High Court of KeralaSingle JudgeWrit petition allowed; Exts.P6 and P8 set aside...

T.P. Paulose and others v. State of Kerala and others

Case / Petition Number:WP(C) 8789/2018

Case Details & Bench

Court
High Court of Kerala
Hon'ble Judges
  • EASWARAN S.
Judgment Date
2024-04-12
Court Decision / Holding
Writ petition allowed. Exts.P6 and P8 set aside. Notably, the Court held that there was no concluded contract between late T.P. Paulose and the respondents; the legal heirs of the deceased contractor are not liable for damages; no order as to costs.
Final Disposition
Writ petition allowed; Exts.P6 and P8 set aside; No order as to costs; The petitioners (legal heirs) are not held liable for damages since there was no concluded contract; the State’s recovery attempt is quashed to that extent.

Parties to the Case

Appellants / Petitioners

  • T.P. Paulose
  • Annamma Paulose
  • Eldho Paul
  • Suni James

Respondents

  • The State of Kerala represented by the Secretary to Government, PWD (Irrigation Department), Government Secretariat, Thiruvananthapuram
  • The Executive Engineer PWD Buildings Division, Ernakulam, Edappally, Kochi - 682 024
  • The Assistant Executive Engineer Buildings Sub Division, Muvattupuzha - 686 673
  • The District Collector, Collect orate, Kakkanad, Ernakulam - 682 030

Legal Representation & Advocates

Counsels for Petitioners

  • • SRI.JACOB P.ALEX
  • • SRI.RANJITH VARGHESE
  • • SRI.RAHUL VARGHESE
  • • SANTHA VARGHESE

Counsels for Respondents

  • • SRI.BIMAL.K.NATH, SR.G.P.

Case Synopsis & Summary

This writ petition challenges revenue-recovery measures for alleged damages arising from re-tendering a rain shade work at the Muvattupuzha court complex following the contractor’s reluctance to execute the work. The 1st petitioner, T.P. Paulose, was the successful tenderer who informed the authority of his inability to perform. Nevertheless, the respondents proceeded to re-tender the project and issued notices claiming a loss to the State and proposing recovery of Rs. 6,01,929.74. The matter raises two core questions: (i) whether the State can initiate revenue-recovery actions for damages due to re-tendering, and (ii) whether the legal heirs of the late contractor can be held liable for those damages. The pleadings reveal a dispute about whether a concluded contract ever existed; the respondents contend that a contract or at least an obligation followed from the tender process, while the petitioners contend there was no concluded contract and that damages cannot be recovered absent civil-quantification. The court surveys established precedents: damages under the Kerala Revenue Recovery Act require civil-quantification (Ponnappan K.A.; Govindankutty); the bidding-stage relationship cannot create an implied contract (K.P.Chaudhari); personal-skill contracts not binding on legal representatives (Vinayak Dube; Morsel Cleaners). The court ultimately holds that there was no concluded contract and that the legal heirs are not liable, allowing the writ petition and setting aside Exts.P6 and P8 with no costs.

Provisions of Law Cited

Kerala Revenue Recovery Act, 1963Indian Contract Act, 1872Section 37, Indian Contract Act, 1872Section 40, Indian Contract Act, 1872Indian Succession Act, 1925Section 306, Indian Succession Act, 1925Article 299(1) of the Constitution of India

Legal Doctrines & Maxims

  • No implied contract between Government and contractor at bidding stage (K.P.Chaudhari v. State of Madhya Pradesh & Others, 1966)
  • No implied contract without a concluded contract; Article 299(1) precludes implied contracts (K.P.Chaudhari)
  • There can be no obligation without a contract (Pollock and Mulla on Indian Contract)
  • Personal skill contracts bind promisor personally; legal heirs not liable (Vinayak Purshottam Dube (D) v. Jayashree Padamkar Bhat; Morsel Cleaners Ltd v Hicks)
  • There must be a concluded contract to fasten liability; implied-contract concept not applicable in bidding
  • Damages under Kerala Revenue Recovery Act require civil-quantification (Ponnappan K.A. v. D.F.O.; Govindankutty v. State of Kerala)
  • Constitutional principle that there can be no implied contract at bidding (K.P.Chaudhari)
  • A contract involving personal skills may not bind legal representatives (Vinayak Dube)
  • Supreme Court authority on non-binding implications of bidding stage (Bombay HSG Board v Karbhase Nairk & Co)

Submissions & Arguments

Contentions of Appellants / Petitioners

The petitioners contend that damages for breach of contract with the Government can be recovered only after damages are quantified in a civil proceeding; Kerala Revenue Recovery Act cannot apply to unliquidated damages. They rely on Build Tech India v. State of Kerala and Others, Tulsi Narayan Garg v. M.P.Road Development Authority, State of Karnataka v. Shree Rameshwara Rice Mills and J.G. Engineers v. Union of India to argue there is no concluded contract and that legal heirs cannot bear liability absent a concluded contract; the decision in K.P.Chaudhari and Article 299(1) are invoked against implied contracts in bidding; the matter should be resolved in light of modern precedents that emphasize personal contract limits and non-liability of heirs.

Contentions of Respondents

The State argues that re-tendering damages were properly initiated as a breach by the contractor and that the legal heirs may be liable where a concluded contract exists or where damages flow from the breach; Ext.R2(a) shows the re-tendering was a response to the contractor’s non-execution; the Department contends damages can be recovered as arrears of revenue and rely on the constitutional and contractual framework including Article 299(1) and related case law.

Cited Precedents (11)

Case NameCitationTreatmentExplanation
Build Tech. India v. State of Kerala and Others[2000] KLJ 142Mentioned OnlyCited by petitioners; court does not rely on its holdings to dispose of the case.
Tulsi Narayan Garg v. M.P.Road Development Authority(2019) SCC OnLine SC 1158Mentioned OnlyCited among authorities; not explicitly applied or distinguished in the judgment.
State of Karnataka v. Shree Rameshwara Rice Mills(1987) 2 SCC 160Mentioned OnlyCited among authorities; no direct ruling adopted in the decision.
J.G.Engineers Pvt. Ltd. v. Union of India and Another(2011) 5 SCC 758Mentioned OnlyCited but not instrumental in the outcome.
Ponnappan K.A. v. D.F.O., Chalakudy and others1984 KHC 442PositiveUsed to establish that Kerala Revenue Recovery Act requires civil-quantification of damages.
Govindankutty v. State of Kerala2016 (4) KLT 929PositiveCited to support the requirement of civil-quantification prior to recovery.
K.P.Chaudhari v. State of Madhyapradesh & Others(1966) SCC Online 21PositiveCited to emphasize no implied contract at bidding under Article 299(1).
Bombay HSG Board v Karbhase Nairk and Co(AIR 1975 SC 763)PositiveCited to illustrate that procedural failure at bidding does not automatically create a contract.
Morsel Cleaners Ltd v Hicks(1966) 2 Lloyd’s Rep 338Mentioned OnlyCited in context of personal-contract principle; not central to the disposition.
Vinayak Purshottam Dube (D) v. Jayashree Padamkar Bhat & Others(2024) SCC Online 212PositiveUsed to support the proposition that personal-skill contracts may not bind legal heirs.
M. Veerappa v. Evelyn SequeriaAIR 1988 SC 506PositiveCited to support the applicability of succession principles to contractual liabilities.

Diagnostic Tool

Beta

Does this judgment govern your specific facts?

Don't risk relying on a distinguishable precedent. Enter your facts or proposition below. We will test it against T.P. Paulose and others v. State of Kerala and others and instantly map out authorities that support, challenge, or govern your position.

Extracted Judgment Text

Exact text extracted from official judgment records.

``` “C.R.” ``` ## **`IN THE HIGH COURT OF KERALA AT ERNAKULAM`** ## **`PRESENT`** ## **`THE HONOURABLE MR. JUSTICE EASWARAN S.`** ``` FRIDAY, THE 12[TH] DAY OF APRIL 2024 / 23RD CHAITHRA, 1946 WP(C) NO. 8789 OF 2018 ``` ## **`PETITIONER/S:`** |**`1`**<br>**`2`**<br>**`3`**<br>**`4`**|**`T.P. PAULOSE`**<br>**`“DIED, LRS IMPLEADED”`**<br>**`AGED 72 YEARS`**<br>**`THELAPPILLY HOUSE, PULIYANAM P.O, ANGAMALY,`**<br>**`ERNAKULAM DISTRICT - 683 572.`**<br>**`ADDL.P2.`**<br> **`ANIAMMA PAULOSE`**<br>**`AGED 56 YEARS, WIFE OF DECEASED T.P.PAULOSE,`**<br>**`RESIDING AT THELAPPILLY HOUSE, PULIYANAM P.O.,`**<br>**`ANGAMALY, ERNAKULAM DISTRICT - 683 572.`**<br>**`ADDL.P3.`**<br> **`ELDHO PAUL`**<br>**`AGED 44 YEARS, SON OF DECEASED T.P.PAULOSE,`**<br>**`RESIDING AT THELAPPILLY HOUSE, PULIYANAM P.O.,`**<br>**`ANGAMALY, ERNAKULAM DISTRICT - 683 572.`**<br>**`ADDL.P4.`**<br> **`SUNI JAMES`**<br>**`AGED 50 YEARS, DAUGHTER OF DECEASED T.P.PAULOSE,`**<br>**`RESIDING AT MARACHERY PUTHENPURA, MARAMANGALAM,`**<br>**`KUTHUKUZHY P.O., KUTHUKUZHY, ERNAKULAM DISTRICT -`**<br>**`686 691.`**| |---|---| ``` [ADDITIONAL PETITIONER NOS.P2 TO P4 ARE IMPLEADED AS PER ORDER DATED 11.07.2022 IN I.A.1/2022 IN WP(C)8789/2018] BY ADVS. SRI.JACOB P.ALEX SRI.RANJITH VARGHESE SRI.RAHUL VARGHESE SANTHA VARGHESE ``` ## **`RESPONDENT/S:`** ``` 1THE STATE OF KERALA REPRESENTED BY THE SECRETARY TO GOVERNMENT, PWD (IRRIGATION DEPARTMENT), GOVERNMENT SECRETARIAT, THIRUVANANTHAPURAM. ``` WP(C) 8789/2018 2 - **`2 THE EXECUTIVE ENGINEER PWD BUILDINGS DIVISION, ERNAKULAM, EDAPPALLY, KOCHI - 682 024.`** - **`3 THE ASSISTANT EXECUTIVE ENGINEER BUILDINGS SUB DIVISION, MUVATTUPUZHA - 686 673.`** - **`4 THE DISTRICT COLLECTOR COLLECTORATE, KAKKANAD, ERNAKULAM - 682 030. BY ADV GOVERNMENT PLEADER`** ## **`OTHER PRESENT:`** ``` SRI.BIMAL.K.NATH,,SR.G.P. ``` ``` THIS WRIT PETITION (CIVIL) HAVING COME UP FOR ADMISSION ON 11.04.2024, THE COURT ON 12.04.2024 DELIVERED THE FOLLOWING ``` WP(C) 8789/2018 3 ``` “C.R” ``` ## `J U D G M E N T` ``` Twointriguingquestionsarisefor consideration in this writ petition. Can the respondents initiate revenue recovery measures for alleged damages caused on account of re-tendering of the work awarded to one Late T.P Paulose? Secondly, even if it is held so, can the legal heirs of the Late T.P.Paulose be held liable to the alleged damages caused to State exchequer. ``` ``` 2.Sri.T.P.Paulose, a contractor, was the successful tenderer in terms of Ext.P1 notice inviting tenders for providing rain shade to the court complex at Muvattupuzha. Ext.P1 is dated 7.10.2016. Sri.T.P.Paulose on 20.10.2016 addressed to the 2[nd] respondent requesting to relieve him from the obligation to complete the work, which was awarded to him. Despite this notice, the 2[nd] respondentproceededtoselectlate Sri.T.P.Poulose as lowest tenderer pursuant to Ext.P1 notice on 28.10.2016. As per Ext.P4 dated ``` WP(C) 8789/2018 4 ``` 14.12.2016, late Sri.T.P.Paulose was put on notice that his failure to execute agreement will entail further consequences and proceedings against him. Thereafter, on 30.1.2017, the attempt of the 2[nd] respondent to persuade the second lowest bidder to complete the work failed, and therefore, proceedings for recovery against Sri.T.P.Paulose was recommended. It is pursuant to this order that Ext.P6 was issued to late Sri.T.P.Paulose stating that an amount of Rs.6,01,929.74 was the loss caused to the Department consequent to the re-tendering of the work. In response to Ext.P6, late Sri.T.P.Paulose addressed to the 2[nd] respondent on 29.7.2017 vide Ext.P7 stating that he is not liable under any circumstances for the loss that was caused. It is pertinent to note that Ext.P6 was dated 8.6.2017 and by Ext.P8, the said request was turned down and the 2[nd] respondent decided to proceed with recovery measures against late Sri.T.P.Paulose. By order dated 11.7.2022 in I.A.No.1/2022, his legal heirs were impleaded as ``` WP(C) 8789/2018 5 ``` additional petitioners 2 to 4, who are prosecuting the present writ petition. ``` ``` 3.A counter affidavit has been filed on behalf of the 2[nd] respondent in which it is contended that as per notice inviting tender for the works, every bidder is expected before quoting his rate to inspect the site of the proposed works. It is also stated that the rates quoted shall be inclusive ones, covering all the operations contemplated in the specifications and tender schedules and all incidental works necessary for such operations such as shoring bailing out work, scaffolding etc. Therefore, it is contended that since late T.P.Paulose carried out joint inspection with officers of the respondent and found that various items involved in the work were not provided in the price schedule and that the petitioner had not inspected the site before quoting the tender. It is further averred that if the contractor does not come forward to execute the original agreement after the work is awarded, the selection notice issued ``` WP(C) 8789/2018 6 ``` in his favour gets cancelled and, hence, a breach is committed by him. ``` ``` 4.Controverting to the averments contained in the counter affidavit, late Sri.T.P.Paulose had filed a reply affidavit, in which it is stated that re-tendering of the work at his risk and cost was belatedly issued on 12.10.2017 as per Ext.R2(a). It is also pointed out that under Ext.R2(a) report, the 3[rd] respondent has submitted to the 2[nd] respondent that the agreement to re-cast the estimate with all required items was done since the drawings were not provided with the tender. The assertion that the cement concrete works under Ext.P1 price schedule needs to be carried out in case rain water falls on the varanda floor etc. is denied. The re-tendering work, according to Sri.T.P.Paulose, has been done without following the procedure laid down under Ext.P10 Government Order. ``` ``` 5.I have heard Sri.Ranjith Varghese, learned counsel appearing for the petitioner and ``` WP(C) 8789/2018 7 ``` the learned Senior Government Pleader on behalf of the respondents. ``` ``` 6.Learned counsel for the petitioner submits that damages for breach of contract with the Government could be recovered only after assessing the damages arising out of the breach. He further contends that unless the said damages are liquidated and found in an appropriate civil proceeding, there cannot be any attempt to recover the alleged loss caused due to re-tendering of the work. He relies on the decision of this Court in Build Tech. India v. State of Kerala and Others [2000 (2) KLJ 142]. He further relies on the decisions of the Hon’ble Supreme Court in Tulsi Narayan Garg v. M.P.Road Development Authority [2019 SCC OnLine SC 1158]; State of Karnataka v. Shree Rameshwara Rice Mills [(1987) 2 SCC 160] and J.G.Engineers Pvt. Ltd. v. Union of India and Another [(2011) 5 SCC 758]. ``` ``` 7.On the other hand, learned Senior Government Pleader takes me to Ext.R2(a) letter in which it is specifically stated by the Assistant ``` WP(C) 8789/2018 8 ``` Executive Engineer that it is because of the refusal of late Sri.T.P.Paulose that the work had to be re-tendered. He also refers to the averments in paragraph Nos.4 and 6 of the counter affidavit to assert that the proceedings initiated for recovery of damages on account of re-tendering of the work was proper. Therefore, he prays for the dismissal of the writ petition. ``` ``` 8.I have considered the rival submissions raised across the bar. ``` ``` 9. Insofar as the first question is concerned, it is explicitly clear that there was no agreement executed between late Sri.T.P.Paulose and the respondents. It is also evident from the records thatatthefirstpossibleinstance, Sri.T.P.Paulose had intimated to the tendering authority his inability to execute the agreement for various reasons. This apparently was ignored while the selection order was issued on 28.10.2016. Thus, there is a unilateral decision on the part of the respondents to award the work ``` WP(C) 8789/2018 9 ``` to late Sri.T.P.Paulose, despite his reluctance to proceed further in this matter. ``` ``` 10.The issue as to whether a claim for either liquidated damages or unliquidated damages could be raised in terms of the provisions contained under the Kerala Revenue Recovery Act, 1963, came up for consideration before this court in Ponnappan K.A. Vs D.F.O., Chalakudy and others [1984 KHC 442] and in Govindankutty v. State of Kerala [2016 (4) KLT 929]. It was held that unless the damages are quantified in a civil proceedings, the provisions of Kerala Revenue Recovery Act cannot be invoked.In the light of the aforesaid principles, I am inclined to take a view that the additional petitioners are justified in contending that the attempt made by the 2[nd] respondent to recover the differential amount between the lowest tenderer - the amount quoted by late Sri.T.P.Paulose and the amount for which the retender was made – cannot be sustained. ``` ``` 11.Insofar as the second question raised in the present writ petition is concerned, ``` WP(C) 8789/2018 10 ``` admittedly, there was no agreement between late Sri.T.P.Paulose and the respondents by which the terms and conditions were settled between the parties. Even one was to assume that there was such contract and the mere application for the bid and its consequential acceptance would result into a contract between the parties, still the question would be whether the legal heirs are liable for the loss allegedly caused due to the respondents. Therefore, while answering the second question, this Court would have to decide whether there is a concluded contract or not, and even if there is none, whether the additional petitioners are liable to the claim for damages. ``` ``` 12.It is pertinent to note that the parties are at variance as to whether there was concluded contract or not between late Sri.T.P.Paulose and the respondents. The argument of the State is that the mere fact that Late T.P Poulose had applied for tender pursuant to the notice inviting e- tender and further that he was selected as lowest ``` WP(C) 8789/2018 11 ``` tenderer itself is sufficient to conclude that there is a concluded contract. ``` ``` 13. Before answering the question on the liability of the legal heirs for damages claimed by the State, the question as to whether there is a concluded contract or not is required to be decided. It is not possible to assume or conclude that due to mere fact that an application was filed/submitted by Sri.T.P.Paulose pursuant to Ext.P1 notice and the consequential acceptance and selection of Sri.T.P.Paulose as the lowest tenderer will not ipso facto lead to a conclusion that there was a concluded contract between the parties. This is especially so, when late Sri.T.P.Paulose had given a request to withdraw from the tender immediately on coming to know that he will not be able to perform his part of the contract. Despite this letter, it appears that the 2[nd] respondent had proceeded to select late Sri.T.P.Paulose as the lowest tenderer. Can such a unilateral decision on the part of the 2[nd] respondent be sufficient to fasten the liabilities ``` WP(C) 8789/2018 12 ``` on late Sri.T.P.Paulose, so as to make his legal heirs liable?. ``` ``` 14. The learned counsel for the petitioner Sri.Ranjith Varghese further submitted that there isnoconcludedcontractbetweenlate Sri.T.P.Paulose and the respondents. The learned counsel for the petitioner, further submits that the stand of the respondents as reflected from the counter affidavit, especially paragraph 8, that the moment late T.P.Paulose submitted his application pursuant to the tender notice, that itself is sufficient to warrant initiation of further steps by the respondents to recover the loss, if any, caused by recovering the same as arrears of land revenue, cannot for a moment be sustained. He further relies on a Constitution Bench decision of the Hon'ble Supreme Court in K.P.Chaudhari v. State of Madhyapradesh & Others [1966 SCC Online 21] to drive home his point. On a close reading of the aforesaid judgment, especially paragraph No.10, shows that the Hon'ble Apex Court had occasion to consider the issue as ``` WP(C) 8789/2018 13 ``` to whether in the absence of a concluded contract between the contractor and the Government in terms of Article 299(1) of the Constitution of India, whether there can be any liability cast upon the contractor?. The question as to whether there could be an implied contract between the parties based on the application submitted for participation in tender process, was also considered. Ultimately, the Hon'ble Apex Court went on to hold that “in view of the mandatory terms of Article 299(1) of the Constitution of India, no implied contract could be spelled out between the Government and the appellant at the stage of bidding, for, Article 299 in effect rules out all implied contracts between the Government and another person.” ``` ``` 15.In view of the categoric finding, this Court finds that on facts of the present case, there was no concluded contract and therefore, this Court has no hesitation in its mind to reject the contention of the respondents that there was a contract between late T.P.Paulose enabling them to ``` WP(C) 8789/2018 14 ``` proceed against his legal heirs. It may be noticed that these incidental issues came up for consideration before this Court only because of the death of Sri.T.P.Paulose during the pendency of the present writ petition and the legal heirs were permitted to implead as additional petitioners and prosecute this writ petition. Hence precisely, the second issue was framed and decided by this court. ``` ``` 16. Another argument raised by the learned Senior Government pleader appearing for the State is that the fact that late T.P Paulose applied for tender and that he was selected itself is sufficient to make him liable for the damages and hence the State is entitled to recover it from the legal heirs. This issue regarding the enforcement of contract on legal representatives becomes rather incidental since this court has already found that there is no concluded contract between the parties. However, since the State insists that it is entitled to recover the damages on account of re-tendering of work from the legal ``` WP(C) 8789/2018 15 ``` representatives of the deceased Late T.P. Paulose, this issue also requires to be considered. ``` ``` 17.Law relating to performance of a contract and the liabilities of legal heirs is stated under Section 37 of the Indian Contract Act, 1872. The effect of death of a person and his liabilities is governed by Section 306 of the Indian Succession Act, 1925. ``` ``` 18. Section 306 of the Indian Succession Act, 1925 reads as under ``` ``` “All demands whatsoever and all rights to prosecute or defend any action or special proceeding existing in favour of or against a person at the time of his decease survive and against his executors or administrators, except causes of action for defamation, assault, as defined in the Indian Penal Code or other personal injuries not causing the death of the party: and except also cases where, after the death of the party, the relief sought could not be enjoyed or granting it would be nugatory.” ``` ``` 19.Though the aforesaid provision speaks only of executors and administrators, the same ``` WP(C) 8789/2018 16 ``` principles must necessarily prevail in the case of other legal representatives also. This proposition is affirmed by the Hon’ble Supreme Court inM. VeerappaVs Evelyn Sequeria [AIR 1988 SC 506]. Therefore, the section applies to devolution of rights and liabilities in contract and proceedings relating to contact. ``` ``` 20. A further question would also have to be necessarily answered by this Court. If the law is as aforesaid, then the question to be considered is whether there is a vested right of action for the breach of contract. If the answer is in affirmative, then the death of either party has no effect upon it, whether or not it arose from a contract of personal nature (see Halsbury’s Law of England, fourth Edn, Vol.9 Page 615). ``` ``` 21.On a further analysis of facts at hand, it is seen that parties did not choose their bargain to be reduced in writing. Although the law relating to enforcement of contracts on legal representative being succinctly stated above, the prime consideration should be that the obligation ``` WP(C) 8789/2018 17 ``` arises only on execution of a contract. In Pollock and Mulla On Indian Contract Twelfth Edition Page 947, the learned Author has opined, that there can be no obligation without a contract. More or less similar issue came up for consideration before the Apex Court in Bombay HSG BoardV Karbhase Nairk and Co [AIR 1975 SC 763], wherein the Apex Court was called upon to decide on a certificate for appeal on a decision of Division Bench of Bombay High Court, whether without a concluded contract, a contractor was bound to be paid at the rates quoted by him in notice for damages. Answering the question, the Apex Court held that mere fact that Engineer-in-charge did not exercise his power to cancel the order would not mean a contract is concluded on contractor’s term. The Apex Court went on to negative the claim of the contractor. ``` ``` 22. Be that as it may, it will also be appropriate to consider whether under a contract which basically involves personal skills of the contractor, whether the legal representatives would be liable to perform the contract?. ``` WP(C) 8789/2018 18 ``` Governing provision under the Indian Contract Act is Section 40 of the Indian Contract Act, 1872 which reads as under: ``` ``` “40.If it appears from the nature of the case that it was the intention of the parties to any contract that any promise in it should be performed by the promisor himself, such promise must be performed by the promisor. In other cases, the promisor or his representatives may employ a competent person to perform it”. ``` ``` Reading of the aforesaid Section gives answer to the question posed before this court in the following manner: ``` ``` A) Necessarily there should be a contract between the parties; ``` ``` B) Liability of the representative should be provided in the contract itself. ``` ``` 23.It may be apposite to note that a contract for designing a building by an architect is held to be a personal contract and which could notbeenforceableagainsthislegal representative. {See Morsel Cleaners Ltd Vs Hicks [(1966) 2 Lloyd’s Rep 338]}. Based on the above, ``` WP(C) 8789/2018 19 ``` this Court is inclined to take a view that in the present case, no liability could be fastened on the legal heirs. ``` ``` 24. InVinayak Purshottam Dube (D) v. Jayashree Padamkar Bhat & Others [2024 SCC Online 212], the Hon’ble Supreme Court was called upon to decide whether a contract executed in a personal capacity would bind the legal heirs or not?While answering the question in affirmative, the Apex Court held as under: ``` ``` “21.Thus, a contract can be performed vicariously by the legal representatives of the promisor depending upon the subject matter of the contract and the nature of performance that was stipulated thereto. But a contract involving exercise of individual’s skills or expertise of the promisor or which depends upon his/her personal qualification or competency, the promisor has to perform the contract by himself and not by his/her representatives. A contract of service is also personal to the promisor. This is because when a person contracts with another to work or to perform service, it is on the basis of the individual’s skills, competency or other qualifications of the promisor and in ``` WP(C) 8789/2018 20 ``` circumstances such as the death of the promisor he is discharged from the contract.” ``` ``` 25. In the aforesaid decision also the principles as expounded by this Court is affirmed by the Hon’ble Supreme Court of India. Added to the above, the Apex Court went on to hold, even in a case of concluded contract which involving personal skill, the legal representatives are not liable. Therefore, it must be necessarily held that the legal representatives are not liable to the claim for damages by the State. ``` ``` 26.In the result, this Court finds that the additional petitioners 2 to 4 are entitled to succeed. It is declared that they are not liable to answer the claim for damages raised by the State against Late T.P. Paulose. ``` ``` Hence the Writ petition is allowed. Exts.P6 and P8 are set aside. No order as to costs. ``` ``` Sd/- EASWARAN S. JUDGE ``` ``` jg ``` WP(C) 8789/2018 21 ## **`APPENDIX OF WP(C) 8789/2018`** ## **`PETITIONER EXHIBITS`** ``` EXHIBIT P1TRUE COPY OF THE PRICE SCHEDULE. EXHIBIT P2TRUE COPY OF LETTER DT. 20.10.2016 ISSUED BY THE PETITIONER TO THE 2ND RESPONDENT. EXHIBIT P3TRUECOPYOFSELECTIONNOTICE DT.28.10.2016ISSUEDBYTHE2ND RESPONDENT TO THE PETITIONER. EXHIBIT P4TRUE COPY OF LETTER DT. 14.12.2016 ISSUED BY THE 2ND RESPONDENT TO THE PETITIONER. ``` - **`EXHIBIT P5 TRUE COPY OF LETTER DT. 30.01.2017 ISSUED BY THE 2ND RESPONDENT TO THE PETITIONER.`** - **`EXHIBIT P6 TRUE COPY OF LETTER DT. 08.06.2017 ISSUED BY THE 2ND RESPONDENT TO THE PETITIONER.`** - **`EXHIBIT P7 TRUE COPY OF LETTER DT. 29.07.2017 ISSUED BY THE PETITIONER TO THE 2ND RESPONDENT.`** - **`EXHIBIT P7(A) TRUE COPY OF ACKNOWLEDGMENT RECEIPT EVIDENCING RECEIPT OF EXHIBIT P7 LETTER.`** - **`EXHIBIT P8 TRUE COPY OF LETTER DT. 16.01.2018 ISSUED BY THE 2ND RESPONDENT TO THE PETITIONER.`** - **`EXHIBIT P9 TRUE COPY OF LETTER DT. 02.03.2018 ISSUED BY THE PETITIONER TO THE 2ND RESPONDENT.`** - **`ADDL.EXHIBIT P10 TRUE COPY OF THE GOVERNMENT ORDER DATED 30.07.2015`** - **`ADDL.EXHIBIT P11 TRUE COPY OF LETTER DATED 29.5.2018 ISSUED BY THE PUBLIC INFORMATION OFFICER OF THE RESPONDENT.`** WP(C) 8789/2018 22 ``` ADDL.EXHIBIT P12TRUE COPY OF LETTER DATED 12.6.2018 ISSUED BY THE 3RD RESPONDENT UNDER THE RIGHT TO INFORMATION ACT. ``` ``` ADDL.EXHIBIT P13TRUE COPY OF THE CIRCULAR DATED 10.5.2005 OF GOVERNMENT OF KERALA. ``` ``` ADDL.EXHIBIT P14DEATH CERTIFICATE ISSUED BY THE KOCHI MUNICIPAL CORPORATION. ``` ``` ADDL.EXHIBIT P15TRUE COPY OF THE LEGAL HEIRSHIP CERTIFICATE ISSUED BY THE TAHSILDAR, ALUVA ``` ## **`RESPONDENT’S EXHIBITS`** ``` EXHIBIT R2(a)TRUE COPY OF THE LETTER DATED 1.12.2016 ```