TUKARAM S/O SADASHIV CHAUDHARI v. THE EXECUTIVE ENGINEER, MAHARASHTRA STATE ELECTRICITY DISTRIBUTION COMPANY LTD. & ANR.
Case Synopsis & Summary
This Supreme Court decision arises from a consumer dispute where Tukaram S/o Sadashiv Chaudhari, an agriculturist, challenged the delay in obtaining an electricity connection for a bore well on agricultural land in Nandurbar, Maharashtra. The appellant applied for a connection on 26 December 1996 and deposited charges, but bills for consumption were raised between September and December 2005 despite no connection having been installed. He filed a consumer complaint in July 2006; the District Consumer Disputes Redressal Forum partly allowed relief, directing payment of certain amounts and ordering the connection. The State Commission reversed, and the National Consumer Disputes Redressal Commission (NCDRC) confirmed a Rs 2,00,000 compensation on revision. The appellant contends that the delay—nearly nineteen years from application to connection granted on 4 September 2015—caused substantial hardship by preventing irrigation. The respondent contends the delay was due to the appellant’s failure to submit a required test report, with a 2007 order establishing that the delay was partly the appellant’s fault; a Bombay High Court order in 2015 and subsequent events led to the grant of a connection. The Supreme Court holds that the delay caused undue hardship justifying enhanced compensation and ultimately allows the appeal, increasing compensation to Rs 5,00,000 with four weeks to pay and 9% interest on default, while denying costs.
Find Cases Like This
Explore other judgments dealing with similar legal situations, facts, or statutory provisions.
Case Details & Bench
- Court
- Supreme Court of India
- Hon'ble Judges
- Dr. Dhananjaya Y. Chandrachud
- Hemant Gupta
- Judgment Date
- 2019-04-08
- Court Decision / Holding
- The civil appeal is allowed. The compensation awarded by the NCDRC is enhanced from Rs 2,00,000 to Rs 5,00,000, to be paid within four weeks from today. If payment is delayed, interest at 9% per annum shall accrue. No costs.
- Final Disposition
- Appeal Allowed
Parties to the Case
Appellants / Petitioners
- Tukaram S/o Sadashiv Chaudhari
Respondents
- The Executive Engineer, Maharashtra State Electricity Distribution Company Ltd.
- Anr.
Legal Representation & Advocates
Counsels for Petitioners
- • Vinay Navare, Senior Counsel
- • Gwen Karthika, Advocate
- • Abha R. C Sharma, Advocate
Counsels for Respondents
- • Neetika Sharma (for M/S. M. V. Kini & Associates)
Provisions of Law Cited
Legal Doctrines & Maxims
- Just and fair compensation
- Hardship and inconvenience as a ground for compensation
- Deficiency in service (consumer protection doctrine)
- Delay by service provider not to be permitted without cogent explanation
Submissions & Arguments
Contentions of Appellants / Petitioners
The appellant contends that an agriculturist was left in lurch for nearly nineteen years after submitting an application for electricity, with the complaint that the respondent falsely claimed the connection had already been granted. He emphasizes the delay was arbitrar,’ resulting in inability to irrigate his land via bore well and causing substantial hardship. He argues that the NCDRC’s Rs 2,00,000 is inadequate and that a fair compensation should reflect the prolonged deprivation and its effects, supported by the Bombay High Court’s 2015 order ordering connection by September 2015.
Contentions of Respondents
The respondent contends the delay was attributable to the appellant’s failure to submit the required test report despite public notices; the District Forum’s findings were correct in limiting liability to the period after the test report was submitted; the NCDRC’s Rs 2,00,000 was reasonable; reliance is placed on the 2015 Bombay High Court order and on the alleged 2007 undertaking. The counterargument emphasizes that the connection could not be granted solely due to the appellant’s inaction until 2007 and that the undertaking content is disputed.
Explore This Legal Issue
Find relevant judgments and authoritative positions on the legal questions discussed here.
Cited Precedents (1)
| Case Name | Citation | Treatment | Explanation |
|---|---|---|---|
| Criminal Writ Petition No. 247 of 2005 | Criminal Writ Petition No. 247 of 2005 | Mentioned Only | Cited to reference a Bombay High Court order connected with the timeline of the connection; not a binding precedent in the Supreme Court's reasoning in this appeal. |
Apply This to My Facts
Share your situation and test whether this judgment governs, supports, or challenges your case.
In The Court Record
TUKARAM S/O SADASHIV CHAUDHARI v. THE EXECUTIVE ENGINEER, MAHARASHTRA STATE ELECTRICITY DISTRIBUTION COMPANY LTD. & ANR.
Related Decisions & Precedents from Supreme Court of India (2019)
Uber India Systems Pvt. Ltd. v. Competition Commission of India & Ors.
Uber India Systems Pvt. Ltd. v. Competition Commission of India & Ors. concerns allegations that Uber, in its ride‑hailing network, abused a dominant position under the Competition Act, 2002. The case arose on appeals challenging the Competition Appellate Tribunal’s order in Appeal No. 31 of 2016, which upheld the Director General’s inquiry into whether Uber’s pricing and incentive practices violated Section 4. The Supreme Court analysed whether the information before it sufficed to constitute a prima facie case under Section 26(1) and whether there was abuse of a dominant position in the National Capital Region. It focused on the two ingredients for abuse: the existence of a dominant position and its misuse. The court considered, based on a statement summarizing driver incentives and a period when Uber reportedly paid high incentives to fleet owners, that Uber may have pursued a pricing strategy that would affect its competitors. Under Section 4(2)(a), abuse includes an unfair price, including predatory pricing. The Court accepted that there is a prima facie case for infringement, yet did not itself interfere with the Appellate Tribunal’s order and dismissed the appeals. It directed the Director General to complete the investigation within six months from today.
STATE OF BIHAR & ORS. v. DR. CHAITRAYA KUMAR SINGH & ORS.
This civil appeal concerns the reorganization of the erstwhile Bihar into Bihar and Jharkhand in 2000 and the post-allocation transfer of an employee. The first respondent, Dr. Chaitraya Kumar Singh, was initially allocated to Jharkhand in 2007 as an Ayurvedic Medical Officer and, following Union guidelines permitting transfer after final allocations, was re-allocated to Bihar on 6 September 2010 with mutual consent of both States. Bihar issued formal orders, and the respondent joined Jharkhand in 2007; however, he remained in Jharkhand and continued to work there until his retirement on 30 April 2017. A few days before retirement, he filed a writ petition in Jharkhand seeking relief to join Bihar and to be relieved by Jharkhand so that Bihar could accept joining. The Jharkhand High Court confirmed a Single Judge’s order directing Bihar to absorb him. The appellants contend that after the 2010 allocation there was no vacancy, the respondent did not pursue available remedies promptly, and seven years of service in Jharkhand after allocation render absorption in Bihar inappropriate. The Court agrees, noting the allocation to Bihar continued to hold and the petitioner failed to pursue remedies in time; his superannuation in Jharkhand eliminates the basis for absorption. The relieving order issued post-retirement is irrelevant. The appeal is allowed, the High Court’s order set aside, and there shall be no costs; pending applications are disposed.
PUNJAB FINANCIAL CORPORATION v. M/S PAULBRO LEATHERS PVT. LTD.
Punjab Financial Corporation (lender) filed against Paulbro Leathers Pvt. Ltd. after Paulbro defaulted on a loan. The dispute was settled under the Corporation’s One Time Settlement (OTS) policy on 01.04.2003, and a court-ordered reference to a Chartered Accountant (CA) was made to determine the remaining outstanding balance. After the CA submitted his report, a new dispute arose about the precise liability and how much had been paid, prompting the Corporation to issue a demand for Rs. 49,86,713 which Paulbro disputed in a writ petition before the Punjab and Haryana High Court. The High Court allowed the petition on the ground that the entire exercise had been carried out with consent and no objection had been raised, effectively barring re-opening of the settlement. The appellant challenged these rulings in this Court. The Supreme Court held that the settlement created a fresh dispute arising out of its terms and that the matter must be decided on its merits under the law. It emphasized that the High Court should record how and on what basis Paulbro satisfied the settlement and discharged liability, and if needed, refer the report to another CA. The Court remanded the case to the High Court to decide the writ petition afresh on merits, with a directions to decide expeditiously (preferably within six months).
RAJESH KUMAR DWIVEDI v. STATE OF U.P. & ANR.
Rajesh Kumar Dwivedi challenges the rejection of his candidature for the post of Instructor in Fitter at Government Industrial Training Institutes in Uttar Pradesh. An advertisement of 17 March 2008 required candidates to possess a certificate in the respective trade from the NCVT, in addition to experience. Dwivedi possessed three National Trade Certificates from Model Industrial Training Institute, Haldwani (one-year basic training in Mechanical, six-month Fitter General module, six-month Metrology and Engineering Inspection), but did not hold a two-year NCVT certificate. The High Court had dismissed his writ petition, holding that three separate courses could not be treated as equivalent to the NCVT qualification. Dwivedi relied on (i) the 16 December 1983 circular clarifying equivalence between the Restructured and Conventional patterns of the Craftsmen Training Scheme, and (ii) 1988 and 1992 UP circulars recognizing MITI, Haldwani training as equivalent to NCVT, including a two-year Fitter trade certificate. The State argued that the amended UP ITI Rules require NCVT certification and that the reliance on circulars cannot override the Rules. The Supreme Court held that the eligibility condition is to have a certificate in the respective trade from NCVT, and that if the State had earlier treated certain qualifications as equivalent through its circulars, such equivalence cannot be disregarded. Consequently, the appellant’s candidature could not be validly rejected, and the State was directed to appoint him within two months. The decision underscores how State-issued equivalence can complement or override rigid Rule-based qualifications when consistently recognized.