The Executive Engineer, Nimna Dudhna Project, Selu, District Parbhani, Maharashtra v. The State of Maharashtra & Others

Case / Petition Number:
Civil Appeal Nos. 246-255 of 2020
Neutral Citation:/null

Case Synopsis & Summary

This is a Supreme Court review of a Bombay High Court order that enhanced compensation for lands acquired for the Nimna Dudhna Project and condoned a substantial delay in challenging that order. The appellant, The Executive Engineer, Nimna Dudhna Project, contends that delaying challenges of about five and a half years should not attract statutory benefits or interest on the enhanced compensation, and argues that the High Court erred in imposing such costs given delay. The respondents/original claimants pressed parity in compensation for lands acquired for the same project under the same notification and urged that the High Court’s condonation of delay should not bar the entitlement to statutory benefits and interest for the intervening period. The judgment clarifies that condoning delay is permissible in appropriate cases, but it is not automatic that the delayed period will bear interest on enhanced compensation. Relying on decisions such as Dhiraj Singh and K. Subbarayudu, the Court notes a settled position that interest on enhanced compensation for the period of delay can be denied. Ultimately, the Court allows the appeals in part and modifies the High Court judgment: denial of interest for the period of delay, while the rest of the award and enhanced compensation, as applicable to similarly situated landowners, remains intact. No costs.

Precedent Explorer

Find Cases Like This

Explore other judgments dealing with similar legal situations, facts, or statutory provisions.

Case Details & Bench

Court
Landmark Cases
Hon'ble Judges
  • M. R. Shah
  • Ashok Bhushan
Judgment Date
2020-01-15
Court Decision / Holding
Appeals allowed in part. The common impugned judgment and order of the High Court is modified to the extent of denying the interest to the respondents/original claimants on the enhanced amount of compensation for the period of delay in preferring the appeals. Rest of the judgment and award passed by the High Court is confirmed. No costs.
Final Disposition
Appeal partly allowed; denial of interest for the period of delay; rest of the High Court’s award and enhanced compensation maintained across similarly situated landowners; no costs.

Parties to the Case

Appellants / Petitioners

  • The Executive Engineer, Nimna Dudhna Project, Selu, District Parbhani, Maharashtra

Respondents

  • The State of Maharashtra
  • Others

Provisions of Law Cited

Land Acquisition Act

Legal Doctrines & Maxims

  • res integra

Submissions & Arguments

Contentions of Appellants / Petitioners

The appellant argues that despite a delay of about five and a half years in filing the First Appeals before the High Court challenging the award, the High Court rightly condoned the delay and enhanced the compensation to be at par with other landowners. However, it contends that the statutory benefits and interest for the delayed period should not be imposed on a public body, and that such liability is not attributable to them. The appellant cites established jurisprudence on condonation of delay and the treatment of interest on enhanced compensation, including Market Committee, Hodal v. Krishan Murari, Collector (LA) v. Katiji, Dhiraj Singh (D) v. State of Haryana, and K. Subbarayudu v. Special Deputy Collector (LA).

Contentions of Respondents

The respondents contend that claimants were entitled to parity in compensation for lands acquired for the same project and under the same notification, and that condonation of delay should not deprive them of statutory benefits or interest for the period of delay. They argue that the High Court’s order condoning delay had attained finality, and the appellants cannot seek to deny statutory benefits or interest thereafter. They maintain that all landowners should be treated equally in terms of compensation for lands acquired for the same project.

Legal Doctrine & Issue Explorer

Explore This Legal Issue

Find relevant judgments and authoritative positions on the legal questions discussed here.

Cited Precedents (4)

Case NameCitationTreatmentExplanation
Market Committee v. Hodal, Krishan Murari(1996) 1 SCC 311PositiveCited as part of the rationale for condoning delay and the approach to statutory benefits/interest in delay.
Collector (LA) v. Katiji(1987) 2 SCC 107PositiveCited for principles on delay and fairness in condonation.
Dhiraj Singh (D) through LRs v. State of Haryana(2014) 14 SCC 127PositiveUsed to justify denial of interest on enhanced compensation for delay when delay is condoned.
K. Subbarayudu v. Special Deputy Collector (LA)(2017) 12 SCC 840PositiveSupporting authority for denying interest on delay despite condonation.
Case Applicability Diagnostic

Apply This to My Facts

Share your situation and test whether this judgment governs, supports, or challenges your case.

Official Judgment Record
•1,083 words•~5 min read

In The Court Record

The Executive Engineer, Nimna Dudhna Project, Selu, District Parbhani, Maharashtra v. The State of Maharashtra & Others

**REPORTABLE** ## **IN THE SUPREME COURT OF INDIA CIVIL APPELLATE JURISDICTION ­ CIVIL APPEAL NOS. 246 255 OF 2020** **The Executive Engineer, Nimna Dudhna Project, Selu, District Parbhani, Maharashtra** **…Appellant** **Versus** **The State of Maharashtra & Others Etc. Etc.** **…Respondents** ## **J U D G M E N T** ## **M.R. SHAH, J.** Feeling aggrieved and dissatisfied with the impugned common judgment and order dated 17.07.2017 passed by the Signature Not Verified Digitally signed by INDU MARWAH Date: 2020.01.15 18:31:22 IST High Court of Judicature at Bombay, Bench at Aurangabad in Reason: First Appeal Nos. 4083­4092 of 2016 whereby the High Court has 1 partly allowed the said first appeals preferred by the original claimants and has enhanced the amount of compensation for the lands acquired, the acquiring body – The Executive Engineer, Nimna Dudhna Project has preferred the present appeals. 2. Learned Advocate appearing on behalf of the appellant has vehemently submitted that as such there was a delay of five and a half years in preferring the first appeals. It is submitted that assuming that the High Court is justified in enhancing the amount of compensation at par with the other land owners/claimants, as there was a huge delay of five and a half years, the High Court ought not to have saddled the interest liability for the period of delay upon the appellants. It is submitted that for the delayed period the claimants shall also not be entitled to any statutory benefits. 2.1 It is submitted by the learned Advocate that as such there was a huge delay of five and a half years and therefore as such the same was not required to be condoned by the High Court. It is submitted that in any case the High Court is not justified in granting the statutory benefits and the interest on the enhanced amount of compensation for the period of delay. In support of his above submission, learned counsel appearing on behalf of the 2 appellant has heavily relied upon the decisions of this Court in the cases of _Market Committee, Hodal v. Krishan Murari, (1996) 1 SCC 311; Collector (LA) v. Katiji, (1987) 2 SCC 107; Dhiraj Singh (D) through LRs v. State of Haryana, (2014) 14 SCC 127; and K. Subbarayudu v. Special Deputy Collector (LA), (2017) 12 SCC 840_ . 3. While opposing the present appeals, learned Advocate appearing on behalf of the respondents/original claimants has vehemently submitted that as such the original claimants claimed the parity in compensation with other land owners. It is submitted that at the time when the High Court condoned the delay, the same was not conditional, namely, to deny the statutory benefits and the interest for the interregnum period – delayed period. It is submitted that the order condoning the delay had attained finality and therefore subsequently it is not open for the appellant to submit that the High Court ought not to have awarded the statutory benefits and the interest for the delayed period. 3.1 It is further submitted by the learned Advocate appearing on behalf of the respondents/original claimants that even otherwise as per the settled proposition of law, all claimants/land owners 3 are entitled to the same compensation for the land acquired for the same project vide the same notification. 3.2 Making the above submissions, it is prayed to dismiss the present appeals. 4. We have heard the learned counsel for the respective parties at length. At the outset, it is required to be noted that the dispute in the present appeals is only with respect to award of statutory benefits and interest for the delayed period. It is not in dispute that there was a huge delay of five and a half years in preferring the appeals before the High Court challenging the judgment and award passed by the Reference Court. However, considering the fact that in other matters the delay was condoned, the High Court condoned the delay and entertained the appeals and enhanced the amount of compensation at par with other land owners/claimants whose lands were acquired for the same project vide the same notification. Therefore, as such, no fault can be found with the order passed by the High Court condoning the delay. It is required to be noted that as such the order condoning the delay has attained finality as the same was not challenged by the appellant at the relevant time. Be that as it 4 may, the issue which is required to be considered is, whether for the delayed period the claimants shall be entitled to the statutory benefits and the interest under the Land Acquisition Act? 4.1 The aforesaid issue is not _res integra_ . In the case of _Dhiraj Singh (supra)_ , while condoning the delay in preferring the appeal before this Court, while enhancing the amount of compensation at par with other similarly situated land owners, this Court has denied the interest on the enhanced amount of compensation for the period of delay in approaching the High Court by way of LPAs. Similar view is expressed by this Court in the case of _K. Subbarayudu (supra)_ and while condoning the delay in preferring the appeal, this Court has denied the interest for the period of delay. Merely because at the time of condoning the delay no such condition was imposed that the claimants shall not be entitled to the interest on the enhanced amount of compensation for the period of delay, the appellant who is otherwise a public body cannot be saddled with the liability to pay the interest for the period of delay, which is not at all attributed to them. Under the circumstances, the common impugned judgment and order passed by the High Court awarding the interest on the enhanced amount of compensation for the period of delay in preferring the 5 appeals deserve to be quashed and set aside and the impugned common judgment and order passed by the High Court is required to be modified to the aforesaid extent. 4.2 In view of the above and for the reasons stated above, all these appeals are allowed in part. The common impugned judgment and order passed by the High Court is modified to the extent denying the interest to the respondents/original claimants on the enhanced amount of compensation for the period of delay in preferring the appeals. Rest of the judgment and award passed by the High Court is confirmed. No costs. ………………………………J. [ASHOK BHUSHAN] NEW DELHI; ………………………………J. JANUARY 15, 2020. [M.R. SHAH] 6
End of Judgment Record
Browse All Landmark Cases Judgments
2019-01-22

State of Himachal Pradesh & Anr. v. Pinju Ram & Others; State of Himachal Pradesh & Ors. v. Ganesh Dutt & Anr.

This batch of appeals concerns regularisation and monetary benefits of part‑time employees in Himachal Pradesh who were converted to daily‑wage status. The State had issued a policy on 27 February 2004: part‑time Class‑IV employees who had completed ten years of continuous service as on 31 December 2003 would be made daily wagers with prospective effect, and posts vacated by such employees would stand abolished; Education and Ayurveda were excluded from the policy. Revenue Chowkidars, engaged by Panchayats, were not covered by that policy and received separate treatment. Following writ petitions and an order of the Himachal Pradesh High Court and in light of later developments, the State drew‑up directions in 2011 (22 September) to give seniority to Revenue Chowkidars on the basis of ten years of service, but with wages from the date of actual appointment and without back‑dated monetary benefits; 7 July 2012 further instructions reiterated this stance for remaining part‑time employees, with monetary benefits not guaranteed in the interregnum. The respondents pressed for back wages dating from 1 January 2007 and broader coverage. The Supreme Court held that the 2007 back‑pay direction was unsustainable, clarified that seniority would count from ten years without past benefits, and that the 2011 policy and Moti Singh principle should guide the approach. The appeals are allowed; no costs. The related writ petitions are to be disposed of consistent with these directions.

2018-08-14

Union Bank of India and Others v. C.G. Ajay Babu and Anr.

This is a Supreme Court of India appeal concerning the forfeiture of gratuity under the Payment of Gratuity Act, 1972. The respondent was a branch manager of the appellant bank and was dismissed on 3 June 2004 after disciplinary proceedings. A show-cause notice sought to forfeit gratuity due to misconduct involving moral turpitude, which was ordered on 20 April 2004. The High Court upheld the dismissal but held that gratuity could be paid since there was no financial loss to the bank, and that a bipartite settlement between the bank and employees permitted forfeiture only where misconduct caused financial loss. The Division Bench, however, held that forfeiture under Section 4(6) must be read together with Section 4(5) and that no loss was proven, thus entitling the employee to gratuity in accordance with the bipartite settlement. The Supreme Court agreed with the High Court that forfeiture is not automatic; it is controlled by Sections 4(5) and 4(6) of the Act and by the bipartite settlement, which requires loss to justify forfeiture. The Court emphasized that an act must constitute an offence involving moral turpitude and that conviction is generally required for forfeiture under 4(6)(b)(ii). The appeal is dismissed with no costs.

2018-09-25

Reema Salkan v. Sumer Singh Salkan

This is a Supreme Court of India criminal appeal under the Criminal Appellate Jurisdiction arising from a maintenance dispute under Section 125 Cr.P.C. The parties, married in 2002, had a protracted litigation history. The Family Court granted maintenance to the wife from 17 July 2003 to 8 December 2010, and held no maintenance thereafter. The High Court, in revision, partly allowed the application, directing Rs.9,000 per month from 9 December 2010 onward, while upholding the earlier period’s Rs.10,000 per month. This Court had earlier granted interim maintenance of Rs.20,000 per month in 2014 (Criminal Appeal Nos. 2347-2349 of 2014). The appellant contends there has been no change in circumstances since the interim order and that the respondent’s substantial assets, education, and overseas earnings establish the capacity to pay higher maintenance. The respondent defends the High Court’s reasoning, arguing that the Family Court’s assessment, demeanor observations, and the principle that maintenance should not be perpetual require careful scrutiny, and that the notional minimum wage approach used by the High Court is flawed. The overarching issue is the quantum of monthly maintenance payable to the appellant and whether the interim amount should be augmented beyond the period up to 2010.”

2019-12-03

M/s Embassy Property Developments Pvt. Ltd. v State of Karnataka & Ors.

This judgment concerns three Civil Appeals filed by a Resolution Applicant, the Corporate Debtor (through its Resolution Professional) and the Committee of Creditors, challenging an Interim Order of the Karnataka High Court staying an NCLT order in proceedings under the Insolvency and Bankruptcy Code, 2016. The NCLT Chennai had admitted an application under Section 7 of the IBC against M/s Tiffins Barytes Asbestos & Paints Ltd. and directed a moratorium under Section 14. The Interim Resolution Professional then sought a deemed extension of a mining lease under MMDR Act, 1957 and the Government of Karnataka rejected it. The NCLT, by an order dated 11.12.2018, set aside the Government’s order and directed execution of Supplement Lease Deeds for the period up to 31.03.2020. The Government of Karnataka challenged this in a High Court writ petition, which stayed the impugned NCLT order. The core issues were: (i) whether the High Court may interfere under Article 226/227 with an NCLT order in IBC when an appeal lies to the NCLAT, and (ii) whether fraud can be inquired into by NCLT/NCLAT in CIRP. The Court reiterates that IBC is a complete, umbrella code with a three‑tier mechanism (NCLT, NCLAT, Supreme Court) and that public‑law disputes arising from MMDR Act obligations lie outside IBC. It ultimately holds that while NCLT/NCLAT may inquire into fraud, they cannot adjudicate MMDR‑related public legal disputes; and the High Court’s writ jurisdiction in public‑law contexts remains permissible. The appeals are dismissed.