The State of Bihar and Others v. Pawan Kumar and Others

Case / Petition Number:
Civil Appeal Nos. 3661-3662 of 2020
Neutral Citation:/

Case Synopsis & Summary

These Civil Appeals challenge the National Green Tribunal’s October 14, 2020 order directing the State of Bihar to prepare fresh District Survey Reports (DSR) for sand mining in Banka district and to rely on procedural frameworks to be followed for environmental clearances. The Tribunal had urged that DSRs be prepared through accredited private consultants, following the 2010 MoEFCC order, and that the District Survey Reports be verified by the District Magistrate before examination by the State Expert Appraisal Committee (SEAC) and final approval by the SEIAA. The State of Bihar and its counsel contended that such directions were misapplied, arguing that the Sand Mining Guidelines and policy framework in force, including the 2020 Enforcement and Monitoring Guidelines for Sand Mining (EMGSM-2020) and the January 2016 MoEFCC notification, mandate DSR preparation before auctions by district/sub-divisional authorities, using site visits, public consultation, and modern technology, without necessitating private consultants. The Court takes the view that the Tribunal’s private-consultant directive is not required in light of these guidelines, and substitutes the directions accordingly. It holds that DSRs should be drafted by Sub-Divisional Magistrates and relevant district officers with site visits and modern technology, submitted to SEAC within six weeks, reviewed by SEIAA within six weeks, and environmental clearances considered within six weeks thereafter. Interim mining through the Bihar State Mining Corporation is permitted with safeguards. The matter is to be listed after 20 weeks; the overall objective remains a balance between development and environmental protection, not a blanket ban on mining.

Precedent Explorer

Find Cases Like This

Explore other judgments dealing with similar legal situations, facts, or statutory provisions.

Case Details & Bench

Court
Landmark Cases
Hon'ble Judges
  • L. Nageswara Rao
  • Sanjiv Khanna
  • B. R. Gavai
Judgment Date
2021-11-10
Court Decision / Holding
The Supreme Court substituted the Tribunal’s directions with a framework that requires DSRs to be prepared afresh by Sub-Divisional Magistrates and district officers, incorporating site visits and modern technology, within six weeks; SEAC to examine within six weeks; SEIAA to consider approvals within six weeks thereafter; and interim mining to continue via the Bihar State Mining Corporation with environmental safeguards. The matter is to be listed after 20 weeks. The decision emphasizes adherence to EMGSM-2020 and related guidelines, ensuring a balanced approach to development and environmental protection rather than a blanket mining ban.
Final Disposition
Appeals kept pending; interim directions issued; matter to be listed after 20 weeks; the State allowed to continue mining via Bihar State Mining Corporation with safeguards.

Parties to the Case

Appellants / Petitioners

  • The State of Bihar and Others

Respondents

  • Pawan Kumar and Others

Legal Representation & Advocates

Counsels for Petitioners

  • • Atmaram Nadkarni (Senior Counsel)

Provisions of Law Cited

O.M. of MoEF & CC dated 16.03.2010SSMMG-2016EMGSM-2020 (Enforcement and Monitoring Guidelines for Sand Mining)Clause 4.1.1(a), (o) and (p) of the 2020 guidelinesMoEF & CC notification dated 15 January 2016Public consultation provisions in EMGSM-2020

Submissions & Arguments

Contentions of Appellants / Petitioners

Shri Atmaram Nadkarni, Senior Counsel for the State of Bihar, submitted that the Tribunal erred in holding that unless SEAC and SEIAA grant approval to the District Survey Reports (DSRs), mining cannot proceed. He argued that the DSRs can be prepared by district-level officers under the 2020 EMGSM guidelines and the January 2016 MoEFCC notification, with site visits, use of modern technology, and public consultation. He contended that inviting tenders prior to final DSR approval cannot be faulted, and that the Tribunal’s emphasis on private consultants would unnecessarily burden the State and delay lawful mining. He urged that interim mining be allowed within environmental safeguards and that the public exchequer not be deprived of revenue while a scientifically sound DSR framework is implemented. He highlighted that reliance on updated guidelines can permit a practical, timely balance between development and ecological safeguards and prevent a surge in illicit mining, without compromising environmental protections.

Contentions of Respondents

Shri P.S. Patwalia, Senior Counsel for the respondents, argued that the Tribunal’s findings—DSRs not prepared in accordance with the relevant rules and policy guidelines—are correct. He stressed that environmental safeguards and scientific rigor must govern the mining process and that the State’s approach appears aimed at financial enrichment rather than balancing environmental concerns. He asserted that the 2016 notification and the 2020 EMGSM guidelines set forth a procedure requiring proper contingencies for environmental clearance through SEAC/SEIAA in line with the law, and that any deviation would undermine environmental governance and public interest. He urged the Court to uphold stringent adherence to the policy framework and ensure that DSRs, mining plans, and permits reflect full compliance with environmental standards before any lease or auction activities proceed.

Legal Doctrine & Issue Explorer

Explore This Legal Issue

Find relevant judgments and authoritative positions on the legal questions discussed here.

Cited Precedents (2)

Case NameCitationTreatmentExplanation
Satendra Pandey v. Ministry of Environment, Forest and Climate Change and Another[1]Partly Overruled / LimitedThe Tribunal’s directive to have DSRs prepared through private accredited consultants is reversed and replaced by the 2020 guidelines and the sub‑divisional‑officer framework; other aspects of the precedent may still apply.
Deepak Kumar v. State of Haryana and Others(2012) 4 SCC 629PositiveNoted as authority that the 2016 DEIAA notification was not in consonance with Supreme Court principles established in Deepak Kumar, thus supporting the Court’s shift to updated guidelines and procedures.
Case Applicability Diagnostic

Apply This to My Facts

Share your situation and test whether this judgment governs, supports, or challenges your case.

Official Judgment Record
•2,284 words•~11 min read

In The Court Record

The State of Bihar and Others v. Pawan Kumar and Others

## **REPORTABLE** # **IN THE SUPREME COURT OF INDIA CIVIL APPELLATE JURISDICTION** ## **­ CIVIL APPEAL NOS. 3661 3662 OF 2020** **THE STATE OF BIHAR AND OTHERS ...APPELLANT(S)** **VERSUS** **PAWAN KUMAR AND OTHERS ETC. ...RESPONDENT(S)** ## **O R D E R** ## **Per Court** **1.** The present appeals challenge the judgment and order dated 14[th] October 2020, passed by the National Green Tribunal, Principal Bench, New Delhi (hereinafter referred to as “the Tribunal”) in O.A. No. 40/2020/EZ with O.A. No. 57/2020/EZ, thereby issuing the following directions:­ 1 - **(i)** “Having regard to the findings at (a), (b) and (c) above, we direct the State to undertake further exercise for preparation of a fresh DSR for the Banka district. - **(ii)** As the DEIAA is not functioning as a consequence of the decision of the Tribunal in _Satendra Pandey_ (supra), the DSR shall be prepared through a consultant(s) accredited by the National Accreditation Board of Education and Training/Quality Control Council of India in terms of O.M. of MoEF & CC dated - 16.03.2010. - **(iii)** The DSR so prepared shall be submitted to the District Magistrate who shall verify the DSR only in respect of the relevant facts pertaining to the physical and geographical features of the district which shall be distinct from the scientific findings based on the parameters 2 prescribed in the SSMMG­ 2016. After such verification, the District Magistrate shall forward the DSR for examination and evaluation by the State Expert Appraisal Committee (SEAC) having regarding to the fact that the SEIAA comprises of technical/scientific experts. The SEAC after appraisal of the report shall forward it to the SEIAA for consideration and approval if it meets all scientific/technical requirements. **(iv)** While preparing the DSR, the MoEF & CC Accredited Agency/Consultant shall scrupulously follow the procedure and the parameters laid down under the SSMMG­2016 and EMGSM­2020 read in sync with each other.” 3 **2.** The appellant­State of Bihar has assailed the said judgment and order dated 14[th] October 2020, on various grounds. **3.** Shri Atmaram Nadkarni, learned Senior Counsel appearing on behalf of the State of Bihar submitted that the Tribunal has grossly erred in holding that unless the State Expert Appraisal Committee (hereinafter referred to as “SEAC”) and the State Environment Impact Assessment Authority (hereinafter referred to as “SEIAA”) grants approval to the District Survey Report (hereinafter referred to as “DSR”) for the purpose of mining of sand, the same cannot be carried out. He submitted that the Tribunal has further held that the very invitation of the tenders without preparing the DSR in accordance with the judgment of the Tribunal in the case of _**Satendra Pandey v. Ministry of Environment, Forest and Climate Change and Another[1]**_ could not have been done. He submitted that after the tenders are invited in accordance with the DSR prepared by the District Level Committee, the 1 **O.A. No. 186 of 2016 (M.A. No. 350/2016)** 4 successful bidder will be required to prepare a mining plan and unless such a mining plan is approved by SEAC and SEIAA, the Environmental Clearance would not be granted and in turn, mining activities cannot be carried out. He submitted that the finding of the Tribunal is like putting the cart before the horse. He further submitted that the Tribunal has also grossly erred in holding that the DSRs prepared by the State were without following the requisite procedure and without considering the relevant factors. He submitted that not only the procedure as prescribed under the relevant rules and regulations was complied with, but the voluminous material in support of the same was also placed on record before the Tribunal. He submitted that the Tribunal has not taken into consideration the said material. He therefore submitted that the judgment and order passed by the Tribunal dated 14[th] October 2020, needs to be set aside and the State needs to be permitted to finalize the tenders received by it. **4.** Shri Nadkarni further submitted that on account of the orders passed by the Tribunal, the old lessees are continuing 5 with the mining activities by paying a meagre amount to the State Government. He therefore submitted that on account of this, a huge loss would be caused to the public exchequer. In the alternative, he submitted that the State, at least, needs to be permitted to undertake mining activities through Bihar State Mining Corporation until the DSRs are finalized in accordance with the judgment of the Tribunal. **5.** Shri P.S. Patwalia, learned Senior Counsel appearing on behalf of the original applicant vehemently opposed the appeals. He submitted that the Tribunal has rightly held that the DSRs are not prepared in accordance with the relevant rules as well as policy guidelines. He submitted that it is apparently clear that the State has taken into consideration only financial enrichment without considering the environmental aspects. **6.** Though, we have heard the learned counsel for both the parties at length on merits, we find that it will be appropriate 6 that the appeals are kept pending for further consideration and till then, certain interim orders are passed. **7.** It cannot be in dispute that though the developmental activities are not stalled, the environmental issues are also required to be addressed. A balanced approach of sustainable development ensuring environmental safeguards, needs to be resorted to. At the same time, it also cannot be ignored that when legal mining is banned, it gives rise to mushroom growth of illegal mining, resulting into clashes between sand mafias, criminalization and at times, loss of human lives. It also cannot be disputed that sand is required for construction of public infrastructural projects as well as public and private construction activities. A total ban on legal mining, apart from giving rise to illegal mining, also causes huge loss to the public exchequer. **8.** Taking into consideration these aspects of the matter, we propose to issue certain interim directions. 7 **9.** The Tribunal, in the case of _**Satendra Pandey**_ (supra), has found that the notification dated 15[th] January 2016, which provided Environmental Clearance to be given by the District Environment Impact Assessment Authority (hereinafter referred to as the “DEIAA”) was not in consonance with the judgment of this Court in the case of _**Deepak Kumar v. State of Haryana and Others[2]**_ . The Tribunal therefore in _**Satendra Pandey**_ (supra), had directed Ministry of Environment, Forest and Climate Change (hereinafter referred to as “MoEF and CC) to take steps to revise the procedure laid down in the notification dated 15[th] January 2016. It is to be noted that MoEF and CC, in accordance with the directions of the Tribunal, had issued Enforcement and Monitoring Guidelines for Sand Mining (hereinafter to referred to as “the 2020 guidelines”) in the month of January 2020. Chapter 4 of the 2020 guidelines deals with identification of possible sand mining sources and preparation of DSR. It will be relevant to refer to Clause 4.1.1 (a), (o) and (p) of the 2020 guidelines:­ > 2 **(2012) 4 SCC 629** 8 ## **“4.1 Identification of possible sand mining sources and preparation of District Survey Report (DSR)** ## **4.1.1 Preparation of District Survey Report.** a) District Survey Report for sand mining shall be prepared before the auction/e­auction/grant of the mining lease/Letter of Intent (Loi) by Mining department or department dealing the mining activity in respective states. o) Potential site for mining having its impact on the forest, protected area, habitation, bridges etc, shall be avoided. For this, a sub­divisional committee may be formed which after the site visit shall decide its suitability for mining. The list of mining lease after the recommendation of the Committee needs to be defined in the following format given in as **Annexure­II** . The Sub­Divisional Committee after the site visit shall make a recommendation on the site for its suitability of mining and also records the reason for selecting the mining lease in the Patta land. The details regarding cluster and contiguous **Annexure­III** . cluster needs to be provided as in The details of the transportation need to ~e provided as in **Annexure IV** . p) **Public consultation** ­The Comments of the various stakeholders may be sought on the list of mining lease to be auctioned. The State Government shall give an advertisement in the local and national newspaper for seeking comments of the general 9 public on the list of mining' lease included in the DSR. The DSR should be placed in the public domain for at least one month from the date of publication of the advertisement for obtaining comments of the general public. The comments so received shall be placed before the sub­divisional committee for active consideration. The final list of sand mining areas [leases to be granted on riverbed & Patta land/Khatedari land, de­siltation location (ponds/lakes/dams), M­Sand Plants (alternate source of sand)] after the public hearing needs to be defined in the final DSR in the format as per **Annexure­V** . The details regarding cluster and contiguous cluster needs to be provided in **Annexure­VI** . The details of the transportation need to be provided in **Annexure­Vll.”** **10.** It could thus be seen that in accordance with the 2020 guidelines, the DSR is required to be prepared before the auction/e­auction/grant of mining lease by Mining Department or Department dealing with mining activity in the respective States. It is further provided that the potential site for mining having its impact on the forest, protected area, habitation and bridges should be avoided. For this, a sub­divisional committee is required to be formed which, after the site visit, is required to decide regarding the suitability of the sites for mining. The 10 sub­divisional committee is further required to record its reasons for selecting the mining lease in the patta land. Various details are required to be given in the annexures appended to the said policy. **11.** It is further to be noted that Appendix­X of the notification dated 15[th] January 2016, issued by MoEF and CC also provides for composition of the sub­divisional committee:­ “A Sub­Divisional Committee comprising of Sub­ Divisional Magistrate, Officers from Irrigation department, State Pollution Control Board or Committee, Forest department, Geology or mining officer shall visit each site for which environmental clearance has been applied for and make recommendation on suitability of site for mining or prohibition thereof.” **12.** It is to be noted that with the advent of modern technology, various technological gadgets like Drones and satellite imaging etc. can be used for identification of the potential sites and preparation of the DSR and also to check misuse and unauthorized mining. 11 **13.** We further find that when the 2020 guidelines as well as the notification issued by MoEF and CC of 2016 itself provide for constitution of sub­divisional committees comprising of the officers of the State Government from various Departments for identification of the potential sites for mining, there would be no necessity of the DSRs being prepared through private consultants as directed by the Tribunal in the impugned order. The sub­divisional committee consists of various officers from Revenue Department, Irrigation Department, State Pollution Control Board, Forest Department and Geology Mining Department of the State Government. They are better equipped to visit the sites and prepare the draft DSR for the concerned district. Apart from that, preparation of DSR through private consultants would also unnecessarily burden the public exchequer. We are therefore of the view that the direction in that regard issued by the Tribunal requires to be modified. We are further of the considered view that until the DSRs are finalized and granted approval by SEAC and SEIAA, it is appropriate that certain necessary arrangements are permitted 12 so that the State can continue with legal mining activities. This apart from preventing illegal mining activities, would also ensure that the public exchequer is not deprived of its share in legalized mining. **14.** We therefore find it appropriate to substitute the directions issued by the Tribunal vide judgment and order dated 14[th] October 2020, with the following directions:­ - (i) The exercise of preparation of DSR for the purpose of mining in the State of Bihar in all the districts shall be undertaken afresh. The draft DSRs shall be prepared by the sub­divisional committees consisting of the Sub­Divisional Magistrate, Officers from Irrigation Department, State Pollution Control Board or Committee, Forest Department, Geological or mining officer. The same shall be prepared by undertaking site visits and also by using modern technology. The said draft DSRs shall be prepared within a 13 period of 6 weeks from the date of this order. After the draft DSRs are prepared, the District Magistrate of the concerned District shall forward the same for examination and evaluation by the SEAC. The same shall be examined by the SEAC within a period of 6 weeks and its report shall be forwarded to the SEIAA within the aforesaid period of 6 weeks from the receipt of it. The SEIAA will thereafter consider the grant of approval to such DSRs within a period of 6 weeks from the receipt thereon; (ii) Needless to state that while preparing DSRs and the appraisal thereof by SEAC and SEIAA, it should be ensured that a strict adherence to the procedure and parameters laid down in the policy of January 2020 should be followed; (iii) Until further orders, we permit the State Government to carry on mining activities 14 through Bihar State Mining Corporation for which it the services of the may employ contractors. However, while doing so, the State Government shall ensure that all environmental concerns are taken care of and no damage is caused to the environment. ## **15.** List the matter after 20 weeks. **……....….......................J.** **[L. NAGESWARA RAO]** **…....….......................J. [SANJIV KHANNA]** **…….........................J. [B.R. GAVAI]** **NEW DELHI; NOVEMBER 10, 2021.** 15
End of Judgment Record
Browse All Landmark Cases Judgments
2019-01-22

State of Himachal Pradesh & Anr. v. Pinju Ram & Others; State of Himachal Pradesh & Ors. v. Ganesh Dutt & Anr.

This batch of appeals concerns regularisation and monetary benefits of part‑time employees in Himachal Pradesh who were converted to daily‑wage status. The State had issued a policy on 27 February 2004: part‑time Class‑IV employees who had completed ten years of continuous service as on 31 December 2003 would be made daily wagers with prospective effect, and posts vacated by such employees would stand abolished; Education and Ayurveda were excluded from the policy. Revenue Chowkidars, engaged by Panchayats, were not covered by that policy and received separate treatment. Following writ petitions and an order of the Himachal Pradesh High Court and in light of later developments, the State drew‑up directions in 2011 (22 September) to give seniority to Revenue Chowkidars on the basis of ten years of service, but with wages from the date of actual appointment and without back‑dated monetary benefits; 7 July 2012 further instructions reiterated this stance for remaining part‑time employees, with monetary benefits not guaranteed in the interregnum. The respondents pressed for back wages dating from 1 January 2007 and broader coverage. The Supreme Court held that the 2007 back‑pay direction was unsustainable, clarified that seniority would count from ten years without past benefits, and that the 2011 policy and Moti Singh principle should guide the approach. The appeals are allowed; no costs. The related writ petitions are to be disposed of consistent with these directions.

2018-08-14

Union Bank of India and Others v. C.G. Ajay Babu and Anr.

This is a Supreme Court of India appeal concerning the forfeiture of gratuity under the Payment of Gratuity Act, 1972. The respondent was a branch manager of the appellant bank and was dismissed on 3 June 2004 after disciplinary proceedings. A show-cause notice sought to forfeit gratuity due to misconduct involving moral turpitude, which was ordered on 20 April 2004. The High Court upheld the dismissal but held that gratuity could be paid since there was no financial loss to the bank, and that a bipartite settlement between the bank and employees permitted forfeiture only where misconduct caused financial loss. The Division Bench, however, held that forfeiture under Section 4(6) must be read together with Section 4(5) and that no loss was proven, thus entitling the employee to gratuity in accordance with the bipartite settlement. The Supreme Court agreed with the High Court that forfeiture is not automatic; it is controlled by Sections 4(5) and 4(6) of the Act and by the bipartite settlement, which requires loss to justify forfeiture. The Court emphasized that an act must constitute an offence involving moral turpitude and that conviction is generally required for forfeiture under 4(6)(b)(ii). The appeal is dismissed with no costs.

2018-09-25

Reema Salkan v. Sumer Singh Salkan

This is a Supreme Court of India criminal appeal under the Criminal Appellate Jurisdiction arising from a maintenance dispute under Section 125 Cr.P.C. The parties, married in 2002, had a protracted litigation history. The Family Court granted maintenance to the wife from 17 July 2003 to 8 December 2010, and held no maintenance thereafter. The High Court, in revision, partly allowed the application, directing Rs.9,000 per month from 9 December 2010 onward, while upholding the earlier period’s Rs.10,000 per month. This Court had earlier granted interim maintenance of Rs.20,000 per month in 2014 (Criminal Appeal Nos. 2347-2349 of 2014). The appellant contends there has been no change in circumstances since the interim order and that the respondent’s substantial assets, education, and overseas earnings establish the capacity to pay higher maintenance. The respondent defends the High Court’s reasoning, arguing that the Family Court’s assessment, demeanor observations, and the principle that maintenance should not be perpetual require careful scrutiny, and that the notional minimum wage approach used by the High Court is flawed. The overarching issue is the quantum of monthly maintenance payable to the appellant and whether the interim amount should be augmented beyond the period up to 2010.”

2019-12-03

M/s Embassy Property Developments Pvt. Ltd. v State of Karnataka & Ors.

This judgment concerns three Civil Appeals filed by a Resolution Applicant, the Corporate Debtor (through its Resolution Professional) and the Committee of Creditors, challenging an Interim Order of the Karnataka High Court staying an NCLT order in proceedings under the Insolvency and Bankruptcy Code, 2016. The NCLT Chennai had admitted an application under Section 7 of the IBC against M/s Tiffins Barytes Asbestos & Paints Ltd. and directed a moratorium under Section 14. The Interim Resolution Professional then sought a deemed extension of a mining lease under MMDR Act, 1957 and the Government of Karnataka rejected it. The NCLT, by an order dated 11.12.2018, set aside the Government’s order and directed execution of Supplement Lease Deeds for the period up to 31.03.2020. The Government of Karnataka challenged this in a High Court writ petition, which stayed the impugned NCLT order. The core issues were: (i) whether the High Court may interfere under Article 226/227 with an NCLT order in IBC when an appeal lies to the NCLAT, and (ii) whether fraud can be inquired into by NCLT/NCLAT in CIRP. The Court reiterates that IBC is a complete, umbrella code with a three‑tier mechanism (NCLT, NCLAT, Supreme Court) and that public‑law disputes arising from MMDR Act obligations lie outside IBC. It ultimately holds that while NCLT/NCLAT may inquire into fraud, they cannot adjudicate MMDR‑related public legal disputes; and the High Court’s writ jurisdiction in public‑law contexts remains permissible. The appeals are dismissed.