High Court of KeralaDivision BenchWrit appeal allowed; judgment of the learned Si...

The Superintending Engineer, PWD, Muvattupuzha; The Executive Engineer, Office of the Civil Engineer, Edamalayar Irrigation Project Division, Angamaly; The Village Officer, Manickamangalam; The Village Officer, Kalady; The Deputy Tahsildar (R.R) Taluk Office, Aluva; The Chief Engineer, Project-II, Irrigation, Trivandrum; State of Kerala, rep. by the Additional Secretary to Government, Water Resources (MP) Department, Government Secretariat, Thiruvananthapuram v. K.A. Joy Kolencherry

Case / Petition Number:WA No. 1605 of 2016

Case Details & Bench

Court
High Court of Kerala
Hon'ble Judges
  • S. Manikumar, Chief Justice
  • Shaji P. Chaly, J
Judgment Date
2020-01-07
Court Decision / Holding
Writ appeal allowed; judgment of the learned Single Judge set aside; appellants entitled to recover interest; up to five equated monthly installments starting 27.01.2020; if any installment is defaulted, recovery may proceed in lump sum under law.
Final Disposition
Writ appeal allowed; judgment of the learned Single Judge set aside; Government entitled to recover interest; five instalment plan; default allows lump-sum recovery.

Parties to the Case

Appellants / Petitioners

  • K.A. Joy Kolencherry

Respondents

  • The Superintending Engineer, PWD, Muvattupuzha
  • The Executive Engineer, Office of the Civil Engineer, Edamalayar Irrigation Project Division, Angamaly
  • The Village Officer, Manickamangalam
  • The Village Officer, Kalady
  • The Deputy Tahsildar (R.R) Taluk Office, Aluva
  • The Chief Engineer, Project-II, Irrigation, Trivandrum
  • State of Kerala, rep. by the Additional Secretary to Government, Water Resources (MP) Department, Government Secretariat, Thiruvananthapuram

Legal Representation & Advocates

Counsels for Petitioners

  • • Philip J. Vettickattu, Advocate
  • • Vineeth KuriaKose, Advocate

Counsels for Respondents

  • • Sri Surin George Ipe, Senior Government Pleader

Case Synopsis & Summary

This writ appeal arises from a dispute over the recovery of interest on a government contract terminated in 1982. The writ petitioner, K.A. Joy Kolencherry, challenged the demand for interest accompanying a principal amount allegedly due following termination of the contract; the original revenue recovery demand (Ext.P2) did not include interest, and attempts to challenge it culminated in the High Court’s 2015 decision (W.P.(C) 7447/2013) that declined interest. The Division Bench, however, held that the amount claimed as interest can be recovered under the Kerala Revenue Recovery Act, 1968, because the “arrears of public revenue due on land” includes engagements such as contracts and other “engagements” as defined by Section 2(a). Relying on Clariant International Ltd. v. SEBI, the court noted that interest may be awarded under an agreement, statutory provision, mercantile usage, or equitable considerations; where none exists, interest is generally payable at market rate. The court allowed the appeal, set aside the single judge’s decision, and granted liberty to recover the interest, but ordered a five-installment payment plan beginning 27.01.2020 to enable settlement, with default permitting lump-sum recovery.

Provisions of Law Cited

Section 6 of Kerala Revenue Recovery Act, 1968Section 2(a) of Kerala Revenue Recovery Act, 1968

Legal Doctrines & Maxims

  • Interest can be awarded in terms of an agreement or statutory provisions. It can also be awarded by reason of usage or trade having the force of law or on equitable considerations. Interest cannot be awarded by way of damages except in cases where money due is wrongfully withheld and there are equitable grounds therefor, for which a written demand is mandatory.
  • In the absence of any agreement or statutory provision or mercantile usage, interest payable can be only at the market rate.

Submissions & Arguments

Contentions of Appellants / Petitioners

The petitioner contends that the Ext.P2 revenue recovery demand raised only the principal amount and did not include interest; there is no express liability for interest under the original contract, and the earlier orders allowing or waiving interest are not binding against the government. The writ petitioner argues that the liability to pay interest would be discriminatory and undermines the previous deposit of Rs. 5,00,000; reliance on Ext.P12 to justify interest demora is misplaced; the decision of the Single Judge to decline interest should be maintained to avoid unwarranted enrichment.

Contentions of Respondents

The respondents submit that under Section 6 of the Kerala Revenue Recovery Act, 1968, arrears of public revenue due on land includes engagements such as contracts; therefore interest is recoverable when money falls due from a contract; the definition under Section 2(a) extends to such engagements; reliance on Clariant v. SEBI (2004) 8 SCC 524 and Municipal Corporation of Delhi v. Sushila Devi supports the proposition that interest can be awarded or recovered under statutory or equitable grounds; the court should permit recovery of interest, with a reasonable instalment plan.

Cited Precedents (2)

Case NameCitationTreatmentExplanation
Clariant International Ltd. v. Securities & Exchange Board of India(2004) 8 SCC 524PositiveCited to illustrate that interest can be awarded under an agreement or statutory provision, or by mercantile usage/equitable grounds; supports the basis for claiming interest in this case.
Municipal Corporation of Delhi v. Sushila Devi(1999) 4 SCC 317PositiveCited for the proposition that interest payable can be at market rate in absence of express agreement or statutory provision; used to ground equitable jurisdiction.

Diagnostic Tool

Beta

Does this judgment govern your specific facts?

Don't risk relying on a distinguishable precedent. Enter your facts or proposition below. We will test it against The Superintending Engineer, PWD, Muvattupuzha; The Executive Engineer, Office of the Civil Engineer, Edamalayar Irrigation Project Division, Angamaly; The Village Officer, Manickamangalam; The Village Officer, Kalady; The Deputy Tahsildar (R.R) Taluk Office, Aluva; The Chief Engineer, Project-II, Irrigation, Trivandrum; State of Kerala, rep. by the Additional Secretary to Government, Water Resources (MP) Department, Government Secretariat, Thiruvananthapuram v. K.A. Joy Kolencherry and instantly map out authorities that support, challenge, or govern your position.

Extracted Judgment Text

Exact text extracted from official judgment records.

IN THE HIGH COURT OF KERALA AT ERNAKULAM PRESENT THE HONOURABLE THE CHIEF JUSTICE MR.S.MANIKUMAR & THE HONOURABLE MR. JUSTICE SHAJI P.CHALY TUESDAY, THE 07TH DAY OF JANUARY 2020 / 17TH POUSHA, 1941 WA.No.1605 OF 2016 AGAINST THE JUDGMENT IN WPC 7447/2013 DATED 10-08-2015 OF HIGH COURT OF KERALA ## APPELLANTS/RESPONDENTS IN W.P.(C): - 1 THE SUPERINTENDING ENGINEER, PWD, MUVATTUPUZHA 686 661. - 2 THE EXECUTIVE ENGINEER, OFFICE OF THE CIVIL ENGINEER, EDAMALAYAR IRRIGATION PROJECT DIVISION, ANGAMALY 683 572. - 3 THE VILLAGE OFFICER, MANICKAANGALAM 683 574. - 4 THE VILLAGE OFFICER, KALADY 683 574. - 5 THE DEPUTY TAHSIDAR (R.R) TALUK OFFICE, ALUVA - 6 THE CHIEF ENGINEER, PROJECT-II, IRRIGATION, TRIVANDRUM 695 001. - 7 STATE OF KERALA, REP. BY THE ADDITIONAL SECRETARY TO GOVERNMENT, WATER RESOURCES (MP) DEPARTMENT, GOVERNMENT SECRETARIAT, THIRUVANANTHAPURAM. BY SRI. SURIN GEORGE IPE, SR. GOVERNMENT PLEADER ## RESPONDENT/PETITIONER IN W.P.(C): K.A.JOY KOLENCHERRY HOUSE, NEELESWARAM P.O, KALADY VIA, MANICKAMANGALAM. R1 BY ADV. SRI.PHILIP J.VETTICKATTU R1 BY ADV. SRI.VINEETH KURIAKOSE THIS WRIT APPEAL HAVING BEEN FINALLY HEARD ON 07-01-2020, THE COURT ON THE SAME DAY DELIVERED THE FOLLOWING: W.A.No. 1605/2016 : 2 : ## **Dated this the 7[th] day of January, 2020.** ## **JUDGMENT** ## **Shaji P. Chaly, J** This writ appeal is filed by the respondents in W.P.(C) No. 7447 of 2013 against the judgment dated 10.08.2015, whereby interest, on the amount due to the Government, on account of the contract awarded was declined by the learned single Judge. The subject issue in the writ petition was the termination of contract awarded to the writ petitioner, on 28.06.1982 and on account of the termination, the appellants have raised a demand to remit an amount of Rs.3,32,550/- presumably in terms of the contract and the relevant provisions of PWD manual in respect of awarding contracts by the Government. Initially, Ext.P2 notice was issued raising the demand for principal amount only, and no demand was raised for interest. The said demand was challenged before this Court by filing OP No. 10188 of 1983, which was dismissed. Eventhough an appeal was preferred by the writ petitioner, it was also dismissed as per judgment dated 19.06.1990 in W.A. No. W.A.No. 1605/2016 : 3 : 348 of 1990, however leaving open the liberty of the writ petitioner to approach the Civil Court challenging the termination of contract. Apparently, the writ petitioner filed O.S. No. 532 of 1990 before the Additional Sub Court, North Paravur and the said suit was decreed declaring that the termination was illegal. Aggrieved, the State filed an appeal as A.S. No. 98 of 1996 before this Court and in the said appeal, the judgment and decree of the Subordinate Judge's Court was set aside and the suit was dismissed. Thereafter, Ext.P6 demand notice and Ext. P7 recovery notices were issued wherein the amount claimed was Rs.15,10,104/- inclusive of interest. It was challenging the said demand that the writ petition in question was filed primarily on the ground that in the original revenue recovery demand i.e., Ext.P2, no demand for interest was raised. Further, it is contended that the amount is claimed as damages and there is no determination of liability and therefore, the liability itself is questionable. Anyhow, from the judgment of the learned single Judge, it is evident that the writ petitioner was prepared to pay the principal amount, and it was submitted before the learned single W.A.No. 1605/2016 : 4 : Judge that already an amount of Rs.5,00,000/- was deposited. The learned single Judge, thereupon, held that normally the interest could be levied based on the determination of liability and for the delay in payment, and further observed that the writ petitioner made a request before the Superintending Engineer to waive interest, which was rejected as per Ext.P14. However, relying upon Ext.P12, a communication issued in the year 2011 in a similar situation against one P.O. Paulose, the learned single Judge found that the Superintending Engineer only demanded principal amount without claiming interest and therefore, the recovery against the petitioner towards the interest will be discriminatory. It is this portion of the judgment that is under challenge in the writ appeal. 2. We have heard Sri. Surin George Ipe, the learned Senior Government Pleader and Sri. Philip J Vettickattu, the learned counsel appearing for the respondent/writ petitioner and have perused the pleadings and documents on record. 3. The learned Government Pleader basically addressed the arguments relying upon Section 6 of the W.A.No. 1605/2016 : 5 : Kerala Revenue Recovery Act, 1968 ('the Act, 1968' for short) dealing with “the interest on arrears of public revenue due on land”, which stipulates that “arrears of public revenue due on land shall bear interest at the rate of 12 per cent per annum or at such other rate as may be notified by the Government from time to time in the Gazette.” Harping upon the said provision, learned Senior Government Pleader contended that eventhough there is no specific provision made in the contract entered into by and between the parties for recovery of interest against any amount due to the Government on account of the termination of the contract, the aforesaid statutory provision will have to be read into the contract, since the Government or any authority functioning under the Government is entitled to enter into a contract overlooking a statutory provision. 4. On the other hand, the learned counsel appearing for the respondent, Sri. Philip J. Vettickattu, has submitted that the amount due under a contract will not be governed by 'the arrears of public revenue due on land' and therefore, Section 6 of the Act, 1968 will not apply to the W.A.No. 1605/2016 : 6 : facts and figures available in the case at hand. 5. The learned counsel has also taken us to Section 2(a) of the Act, 1968 dealing with the definition of 'the arrears of public revenue due on land', which defines that “means the whole or any portion of any kist or instalment of such revenue not paid on the day on which it falls due according to the kistbandy or any engagement or usage.” 6. The contention advanced by the learned counsel is that none of the eventualities contemplated under 'the arrears of public revenue due on land' will come into play so as to invoke the powers to demand interest as is contemplated under Section 6 of the Act, 1968. 7. We have appreciated the rival contentions made across the Bar. In our considered opinion, 'the arrears of public revenue due on land' as defined under Section 2(a) of the Act, 1968 deals also with 'engagement, other than kistbandy'. The word 'engagement' is not defined under the Act, 1968. The word 'engagement' is defined under the Black's Law Dictionary, 9[th] Edition to mean 'a contract or agreement involving mutual promise'. It is an admitted fact that the amount has fallen due from the writ petitioner on W.A.No. 1605/2016 : 7 : account of a contract entered into by the writ petitioner with the Government. Therefore, the issue is squarely covered under 'the arrears of public revenue due on Land'. We are also of the opinion that whatever be the terms of the contract, if any amount had fallen due from the writ petitioner on account of the contract, necessarily the provision contained under the Act, 1968 will come into play and therefore, Section 6 has come into play, when the amount had fallen due from the writ petitioner on account of the contract entered into by and between the parties. This is exactly the question considered by the Apex Court in the judgment in **Clariant International Ltd. v. Securities & Exchange Board of India**[1] and paragraphs 30 and 31 are relevant to the context, which read thus: “30. Interest can be awarded in terms of an agreement or statutory provisions. It can also be awarded by reason of usage or trade having the force of law or on equitable considerations. Interest cannot be awarded by way of damages except in cases where money due is wrongfully withheld and there are equitable grounds therefor, for which a written demand is mandatory. 31. In the absence of any agreement or statutory provision or a mercantile usage, interest payable can be only at the market rate. Such interest is payable upon establishment of totality of circumstances justifying exercise of such equitable jurisdiction. (See _**Municipal Corpn. of Delhi v. Sushila Devi, SCC para 16**_ [(1999) 4 SCC 317]” 1 (2004) 8 SCC 524 W.A.No. 1605/2016 : 8 : 8. We are also informed by the learned Government Pleader, Sri. Surin George Ipe, that demand was raised towards interest against Mr. P.O. Paulose after the writ petition was disposed of and the same was recovered. So much so, we are of the considered opinion that merely because the demand was not raised for interest against yet another contractor, that cannot be a binding precedent for a Court to consider the question as to whether the demand for interest raised by the Government against the writ petitioner was in accordance with law. We are satisfied that the issue was raised by the writ petitioner before the Superintending Engineer itself, which was declined and merely because when a demand was raised originally, no interest was demanded, that will not detain the Government from demanding interest at a later point of time. 9. That being the legal and factual situation, we are of the considered opinion that the appellants are entitled to succeed in the writ appeal and the writ appeal is accordingly allowed and the judgment of the learned single Judge is set aside. Needless to say, the appellants are at W.A.No. 1605/2016 : 9 : liberty to proceed with the demand for recovering the interest. However, we feel that an opportunity can be provided to the writ petitioner to pay outstanding amount of interest in reasonable equated monthly instalments. Accordingly, we permit the petitioner to pay the interest amount outstanding in 5 equated monthly instalments starting from 27.01.2020 and on the corresponding dates of the successive four months. However, if any of the instalments is violated, the appellants will be at liberty to proceed with the recovery and to recover the amount in lump and in accordance with law. sd/- **S. MANIKUMAR, CHIEF JUSTICE.** sd/- **SHAJI P. CHALY, JUDGE.** Rv W.A.No. 1605/2016 : 10 :