Case Synopsis & Summary

These two Civil Appeals revolve around Section 28-A of the Land Acquisition Act, 1894 and the compute-ment period for redetermination of compensation where multiple awards have been passed for lands covered by the same notification. The Gauhati High Court had held petitions for redetermination within time by treating the three-month period as running from the earliest award, and the Land Acquisition Collector had rejected petitions as time-barred on that basis. The Supreme Court nonetheless addressed the legal question in light of prior judgments: Pradeep Kumari (1995) and Jose Antonio Cruz Dos R. Rodriguese (1996) had held that the right to seek redetermination arises from the award on which redetermination is sought, and there is no confinement to the earliest award; the Court overruled Babua Ram and Karnail Singh to the extent they restricted the period to the earliest award, while affirming that the limitation period must be computed from the Court’s award underpinning the redetermination. The Court, relying on these decisions and citing Hansoli Devi (2002) in a related discussion, affirms that Section 28-A permits redetermination on the basis of any award, and the petitions are to be considered in light of the award(s) on which redetermination is sought. The appeals are dismissed. The judgment is delivered by Raju, J., sitting with ShivaraJ V. Patil, Jj.

Precedent Explorer

Find Cases Like This

Explore other judgments dealing with similar legal situations, facts, or statutory provisions.

Case Details & Bench

Court
Supreme Court of India
Hon'ble Judges
  • Doraiswamy Raju
  • Shivraj V. Patil
Judgment Date
2002-12-03
Court Decision / Holding
Appeals dismissed.
Final Disposition
Appeals dismissed.

Parties to the Case

Appellants / Petitioners

  • The State of Tripura
  • Anr.

Respondents

  • Roopchand Das
  • and others

Legal Representation & Advocates

Counsels for Petitioners

  • • Gopal Singh
  • • Navin Prakash
  • • Rahul Singh

Provisions of Law Cited

Land Acquisition Act, 1894; Section 28-ASection 4(1) of the ActSection 18 of the ActPart-III of the Act

Submissions & Arguments

Contentions of Appellants / Petitioners

The applicants contended that, under Section 28-A, the right to seek redetermination arises from the court’s award and is not confined to the earliest award; the three-month limitation should not be tethered to the earliest award, but to the award on which redetermination is sought, allowing relief against subsequent awards when more favorable compensation is determined. They urged adherence to the beneficent aim of Section 28-A, citing Pradeep Kumari (1995) and Dos R. Rodriguese (1996) to show the absence of an earliest-award restriction.

Contentions of Respondents

The respondents argued that the period of three months for filing under Section 28-A could be anchored to the earliest award and that time-bar under the Collector’s interpretation should be maintained; they maintained that redetermination petitions based on later awards must be viewed through the lens of the earlier award, and the time-limit should be calculated accordingly, consistent with the Collector’s approach.

Legal Doctrine & Issue Explorer

Explore This Legal Issue

Find relevant judgments and authoritative positions on the legal questions discussed here.

Cited Precedents (5)

Case NameCitationTreatmentExplanation
Union of India and Anr. v. Pradeep Kumari and Ors.1995(2) SCC 736PositiveHeld that the right to apply under Section 28-A arises from the Court’s award and is not confined to the earliest award; this guided subsequent reasoning.
Jose Antonio Cruz Dos R. Rodriguese and Anr. v. Land Acquisition Collector and Anr.1996(6) SCC 746PositiveFollowed Pradeep Kumari; supports a broad reading of Section 28-A beyond the earliest award.
Babua Ram v. State of U.P.—OverruledOverruled on the limited question that it confined the right to seek redetermination to the earliest award.
Union of India v Karnail Singh—OverruledOverruled on the limited question of restricting 28-A redetermination to the earliest award.
Union of India and Anr. v. Hansoli Devi and Ors.2002(7) SCC 273Mentioned OnlyCited in discussion; the Constitution Bench did not answer the specific question here.
Case Applicability Diagnostic

Apply This to My Facts

Share your situation and test whether this judgment governs, supports, or challenges your case.

Official Judgment Record
•2,019 words•~10 min read

In The Court Record

THE STATE OF TRIPURA AND ANR. v. ROOPCHAND DAS AND ORS.

A THE STATE OF TRIPURA AND ANR. v. # ROOPCHAND DAS AND ORS. DECEMBER 3, 2002 ## B [DORAISWAMY RAJU AND SHIVARAJ V. PATIL, JJ.] _Land Acquisition Act, 1894; Section 28-A:_ _Land acquisition-Compensation-More than one award-Petition filed_ C _for redetermination of compensation against subsequent award-Rejected by Land Acquisition Collector as time barred counting period of limitation from an earlier award in respect of same lands_:_Reversed by High Court-On appeal, Held: Since provisions of law allow filing of application by the awardee for redetermination of compensation against an award without any_ D _restriction as to choice of award when more than one awards passed-Application for redetermination of compens(ltion could be filed against subsequent award counting period of limitation accordingly._ The question of law which arose in these appeals was when more than one award passed by the Reference Court on different dates in respect of lands E covered by the same Notification for the purpose of computing three months period for filing of application for redetermination of compensation as stipulated in Section .28-A of the Land Acquisition Act whether the date of earliest award would only be relevant and not the ~ubsequent or latest date of awards. F Answering the question in negative, the Court HELD: The later part. of Section 28-A of the Land Acquisition Act stipulates that the amount of compensation payable to awardee may be redetermined on the basis of.the amount of compensation·awarded by the Court and leaves the choice to the person making such an application for reG determination, without confining o~ restricting the area of choice of such person to any one or the other award though it could be availed of only once and not as many number of times as there are so many awards. Under the circumstances, the reasoning of the Land Acquisition Officer that for purposes of computing the three months period stipulated in Section 28-A of H the Act, the date of the earliest award would be relevant and not the subsequent . 448 STATE _v._ ROOPCHAND DAS [DORAISWAMY RAJU. J.] 449 A or latest was rightly rejected by the High Court. [451-C; 450-D-Ej _Union of India and Anr. v. Pradeep Kumari and Ors.,_ f 1995[ 2 SCC 736 **and** _Jose Antonio Cruz Dos R. ·Rodr.iquese and Anr._ v. _land Acquisition Collector and Anr.,_ j1996f 6 SCC 746, relied on. _Union of India and Anr._ v. _Hanso/i Devi and Ors.,_ [20021 7 SCC 273, B referred to. CIVIL APPELLATE JURl.SDICTION: Civil Appeal No. 3515of1997. From the Judgment and Order dated 21.1.1997 of the High Court of Gauhati, in C.R. Nos. 12of1997. Gopal Singh, Navin Prakash and Rahul Singh, for the Appellants. For Respondent Ex-parte .in CA 3516/1997. -I > The Judgment of the Court was delivered by D **RAJU, J.** These two appeals involve common and identical questions of law and are dealt with together. In C.A.No. 3515 of 1997, the challenge is to the judgment dated 21.1.97 of the Gauhati High Court, Agartala Bench, made in Civil Rule No.12 of 1997,.whereunder the High Court, applying the earlier decision rendered in Civil Rule IO of 1997, directed, while setting aside E the order dated 18.9.96 of the Land Acquisition Collector, the said Collector to consider the petitions filed by the respondent-landowners under Section 28-A of the Land Acquisition Act, 1894 (hereinafter referred to as "The Act") on merits and in accordance with law, holding them to be within the period of limitation stipulated therefor. The appeal in C.A. No.351611997 is against F the above noticed earlier decision in Civil Rule I 0 of 1997 dated 21.1.97. So far as C.A. No.3515 of 1997 is concerned, relying upon the Reference Court's Award dated 19.9.94 in case Nos. Misc. L.A.29/92 and 30/92, the respondents sought by a petition filed on 16.12.94 for re-determination of the compensation for their lands invoking Section 28-A of the Act. The Land G Acquisition Collector rejected the claim by his order dated 18.9.96 on the ground that the same was not filed within the stipulated period of three months inasmuch as, according to the Collector, the period of limitation had to be calculated from 25.5.94, an earlier Award of the Reference Court in respect of the !ands covered by the same Notification under Section 4 ( 1) of the Act and not with reference to the latest or subsequent Awards of the H 450 SUPREME COURT REPORTS [2002] SUPP. 4 S.C.R. A Reference Court. So far as the appeal in C.A. 3516 of 1997 is concerned, the Land Acquisition Collector, was moved by the land-owners for re-detennination of compensation in respect of their lands invoking Section 28~A of the Act, with reference to an award of the Reference Court made on 5 .5. 94 in respect of cases Misc.LA. 34-36/1992 and on 8.6.94 in Misc. Cases Nos.40, 41, 45 & B 46/1992. The petition was filed on 1.8.94. But the Land Acquisition Collector by his order dated 18.9.96, rejected the same as time-barred on the view that in respect of the lands covered. by the very same Notification under Section 4(1) of the Act, there was an earlier Award passed by the Reference Court on 21.12.93 itself in Misc. Case Nos.37, 38, 39, 42, 43 and 44/1992 and that the period of limitation has to be calculated from the earliest of the Awards, C which in this case, as per Collector, was on 21.12.93. I- The fact that ifthe latest Awards are taken into account, the claim made under Section 28-A of the Act is well within time, is not in controversy and the Land Acquisition Collector himse:: noticed the said aspect. But in view of his opinion that of the Awards by the Reference Court when more than D one passed on different dates are available in respect of lands covered by the same Notification, for purposes of computing the three months period stipulated in Section 28-A of the Act, the date of the earliest one would be relevant and not the subsequent or latest, the claims came to be rejected. It was this reasoning of the Land Acquisition Collector that did not meet with the E approval of the High Court, in our view rightly too, in the light of the decision of this Court in _Union of India and Anr._ v. _Pradeep Kumari and Ors.,_ [1995] 2 sec 736. Heard, the learned counsel appearing on either side, who reiterated the stand taken for the respective parties before the High Court. This Court in _p_ the decision in _Pradeep Kumari and Ors.,_ (supra) categorically held that "the right to make the application under Section 28-A of the Act arises from the award of the Court on the basis of which the person making the application ·is seeking re-determination of the compensation. There is nothing in Sub_ section (l) of Section 28-A to indicate that this right is confined in respf'.Ct of the earliest award that is made by the court after the coming into force of G Section 28-A." Any construction to the contra introducing such words, not found.engrafted in the very provision would amount to curtailing the ~plitude of the provision resulting virtually in restricting a benefit conferred, particularly of a beneficent provision normally not permissible by judicial interpretation~ It w~ also held therein that there is nothing iD. the wordings of Section 28H A to indicate that the legislature intended to confer any such limited benefit 451 STATE _v._ ROOPCHAND DAS [DORAlSWAMY RAJU . .1.J thereunder which would have ~he inevitable consequence of denying the A **benefit of higher a1nount on the basis of the subsequent award. Such an** interpretation as would restrict the benefit of Section 28-A to the first of the **Award in the series and in point of tin1e, was also considered to result 111ore in· the perpetuation of the inequality in the pay1nent of compensation, which the legislature specifically intended to remove by enacting the provision and B** that, therefore, the object underlying Section 28-A would be better served and **achieved by giving the word "an award" in Section 28-A its natural meaning,** as meaning any one of the award(s) made by the court under Part-III, after the coming into force of Section 28-A. That apart, in our view, even the later part of Section 28-A which stipulates, "require that the amount of compensation payable to them may be re-determined on the basis of the amount of C compensation awarded by the Court", leaves the choice to the person making **such an application for re-determination, without confining or restricting the** area of choice of such person to any one or the other, "though it could be **availed of only once and not as many number of times as there are so many awards.** D The principles laid down by a bench of three learned Judges of this Court in _Pradeep Kumari and Ors._ (supra) was also followed in yet another decision of a bench of three learned Judges in Jose _Antonio Cruz Dos R. Rodriguese and Anr._ v. _land Acquisition Collector and Anr .._ [1996] 6 SCC 746, observing as hereunder: E **"'4. We may now refer to the case-law. A two-Judge Bench of this** Court in _Babua Ram_ v. _State of U.P._ dealt with this precise question and held that the period of limitation begins to run from the date of the first award made on a reference under Section 18 of the Act, and successive awards cannot save the period of limitation; vi de paragraphs F 19 and 20 of the reporter. This view was reiterated by the same _Bench in Union of India_ v. _Karnail Singh_ wherein this Court held that the limitation of three months for an application for redetermination of compensation must be computed from the date of the earliest award made by a civil court, a~d not the judgment rendered by an appellate court. This was followed by the decision of a three-Judge Bench in G _Union of India_ v. _Pradeep Kumari_ wherein it was held that the benefit under Section 28-A can be had within three months from the date of 1. 119951 2 sec 689 2. [19951 2 sec 728 3. [19951 2 sec 736 **H** 452 SUPREME COURT REPORTS [2002] SUPP. 4 S.C.R. ## A ## B c the award of the Reference Court on the basis whereof redetermination is sought. The earlier two decisions in the case of Babua Ram I and Karnail Singh 2 were overruled on the limited question that they sought to confine the right to seek redetermination to the earliest award made by the Court under Section 18 of the Act after the introduction of Section 28-A into the Act. _There_ is, _however, no doubt that the period of limitation has to be computed from the date of the Court's award under Section I 8 on the basis whereof redetermination_ is _sought._ Admittedly, in both the cases at hand, the applications for redetermination of compensation under Section 28-A were made long after the expiry of three months from the date of the award ·of the Court which constituted the basis for seeking redetermination. We are, therefore, of the opinion that the High Court was right in taking the view that both the applications were timebarred." ## (Emphasis supplied) ## D > The correctness of _Pradeep Kumari's_ case (supra) on this aspect when sought to be raised before the Constitution Bench in the batch of cases, including the appeals before us in _Union of India and Anr._ v. _Hansoli Devi and Ors._ reported in [2002] 7 SCC 273, it was observed, "But since that question has neither been referred to us under the order of reference made E in the present case nor does it arise in the case in hand, we refrain from answering -the same." A Review Petition filed by the appellants herein before the Constitution Bench in these appeals, viz., R.P.(C) 1437-38 of2002, has also been dismissed. In the light of the above, we see no merit in the challenge made to the orders of the High Court. The appeals, consequently, fail and F[shall stand dismissed. No costs. ] ## S.K.S. Appeals dismissed.
End of Judgment Record
Browse All Supreme Court of India (2002) Decisions
2002-12-17

Devender Pal Singh v. State N.C.T. of Delhi

This judgment deals with three review petitions under Article 137 of the Constitution challenging the death sentence in cases involving murder. The petitions focus on whether death should be imposed when one of the three Judges on the bench records acquittal or advocates a life sentence. The Court clarifies that while the scope of review in criminal proceedings has broadened, a review is not a re-hearing of the original appeal and must be grounded in a miscarriage of justice. Review petitions are normally disposed of by circulation, not as full-blown re-arguments, and are permissible only where there is a grave error, manifest on the face of the order, or a miscarriage of justice. The opinion cites P.N. Eswara Iyer and Suthendraraja to stress that review is not routine and cannot be equated with the original hearing; the finality of judgments is preserved unless compelling reasons exist. The majority holds that a death sentence should not be reconsidered merely because two Judges share a different view than one Judge, nor should acquittal by a lower court automatically negate the Possibility of a death sentence if the circumstances still warrant it. The judgment also discusses the “rarest of rare” standard from Bachan Singh and the scope of reference to a larger Bench. A dissent by Shah, J. proposes that altering the death sentence to life imprisonment would meet justice in some cases, but the majority dismisses the petitions.

2002-04-24

Narpat Singh v Jaipur Development Authority

This Supreme Court decision concerns the long-running dispute over land acquired under the Lal Kothi Scheme in Jaipur. Land belonging to four appellants was acquired for a public purpose and an award awarded monetary compensation along with directions to allot residential plots of 1000 or 2000 square yards. On reference, courts enhanced the monetary compensation while upholding the plot allotments. A tripartite settlement among the claimants, the State Government and the Urban Improvement Trust ( UIT, later Ja ipur Development Authority, JDA) reduced the compensation in exchange for plot allotments, with contestants paying a reduced price to acquire plots. Executions proceeded and plots were delivered. The High Court later set aside the compromise decree, holding that the allotment of land by an award in land acquisition proceedings lacked jurisdiction and was inexecutable, relying on precedents such as Jaipur Development Authority v. Radhey Shyam and Secretary v. Daulat Mal Jain. The Supreme Court, while acknowledging the discretionary nature of Article 136, held that this case does not justify upsetting the compromise. It directed the state to restore appeals for merits and to determine quantum of monetary compensation excluding plots, while also directing allotment of smaller plots (about 250 sq yards) in another scheme within three months to maintain consistency with earlier judgments. The land must be used for the public purpose for which it was acquired. The appeals were disposed of with these directions under Article 142 for complete justice.

2002-11-13

Shrawan Bhadaji Bhirad and Ors. v. State of Maharashtra

Shrawan Bhadaji Bhirad and others, members of the Bhirad family, were convicted by an Additional Sessions Judge under sections 147, 148 and 307 read with section 149 IPC for forming an unlawful assembly and assaulting Ganesh Dhage with swords, causing extensive injuries and a prolonged hospitalisation. Ganesh Dhage survived and implicated the appellants, naming them in the dying/dependant statements, which were corroborated by eyewitnesses. The High Court upheld the Sessions Court’s conviction, rejecting the appellants’ contention that the victim did not know the assailants’ names and that the names were a product of enmity. In appeal, the appellants argued that their alleged involvement had no basis and was speculative. The Court emphasised that the dying declaration, though recorded after severe injuries and while the victim was in medical care, had significant content; and even if considered under Section 164 CrPC rather than as a strict dying declaration, it remained corroborated by the testimony of the eye-witnesses. The Court found overwhelming evidence on record supporting the prosecution’s case and concurred with the concurrent findings of the Sessions Judge and the High Court. Accordingly, the appeal was dismissed, bail bonds cancelled, and the appellants were to serve the remainder of their sentences.

2002-10-10

Alla China Apparao and Ors. v. State of Andhra Pradesh

Alla China Apparao and six co-accused were convicted by the trial court under Sections 302/149 and 148 of the IPC, and each was sentenced to life imprisonment, with a concurrent one-year term on the 148 IPC count and a fine. The High Court affirmed the convictions against the appellants while acquitting three others. The prosecution’s case rests on four eyewitnesses who say the deceased was attacked near his house, dragged to a wall, and slain by multiple appellants; medical and objective evidence were said to corroborate the eyewitnesses. The appellants contend that the three acquitted co-accused show the same evidence cannot justify conviction of the others; the witnesses were partisan, and there was no independent corroboration; the lack of injuries beyond what witnesses described and alleged dragging marks undermine the case; and a delay in forwarding the FIR to the Magistrate merits acquittal. The State argues the eyewitnesses were credible, corroborated by medical evidence and police findings, that non-examination of other witnesses is not fatal, and that the absence of dragging marks or blood on weapons does not negate the prosecution. The Court holds that eyewitness credibility is supported by evidence, the delay was within reasonable limits given workload, and the case remains trustworthy. The appeal is dismissed and the convictions upheld.