High CourtSingle JudgeAppeal allowed. Division Bench of the High Cour...

UCO Bank & Ors. v. Sushil Kumar Saha

Case / Petition Number:Civil Appeal No. 7515 of 2012
Neutral Citation:[2012] 9 S.C.R. 611

Case Details & Bench

Court
High Court
Hon'ble Judges
  • K. S. RadhaKrishnan
  • Dipak Misra
Judgment Date
2012-10-15
Court Decision / Holding
Appeal allowed. The Supreme Court held that the AGM had jurisdiction to initiate and conduct the disciplinary enquiry into the irregularities committed during the respondent’s earlier posting, in line with Regulation 5(1) and the subsequent circulars that were designed to expedite action. The judgment of the Division Bench of the High Court is set aside, and the Bank’s disciplinary action, including the order of dismissal, remains valid.
Final Disposition
Appeal allowed. Division Bench of the High Court is set aside; AGM had jurisdiction; the Bank’s disciplinary action stands.

Parties to the Case

Appellants / Petitioners

  • UCO Bank and Ors.

Respondents

  • Sushil Kumar Saha

Legal Representation & Advocates

Counsels for Petitioners

  • • Vivek Tankha
  • • Santosh Paul
  • • Sameer Sodhi
  • • Arti Singh
  • • Pooja Singh
  • • Naveen Kumar

Counsels for Respondents

  • • Soumitra G. Chaudhuri
  • • Raja Chatterjee
  • • Runa Bhuyan
  • • G. S. Chatterjee

Case Synopsis & Summary

This appeal concerns the legality of disciplinary proceedings against an officer of UCO Bank for irregularities alleged to have occurred while the respondent was posted at a branch, with the proceedings later continuing when he was under the administrative jurisdiction of another office. The central question is whether the disciplinary authority of the erstwhile place of posting can institute and complete disciplinary proceedings against an employee who has since been posted elsewhere. The Calcutta High Court, sitting as a Division Bench, quashed the proceedings, holding that the AGM (Disciplinary Authority) had no jurisdiction to initiate the enquiry because the respondent was then under the control of a different authority. The Supreme Court examines the statutory framework governing disciplinary action in the UCO Bank (Discipline and Appeal) Regulations, 1976, focusing on Regulation 5(1) which authorizes the MD or ED or other empowered authority to initiate or direct disciplinary proceedings, and Regulations 5, 6 and 18, along with the effect of the Note dated 3 August 2004 and Circular dated 11 August 2004, which sought expeditious disposal of cases. It holds that the Note and Circular are statutory instruments aiding speedy action and that the erstwhile disciplinary authority could proceed. Accordingly, the AGM’s jurisdiction is affirmed, the High Court’s quashment is set aside, and the Bank’s appeal is allowed, upholding the disciplinary action and its consequences.

Provisions of Law Cited

UCO Bank (Discipline and Appeal) Regulations, 1976 - Regulation 3(g)Regulation 4Regulation 5(1)Regulation 5(2)Regulation 5(3)Regulation 6(1)Regulation 6(2)Regulation 6(3)Regulation 18Schedule GNote dated 3 August 2004Circular dated 11 August 2004Head Office Circular CHO/PMG/4/2002Regulation 3(g)Banking Companies (Acquisition and Transfer of Undertakings) Act, 1970Section 19Section 12(2) of the Act 1970

Submissions & Arguments

Contentions of Appellants / Petitioners

The Appellant-Bank submits that the High Court erred in holding that the AGM lacked jurisdiction to initiate disciplinary proceedings against the respondent, relying on Regulations 5(1) and 6 read with Schedule. It contends that the 3 August 2004 Note and 11 August 2004 Circular, approved by the CMD and issued under Regulation 5(1), are statutory instruments intended to expedite disposal of disciplinary actions and were rightly applied to cases like the present one, where irregularities were detected after transfer of the employee. The Bank argues that the circulars and note were intended to preserve records and ensure timely action, preventing unwarranted delays, and that the new disciplinary authority could complete the proceedings efficiently without sitting in judgment on the Bank’s wisdom. The Bank also relies on Allahabad Bank v. Prem Narain Pande to argue against hyper-technical readings of the regulations and to support expediency and jurisdiction to initiate proceedings at the erstwhile place of posting.

Contentions of Respondents

The respondent contends that the AGM did not have jurisdiction to initiate disciplinary proceedings against him since he had moved under another authority after transfer, and Regulations 5(1) and 6 do not permit initiation by the AGM in the circumstances described. Relying on the Division Bench decision of the Calcutta High Court, the respondent argues that the DGM should have initiated rather than the AGM, and that the subsequent procedure was improper. The respondent further asserts that the circulars and the note cannot override the statutory framework in Regulation 5(1) and that expediency cannot trump the prescribed hierarchy and jurisdiction for disciplinary actions. He emphasizes that the High Court correctly held lack of jurisdiction and that reinstatement was warranted on that basis.

Cited Precedents (2)

Case NameCitationTreatmentExplanation
Allahabad Bank v. Prem Narain Pande and Others1995 (4) Suppl. SCR 481PositiveCited to support a non-hyper-technical reading of the disciplinary regulations and to uphold the Bank’s approach to expeditious disciplinary action.
Allahabad Bank v. Prem Narain Pande and Others1995 (6) SCC 634PositiveSame case cited to reinforce the principle of broader interpretation of the regulations in disciplinary matters.

Diagnostic Tool

Beta

Does this judgment govern your specific facts?

Don't risk relying on a distinguishable precedent. Enter your facts or proposition below. We will test it against UCO Bank & Ors. v. Sushil Kumar Saha and instantly map out authorities that support, challenge, or govern your position.

Extracted Judgment Text

Exact text extracted from official judgment records.

A [2012) 9 S.C.R. 611 ## UCO BANK & ORS. _v._ SUSHIL KUMAR SAHA (Civil Appeal No. 7515 of 2012) ## OCTOBER 15, 2012 B [K.S. RADHAKRISHNAN AND DIPAK MISRA, JJ.] ## _SERVICE LAW:_ _Disciplinary proceedings_ - _Disciplinary authority_ - _Bank_ c _Officer, transferred to Head Office stated to have committed_ - _various irregularities during his earlier posting Disciplinary authority of the erstwhile place of posting nominated to_ - _conduct disciplinary proceedings Held: The disciplinary authority was duly empowered under the relevant provision to_ D - _institute the disciplinary proceedings Court is not expected to sit in judgment over wisdom of the Bank in taking such_ a _decision which is to expedite the disciplinary proceedings_ - _Division Bench of High Court erred in quashing the proceedings. and the punishment of dismissal_ - _Impugned_ E - _order set aside UCO Bank (Discipline and Appeal) Regulations 1976_ - _Regulation_ 5 - _Note dated 3.8.2004_ - _Circular dated 11. 8. 2004._ The respondent, while working as the Senior Manager in the scale of MMGS-111, in a Branch of the UCO F Bank from 15.10.2001 to 23.8.2005, was stated to have committed serious irregularities in sanctioning loan and granting indiscriminate excess drawings and overdrawing facilities to various parties beyond his powers and without approval of the Controlling Office. G This was detected subsequently after he was transferred and posted as Senior Chief Officer at the Head Office of the Bank in August 2005. The Bank issued a charge-sheet to the respondent through the AGM (disciplinary 611 H 612 SUPREME COURT REPORTS [2012] 9 S.C.R. A authority). Ultimately, the AGM found the charges fully proved, and imposed the penalty of dismissal from service. The departmental appeal and the writ petition of the respondent were dismissed. However, the Division Bench of the High Court allowed his appeal holding that B the AGM had no jurisdiction to hold the disciplinary proceedings, and directed his reinstatement. In the instfint appeal filed by the Bank, the question for consideration before the Court was: whether the C disciplinary authority of the erstwhile place of posting, where irregularities stated to have occurred/committed, could institute and complete the disciplinary proceedings against the erring officials (both officer and award staff), notwithstanding the fact that such persons are later posted under the administrative jurisdiction of some D other authorities. ## Allowing the appeal, the Court HELD: 1.1 In the instant case, the AGM is justified in E initiating disciplinary proceedings which is in accordance with the decision dated 3.8.2004 as well as the circular dated 11.8.2004. The Note dated 3.8.2004 which was approved by CMD in exercise of the powers conferred on him under Regulation 5(1) of the UCO Bank (Discipline and Appeal) Regulations, 1976 is statutory in nature. F Regulation 5 specifically provides that the Managing· Director or the Executive Director or any other authority empowered by either of them by general or special order, may institute or direct the disciplinary authority to institute disciplinary proceedings. Further, note 2 to the Schedule G also stipulates that the powers of the specified authorities may be exercised by any other authority nominated by the Executive Director/CMD, who is equal in rank or higher than the authority specified therein. The reason for entrusting the -task of initiating the disciplinary H UCO BANK & ORS. _v._ SUSHIL KUMAR SAHA 613 proceedings on the disciplinary authority of the erstwhile A place of posting is that the new disciplinary authority might not be aware of the nature and extent of irregularities allegedly committed by the employee in his earlier place of posting, since the relevant records, documents etc. are kept in the old place of posting. The 8 Bank in its wisdom felt that such a course will expedite disposal of the disciplinary cases within the stipulated time frame. This Court is not expected to sit in judgment over wisdom of the Bank in taking such a decision which is to expedite the disciplinary proceedings. [para 18) [625C G-H; 626-A-D] A C 1.2 Consequently, the AGM who had the disciplinary control over the respondent while he was working at the Branch Office has got jurisdiction to conduct an enquiry with regard to the irregularities committed by the respondent while he was working as the Senior Manager at the Branch Office of the Bank from 15.11.2001 to 23.8.2005. The High Court has taken a narrow view while interpreting Regulation 1976, the Note dated 3.8.2004, Circular dated 11.8.2004 read with Regulation 5(1 ). Omitting to note the purpose and object of the note and the circular, that is, speedy and expeditious disposal of cases with regard to the disciplinary proceedings against erring officials, the High Court has committed an error in quashing the note as well as the circular. [para 19-20] [626-E-F-H; 627-A-B] D E F _Allahabad Bank v. Prem Narain Pande and Others_ 1995 (4) Suppl. SCR 481 = 1995 (6) SCC 634 - relied on. > 1.3 In the facts and circumstances of the case, the G > Division Bench of the High Court has committed an error in quashing the proceedings initiated by the AGM (Disciplinary Authority) and the punishment imposed. > Consequently, the judgment of the Division Bench of the High Court is set aside. [para 21) [627-B-C] H H 614 SUPREME COURT REPORTS (2012] 9 S.C.R. A Case Law Reference: 1995 (4) Suppl. SCR 481 relied on para 8 CIVIL APPELLATE JURISDICTION : Civil Appeal No. 7515 of 2012. B From the Judgment and Order dated 19.12.2011 of High Court of Calcutta in APO No. 342 of 2009. Vivek Tankha, Santosh Paul, Sameer Sodhi, Arti Singh, Pooja Singh, Naveen Kumar for the Appellant. C Soumitra G. Chaudhuri, Raja Chatterjee, Runa Bhuyan, G.S. Chatterjee for the Respondent. The Judgment of the Court was delivered by K.5. RADHAKRISHNAN, J. 1. Leave granted. 2. The question that is posed for consideration in this case D is whether the disciplinary authority of the erstwhile place of posting, where irregularities stated to have occurred/committed, could institute and complete the disciplinary proceedings against the erring officials (both officer and award staff), notwithstanding the fact that such persons are later posted E under the administrative jurisdiction of some other authorities. 3. The High Court, placing reliance on Regulations 5(1) and 6 of the UCO Bank (Discipline and Appeal) Regulations, 1976 [for short 'Regulations 1976'] read with Schedule thereto, F took the view that it was only the Deputy General Manager (for short 'DGM') who had the power to initiate disciplinary proceedings against the respondent and not the Assistant General Manager (for short 'AGM'), as per the Schedule to Regulations 1976, since at the time of initiation of proceedings he was under the jurisdiction of the DGM. The High Court, - G therefore, set aside the entire disciplinary proceedings, including the charge-sheet, enquiry report, final order of punishment and the appellate order and directed the Bank to release all the admissible service benefits and pay admissible dues to the respondent. We are, in this case, concerned with H UCO BANK & ORS. _v._ SUSHIL KUMAR SAHA 615 [K.S. RADHAKRISHNAN, J.] A the legality of the order of the High Court. 4. The Respondent joined the services of the Appellant UCO Bank (for short 'Bank') as the Field Officer on 11.11.1978. He was later promoted to the scale of MMGS-111 on 17.7.2001. Respondent functioned as the Senior Manager in the Bansdroni Branch of the Bank from 15.10.2001 to 23.8.2005. Respondent B was later transferred and posted as the Senior Chief Officer at the Head Office of the Bank situated at Kolkata in August 2005. It was then noticed that while the respondent was working as the Senior Manager at Bansdroni Branch, he had committed serious irregularities in sanctioning loan and had granted C indiscriminate excess drawings and overdrawing facilities to various parties beyond his powers and without approval from the Controlling Office. Consequently, a show-cause-notice dated 23.3.2006 was issued by the Chief Officer, Regionaf Office, Kolkata. Respondent filed his reply to the said showD cause-notice on 17.4.2006. Being dissatisfied with the reply submitted by the respondent, the Bank issued a charge-sheet along with Statement of Allegations dated 15.12.2006 through the AGM (Disciplinary Authority) to hold a domestic enquiry against the respondent in terms of Regulation 6 of the E Regulations 1976, levelling 7 charges which are extracted hereunder for easy reference: (i) that the respondent granted indiscriminate excess drawings over the sanctioned Cash Credit Limits of various parties beyond his delegated power and without F prior approval from Controlling Office; (ii) that while granting unauthorized excess drawings, the respondent concealed the said fact from the controlling office; (iii) that the respondent failed to induce the parties to observe credit discipline and indulged in granting them unauthorized accommodation detriment to the interest of the bank; G H 616 SUPREME COURT REPORTS [2012] 9 S.C.R. - A (iv) that before disbursement of credit facility, respondent did not take collateral security in respect of various cash credit borrowers violating sanction stipulation rather extended the enhanced limit in favour of the borrowers etc.; - (v) that the respondent did not take steps for creation of - B valid stipulation in various cases and failed to effectively monitor/control and supervise the following advance accounts to protect the interest of the bank; c D E - (vi) that the respondent in blatant violation of the sanctioned limits in the case of Mis J.C. Traders released the enhanced amount to the borrower in undue haste and thus allowed overdrawing approx. Rs.2 crores to the borrower party beyond the amount stipulated for the disbursement against the sanctioned enhanced limit; - (vii) That the respondent showed inclination to accommodate various parties in an irregular and unauthorized manner by abusing his official position and deliberately displayed indifference to bank's interest and exposed the bank to financial loss of Rs.598.07 lacs approx. as most of the accounts turned potential NPA/ NPA." 5. Respondent filed his reply to the said charge-sheet on 17.1.2007. The reply submitted by the respondent was considered by AGM in the capacity of the Disciplinary Authority F and he found the same unsatisfactory and decided to hold a departmental enquiry against the respondent and appointed Shri Benod Bihari Hazra, Retired Executive of the Bank as an Enquiring Authority to enquire into various charges leveled against the respondent. Detailed enquiry was conducted and, G ultimately, the enquiry report dated 12.3.2008 was submitted to the AGM. 6. AGM concurred with the findings of the Enquiring Officer in respect of the charges, including Charge No. 4, which the AGM found to be fully proved. A copy of the enquiry report was H served on the respondent, to which he filed a detailed reply. UCO BANK & ORS. _v._ SUSHIL KUMAR SAHA 617 [K.S. RADHAKRISHNAN, J.] AGM, after considering the reply submitted by the respondent, A passed final order on 19.4.2008, in exercise of his powers conferred under Regulation 4 of the Regulations 1976 and imposed penalty of dismissal from service. Aggrieved by the said order of AGM, Respondent filed an appeal before the Appellate Authority, namely DGM, Personnel Services, B Department, Head Office. Appellate authority dismissed the appeal vide its order dated 22.7.2008. 7. Aggrieved by the order of the Appellate Authority, respondent filed a writ petition No. 1546 of 2008 before the High Court of Calcutta, which was dismissed by the learned single Judge of the High Court vide its judgment dated 19.11.2009. Appeal was preferred by the respondent to the Division Bench vide A.P.O. No. 342 of 2009 and the Bench vide its judgment dated 19.12.2011 allowed the appeal holding that AGM has no jurisdiction to initiate the disciplinary proceedings. The Division Bench also directed reinstatement of the respondent into service along with all consequential benefits, against which this appeal has been preferred by the Bank. C D 8. Shri Vivek Tankha, learned senior counsel appearing for the Appellant-Bank, submitted that the High Court has committed a grave error in holding that the proceedings initiated by AGM were without jurisdiction and ordered reinstatement of the respondent with all consequential benefits. Learned senior counsel also submitted that the respondent had not challenged the validity of the Circular dated 11.8.2004 or the note dated 3.8.2004 and that the High Court, on a wrong interpretation of those provisions, took the view that AGM had no jurisdiction to act as the Disciplinary Authority. In support of his contention, learned senior counsel relied upon the judgment of this Court in Allahabad Bank v. Prem Narain Pande and Others (1995) 6 sec 634. E F G 9. Shri Soumitra G. Chaudhuri, learned counsel appearing for the respondent, submitted that AGM has no jurisdiction to act as the Disciplinary Authority over the respondent and the H 618 SUPREME COURT REPORTS [2012] 9 S.C.R. - A Division Bench of the High Court has rightly held that the entire disciplinary proceedings, starting from the charge-sheet till the dismissal of the respondent, was without jurisdiction Learned counsel, placing reliance on Regulations 5(1) and 6 of the Regulations 1976, contended that the DGM alone could have - B initiated the disciplinary proceedings against the respondent. Learned counsel, therefore, submitted that the Division Bench of the High Court has rightly quashed the entire proceedings and ordered reinstatement of the respondent with all consequential benefits. C C 10. We are, in this case, concerned only with the question whether the disciplinary proceedings were lawfully initiated by the AGM and whether power has been conferred on him to act as the Disciplinary Authority against the respondent, since the irregularities stated to have been committed while he was D working at Bansdroni Branch of the Bank. 11. Regulations 1976 was framed by the Board of Directors of the UCO Bank, in exercise of its p9wers conferred under Section 19 of the Banking Companies (Acquisition and Transfer of Undertakings) Act, 1970 (for short 'Act 1970'), in E consultation with the Reserve Bank of India and the previous sanction of the Central Government. Regulation 3(g) of the Regulations 1976 reads as under: F "Disciplinary Authority" means the authority specified in the Schedule which is competent to impose on an officer employee any of the penalties specified in regulation 4." 12. Regulation 4 deals with Minor and Major Penalties. Regulation 5 refers to the Authority to initiate disciplinary proceedings and impose penalties. Regulation 5 is extracted G hereunder for easy reference: "5. Authority to institute disciplinary proceedings and impose penalties: (1) The Managing Director or the Executive Director or any other authority empowered by either of them by general or H special order may institute or direct the Disciplinary UCO BANK & ORS. _v._ SUSHIL KUMAR SAHA 619 [K.S. RADHAKRISHNAN, J.] Authority to institute disciplinary proceedings against an A officer employee of the bank. > (2) The Disciplinary Authority may himself institute disciplinary proceedings. (3) The Disciplinary Authority or any authority higher than it, may impose any of the penalties specified in regulation B 4 on any officer employee." (emphasis added) Regulations 6(1) and (2) deal with the procedure for imposing major penalties and they are as follows: c "6. Procedure for imposing major penalties: ( 1) No order imposing any of the major penalties specified in clauses (f), (g), (h), (i) and 0) of regulation 4 shall be made except after an inquiry is held in accordance with this regulation. D (2) Whenever the Disciplinary Authority is of the opinion that there are grounds for inquiring into the truth of any imputation of misconduct or misbehavior against an officer employee, it may itself enquire imo, or appoint any other public servant (hereinafter referred to as the inquiring E authority) to inquire into the truth thereof." 13. Regulation 18 (unamended) deals with Review and the same reads as follows: "18. Review: Notwithstanding anything contained in these regulations, the Reviewing Authority may call for the record of the case within six months of the date of the final order and after reviewing the case pass such orders thereon as it may deem fit. Provided that - (i) If any enhanced penalty, which the Reviewing Authority proposes to impose, is a major penalty specified in clauses (f), (g), (h), (i) or (j) of regulation 4 and an enquiry as provided under regulation 6 has not already been held F G H 620 SUPREME COURT REPORTS [2012] 9 S.C.R. A in the case, the Reviewing Authority shall direct that such an enquiry be held in accordance with the provisions of regulation 6 and thereafter consi.der the record of the enquiry and pass such orders as it may deem proper; - (ii) If the Reviewing Authority decides to enhance the - B punishment but an enquiry has already been held in accordance with the provisions of regulation 6, the Reviewing Authority shall give show cause notice to the officer employee as to why the enhanced penalty should not be imposed upon him and shall pass an order after - c taking into account the representation, if any, submitted by the officer employee." 14. The Board of Directors of UCO Bank, in exercise of its powers conferred under Section 19 read with sub-section (2) of Section 12 of the Act 1970, approved the amendment to D Regula.tion 18 and the Schedule to the Regulations 1976, in consultation with the Reserve Bank of India and with previous sanction of the Central Government, and a circular No. CHO/ POS/11/2002 dated 4.4.2002 to that effect was issued and sent by the Bank to all branches/office, the operative portion of E the same reads as follows: "In the UCO Bank Officer Employees (Discipline and Appeal) Regulatibns, 1976. (a) For regulation 18, the following regulation shall be substitute? namely: F G H 18. Review Notwithstanding anything contained in these regulations, the Reviewing Authority may at any time within six months from the date of the final order, either on his own motion or otherwise review the said order, when any new material or evidence which could not be produced or was not available at the time of passing the order under review and which was the effect of changing the nature of the case has come or has been brought to his notice and pass such orders thereon as it may deem fit. 621 # UCO BANK & ORS. _v._ SUSHIL KUMAR SAHA [K.S. RADHAKRISHNAN, J.] xxx )()(){ xxx xxx )()(){ xxx A The existing schedule, the following schedule shall be substituted namely: ||substituted namely:y::|||| |---|---|---|---|---| |a.|Scale/<br>category<br>of post|Disciplinary Appellate Reviewing<br>authority|Disciplinary Appellate Reviewing<br>authority authority|Disciplinary Appellate Reviewing<br>authority authority| ||xxx|xxx|xxx|xxx| |b)|OfficersinMMG/Scale<br>Ill&officersinGrade<br>B posted at Branches/<br>Offices under jurisdi-<br>ction of Regional Offices respective<br>headed by Regional<br>ManagerinSenior<br>Management Grade/<br>Scale IV/ Grade A<br>including officers sent<br>ondeputation|Asst. Gen.<br>Manager<br>attached to<br>office of<br>ction of Regional Offices respective<br>General<br>Manager<br>(Operations)|General<br>Manager|E.D.| ||xxx|xxx|xxx|xxx| |c|Posted at Head office<br>or any other office/<br>establishment coming<br>under direct control of<br>Head Office including<br>the regional Rural<br>Banks/ Regional Train-<br>ing Centres/Central Staff<br>college and officers sent<br>ondeputation&<br>inspectingofficers|Dy.General<br>Manager<br>(Personal)|G.M.<br>(Pers)|E.D.| ||xxx|xxx|xxx|xxx| Note- 1. Where a post of any of the above said authorities remains vacant without officiating/ acting arrangement having been authorized, the powers H 622 SUPREME COURT ~EPORTS (2012] 9 S.C.R. ## A ## B should be exercised by the next higher authority. 2. The powers of any of the above specified authorities may be exercised by any other authority nominated by the Executive Director/Chairman & Managing Director who is equal in rank to or higher than the authority specified above. The amendments to the above regulation and to the schedule came into force w.e.f. 9.2.2002." 15. The Top Management Committee (for short 'TMC') of C the Bank convened its 11th Meeting on 26.6.2004 at Bank's Head Office at Calcutta and the necessity of expeditious disposal of disciplinary cases was discussed in that meeting., though it was not minuted in the proceedings, says the learned senior counsel appearing on behalf of the Bank. Following the TMC meeting held on 26.6.2004, an Inter Departmental Note - D dated 3.8.2004 was placed by the GM (Personnel) of the Bank before the Chairman and Managing Director (for short 'CMD') referring to the decision taken for expeditious disposal of disciplinary cases, the operative portion of the same reads as follows: - E "NOTE TO CHAIRMAN & MANAGING DIRECTOR - Sub: Expeditious disposal of disciplinary action cases - decision taken in the TMC meeting dated 26.06.2004 - In terms of existing Schedule of Disciplinary Authorities, - F consequent upon transfer of any employee (both officer and Award staff) from one region to another, the disciplinary authority changes. As per Head Office Circular No. CHO/PMG/4/2002 dated 16.1.2002 with the transfer of a charge sheeted- employee (both officer and award - G staff), the disciplinary authority over him will remain the same and the said disciplinary authority would complete the RDA cases, irrespective of the fact that the charge sheeted employee has been transferred. This order has been made effective from 1.2.2002. In terms of the above - H circular, however, if the irregularity is detected after the UCO BANK & ORS. _v._ SUSHIL KUMAR SAHA 623 [K.S. RADHAKRISHNAN, J.] transfer of the employee, the disciplinary authority at the A new place of posting will take appropriate action. In view of the above, it has been observed that delay occurs in the matter of initiating appropriate action including disciplinary action against the erring employees. who had committed irregularities in his earlier place of posting. Therefore, the TMC in its meeting held on 26.6.2004 decided that henceforth the disciplinary authority of erstwhile place of posting where the irregularities took place. will institute and complete the RDA against the erring official (both officer and award staffi considering the nature and extent of irregularities as the relevant records are readily available with them. B C Accordingly, Personnel Department, Head Office proposes to issue a Circular which would be made effective from 16.8.2004, in compliance with the above directives of TMC, a copy of which is enclosed for kind perusal and approval." D (emphasis added) E 16. The note was perused and approved by the CMD of the Bank on 10.8.2004 in exercise of his powers conferred under Regulation 5( 1) of the Regulations 1976. On the next day, i.e. 11.8.2004, the General Manager (Personnel) of the Bank issued a Circular No. CHO/PMG/22/2004 to all the branches for expeditious disposal of disciplinary cases stating, inter alia, as follows: F "As the new disciplinary authority is not naturally aware of the nature and extent of irregularities allegedly committed G by the employee in his earlier place of posting and relevant records _I_ documents etc. are kept in the old place of posting, it was decided vide Bank's Circular No. ·cHO/ PMG?4/2002 dated 16.1.2002 that with the transfer of a charge sheeted employee (both officer _I_ award staff) the H G SUPREME COURT REPORTS [2012] 9 S.C.R. 624 A B c D E F G H disciplinary authority over him would remain the same and the said DA would complete the RDA case irrespective of the fact that the charge sheeted employees has been transferred. The operation of the circular was made effective from 1.2.2002. However the provision of this circular was not made applicable for employees, in whose cases the irregularities were detected subsequently and no appropriate steps for such irregularities which warrant timely action including disciplinary action against the erring officials, often gets delayed as neither the new disciplinary authority nor the old office/branch from where the employee has been transfers, takes proper care to facilitate initiation of RDA and expeditious disposal of the same. The matter was thoroughly discussed in the Top Management Committee in meeting dated 26.6.2004. _To obviate delay in initiation of RDA and conclusion of the same, due to change of disciplinary authority consequent upon transfer of the employee, against whom lapses are attributable for his irregular action in earlier place of posting, the committee decided that henceforth, in terms of bank's circular No. CHOIPAS/212000 dated 23.6.2000 for Award staff and CHO!POS/1112002 dated 4.4.2002 for officers, the disciplinary authority of erstwhile place of posting, where irregularities occurred/committed, will institute and complete the RDA against the erring officials (both officer and award staff), considering the nature and extent of the irregularities on case to case basis, notwithstanding such employees are presently posted under the administrative jurisdiction of some other authorities._ Similarly, the appellate authorities of earlier place of posting of the erring official (both officer and award staff) would take steps for disposal of the appeals preferred against the final orders passed by such disciplinary authorities. This decision has been taken keeping in view the position that the earlier disciplinary authority/appellate authority is better aware of the facts and UCO BANK & ORS. _v._ SUSHIL KUMAR SAHA 625 [K.S. RADHAKRISHNAN, J.] circumstances of such cases and the relevant documents/ A records are readily available in the eariier place of posting. We feel that the above revised guidelines will expedite disposal of RDA cases within the stipulated time frame of four and six months for non vigilance and vigilance cases respectively as directed by the DPC. B The disciplinary authorities/appellate authorities are advised to note this changes for strict compliance, which would come into operation w.e.f. 16.8.2004. Existing cases, where charge sheets _I_ letters of imputations or C lapses have already been issued, will however, not be affected by the operation of this circular. A copy of this circular should be displayed on the notice board for the information of all concerned." (emphasis added) D 17. We have already indicated that the respondent was working as the Senior Manager at Bansdroni Branch of the Bank from 15.10.2001 to 23.8.2005 and the irregularities were committed or occurred while he was working at that branch of E the Bank and the respondent was later transferred to the Head Office on August 2005. While he was working at the Head Office, the Bank came to know of the irregularities committed by him while he was working at the Branch Office of the Bank during the above mentioned period. Consequently, disciplinary proceedings were initiated against him and a charge-sheet F dated 15.12.2006 was issued to him by AGM following the above mentioned circular dated 11 .. 8.2004, which conferred powers on AGM since the irregularities occurred or committed when he was functioning at the Branch Office. G 18. In the instant case, however, AGM is justified in initiating disciplinary proceedings which is in accordance with the decision dated 3.8.2004 as well as the circular dated 11.8.2004. The Note dated 3.8.2004 which was approved by CMD in exercise of the powers conferred on him under H [2012] 9 S.C.R. SUPREME COURT REPORTS 626 A Regulation 5(1) is statutory in nature. Regulation 5 specifically empowers the Managing Director or the Executive Director or any other authority empowered by either of them by general or special order, may institute or direct the disciplinary authority to institute disciplinary proceedings. Further, note 2 to the B schedule also stipulates that the powers of the specified authorities may be exercised by any other authority nominated by the Executive _I_ CMD, who is equal in rank or higher than the authority specified therein. The reasons for entrusting the task of initiating the disciplinary proceedings on the disciplinary C authority of the erstwhile place of posting is that the new disciplinary authority might not be aware of the nature and extent of irregularities allegedly committed by the employee in his earlier place of posting,· since the relevant records, documents etc. are kept in the old place of posting. The Bank in its wisdom felt that such a course will expedite disposal of 0 the disciplinary cases within the stipulated time framed. This Court is not expected to sit in judgment over wisdom of the Bank in taking such a decision which is to expedite the disciplinary proceedings. E 19. Consequently, the AGM who had the disciplinary control over the respondent while he was working at the Branch Office has got jurisdiction to conduct an e:iquiry with regard to the irregularities committed by the respondent while he was working as the Senior Manager at the Branch Office of the F Bank from 15.11.2001 to 23.8.2005. We may indicate that in Allahabad Bank (supra), this Court while interpreting the provisions of Regulations 3, 4, 5(1) & (2), 6(3), 21 (ii) and 7(3) of the Allahabad Bank (Discipline and Appeal) Regulations, 1976, held that the High Court has taken too narrow a view of G the controversy posed before it and has set aside the dismissal on too hyper-technical a view which cannot be sustained on the scheme of the Regulations. H 20. We are of the view that, in this case also, the High Court has taken a narrow view while interpreting Regulation UCO BANK & ORS. _v._ SUSHIL KUMAR SAHA 627 (K.S. RADHAKRISHNAN, J.] 1976, the Note dated 3.8.2004, Circular dated 11.8.2004 read A with Regulation 5(1). Omitting to note its purpose and object, that is speedy and expeditious disposal of cases with regard to the disciplinary proceedings against erring officials, the High Court has committed an error in quashing the note as well as the circular. B B 21. In the facts and circumstances of the case, we are of the view that the Division Bench of the High Court has committed an error in quashing the proceedings initiated by the AGM (Disciplinary Authority) and the punishment imposed. C Consequently, the appeal is allowed and the judgment of the Division Bench of the High Court is set aside. R.P. Appeal allowed.