaid case, Justice B Sapre made the following pertinent observations: “31. Coming now to the post-award interest. Section 31(7)(b) of the Act employs the words, “A sum directed to be paid by an arbitral award ... “. Clause (b) uses the words “arbitral award” and not the “Arbitral Tribunal”. The **arbitral award. as held** C **“ ” above, is made in respect of a sum which includes the interest.** It is, therefore, obvious that what carries under Section 31 (7)(b) of the Act is the “ _sum directed to be paid by an arbitral award_ ” and not any other amount much less by or under the name “ _interest_ ”. **In such situation. it cannot be said that what** D **is being granted under Section 31(7)(b) of the Act is “** _**interest**_ **”** _**on interest**_ **. Interest under clause (b) is granted on the “** _**sum**_ **” directed to be paid by an arbitral award wherein the “sum” is nothing more than what is arrived at under clause (a).”** E ## _**[emphasis supplied]**_ 6. As the judgment in the case of _**S.L. Arora**_ (supra), on which reliance has been placed by the Division Bench of the High Court of Himachal Pradesh, has since been overruled by a three-Judge Bench of this Court in the case of _**Hyder Consulting (UK) Ltd.**_ (supra), the F findings returned by the Appellate Court in the impugned judgment to the effect that the Arbitral Tribunal is not empowered to grant compound interest or interest upon interest and only simple interest can be awarded in favour of UHL on the principal amount claimed, is quashed and set aside. As a result, the findings returned in para 54(a) of the impugned judgment insofar as it relates to grant of the interest component, are G reversed while restoring the arbitral award on the above aspect in favour of UHL. 7. Proceeding to the submission made by Mr. Abhinav Mukerji, learned Additional Advocate General for the State for assailing the impugned judgment, we may note that two-fold arguments have been H put forth. Firstly, that the Division Bench has gravely erred in upsetting 9 UHL POWER COMPANY LTD. v. STATE OF HIMACHAL PRADESH [HIMA KOHLI, J.] the findings returned by the learned Single Judge _vide_ judgment dated 16[th] December, 2008 and has failed to appreciate that the Memorandum of Undertaking[6] dated 10[th] February, 1992, did not merge into the Implementation Agreement dated 22[nd] August, 1997, as both were distinct documents and that the MoU contained a separate Arbitration clause numbered as Clause 18, whereas the Implementation Agreement contained Clause 20. Secondly, it has been canvassed that the Appellate Court as also the Arbitral Tribunal have committed a grave error in arriving at the conclusion that the Implementation Agreement was prematurely terminated by the State much before the expiry of the prescribed period. 8. Coming first to the argument urged on behalf of the State that the MoU dated 10[th] February, 1992 did not merge with the Implementation Agreement dated 22[nd] August, 1997, a perusal of the recitals and the clauses contained in the Implementation Agreement dated 22[nd] August, 1997, belies such a submission. One of the recitals on the second page of the Implementation Agreement is as follows: A B C D “WHEREAS the Government in accordance with the policy guidelines of Government of India (hereinafter referred to as “GOI” had entered into Memorandum of Understanding (MOU) (APPENDIX ‘A’) on February 10, 1992 with the Company to carry out detailed investigations of the UHL-III Hydro - electric Project of 100 MW capacity and located in District Mandi, Himachal Pradesh (hereinafter referred to a “Project”) and has submitted, within the stipulated period from the date of signing of the MOU, a Detailed project Report (DPR).” 9. Further, the definition of different words used in the Implementation Agreement form a part of Clause (2). The term “Agreement” has been defined in Clause 2.2 as follows: E F ## **“CLAUSE 2 DEFINITIONS** For all purposes of this Agreement, the. various terms shall have G the following meanings, except where the context otherwise requires, definitions and other terms expressed in the singular shall, include the plural and vice versa. 2.1 xxx xxx xxx > 6 For short ‘MoU’ H 10 SUPREME COURT REPORTS [2022] 1 S.C.R. - A 2.2 **“Agreement”** shall mean this Agreement together with all its appendices and annexures and any amendments thereto made in accordance with the provisions herein contained.” 10. The very fact that the State admits to having executed the B MoU with UHL on 10[th] February, 1992 and the said MoU has been mentioned as “Appendix A” in the second recital of the Implementation Agreement, as reproduced above, itself demolishes the plea taken by the State that the Arbitral Tribunal and the Appellate Court have erred in returning a finding that the MoU dated 10[th] February, 1992 did not merge into the Implementation Agreement dated 22[nd] August, 1997. The aforesaid C view is reinforced on a reading of the definition of the word “Agreement” as used in Clause 2.2 of the Implementation Agreement which clearly states that the word “Agreement” wherever used in the Implementation Agreement, shall include all its appendices and annexures. The MoU having been described by the parties as Appendix A to the Implementation - D Agreement, would have to be treated as having merged with the Implementation Agreement for all effects and purposes. In the light of the aforesaid recitals and clauses of the Implementation Agreement, this Court endorses the findings returned in para 47 of the impugned judgment, wherein it has been held that a plain reading of the second recital read with Clause 2.2 of the Implementation Agreement suggested - E that the MoU has merged with the Implementation Agreement and, therefore, the disputes that were referable to arbitration under the Implementation Agreement in terms of Clause 20, were to include disputes arising under the MoU, even though the latter document did contain a separate arbitration clause. F 11. No exception can be taken to the observations made by the Appellate Court that the learned Single Judge erred in singularly relying on the contents of Clause 1 of the Implementation Agreement, which states as follows: ## “ **CLAUSE 1 STATEMENT OF IMPLEMENTATION OF PROJECT :** G Both the parties i.e. the Government and the company agree that the Project shall be implemented, subject to the terms mentioned in the Agreement, as per the provisions of the DPR as approved by· the Government/ GOI. The parties also agree that the MOU signed on 10.2.1992 shall stand lapsed as on today the twenty H second August, 1997.” 11 UHL POWER COMPANY LTD. v. STATE OF HIMACHAL PRADESH [HIMA KOHLI, J.] This Court is in agreement with the Appellate Court that Clause 1 of the Implementation Agreement could not have been read in isolation and when read in conjunction with the second recital and Clause 2.2 of the Implementation Agreement, it is apparent that the MoU was made a part and parcel of the Implementation Agreement. In view of the above, the view taken by the learned Sole Arbitrator that the MoU forms a part of the Implementation Agreement, as has been upheld by the Appellate Court, does not deserve any interference. All the points of dispute between the parties regarding performance of the contractual obligations including claims for damages and expenses incurred by UHL either arising from the MoU dated 10[th] February, 1992, or under the Implementation Agreement dated 22[nd] August, 1997, were referable to arbitration in accordance with Clause 20 forming a part of the Implementation Agreement. 12. The second plea taken by the learned Additional Advocate General the State is that the Appellate Court has erred in setting aside the order of the learned Single Judge and restoring the findings of the Sole Arbitrator on the aspect of pre-mature termination of the Implementation Agreement on the part of the State well before expiry of the prescribed period. For examining this point, Clause 4 of the Implementation Agreement gains significance. The said clause prescribes the starting date of the project and states as follows: A B C D E ## “ **CLAUSE 4 STARTING DATE OF PROJECT.** - 4.1 Within one year from the Effective Date, the Company shall start the construction of the Project after meeting the major requirements, e.g.:- - a) Obtain techno economic clearance from CEA. F - b) Obtain environmental clearance from GO!, Ministry of Environment and Forests (MOEF). - c) Identify the purchaser of power and finalise Power Schedules Agreement(s). G - d) Commence· detailed designs of Project components/ structures. - e) Finalise selection of Engineering, Procurement and construction (EPC) contractor/ executing agencies, if required. H 12 SUPREME COURT REPORTS [2022] 1 S.C.R. A - f) Establish site office and take over the site from Government including the Government land or private land already acquired by Government on lease etc., for the purpose of carrying out preparatory works. - g) Achieve Financial Closure. B Both parties acknowledge that fulfillment of activities enumerated at 4.1(a), 4.l(b) of this clause and clause 16.8 of this Agreement are not totally under the control of the Company, therefore, if the fulfillment of these activities is delayed beyond three 3 months from effective Date, the stipulated period of one C year, shall be extended by one month for each month of delay in fulfillment of any of the activities enumerated at 4.1(a), 4.1 (b) and 16.8 provided that the total of the monthly extensions shall not exceed twelve (12).” 13. A plain reading of Clauses 4.1(a) and (b) leaves no manner of D doubt that UHL was required to commence construction of the project within a period of one year from the effective date only after obtaining a techno-economic clearance from CEA and an environmental clearance from the Government of India, Ministry of Environment and Forests. However, it was agreed by the parties that since obtaining of the relevant clearances referred to above and under Clause 16.8 of the Agreement E whereunder the State was required to discharge certain obligations, were not entirely in the hands of UHL, in the event of any delay beyond a period of three months reckoned from the effective date, the stipulated period of one year contemplated in the Implementation Agreement could be extended, but not beyond the additional period of twelve months. In F the light of the aforesaid clauses of the Implementation Agreement, the submission made by learned Additional Advocate General for the State that, under all circumstances, the Implementation Agreement had to be executed within a period of one year and since the provision for extension beyond one year was applicable only to the conditions contemplated in Clause 4.1(a) and (b) and not to those stipulated in Clause 4.1(c) to (g), G is found to be unmerited and is turned down. When the parties to the Implementation Agreement were _ad idem_ that the period of one year available to UHL to commence the construction activity was to be reckoned after the major requirements prescribed in Clause 4.1 could be obtained, then any argument sought to be advanced to segregate the H obligations under different sub-heads of Clause 4.1 only to lay the blame 13 UHL POWER COMPANY LTD. v. STATE OF HIMACHAL PRADESH [HIMA KOHLI, J.] at the door of UHL when the requisite clearances were to be obtained by the State Government from the Central Government and Centralized Authorities, is devoid of merits, besides being completely unreasonable and illogical. 14. This Court also accepts as correct, the view expressed by the Appellate Court that the learned Single Judge committed a gross error in re-appreciating the findings returned by the Arbitral Tribunal and taking an entirely different view in respect of the interpretation of the relevant clauses of the Implementation Agreement governing the parties inasmuch as it was not open to the said Court to do so in proceedings under Section 34 of the Arbitration Act, by virtually acting as a Court of Appeal. 15. As it is, the jurisdiction conferred on Courts under Section 34 of the Arbitration Act is fairly narrow, when it comes to the scope of an appeal under Section 37 of the Arbitration Act, the jurisdiction of an Appellate Court in examining an order, setting aside or refusing to set aside an award, is all the more circumscribed. In _**MMTC Limited v. Vedanta Limited 7**_ , the reasons for vesting such a limited jurisdiction on the High Court in exercise of powers under Section 34 of the Arbitration Act has been explained in the following words: A B C D “11. As far as Section 34 is concerned, the position is well- settled by now that the Court does not sit in appeal over the arbitral award and may interfere on merits on the limited ground provided E under Section 34(2)(b) (ii) i.e. if the award is against the public policy of India. As per the legal position clarified through decisions of this Court prior to the amendments to the 1996 Act in 2015, a violation of Indian public policy, in turn, includes a violation of the fundamental policy of Indian law, a violation of the interest of F India, conflict with justice or morality, and the existence of patent illegality in the arbitral award. Additionally, the concept of the “fundamental policy of Indian law” would cover compliance with statutes and judicial precedents, adopting a judicial approach, compliance with the principles of natural justice, and _Wednesbury_ [Associated Provincial Picture Houses v. Wednesbury Corpn., G (1948) 1 KB 223 (CA)] reasonableness. Furthermore, “patent illegality” itself has been held to mean contravention of the substantive law of India, contravention of the 1996 Act, and contravention of the terms of the contract.” 7 (2019) 4 SCC 163 H 14 SUPREME COURT REPORTS [2022] 1 S.C.R. A 16. A similar view, as stated above, has been taken by this Court in _**K. Sugumar v. Hindustan Petroleum Corporation Ltd.8**_ , where it has been observed as follows: - “2. The contours of the power of the Court under Section 34 of the Act are too well established to require any reiteration. Even a - B bare reading of Section 34 of the Act indicates the highly constricted power of the civil court to interfere with an arbitral award. The reason for this is obvious. When parties have chosen to avail an alternate mechanism for dispute resolution, they must be left to reconcile themselves to the wisdom of the decision of the arbitrator and the role of the court should be restricted to the - C bare minimum. Interference will be justified only in cases of commission of misconduct by the arbitrator which can find manifestation in different forms including exercise of legal perversity by the arbitrator.” 17. It has also been held time and again by this Court that if there D are two plausible interpretations of the terms and conditions of the contract, then no fault can be found, if the learned Arbitrator proceeds to accept one interpretation as against the other. In _**Dyna Technologies (P) Ltd. V. Crompton Greaves Ltd.9**_ , the limitations on the Court while exercising powers under Section 34 of the Arbitration Act has been highlighted thus: - E “24. There is no dispute that Section 34 of the Arbitration Act limits a challenge to an award only on the grounds provided therein or as interpreted by various Courts. We need to be cognizant of the fact that arbitral awards should not be interfered with in a casual and cavalier manner, unless the Court comes to a conclusion - F that the perversity of the award goes to the root of the matter without there being a possibility of alternative interpretation which may sustain the arbitral award. Section 34 is different in its approach and cannot be equated with a normal appellate jurisdiction. The mandate under Section 34 is to respect the finality of the arbitral award and the party autonomy to get their dispute - G adjudicated by an alternative forum as provided under the law. If the Courts were to interfere with the arbitral award in the usual course on factual aspects, then the commercial wisdom behind opting for alternate dispute resolution would stand frustrated.” - 8 (2020) 12 SCC 539 - H 9 (2019) 20 SCC 1 15 UHL POWER COMPANY LTD. v. STATE OF HIMACHAL PRADESH [HIMA KOHLI, J.] 18. In _**Parsa Kente Collieries Limited v. Rajasthan Rajya Vidyut Utpadan Nigam Limited10**_ , adverting to the previous decisions of this Court in _**McDermott International Inc. v. Burn Standard Co. Ltd. And Others11**_ and _**Rashtriya Ispat Nigam Ltd. V. Dewan Chand Ram Saran12**_ , wherein it has been observed that an Arbitral Tribunal must decide in accordance with the terms of the contract, but if a term of the contract has been construed in a reasonable manner, then the award ought not to be set aside on this ground, it has been held thus: “9.1 ……….. **It is further observed and held that construction of the terms of a contract is primarily for an Arbitrator to decide unless the Arbitrator construes the contract in such a way that it could be said to be something that no fairminded or reasonable person could do** . It is further observed by this Court in the aforesaid decision in paragraph 33 that when a court is applying the “public policy” test to an arbitration award, it does not act as a court of appeal and consequently errors of fact cannot be corrected. **A possible view by the Arbitrator on facts has necessarily to pass muster as the Arbitrator is the ultimate master of the quantity and quality of evidence to be relied upon when he delivers his arbitral award.** It is further observed that thus an award based on little evidence or on evidence which does not measure up in quality to a trained legal mind would not be held to be invalid on this score. A B C D E 9.2 Similar is the view taken by this Court in _NHAI v. ITD Cementation (India) Ltd._ (2015) 14 SCC 21, para 25 and _SAIL v. Gupta Brother Steel Tubes Ltd._ (2009) 10 SCC 63, para 29.” [emphasis supplied] F 19. In _**Dyna Technologies (P) Ltd.**_ (supra), the view taken above has been reiterated in the following words: “25. Moreover, umpteen number of judgments of this Court have categorically held that the courts should not interfere with an award merely because an alternative view on facts and interpretation of contract exists. The courts need to be cautious and should defer to the view taken by the Arbitral Tribunal even if the reasoning G > 10 (2019) 7 SCC 236 11 (2006) 11 SCC 181 12 (2012) 5 SCC 306 H 16 SUPREME COURT REPORTS [2022] 1 S.C.R. A provided in the award is implied unless such award portrays perversity unpardonable under Section 34 of the Arbitration Act.” ## 20. An identical line of reasoning has been adopted in _**South East Asia Marine Engg. & Constructions Ltd.[SEAMAC Limited] V. Oil India Ltd. 13**_ and it has been held as follows: B **“12.** It is a settled position that a court can set aside the award only on the grounds as provided in the Arbitration Act as interpreted by the courts. Recently, this Court in _Dyna Technologies (P) Ltd._ v. _Crompton Greaves Ltd._ [ _Dyna Technologies (P) Ltd._ v. _Crompton Greaves Ltd._ , (2019) 20 SCC 1 : 2019 SCC OnLine C SC 1656] laid down the scope of such interference. This Court observed as follows : (SCC pp. 11-12, para 24) “ _24_ . There is no dispute that Section 34 of the Arbitration Act limits a challenge to an award only on the grounds provided therein or as interpreted by various Courts. _We need to be_ D _cognizant of the fact that arbitral awards should not be interfered with in a casual and cavalier manner, unless the Court comes to a conclusion that the perversity of the award goes to the root of the matter without there being a possibility of alternative interpretation which may sustain_ E _the arbitral award._ Section 34 is different in its approach and cannot be equated with a normal appellate jurisdiction. The mandate under Section 34 is to respect the finality of the arbitral award and the party autonomy to get their dispute adjudicated by an alternative forum as provided under the law. If the Courts were to interfere with the arbitral award in the usual course on F factual aspects, then the commercial wisdom behind opting for alternate dispute resolution would stand frustrated.” **13. It is also settled law that where two views are possible, the Court cannot interfere in the plausible view taken by the arbitrator supported by reasoning.** This Court in _Dyna_ G _Technologies [Dyna Technologies (P) Ltd. V. Crompton Greaves Ltd., (2019) 20 SCC 1 : 2019 SCC OnLine SC 1656] observed as under : (SCC p.12, para 25)_ H 13 (2020) 5 SCC 164 17 UHL POWER COMPANY LTD. v. STATE OF HIMACHAL PRADESH [HIMA KOHLI, J.] 25. Moreover, umpteen number of judgments of this Court have categorically held that the Court should not interfere with an award merely because an alternative view on facts and interpretation of contract exists. The Courts need to be cautious and should defer to the view taken by the Arbitral Tribunal even if the reasoning provided in the award is implied unless such award portrays perversity unpardonable under Section 34 of the Arbitration Act.” A B ## [emphasis supplied] 21. In the instant case, we are of the view that the interpretation of the relevant clauses of the Implementation Agreement, as arrived at by the learned Sole Arbitrator, are both, possible and plausible. Merely because another view could have been taken, can hardly be a ground for the learned Single Judge to have interfered with the arbitral award. In the given facts and circumstances of the case, the Appellate Court has rightly held that the learned Single Judge exceeded his jurisdiction in interfering with the award by questioning the interpretation given to the relevant clauses of the Implementation Agreement, as the reasons given are backed by logic. 22. We, therefore, uphold the decision of the Appellate Court that has restored the findings returned in the arbitral award dated 05[th] June, 2005 to the effect that the State of Himachal Pradesh had proceeded to terminate the Implementation Agreement before expiry of the prescribed period which could have been extended up to 24 months, reckoned from the “effective date”. In the instant case, the State of H.P. had terminated the Implementation Agreement five months prior to the stipulated period by adopting a distorted interpretation of Clause 4 of the Implementation Agreement, which was impermissible. 23. In view of the above discussion, Civil Appeal No. 10341 of 2011 preferred by UHL is partly allowed to the extent mentioned in para 6 above, while Civil Appeal No. 10342 of 2011 filed by the State of Himachal Pradesh is rejected in toto. Parties are left to bear their own costs. C D E F G Devika Gujral H Appeals disposed of.
End of Judgment Record
Browse All Supreme Court of India (2022) Decisions
2022-12-09

MOHD. SABEER @ SHABIR HUSSAIN v. RM, U. P. STATE ROAD TRANSPORT CORP.

The appellant, Mohd. Sabeer (also known as Shabir Hussain), a scrap dealer, was a passenger in a UP State Road Transport Corporation bus when the driver rashly and negligently drove the vehicle, causing a collision near Ghaziabad in 2009. He sustained grave injuries including an amputation of the right lower limb and other bodily injuries. The Motor Accident Claims Tribunal (MACT) awarded Rs. 15,76,465 with interest; the High Court of Delhi enhanced the amount to Rs. 16,70,932. The Disability Certificate recorded 70% permanent disability. The High Court had treated the claimant’s functional disability as 35%, relying on post‑accident income reflected in IT returns, and erred in not adequately recognizing the impact on earning capacity of a self‑employed person who cannot drive. The Supreme Court held that the appellant’s functional disability should be treated as 60% for loss of future earning capacity and that permanent disablement warrants consideration of future prospects in addition to future income. It invoked National Insurance Co. v. Pranay Sethi to apply a 40% addition for future prospects, and directed compensation for prosthetic limb purchase and maintenance, as well as enhanced non‑pecuniary damages. The final award was increased to Rs. 38,70,120 with 9% interest from the date of application, and the appeals were allowed, emphasizing liberal, holistic justice to restore the claimant to his pre‑accident position in light of socio‑economic factors.

2022-01-25

Intercontinental Hotels Group (India) Pvt. Ltd. & ANR. v. Waterline Hotels Pvt. Ltd.

Intercontinental Hotels Group (India) Pvt. Ltd. & Anr. v Waterline Hotels Pvt. Ltd. is a Supreme Court decision addressing appointment of a sole arbitrator under Section 11(6) read with Section 11(12)(a) of the Arbitration and Conciliation Act, 1996, in a dispute arising from a Hotel Management Agreement (HMA) for renovating the Holiday Inn & Suites Bengaluru, Whitefield. The petitioners allege breach by Waterline Hotels, including non-payment of incentive management fee and related charges, culminating in Waterline’s email termination of the HMA on 12 October 2018 after rebranding the hotel as Miraya. The petitioners invoked arbitration; Waterline challenged the enforceability of the arbitration clause on the ground that the HMA is an unstamped instrument under the Karnataka Stamp Act. A Karnataka High Court ad‑interim relief was granted in 2018, but the Supreme Court’s judgment focuses on the scope of judicial interference at the pre‑appointment stage. The Court reiterates a pro‑arbitration stance, noting that arbitrability/validity are generally matters for the arbitrators, with a narrow exception to cut deadwood or to refer for authoritative settlement where necessary, invoking Vidya Drolia. It also analyzes stamp duty, observing that stamp duty has been paid (albeit disputed) and that the question of the correct stamp duty may be resolved later, not as a precondition to appointing an arbitrator. Consequently, the Court appoints Justice A. V. Chandrashekara as a sole arbitrator, directs SIAC to proceed under its rules, and allows the petition in terms stated, while leaving stamp duty issues for arbitration to determine later.

2022-02-01

The State of Sikkim v. Jasbir Singh & ANR

This appeal by the State of Sikkim challenges a High Court judgment upholding a Sessions Judge’s order directing a written notice to the Army’s commanding officer to transfer the case to a court-martial. The case concerns concurrent jurisdiction between a court-martial and an ordinary criminal court under the Army Act for an offence allegedly committed by Lance Naik Jasbir Singh during active service in Sikkim, with the FIR under IPC 302 and related charges. The High Court held that the procedure under Sections 125/126 Army Act, the 1978 Rules (Rules 3-5) and CrPC Rule 475 had not been observed and that the Army authorities had exercised their discretion to prefer a court-martial; thus, the court-martial alone would have jurisdiction. The Supreme Court, however, held that the offence falls into a category with concurrent jurisdiction under Sections 69 and 70 of the Army Act, and that where there is concurrent jurisdiction, the first instance discretion to choose the forum lies with the designated officer under Section 125. In the present case there was no decision by the designated officer to institute proceedings before a court-martial, and the sequence of events showed significant cooperation with the CrPC process. Consequently, the Sessions Judge’s competence to proceed in the criminal court was not in error, the High Court’s order is set aside, and the respondent-accused is to be transferred to civil custody to face trial in the criminal court. The appeal is allowed.

2022-07-22

Hemant Kumar Verma & Ors. v. Employees State Insurance Corporation & Ors.

This writ petition concerns whether junior resident doctors in ESIC-run medical colleges should be eligible for the 50% in-service reservation for postgraduate medical courses, a benefit presently available to Insurance Medical Officers Grade-II (IMO-II) recruited through competitive selection. ESIC recruits IMO-II and provides a 50% in-service quota for PG seats; however junior residents, who complete MBBS under bond and serve as part of ESIC's residency scheme, are not deemed in-service doctors. The petitioners argued parity with IMO-II because their qualifications, duties, and work environment are similar, and urged the Court to treat them as in-service to extend the 50% reservation to their batch. ESIC contends that junior residents are contractual, bond-based appointees governed by the ESIC Residency Scheme; IMO-II is a permanent post governed by the ESIC Staff and Condition of Service Regulations 1959; the bond reduction in 2020 and the 2018/2020 memoranda cannot convert junior residents into in-service doctors. The Court relies on precedents establishing institutional preference in PG admissions—Saurabh Chaudri v. Union of India, Yatin Kuma Jasubahi v. State of Gujarat, and Pradeep Jain v. Union of India — to acknowledge the legitimacy of institutional preference, but ultimately holds that junior residents and regular ESIC doctors are distinct categories and the in-service quota cannot be equitably extended to junior residents. The petition is dismissed.