T.N. Godavarman Thirumulpad v Union of India & Ors; M/s Shewalkar Developers Ltd.

Case / Petition Number:
Writ Petition (Civil) No. 202 of 1995

Case Synopsis & Summary

Interlocutory applications filed by M/s Shewalkar Developers Limited challenge the inaction of the respondents in deciding an application seeking permission to construct a health/eco-resort on Plot Nos. 14/3 and 14/4 in Sheet No. 20, Pachmarhi, Madhya Pradesh. The land spanning about 108,900 sq ft lies near Pachmarhi, within the broader Pachmarhi Wildlife Sanctuary and an ESZ notified in 2017. The matter runs through a long history: sale in 1991, mutation in favor of the applicant, and a sequence of orders seeking to exclude Nazul areas from the sanctuary; litigation in the Madhya Pradesh High Court and before this Court under Writ Petition No. 202 of 1995; and a Central Empowered Committee (CEC) report dated 16 June 2020 indicating no permission for construction. The State of MP has filed an affidavit stating the land falls within the sanctuary, and the ESZ notification applies. The Court observed that the applicant was not a party to earlier proceedings and that the applicant’s title rights under Article 300A cannot be defeated merely by pendency of a writ appeal, while also acknowledging ESZ restrictions and the CEC’s report. The Court ultimately directed that the applicant's request be evaluated by the CEC/competent authority, with reference to ESZ boundaries, and within two months. Costs were reserved.

Precedent Explorer

Find Cases Like This

Explore other judgments dealing with similar legal situations, facts, or statutory provisions.

Case Details & Bench

Court
Landmark Cases
Hon'ble Judges
  • B. R. Gavai
  • Sandeep Mehta
Judgment Date
2024-05-16
Court Decision / Holding
The applications are disposed of in terms: the applicant’s request for permission to raise construction on Plot Nos. 14/3 and 14/4 shall be decided objectively by the CEC/competent local authority within two months, considering ESZ boundaries and related compliance, and subject to the outcome of pending writ proceedings. The applicant may challenge adverse orders as per law. No order as to costs.
Final Disposition
Disposed of; no costs

Parties to the Case

Appellants / Petitioners

  • M/s Shewalkar Developers Ltd.

Respondents

  • Union of India

Legal Representation & Advocates

Counsels for Petitioners

  • • D. S. Naidu

Provisions of Law Cited

Wildlife (Protection) Act, 1972 – Section 18(1)Wildlife (Protection) Act, 1972 – Section 21Eco-sensitive Zone notification dated 09.08.2017 (MoEFCC)Constitution of India, Article 300A

Legal Doctrines & Maxims

  • Constitution of India, Article 300A – Right to property (proprietary rights) cannot be infringed except through due process

Submissions & Arguments

Contentions of Appellants / Petitioners

The applicant contends that the land comprising Plot Nos. 14/3 and 14/4 lies in an urban area and not within the Pachmarhi Wildlife Sanctuary. The title to the plots, acquired via sale in 1991 and mutation subsequently, has not been legally challenged, and the applicant’s proprietary rights under Article 300A cannot be defeated by the pendency of unrelated writ proceedings. The ESZ notification of 2017 and the sanctity of the sanctuary boundaries must be respected, and any construction must occur under ESZ norms and with appropriate permissions routed through the Central Empowered Committee (CEC) or competent authorities. The applicant argues that the CEC’s 2020 report denying permission should be reconciled with the record showing urban land and that the matter should proceed to a determination rather than be blocked by pendency of appeals. The court should ensure that due process and statutory protections are upheld while evaluating permissible activity on the land.

Contentions of Respondents

The respondents argued that the plots are within the Pachmarhi Wildlife Sanctuary and subject to ESZ restrictions. They contend that ESZ notifications prohibit new constructions and that the matter is tied to ongoing writ appeals in the Madhya Pradesh High Court, so relief should not be granted until those proceedings are resolved. They emphasize that the title to the land and its current recording as Nazul land in State records require careful scrutiny, with any development subject to ESZ compliance and routed through the CEC and other statutory authorities.

Legal Doctrine & Issue Explorer

Explore This Legal Issue

Find relevant judgments and authoritative positions on the legal questions discussed here.

Case Applicability Diagnostic

Apply This to My Facts

Share your situation and test whether this judgment governs, supports, or challenges your case.

Official Judgment Record
•3,796 words•~18 min read

In The Court Record

T.N. Godavarman Thirumulpad v Union of India & Ors; M/s Shewalkar Developers Ltd.

**REPORTABLE** 2024 INSC 426 **==> picture [72 x 72] intentionally omitted <==** # **IN THE SUPREME COURT OF INDIA CIVIL ORIGINAL JURISDICTION** # **IA NO(S). 2930 OF 2010, 3963 OF 2017, 160714 OF 2019, 77320 OF 2023 AND 79064 OF 2023** **IN** **WRIT PETITION(CIVIL) NO(S). 202 OF 1995** **IN RE:** **T.N. GODAVARMAN THIRUMULPAD .…PETITIONER(S)** ## **VERSUS** **UNION OF INDIA & ORS. ….RESPONDENT(S)** **IN RE:** **M/S SHEWALKAR DEVELOPERS LTD. .…APPLICANT(S)** ## **J U D G M E N T** **Mehta, J.** 1. These interlocutory applications have been preferred by the applicant M/s Shewalkar Developers Limited being aggrieved by the inaction of the respondents in deciding the application filed by > Signature Not VerifiedDigitally signed by the applicant seeking permission to construct a health/eco-resort Deepak Singh Date: 2024.05.16 12:43:11 IST > Reason: on the subject land being Plot Nos. 14/3 and 14/4, falling in Sheet 1 No. 20, Civil Station, Pachmarhi, District Hoshangabad, Madhya Pradesh. The total area of these two plots is around 59,265 sq. ft. and 49,675 sq. ft., respectively. 2. The applicant herein approached the Madhya Pradesh High Court by filing Writ Petition No. 14478 of 2006 seeking a direction to the respondents to favourably consider the prayer of the applicant. Vide order dated 22[nd] November, 2006, the Division Bench of Madhya Pradesh High Court permitted the applicant to approach the Central Empowered Committee(hereinafter being referred to as ‘CEC’) constituted under the directions given by this Court in Writ Petition(Civil) No. 202 of 1995. Consequently, the applicant preferred an application to the CEC seeking permission to construct the health/eco-resort on the land mentioned above asserting that the said chunk of land was not a forest land and had been acquired under valid title deeds and thus, the prayer for permission to construct may be allowed. However, the prayer made by the applicant was not accepted whereupon, the applications under consideration came to be filed before this Court. 3. The State Government had previously taken a stand in its counter that the land in issue falls within the limits of Pachmarhi Wildlife Sanctuary and therefore, by virtue of the directions issued by the CEC vide letter dated 2[nd] July, 2004, no commercial activity was permissible thereupon, without the permission of this Court. 4. Much water has flown during pendency of the original application(I.A. No.2930 of 2010) which has remained pending for almost 14 years. For sake of convenience, a chronological flow chart of dates and events is narrated hereinbelow in a tabular form: - ## **CHRONOLOGICAL FLOW CHART OF DATES AND EVENTS** ## **BACKGROUND FACTS IN RELATION TO I.A. No.2930 of 2010** |**CHRONOLOGICAL FLOW CHART OF DATES AND EVENTS**|**CHRONOLOGICAL FLOW CHART OF DATES AND EVENTS**|**CHRONOLOGICAL FLOW CHART OF DATES AND EVENTS**| |---|---|---| |**BACKGROUND FACTS IN RELATION TO I.A. No.2930 of 2010**||| |**S.No.**|**DATE**|**EVENT**| |1.|01.06.1977|The Government of Madhya Pradesh notified<br>Pachmarhi Sanctuary under Section 18(1) of the<br>Wild Life (Protection) Act, 1972 but did not<br>specify/demarcate<br>the<br>area<br>to<br>be<br>included/excluded in the Sanctuary.| |2.|01.05.1991|The owner of the plots in question, Mr. Dennis<br>Torry obtained permission to sale from the<br>Government of Madhya Pradesh as required<br>under Clause 16 of Chapter-IV Part 1 of<br>Revenue<br>Book<br>Circular<br>issued<br>by<br>the<br>Government of Madhya Pradesh.| |3.|13.09.1991|The applicant purchased the subject plots of<br>land vide sale deed dated 13thSeptember,1991.| |4.|10.05.1996|In light of order dated 10thMay,1996 passed by<br>this Court in W.P.(C) No.262 of 1995, the State<br>Government issued instructions to the Collector<br>to expedite the proceedings of settlement of<br>rights in National Parks/Sanctuaries.| |5.|23.10.1996|In compliance of the abovementioned order,<br>Collector,Hoshangabadmadeaproclamation| 3 |||under Section 21 of the Wild Life(Protection) Act,<br>1972 inviting claims from the affected persons.| |---|---|---| |6.|20.06.2000|After inviting claims and hearing the objections,<br>Collector, Hoshangabad passed various orders<br>determining the rights of the affected people and<br>vide order dated 20thJune, 2000, Civil/Nazul<br>area of Pachmarhi Town was excluded from the<br>Sanctuary.| |7.|15.12.2000|Application was preferred by the applicant<br>seeking mutation based on registered sale deed<br>dated 13thSeptember, 1991. The SDO directed<br>the same to be mutated in the name of M/s<br>Shewalkar Developers Ltd., through Ashutosh<br>Shewalkar.| |8.|2002|PIL bearing W.P No. 5937 of 2002 was filed<br>before the High Court seeking directions to stop<br>illegal<br>construction<br>activities<br>in<br>reserved/protected area at Pachmarhi, wherein<br>a six-member Committee was constituted to<br>examine the issue.| |9.|15.01.2004|The High Court vide interim order passed in<br>W.P. No. 5937 of 2002, directed that the order<br>of exclusion of Cantonment and Civil/Nazul<br>area of Pachmarhi Town and 33 revenue villages<br>from the Pachmarhi Sanctuary and settlement<br>of rights passed by the District Collector,<br>Hoshangabad shall remain stayed until further<br>orders.| |10.|2005|The report of six-member Committee suggested<br>that Nazul area within the administrative<br>control of SADA and army cantonment area<br>falling in Pachmarhi plateau may be considered<br>to be deleted from the boundary of the<br>Sanctuary.| |11.|31.03.2005|The State Government following the advice of<br>the State Wildlife Advisory Board moved the<br>Government of India for seeking approval of<br>National Board for Wildlife(NBWL) for excluding<br>these areas.| |12.|24.10.2005|The Standing Committee of the NBWL, vide<br>letter dated 24thOctober, 2005, recommended<br>exclusionofcantonment and Civil/Nazul Area.| 4 |13.|2006|The applicant approached the High Court by<br>filing W.P(C) No. 14478 of 2006, being aggrieved<br>by inaction of the respondents in deciding the<br>application seeking permission to construct<br>health/eco-resort on the subject plots of land.| |---|---|---| |14.|22.11.2006|The High Court permitted the applicant to move<br>an application before the CEC.| |15.|22.02.2007|The applicant preferred an application before<br>the CEC being I.A No. 1008 of 2007.| |16.|19.09.2008|The CEC submitted a report dated 16th/19th<br>September, 2008 before this Court, in IA<br>Nos.2202-2203<br>of<br>2007,<br>filed<br>by<br>the<br>Cantonment Board.| |17.|29.03.2010|The CEC considered the application filed by the<br>applicant seeking permission to construct<br>health/eco-resort and observed that an affidavit<br>dated 1st February, 2010 has been filed by the<br>State Government clearly stating that the<br>applicant’s land falls within the Sanctuary and<br>was purchased in violation of the Wild<br>Life(Protection) Act, 1972. The CEC also<br>intimated<br>the<br>applicant<br>that<br>no<br>recommendation could be passed by it in<br>absence of an order passed by the Supreme<br>Court.| |**I.A. No.2930 of 2010 CAME TO BE FILED BEFORE THIS COURT**||| |**S.No.**|**DATE**|**EVENT**| |1.|2010|Aggrieved by the order of CEC, the applicant<br>approached this Court by filing I.A. No.2930 of<br>2010.| |2.|2011|Government of Madhya Pradesh filed an<br>affidavit<br>before<br>this<br>Court<br>stating<br>that<br>Pachmarhi Township may be excluded from the<br>forest area of Pachmarhi Sanctuary so that<br>difficulties of the residents of Pachmarhi<br>Township can be sorted out.| |3.|12.08.2013|This Court accepted the recommendations of<br>the CECforexcluding 395.939Ha.land of| 5 |||Civil/Nazul area from the sanctuary in which<br>the subject plots are situated.| |---|---|---| |4.|15.04.2017|The applicant moved I.A. No.3963 of 2017,<br>seeking to place additional documents on record<br>depicting functional resorts and hotels around<br>thearea where theapplicant’s plotis situated.| |5.|09.08.2017|The Ministry of Environment, Forest and<br>Climate Change issued ESZ notification.| |6.|16.04.2018|This Court de-tagged I.A. Nos.2929-2931 of<br>2010 filed by the applicant herein from other<br>I.A.s concerning the cantonment area.| |7.|04.10.2018|This<br>Court<br>allowed<br>the<br>application<br>for<br>impleadment for the purposes of directions and<br>the application to place additional documents<br>on record.| |8.|19.08.2019|The State Government was directed to file reply<br>to the interlocutory applications.| |9.|27.09.2019|This Court directed that response be filed by the<br>State of Madhya Pradesh as well as by the CEC.| |10.|13.11.2019|The CEC was directed to examine the matter<br>and submit its report.| |11.|16.06.2020|The CEC filed its report before this Court, in<br>terms of orders passed by this Court objecting<br>to the permission sought for by the applicant for<br>constructing health/eco-resort on the plots.| |12.|22.11.2023|This Court directed the Collector, Hoshangabad<br>to file an affidavit annexing therewith a map of<br>the<br>aforesaid<br>area<br>of<br>395.939<br>hectares<br>specifying as to whether the land belonging to<br>the applicant(s) is within those 395.939<br>hectares or beyond it.<br>The applicant was directed to place on record as<br>to whether it has obtained the necessary<br>permission for acquiring the land.| |13.|13.04.2023|The applicant moved I.A. No.79064 of 2023,<br>seeking leave to amend the I.A. No.2930 of 2010,<br>in light of the CEC report dated 16thJune, 2020.| |14.|12.02.2024|The State Government filed compliance affidavit<br>in terms of order dated 22ndNovember, 2023.| 6 5. Another litigation took place regarding other transactions of land done by Dennis Torry and it will be essential to trace the history thereof. Chronological list of events in relation to the plot are being narrated hereinbelow for the sake of ready reference: - 5.1 The District Collector, Hoshangabad registered _suo moto_ revisions against the mutation orders issued in favour of Kripa Torry and Sanjay Bhandari(purchasers of land from Dennis Torry) and vide order dated 9[th] August, 2004, these revisions were allowed holding that the transfer of land by the perpetual land holder Rodrigues in favour of Dennis Torry on 8[th] September, 1977 was illegal and without force of law and thus, mutation of land in favour of Dennis Torry was illegal. The transfer and consequent mutation in favour of Sanjay Bhandari and Shri Kripa Torry(son of Dennis Torry) was quashed and set aside by the District Collector vide order dated 9[th] August, 2004. 5.2 The aforesaid order was challenged by the purchasers by filing an appeal to the Board of Revenue, Madhya Pradesh which came to be allowed and the order dated 9[th] August, 2004 passed by the District Collector was quashed by learned 7 Single Member, Board of Revenue vide order dated 16[th] April, 2007. 5.3 The Chairman of Revenue Board registered a _suo moto_ revision and vide order dated 15[th] March, 2011, set aside the order passed by the learned Single Member. 5.4 The land owners Shri Sanjay Bhandari and Shri Kripa Torry preferred a Writ Petition No. 8098 of 2011 for questioning the legality of order dated 15[th] March, 2011 and the said writ petition was allowed by the learned Single Judge of the Madhya Pradesh High Court vide order dated 3[rd] January, 2014 thereby, reversing the order dated 15[th] March, 2011 passed by the Board of Revenue. 6. This Court is apprised that the State has preferred an appeal(Writ Appeal No. 2100 of 2019) against the order passed by the learned Single Judge which is still pending adjudication and no order of stay is passed in the said writ appeal. 7. The CEC has submitted a report dated 16[th] June, 2020 in these proceedings objecting to the permission sought by the applicant. The applicant has also filed objection to the report of the CEC. 8 8. The issue which has now been raised by the State of Madhya Pradesh is with respect to the identification of the land owned by the applicant contending that the same forms a part of the Pachmarhi Wildlife Sanctuary. Considering the above contention, this Court raised the following query on 22[nd] November, 2023: - “2. We, therefore, direct the Collector, Hosangabad to file an affidavit annexing therewith a map of the aforesaid area of 395.939 hectares and also specify as to whether the land belonging to the applicant(s) is within those 395.939 hectares or beyond that area.” 9. In compliance of the said direction, an affidavit has been filed on behalf of the State of Madhya Pradesh(also referred to as, ‘compliance affidavit’). The relevant portions thereof are extracted hereinbelow: - **“2.** That, this Hon'ble Court has raised following queries to the respondent/State of M.P.:- (i) To annex the map demarcating an area of 395.939 hectares of the Nazul Land falling in the Panchmarhi Plateau, which was to be excluded from the Panchmarhi Wildlife Sanctuary as per order dated 12.08.2013 passed by this Hon'ble Court in I.A. No.2202-2203. In respect of aforesaid, it is pertinent to mention here that the said map demarcating an area of 395.939 hectares of Nazul Land falling in the Panchmarhi Plateau, the Plot No.14/3 area 59255 sq. ft. and 14/4 area 49365 sq. ft. are excluded from Panchmarhi Wildlife Sanctuary and the same are within the area of 395.939 hectares and recorded as Nazul Land in the name of State of M.P. A true copy of colored map of is being marked and filed herewith as **Annexure A-1** . (ii) The Collector Hosangabad was directed to file an affidavit annexing therewith a map of the aforesaid area of 395.939 9 hectares and also specify as to whether the land belonging to the applicant is within those 395.939 hectares or beyond that area. In respect of aforesaid, it is pertinent to mention here that the Collector, Hoshangabad vide affidavit dated 06.01.2024 stated that the land mentioned, NazulBhumi Sheet No.20, Plot No.14/3 and 14/4, area 59255 sq. ft. and 49365 sq. ft. total area 108900 sq. ft. is situated in Panchmarhi and recorded as maintenance Khasra in the Government of M.P. **The plot No.14/3, 14/4 is within the area of 395.939 hectares which was excluded from the Panchmarhi Wildlife Sanctuary.** **2.** That, it is respectfully submitted that in respect of Plot No.14/3 and 14/4 a report was sought from Sub-Divisional Officer, Revenue, Pipariya whereby it was reported that Plot No.14/3 and 14/4 are recorded in name of State of M.P. in Sheet No.20 of Nazul Maintenance Khasra No.2023-24 **, said land of Plot No.14/3 and 14/4 is vacant on the spot, there is no kind of construction over there, said plots are situated under urban area of Panchmarhi. Moreover, the permission for - construction/re construction in the Cantonment Board, Panchmarhi lies under the jurisdiction of Chief Executive Officer, Cantonment Board, Panchmarhi and the permission - for construction/re construction in the Special Area Development Authority (SADA), Panchmarhi lies with the jurisdiction of Chief Executive Officer, Special Area Development Authority (SADA), Pachmarhi, In respect of above, no permission for construction/re- construction was issued by the Tehsildar, Pipariya.** **8.** That, on 03.01.2014, the Hon'ble High Court of M.P. at Jabalpur passed an order in W.P. No.8098/2018 in petition filed by Kripa Tori and others challenging the order dated 15.03.2011 of the Board of Revenue. The Hon'ble High Court set aside the order dated 15.03.2011 and thereby restored the previous order dated 22.07.1995 whereby the order of the Nazul Adhikari had been affirmed. A true copy of the order dated 03.01.2014 passed by the Hon'ble High Court of M.P. at Jabalpur in Writ Petition No.8098/2011 is being marked and filed herewith as **Annexure A-9** . It is pertinent to mention here that the aforesaid order dated 03.01.2014 of the Hon'ble High Court is in respect of Plot No.14/1 and 14/2 whereas the applicant herein is claiming relief in respect of Plot No.14/3 and 14/4 which were purchased by Ashutosh S/o Shriram Shewalkar and M/s Shewalkar Developers Pvt. Ltd. on 13.09.1991. The said Plot No.14/3 and 14/4 at present are recorded in the name of State of M.P. as Nazul Land. The State of Madhya being aggrieved with the order dated 03.01.2014 has filed an appeal before the Division Bench 10 of the Hon'ble High Court which is pending adjudication as Writ Appeal No.2100/2019. ## **9. That, it is submitted here that the said proceedings before the Hon'ble High Court pertains to Kripa Tori &Ors. and the present intervenor M/s Shewalkar Developers was not a party before any of the Revenue Courts or the High Courts.** **10. That, as per notification dated 19.08.2017, the area under the entire Pachmarhi region admeasuring 1532.521 hectares has been declared as "Eco-sensitive Zone" and the Plot No.14/3 and 14/4 fall within the notified boundaries of said notification.** **11.** That, in view of notification dated 09.08.2017 "no new resort can be constructed and only repairs etc. can be done". Moreover, the Hon'ble High Courtvide interim order dated 01.11.2002 in W.P. No.5937/2002 stayed the construction by making following observation:- "Subject to hearing other side, further construction in and around Pachmarhi Hill Resort is stayed till further order". The aforesaid clarification about stay order being applicable only to new construction has been reiterated by the Hon'ble High Court in its order dated 22.01.2004 in following words:- “By further order dated 13.07.2004, the interim order was clarified that the order of stay will not come in the way of repairing of roads by the State or carrying out repairs to existing building by respective provided, however, that repairs work of any building can be undertaken only after taking due permission from the concerned authority.”” (emphasis supplied) 10. Shri D.S. Naidu, learned senior counsel representing the applicant drew the Court’s attention to the order dated 15[th] December, 2000 passed by the Department Officer(SDO), Pipariya on the application preferred by the applicant seeking mutation based on a registered sale deed dated 13[th] September, 1991 executed by the land owner Dennis Torry in favour of the applicant. The SDO accepted the said application taking note of 11 the fact that Plot No.14 admeasuring 3,23,365 sq. ft. was entered in the name of Dennis Torry who sought and was granted permission to sell the plot in question, by the Government of Madhya Pradesh vide order dated 1[st] May, 1991. Thereafter, by a registered sale deed dated 13[th] September, 1991, Dennis Torry had sold the subject plots of land to Ashutosh Shewalkar on behalf of the applicant company. Consequently, the SDO directed that the land sold by Dennis Torry should be mutated in the name of M/s Shewalkar Developers Ltd. through Ashutosh Shewalkar, resident of Nagpur. There is no dispute that the aforesaid order passed by the jurisdictional Revenue Officer in favour of the applicant has not been questioned in any Court of law. 11. Shri Naidu also drew the Court’s attention to the report of the CEC dated 16[th] June, 2020, as per which the permission to construct has been denied to the applicant on the ground that the State of Madhya Pradesh had filed an affidavit stating that the land falls in the Pachmarhi Wildlife Sanctuary and that the same had been purchased in violation of the provisions of the Wild Life(Protection) Act, 1972. 12. Shri Naidu contended that this objection raised by the State with reference to the Eco Sensitive Zone(hereinafter being referred 12 to as ‘ESZ’) notification dated 9[th] August, 2017 is totally against the material available on record. He drew the Court’s attention to the site map dated 26[th] December, 2023(Annexure A-1 annexed with the compliance affidavit dated 12[th] February, 2024 filed by the respondent-State of Madhya Pradesh) to contend that as a matter of fact, the land owned by the applicant is located right on the periphery of the Nazul land, at a distance of about 10 kms. from the forest area and therefore, the same is well beyond the ESZ area. 13. Shri Naidu further submitted that in view of the categoric assertion made in the compliance affidavit dated 12[th] February, 2024, filed on behalf of the State, it is clear that the plots in question are located in the urban area of Pachmarhi and thus, there is no question of these plots being covered either under the wildlife sanctuary or the ESZ area. He thus urged that the applicant deserves the relief sought for. 14. _Per contra_ , learned counsel appearing for the respondents have opposed the submissions advanced by Mr. Naidu. Learned counsel for the State of Madhya Pradesh urged that the plots in question are subject matter of litigation in the writ appeal pending before the Division Bench of the Madhya Pradesh High Court and 13 thus, the applicant should await the outcome of the aforesaid writ appeal before seeking permission to construct the health/ecoresort on the land in question. 15. His further contention was that the plots in question are recorded in the name of the State of Madhya Pradesh and hence, the applicant cannot claim any right thereupon. 16. Mr. K. Parameshwar, learned Amicus Curiae appearing on behalf of the CEC submitted that in view of the ESZ notification dated 9[th] August, 2017, permission to raise a new construction on the land in question cannot be granted and whatever permissions are sought for, have to be routed through the CEC. 17. Learned counsel appearing for the Union of India adopted the submissions advanced by the standing counsel for the State and learned Amicus Curiae. 18. We have given our thoughtful consideration to the submissions advanced at bar and have gone through the material placed on record. 19. It is not in dispute that the applicant herein was never impleaded in any of the proceedings before the Revenue Courts or the High Court as has been emphatically stated in Para-9 of the 14 compliance affidavit dated 12[th] February, 2024. It is thus, clear that irrespective of the fact that the order passed by the District Collector dated 9[th] August, 2004, purportedly covers entire area of the Plot No. 14 and the transactions done in favour of and by Dennis Torry, the sale deed executed in favour of the applicant and the mutation made in its name had never been questioned in any Court of law. Neither the Revenue Department nor the State Government authorities took the trouble of impleading the applicant as party in any of the abovementioned litigations. The title acquired by the applicant over the subject plots not having been challenged, attainted finality and thus the State cannot claim a right thereupon simply because at some point of time, the plots came to be recorded as Nazul lands in the revenue records. The categoric stand in the compliance affidavit filed by the State(reproduced _supra_ ) fortifies the claim of the applicant that these plots are falling under the urban area. 20. In this background, the applicant is justified in claiming that its proprietary rights guaranteed under Article 300A of the Constitution of India cannot be infringed merely on account of the pending writ appeal before the Madhya Pradesh High Court. 15 21. Resultantly, we are of the firm opinion that the permission sought by the applicant for raising construction of health/ecoresort cannot be opposed only on account of pendency of the writ appeal before the Madhya Pradesh High Court. However, it can be said without a cavil of doubt that activities, if any, on the Plot Nos. 14/3 and 14/4 purchased by the applicant from Dennis Torry would have to be carried out strictly in accordance with the ESZ notification dated 9[th] August, 2017, issued by the Ministry of Environment, Forest and Climate Change. Nonetheless, the applicant would be at liberty to satisfy the authorities that the plots in question are beyond the Eco-Sensitive Zone. 22. Furthermore, since the writ appeal pending before the Madhya Pradesh High Court arises out of the orders passed in relation to the title rights of Dennis Torry, from whom the applicant purchased the plots in question, the activities, if any, undertaken by the applicant on the said plot of land would also remain subject to the outcome of the said writ appeal. 23. We, therefore, direct that the application filed by the applicant for raising construction on plot Nos. 14/3 and 14/4 shall be decided objectively by the CEC/Competent Authority of the 16 local body keeping in view the location of the land with reference to the notified boundaries of the ESZ. 24. While deciding the application filed by the applicant, the authorities shall also bear in mind the fact that it is the pertinent case presented before this Court that a large number of resorts of Madhya Pradesh Tourism Development Corporation and Special Area Development Authority(SADA) are existing on areas abutting the land owned by the applicant. 25. The application/s shall be decided within a period of two months from today. Needless to say, that in the event of any adverse orders being passed, the applicant shall be at liberty to challenge the same as per law. 26. The applications are disposed of in above terms. No order as to costs. **………………….……….J. (B.R. GAVAI)** **………………………….J. (SANDEEP MEHTA)** **New Delhi; May 16, 2024** 17
End of Judgment Record
Browse All Landmark Cases Judgments
2019-01-22

State of Himachal Pradesh & Anr. v. Pinju Ram & Others; State of Himachal Pradesh & Ors. v. Ganesh Dutt & Anr.

This batch of appeals concerns regularisation and monetary benefits of part‑time employees in Himachal Pradesh who were converted to daily‑wage status. The State had issued a policy on 27 February 2004: part‑time Class‑IV employees who had completed ten years of continuous service as on 31 December 2003 would be made daily wagers with prospective effect, and posts vacated by such employees would stand abolished; Education and Ayurveda were excluded from the policy. Revenue Chowkidars, engaged by Panchayats, were not covered by that policy and received separate treatment. Following writ petitions and an order of the Himachal Pradesh High Court and in light of later developments, the State drew‑up directions in 2011 (22 September) to give seniority to Revenue Chowkidars on the basis of ten years of service, but with wages from the date of actual appointment and without back‑dated monetary benefits; 7 July 2012 further instructions reiterated this stance for remaining part‑time employees, with monetary benefits not guaranteed in the interregnum. The respondents pressed for back wages dating from 1 January 2007 and broader coverage. The Supreme Court held that the 2007 back‑pay direction was unsustainable, clarified that seniority would count from ten years without past benefits, and that the 2011 policy and Moti Singh principle should guide the approach. The appeals are allowed; no costs. The related writ petitions are to be disposed of consistent with these directions.

2018-08-14

Union Bank of India and Others v. C.G. Ajay Babu and Anr.

This is a Supreme Court of India appeal concerning the forfeiture of gratuity under the Payment of Gratuity Act, 1972. The respondent was a branch manager of the appellant bank and was dismissed on 3 June 2004 after disciplinary proceedings. A show-cause notice sought to forfeit gratuity due to misconduct involving moral turpitude, which was ordered on 20 April 2004. The High Court upheld the dismissal but held that gratuity could be paid since there was no financial loss to the bank, and that a bipartite settlement between the bank and employees permitted forfeiture only where misconduct caused financial loss. The Division Bench, however, held that forfeiture under Section 4(6) must be read together with Section 4(5) and that no loss was proven, thus entitling the employee to gratuity in accordance with the bipartite settlement. The Supreme Court agreed with the High Court that forfeiture is not automatic; it is controlled by Sections 4(5) and 4(6) of the Act and by the bipartite settlement, which requires loss to justify forfeiture. The Court emphasized that an act must constitute an offence involving moral turpitude and that conviction is generally required for forfeiture under 4(6)(b)(ii). The appeal is dismissed with no costs.

2018-09-25

Reema Salkan v. Sumer Singh Salkan

This is a Supreme Court of India criminal appeal under the Criminal Appellate Jurisdiction arising from a maintenance dispute under Section 125 Cr.P.C. The parties, married in 2002, had a protracted litigation history. The Family Court granted maintenance to the wife from 17 July 2003 to 8 December 2010, and held no maintenance thereafter. The High Court, in revision, partly allowed the application, directing Rs.9,000 per month from 9 December 2010 onward, while upholding the earlier period’s Rs.10,000 per month. This Court had earlier granted interim maintenance of Rs.20,000 per month in 2014 (Criminal Appeal Nos. 2347-2349 of 2014). The appellant contends there has been no change in circumstances since the interim order and that the respondent’s substantial assets, education, and overseas earnings establish the capacity to pay higher maintenance. The respondent defends the High Court’s reasoning, arguing that the Family Court’s assessment, demeanor observations, and the principle that maintenance should not be perpetual require careful scrutiny, and that the notional minimum wage approach used by the High Court is flawed. The overarching issue is the quantum of monthly maintenance payable to the appellant and whether the interim amount should be augmented beyond the period up to 2010.”

2019-12-03

M/s Embassy Property Developments Pvt. Ltd. v State of Karnataka & Ors.

This judgment concerns three Civil Appeals filed by a Resolution Applicant, the Corporate Debtor (through its Resolution Professional) and the Committee of Creditors, challenging an Interim Order of the Karnataka High Court staying an NCLT order in proceedings under the Insolvency and Bankruptcy Code, 2016. The NCLT Chennai had admitted an application under Section 7 of the IBC against M/s Tiffins Barytes Asbestos & Paints Ltd. and directed a moratorium under Section 14. The Interim Resolution Professional then sought a deemed extension of a mining lease under MMDR Act, 1957 and the Government of Karnataka rejected it. The NCLT, by an order dated 11.12.2018, set aside the Government’s order and directed execution of Supplement Lease Deeds for the period up to 31.03.2020. The Government of Karnataka challenged this in a High Court writ petition, which stayed the impugned NCLT order. The core issues were: (i) whether the High Court may interfere under Article 226/227 with an NCLT order in IBC when an appeal lies to the NCLAT, and (ii) whether fraud can be inquired into by NCLT/NCLAT in CIRP. The Court reiterates that IBC is a complete, umbrella code with a three‑tier mechanism (NCLT, NCLAT, Supreme Court) and that public‑law disputes arising from MMDR Act obligations lie outside IBC. It ultimately holds that while NCLT/NCLAT may inquire into fraud, they cannot adjudicate MMDR‑related public legal disputes; and the High Court’s writ jurisdiction in public‑law contexts remains permissible. The appeals are dismissed.