TUKARAM S/O SADASHIV CHAUDHARI v. THE EXECUTIVE ENGINEER, MAHARASHTRA STATE ELECTRICITY DISTRIBUTION COMPANY LTD. & ANR.

Case / Petition Number:
Civil Appeal No. 3578 of 2019
Neutral Citation:[2019] 5 S.C.R. 765

Case Synopsis & Summary

This Supreme Court decision arises from a consumer dispute where Tukaram S/o Sadashiv Chaudhari, an agriculturist, challenged the delay in obtaining an electricity connection for a bore well on agricultural land in Nandurbar, Maharashtra. The appellant applied for a connection on 26 December 1996 and deposited charges, but bills for consumption were raised between September and December 2005 despite no connection having been installed. He filed a consumer complaint in July 2006; the District Consumer Disputes Redressal Forum partly allowed relief, directing payment of certain amounts and ordering the connection. The State Commission reversed, and the National Consumer Disputes Redressal Commission (NCDRC) confirmed a Rs 2,00,000 compensation on revision. The appellant contends that the delay—nearly nineteen years from application to connection granted on 4 September 2015—caused substantial hardship by preventing irrigation. The respondent contends the delay was due to the appellant’s failure to submit a required test report, with a 2007 order establishing that the delay was partly the appellant’s fault; a Bombay High Court order in 2015 and subsequent events led to the grant of a connection. The Supreme Court holds that the delay caused undue hardship justifying enhanced compensation and ultimately allows the appeal, increasing compensation to Rs 5,00,000 with four weeks to pay and 9% interest on default, while denying costs.

Precedent Explorer

Find Cases Like This

Explore other judgments dealing with similar legal situations, facts, or statutory provisions.

Case Details & Bench

Court
Supreme Court of India
Hon'ble Judges
  • Dr. Dhananjaya Y. Chandrachud
  • Hemant Gupta
Judgment Date
2019-04-08
Court Decision / Holding
The civil appeal is allowed. The compensation awarded by the NCDRC is enhanced from Rs 2,00,000 to Rs 5,00,000, to be paid within four weeks from today. If payment is delayed, interest at 9% per annum shall accrue. No costs.
Final Disposition
Appeal Allowed

Parties to the Case

Appellants / Petitioners

  • Tukaram S/o Sadashiv Chaudhari

Respondents

  • The Executive Engineer, Maharashtra State Electricity Distribution Company Ltd.
  • Anr.

Legal Representation & Advocates

Counsels for Petitioners

  • • Vinay Navare, Senior Counsel
  • • Gwen Karthika, Advocate
  • • Abha R. C Sharma, Advocate

Counsels for Respondents

  • • Neetika Sharma (for M/S. M. V. Kini & Associates)

Provisions of Law Cited

Consumer Protection Act, 1986Indian Penal Code: Sections 166, 167, 384, 420, 465, 468, 471, 477A and 34Information Technology Act, 2002

Legal Doctrines & Maxims

  • Just and fair compensation
  • Hardship and inconvenience as a ground for compensation
  • Deficiency in service (consumer protection doctrine)
  • Delay by service provider not to be permitted without cogent explanation

Submissions & Arguments

Contentions of Appellants / Petitioners

The appellant contends that an agriculturist was left in lurch for nearly nineteen years after submitting an application for electricity, with the complaint that the respondent falsely claimed the connection had already been granted. He emphasizes the delay was arbitrar,’ resulting in inability to irrigate his land via bore well and causing substantial hardship. He argues that the NCDRC’s Rs 2,00,000 is inadequate and that a fair compensation should reflect the prolonged deprivation and its effects, supported by the Bombay High Court’s 2015 order ordering connection by September 2015.

Contentions of Respondents

The respondent contends the delay was attributable to the appellant’s failure to submit the required test report despite public notices; the District Forum’s findings were correct in limiting liability to the period after the test report was submitted; the NCDRC’s Rs 2,00,000 was reasonable; reliance is placed on the 2015 Bombay High Court order and on the alleged 2007 undertaking. The counterargument emphasizes that the connection could not be granted solely due to the appellant’s inaction until 2007 and that the undertaking content is disputed.

Legal Doctrine & Issue Explorer

Explore This Legal Issue

Find relevant judgments and authoritative positions on the legal questions discussed here.

Cited Precedents (1)

Case NameCitationTreatmentExplanation
Criminal Writ Petition No. 247 of 2005Criminal Writ Petition No. 247 of 2005Mentioned OnlyCited to reference a Bombay High Court order connected with the timeline of the connection; not a binding precedent in the Supreme Court's reasoning in this appeal.
Case Applicability Diagnostic

Apply This to My Facts

Share your situation and test whether this judgment governs, supports, or challenges your case.

Official Judgment Record
•2,155 words•~10 min read

In The Court Record

TUKARAM S/O SADASHIV CHAUDHARI v. THE EXECUTIVE ENGINEER, MAHARASHTRA STATE ELECTRICITY DISTRIBUTION COMPANY LTD. & ANR.

765 # [2019] 5 S.C.R. 765 # TUKARAM S/O SADASHIV CHAUDHARI A v. THE EXECUTIVE ENGINEER, MAHARASHTRA STATE ELECTRICITY DISTRIBUTION COMPANY LTD. & ANR. (Civil Appeal No. 3578 of 2019) B APRIL 08, 2019 ## **[DR. DHANANJAYA Y CHANDRACHUD AND** ## **HEMANT GUPTA, JJ.]** _Consumer Protection Act, 1986 – Appellant, an agriculturist_ C _held agricultural land – For a bore well to be dug on the land, appellant applied for electricity connection to the respondent on 26 Dec. 1996 and deposited the requisite charges – Respondent raised bill for consumption charges between 30 Sep. 2005 and 31 Dec. 2005 – Appellant filed complaint before District Consumer_ D _Disputes Redressal Commission claiming that no electricity connection had been installed– Complaint allowed– State Consumer Disputes Redressal Commission reversed the order – National Consumer Disputes Redressal Commission (NCDRC) dismissed the revision – Appellant filed review petition, which was allowed – Compensation of Rs 2,00,000/- granted to the appellant – Plea of_ E _appellant that he was left in lurch for nearly nineteen years after the submission of application for the grant of electricity connection as the same was granted only on 4 Sep.2015 hence, the compensation granted does not meet the requirement of fair compensation – Held: Appellant applied for electricity connection in Dec.1996, however_ F _submitted a test report, required for obtaining such connection, only in March 2005 – Respondent cannot be faulted for the delay which occurred between the date of the submission of the application and until the appellant complied with the requirement of submitting the test report on 24 March 2005 – No cogent explanation on the part of the respondent as to why a decade thereafter elapsed before the_ G _electricity connection was granted to the appellant on 4 Sep.2015 – After the submission of the test report, no further steps were required to be carried out by the appellant – Appellant suffered hardship and inconvenience as a result of an unexplained delay of a decade on the part of the respondent(s) in granting the electricity_ D G H 765 766 SUPREME COURT REPORTS [2019] 5 S.C.R. - A _connection – Compensation granted by NCDRC not adequate to meet the requirement of just and fair compensation – Compensation enhanced to Rs.5,00,000/-, be paid within four weeks from today – In default, the compensation to carry interest at the rate of 9 % p.a._ CIVIL APPELLATE JURISDICTION : Civil Appeal No. 3578 B of 2019. From the Judgment and Order dated 06.06.2016 of the National Consumer Disputes Redressal Commission, New Delhi in Review Application No. 98 of 2016 in Revision Petition No. 1737 of 2014. Vinay Navare, Sr. Adv., Ms. Gwen Karthika, Ms. Abha R. C Sharma, Advs. for the Appellant. Ms. Neetika Sharma (for M/S. M. V. Kini & Associates), Adv. or the Respondents. The following Order of the Court was passed: D ## **ORDER** 1. Leave granted. ## E F G 2. This appeal arises from a decision of the National Consumer Disputes Redressal Commission[1] dated 6 June 2016 by which compensation of Rs 2,00,000 has been granted to the appellant. 3. The appellant who is an agriculturist holds agricultural land bearing Gat No. 258/1B admeasuring five Hectares and fifteen Ares situated at Mauje Bamkheda Taluka Shahada, District Nandurbar, Maharashtra. The appellant caused a bore well to be dug on the land. He then applied for an electricity connection to the respondent on 26 December 1996 and deposited charges of Rs 2,620. On 31 July 2004, he deposited a further sum of Rs 2,250 towards meter charges. 4. The respondent raised a bill for consumption charges between 30 September 2005 and 31 December 2005 amounting to Rs 1,380. The appellant claimed that no electricity connection had been installed. 5. In these circumstances, he filed a consumer complaint on 14 July 2006 before the District Consumer Disputes Redressal Forum, Nandurbar[2] . 1(“NCDRC”) H - 2“District Forum” TUKARAM S/O SADASHIV CHAUDHARI v. THE EXECUTIVE 767 ENGINEER, MAH. STATE ELECTRICITY DIST. CO. LTD. 6. In the written statement, the case of the respondent was that A an electricity connection was granted to the appellant. The respondent stated that after applying for a connection in 1996 for the grant of an electricity connection, the appellant did not submit a test report in spite of a public notice dated 7 July 2004. This had resulted in delay, which was attributable to the appellant. Evidently, the test report was received B by the respondent on 24 March 2005. According to the respondent, after the receipt of the report, the work of issuing electricity bills was going on and a bill was issued to the appellant. In the circumstances, it was submitted that the delay in the grant of an electricity connection to the appellant was on account of the default of the appellant since it was only in March 2005 that the test report was submitted. C 7. The District Forum by its order dated 24 January 2007 allowed the complaint in the following terms: “1) The complaint of the complainant is partly allowed and the opponents shall pay to the complainant the amount of Rs 4870 (in words Rupees Four Thousand Eight Hundred Seventy Only) plus the expenditure of borewell of Rs 30,000/- [in words Rupees Thirty Thousand only], so also the amount of Rs 1,00,000/- [in words Rupees One Lakh Only] towards physical, mental agony and financial loss, thus total Rs. 1,34,870/- [in words Rupees One Lakh Thirty Four Thousand Eight Hundred Seventy Only] on or before 22.2.2007, failing which the complainant shall be entitled to recover the said amount together with interest @ 12% p.a. from 22.2.2007 till realization of the said amount. [2] The opponent should give electricity connection to the complainant as per rules before 22.2.2007 on getting compliance of necessary amount of documents, failing which the complainant will be entitled to recover the amount of Rs. 11,34,870/- [in words Rs. Eleven Lakhs Thirty Four Thousand Eight Hundred Seventy only] as demanded by him in his complaint.” 8. In appeal, the State Consumer Disputes Redressal Commission[3] reversed the order of the District Forum on 19 December 2013. The SCDRC held that though the appellant had applied for an electricity connection in 1996, he did not submit a test report. The SCDRC held that at the highest, the respondent could be held liable for a deficiency in service as the electricity connection was not given even after 2007. Yet the appeal was allowed and the complaint was, in consequence, dismissed. D E F G H 768 SUPREME COURT REPORTS [2019] 5 S.C.R. - A 9. When the appellant carried the matter to the NCDRC, the revision was initially dismissed. However, the appellant filed a review petition. The Review Petition was allowed and a compensation of Rs 2,00,000 was awarded to the appellant. 10. Mr. Vinay Navare, learned senior counsel appearing on behalf B of the appellant submits that this is a case where an agriculturist was left in the lurch for nearly nineteen years after the submission of an application for the grant of an electricity connection. It was urged that in the written statement, a false stand was taken by the respondent to the effect that the electricity connection had already been granted. The fact of the matter is that it was only when the High Court of Judicature at Bombay C passed an order on 14 August 2015 in Criminal Writ Petition No. 247 of 2005 that the connection was granted on 4 September 2015. Hence, it was urged that a case for the grant of compensation was made out since the appellant was disabled from using his bore well in the absence of electricity. The purpose of having a bore well was defeated as a D consequence of which the land of the appellant could not be irrigated. The damage which was sustained by the appellant, was in the submission, liable to be compensated. The award of Rs 2,00,000, it was urged, does not meet the requirement of fair compensation. 11. On the other hand, learned counsel appearing on behalf of the E respondent submitted that it was the failure of the appellant to submit a test report for nearly eight years after the submission of the application that led to a delay in the grant of an electricity connection. Reliance was placed on an undertaking alleged to have been issued by the appellant on 2 February 2007 to the effect that he had been granted a connection for the purposes of the bore well after the order of the District Forum (On F this aspect, Mr. Navare, learned senior counsel has pointed out that the alleged undertaking has been produced for the first time before this Court in the counter affidavit and was not either pleaded or set up in the proceedings before the District Forum.) 12. The facts as they emerge from the record indicate that the G appellant had initially applied for an electricity connection in December 1996. The appellant, however, submitted a test report, which is a requirement for obtaining such a connection, only in March 2005. Hence, the respondent cannot be faulted for the delay which occurred between - H 3“SCDRC” TUKARAM S/O SADASHIV CHAUDHARI v. THE EXECUTIVE 769 ENGINEER, MAH. STATE ELECTRICITY DIST. CO. LTD. the date of the submission of the application and until the appellant complied with the requirement of submitting a test report. A 13. But the fact of the matter is that the test report was submitted on 24 March 2005. There is no cogent explanation on the part of the respondent as to why a decade thereafter elapsed before the electricity connection was granted to the appellant. As a matter of fact, a criminal B complaint was lodged by the appellant. Criminal Writ Petition No. 247/ 2015 was instituted by the Executive Engineer of the respondent. On 14 August 2015, a Division Bench of the Bombay High Court, while quashing the complaint, passed the following order: “The learned counsel appearing for the petitioners, on instructions of Assistant Engineer i.e. petitioner no. 2, makes a statement that, by 5[th] September, 2015 the new meter with electric supply will be supplied in agricultural field of Respondent no. 1 i.e. in Gut No. 258/1B at Bamkheda Shivar, Tq. Shahada, Dist. Nandurbar. The earlier electricity bills will be treated as ‘Zero’. 2. In the light of statement of the learned Advocate appearing for the petitioners, the learned counsel appearing for Respondent No. 1, on instructions of Respondent No. 1, submits that, the Respondent No. 1 has no objection, if the Petition is allowed and the proceedings in R.C.C. No. 4/2015 pending on the file of J.M.F.C. Shahada are quashed and set aside along with Crime No. 1/2015 under Sections 166, 167, 384, 420, 465, 468, 471, 477A and 34 of I.P.C. r/w Section 66D of Information Technology Act, 2002 registered with Sarangkheda Police Station, Dist. Nandurbar. 3. In the light of above, the proceedings in R.C.C. No. 4/2015 pending on the file of J.M.F.C. Shahada and Crime No. 1/2015 under Sections 166, 167, 384, 420, 465, 468, 471, 477A and 34 of I.P.C. r/w Section 66D of Information Technology Act, 2002 registered with Sarangkheda Police Station, Dist. Nandurbar are quashed and set aside. The Petition stands allowed in above terms.” C D E F G 14. The above order indicates that a statement was made on behalf of the respondents that a new meter with electricity supply will be provided to the agricultural field of the appellant on 5 September 2015. Such an exercise was carried out on 4 September 2015. H 770 SUPREME COURT REPORTS [2019] 5 S.C.R. A B 15. In this background, we are of the view that the appellant has suffered hardship and inconvenience as a result of an unexplained delay of one decade on the part of the respondent(s) in granting an electricity connection. After the submission of the test report, no further steps were required to be carried out by the appellant. The appellant evidently required an electricity connection for the purpose of activating the bore well for supplying water to his agricultural fields. 16. In our view, having regard to the above facts and circumstances of the case, the grant of compensation by the NCDRC in the amount of Rs 2,00,000 will not be adequate to meet the requirement of just and fair compensation to a consumer who has suffered as a consequence of the C default of the respondent. D 17. We accordingly, enhance the compensation which has been awarded by the NCDRC to an amount of Rs 5,00,000 which shall be paid over within a period of four weeks from today. In default, the compensation shall carry interest at the rate of 9 per cent per annum. 18. The civil appeal is allowed in these terms. No costs. 19. Pending application(s), if any, shall stand disposed of. Divya Pandey Appeal allowed. E F G H
End of Judgment Record
Browse All Supreme Court of India (2019) Decisions
2019-09-03

Uber India Systems Pvt. Ltd. v. Competition Commission of India & Ors.

Uber India Systems Pvt. Ltd. v. Competition Commission of India & Ors. concerns allegations that Uber, in its ride‑hailing network, abused a dominant position under the Competition Act, 2002. The case arose on appeals challenging the Competition Appellate Tribunal’s order in Appeal No. 31 of 2016, which upheld the Director General’s inquiry into whether Uber’s pricing and incentive practices violated Section 4. The Supreme Court analysed whether the information before it sufficed to constitute a prima facie case under Section 26(1) and whether there was abuse of a dominant position in the National Capital Region. It focused on the two ingredients for abuse: the existence of a dominant position and its misuse. The court considered, based on a statement summarizing driver incentives and a period when Uber reportedly paid high incentives to fleet owners, that Uber may have pursued a pricing strategy that would affect its competitors. Under Section 4(2)(a), abuse includes an unfair price, including predatory pricing. The Court accepted that there is a prima facie case for infringement, yet did not itself interfere with the Appellate Tribunal’s order and dismissed the appeals. It directed the Director General to complete the investigation within six months from today.

2019-07-19

STATE OF BIHAR & ORS. v. DR. CHAITRAYA KUMAR SINGH & ORS.

This civil appeal concerns the reorganization of the erstwhile Bihar into Bihar and Jharkhand in 2000 and the post-allocation transfer of an employee. The first respondent, Dr. Chaitraya Kumar Singh, was initially allocated to Jharkhand in 2007 as an Ayurvedic Medical Officer and, following Union guidelines permitting transfer after final allocations, was re-allocated to Bihar on 6 September 2010 with mutual consent of both States. Bihar issued formal orders, and the respondent joined Jharkhand in 2007; however, he remained in Jharkhand and continued to work there until his retirement on 30 April 2017. A few days before retirement, he filed a writ petition in Jharkhand seeking relief to join Bihar and to be relieved by Jharkhand so that Bihar could accept joining. The Jharkhand High Court confirmed a Single Judge’s order directing Bihar to absorb him. The appellants contend that after the 2010 allocation there was no vacancy, the respondent did not pursue available remedies promptly, and seven years of service in Jharkhand after allocation render absorption in Bihar inappropriate. The Court agrees, noting the allocation to Bihar continued to hold and the petitioner failed to pursue remedies in time; his superannuation in Jharkhand eliminates the basis for absorption. The relieving order issued post-retirement is irrelevant. The appeal is allowed, the High Court’s order set aside, and there shall be no costs; pending applications are disposed.

2019-01-07

PUNJAB FINANCIAL CORPORATION v. M/S PAULBRO LEATHERS PVT. LTD.

Punjab Financial Corporation (lender) filed against Paulbro Leathers Pvt. Ltd. after Paulbro defaulted on a loan. The dispute was settled under the Corporation’s One Time Settlement (OTS) policy on 01.04.2003, and a court-ordered reference to a Chartered Accountant (CA) was made to determine the remaining outstanding balance. After the CA submitted his report, a new dispute arose about the precise liability and how much had been paid, prompting the Corporation to issue a demand for Rs. 49,86,713 which Paulbro disputed in a writ petition before the Punjab and Haryana High Court. The High Court allowed the petition on the ground that the entire exercise had been carried out with consent and no objection had been raised, effectively barring re-opening of the settlement. The appellant challenged these rulings in this Court. The Supreme Court held that the settlement created a fresh dispute arising out of its terms and that the matter must be decided on its merits under the law. It emphasized that the High Court should record how and on what basis Paulbro satisfied the settlement and discharged liability, and if needed, refer the report to another CA. The Court remanded the case to the High Court to decide the writ petition afresh on merits, with a directions to decide expeditiously (preferably within six months).

2019-12-06

RAJESH KUMAR DWIVEDI v. STATE OF U.P. & ANR.

Rajesh Kumar Dwivedi challenges the rejection of his candidature for the post of Instructor in Fitter at Government Industrial Training Institutes in Uttar Pradesh. An advertisement of 17 March 2008 required candidates to possess a certificate in the respective trade from the NCVT, in addition to experience. Dwivedi possessed three National Trade Certificates from Model Industrial Training Institute, Haldwani (one-year basic training in Mechanical, six-month Fitter General module, six-month Metrology and Engineering Inspection), but did not hold a two-year NCVT certificate. The High Court had dismissed his writ petition, holding that three separate courses could not be treated as equivalent to the NCVT qualification. Dwivedi relied on (i) the 16 December 1983 circular clarifying equivalence between the Restructured and Conventional patterns of the Craftsmen Training Scheme, and (ii) 1988 and 1992 UP circulars recognizing MITI, Haldwani training as equivalent to NCVT, including a two-year Fitter trade certificate. The State argued that the amended UP ITI Rules require NCVT certification and that the reliance on circulars cannot override the Rules. The Supreme Court held that the eligibility condition is to have a certificate in the respective trade from NCVT, and that if the State had earlier treated certain qualifications as equivalent through its circulars, such equivalence cannot be disregarded. Consequently, the appellant’s candidature could not be validly rejected, and the State was directed to appoint him within two months. The decision underscores how State-issued equivalence can complement or override rigid Rule-based qualifications when consistently recognized.