These Civil Appeals arise from judgments of the High Court of Karnataka at Kalaburagi, enhancing compensation for land acquired for the Bennethora, Amarja and Lower Mullamari projects under the Land Acquisition Act, 1894. The State agency Karnataka Neeravari Nigam Limited (KNNL) challenges the enhanced awards, while landowners seek higher compensation. Acquisition spanned decades, involving about 13,000 acres across multiple villages. Initial Section 4 notifications and Section 6 declarations were issued across the 1980s–1990s; SLAO awarded compensation which was later enhanced by the Reference Court and further enhanced by the District Court, with the High Court ultimately increasing rates further in impugned judgments. The per-acre figures varied widely between dry and wet lands and across projects. In Annarao @ Anveerappa (supra) and related rulings, this Court has emphasized independent, notification-wise, village-wise analysis and, where necessary, remand for reconsideration. It was argued that some High Court decisions were not uniform, relied on older precedents (Rajshekhar, Malkajappa, Kalappa, Motibee), and could not prescribe a uniform scheme. The Supreme Court remanded the matters to the High Court for fresh, project-wise reconsideration, ensuring uniformity while protecting amounts already paid, and directed expeditious disposal (ideally within three months). The appeals are disposed of in the above terms, with guidance for a holistic, standardized reassessment across projects.

Precedent Explorer

Find Cases Like This

Explore other judgments dealing with similar legal situations, facts, or statutory provisions.

Case Details & Bench

Court
Landmark Cases
Hon'ble Judges
  • Surya Kant
  • K. V. Viswanathan
Judgment Date
2024-03-12
Court Decision / Holding
The Supreme Court set aside the impugned High Court judgments and remanded the matters to the High Court of Karnataka at Kalaburagi for fresh adjudication. The remand is to be project-wise and notification-wise to achieve uniformity in awards, with the stipulation that the High Court shall not reduce compensation already paid and that the process should be expeditiously completed, ideally within three months from the date of the judgment. The appeals are disposed of in these terms; pending applications stand disposed of as well.
Final Disposition
Appeals disposed of by remand to the High Court for fresh consideration, with directions to ensure project-wise, notification-wise analysis and to preserve sums already paid; expedited timeline prescribed.

Parties to the Case

Appellants / Petitioners

  • The Executive Engineer, KNNL

Respondents

  • Subhashchandra and others

Legal Representation & Advocates

Counsels for Petitioners

  • • Naveen R. Nath
  • • Hetu Arora Sethi
  • • Abhimanyu Verma
  • • Lalit Mohini Bhat
  • • Disha Gupta

Counsels for Respondents

  • • Anand Sanjay M Nuli
  • • Suraj Kaushik
  • • Agam Sharma
  • • Nanda Kumar
  • • Dharm Singh
  • • Nuli & Nuli
  • • Kiran Suri
  • • Sharanagouda Patil
  • • Harshvardhan Malipatil
  • • Jyotish Pandey
  • • Supreeta Sharanagouda
  • • S. J. Amith
  • • S. Anuradha Bhat
  • • Harisha S.R.

Provisions of Law Cited

Land Acquisition Act, 1894 – Sections 4 and 6

Legal Doctrines & Maxims

  • Uniformity in award of compensation across villages and projects (doctrine)
  • Remand to High Court for fresh adjudication on a project-wise basis (doctrine)
  • High Court to avoid reducing compensation already paid (doctrine)

Submissions & Arguments

Contentions of Appellants / Petitioners

The applicants contended that the High Court’s judgments failed to analyze each case independently and did not apply notification-wise or village-wise scrutiny, resulting in inconsistent and inflated awards. Relying on Annarao @ Anveerappa (supra), they urged remand to the High Court for fresh, project-wise reconsideration to ensure uniform application of compensation parameters without reducing sums already paid. They pressed for expeditious disposal, urging a decision within three months of remand, and cautioned against reliance on older precedents such as Rajshekhar, Malkajappa, Kalappa, and Motibee, which the Court would not endorse as controlling authorities in the present batch.

Contentions of Respondents

The respondents argued that the High Court’s enhanced awards reflect fair compensation and that many judgments have attained finality. They emphasized that parity across villages and notifications is not feasible, and further delay could prejudice landowners who have already received enhanced compensation. They pointed to the long gestation of these acquisitions and urged that the High Court be allowed to adjudicate consistently within the remand framework, taking into account project-wise considerations while ensuring due process.

Legal Doctrine & Issue Explorer

Explore This Legal Issue

Find relevant judgments and authoritative positions on the legal questions discussed here.

Cited Precedents (5)

Case NameCitationTreatmentExplanation
Annarao @ Anveerappa caseN/APositiveCited to support remand and a fresh, case-by-case analysis in line with Annarao’s reasoning.
Rajshekhar s/o Sangappa deceased by Lrs. v. The Special Land Acquisition Officer, MSA No.200014/2018 (LAC)MSA No.200014/2018 (LAC)DistinguishedCourt states that reliance on Rajshekhar’s case is not favored and does not sustain the High Court’s approach.
Malkajappa @ Mallikarjun v. The Special Land Acquisition Officer & Anr.MSA No.200055/2016 (LAC)DistinguishedNot endorsed by this Court in the Annarao framework; not followed as controlling authority.
Kalappa S/o Paudapppa v. The Special Land Acquisition OfficerN/ADistinguishedNot favored by the Court’s approach as per Annarao.
Motibee W/o Mashak Patel v. The Spl. Land Acquisition Officer & Anr.MSA No.200147/2017 (LAC)DistinguishedNot treated as controlling precedent; not followed in this batch.
Case Applicability Diagnostic

Apply This to My Facts

Share your situation and test whether this judgment governs, supports, or challenges your case.

Official Judgment Record
•3,477 words•~16 min read

In The Court Record

The Executive Engineer, KNNL v. Subhashchandra & Ors.

**REPORTABLE** 2024 INSC 208 **==> picture [72 x 72] intentionally omitted <==** # **IN THE SUPREME COURT OF INDIA CIVIL APPELLATE JURISDICTION** ## **CIVIL APPEAL NO. OF 2024 (Arising out of SLP (Civil) No.13065/2022)** THE EXECUTIVE ENGINEER, KNNL …APPELLANT VERSUS SUBHASHCHANDRA & ORS. …RESPONDENTS ## **WITH** |<br> <br> <br> <br> <br> <br>Digitally signed by<br>Deepak Singh<br>Date: 2024.03.15<br>17:39:05 IST<br><br>Signature Not Verified|CIVIL APPEAL NO.<br>OF 2024<br>(Arising out of SLP(Civil) No.9897/2022)<br>CIVIL APPEAL NO.<br>OF 2024<br>(Arising out of SLP(Civil) No.10982/2022)<br>CIVIL APPEAL NO.<br>OF 2024<br>(Arising out of SLP(Civil) No.14054/2022)<br>CIVIL APPEAL NO.<br>OF 2024<br>(Arising out of SLP(Civil) No.13826/2022)<br>CIVIL APPEAL NO.<br>OF 2024<br>(Arising out of SLP(Civil) No.13864/2022)<br>CIVIL APPEAL NO.<br>OF 2024<br>(Arising out of SLP(Civil) No.14053/2022)<br>CIVIL APPEAL NO.<br>OF 2024<br>(Arising out of SLP(Civil) No.14055/2022)<br>CIVIL APPEAL NO.<br>OF 2024<br>(Arising out of SLP(C) No.13876/2022)<br>CIVIL APPEAL NO.<br>OF 2024<br>(Arising out of SLP(C) No.14048/2022)| |---|---| ||| 1 | P a g e |CIVIL APPEAL NO.<br>OF 2024| |---| |(Arising out of SLP(C) No. 13950/2022)| |CIVIL APPEAL NO.<br>OF 2024| |(Arising out of SLP(C) No. 13948/2022)| |CIVIL APPEAL NO.<br>OF 2024| |(Arising out of SLP(C) No. 13827/2022)| |CIVIL APPEAL NO.<br>OF 2024| |(Arising out of SLP(C) No. 14045/2022)| |CIVIL APPEAL NO.<br>OF 2024| |(Arising out of SLP(C) No. 13949/2022)| |CIVIL APPEAL NO.<br>OF 2024| |(Arising out of SLP(C) No. 13859/2022)| |CIVIL APPEAL NO.<br>OF 2024| |(Arising out of SLP(C) No. 13873/2022)| |CIVIL APPEAL NO.<br>OF 2024| |(Arising out of SLP(C) No. 13877/2022)| |CIVIL APPEAL NO.<br>OF 2024| |(Arising out of SLP(C) No. 11398/2022)| |CIVIL APPEAL NO.<br>OF 2024| |(Arising out of SLP(C) No. 10980/2022)| |CIVIL APPEAL NO.<br>OF 2024| |(Arising out of SLP(C) No. 10007/2022)| |CIVIL APPEAL NO.<br>OF 2024| |(Arising out of SLP(C) No. 10176/2022)| |CIVIL APPEAL NO.<br>OF 2024| |(Arising out of SLP(C) No. 9860/2022)| |CIVIL APPEAL NO.<br>OF 2024| |(Arising out of SLP(C) No. 11163/2022)| |CIVIL APPEAL NO.<br>OF 2024| 2 | P a g e ## (Arising out of SLP(C) No. 10570/2022) |CIVIL APPEAL NO.<br>OF 2024| |---| |(Arising out of SLP(C) No. 11170/2022)| |CIVIL APPEAL NO.<br>OF 2024| |(Arising out of SLP(C) No. 14052/2022)| |CIVIL APPEAL NO.<br>OF 2024| |(Arising out of SLP(C) No. 14046/2022)| |CIVIL APPEAL NO.<br>OF 2024| |(Arising out of SLP(C) No. 13825/2022)| |CIVIL APPEAL NO.<br>OF 2024| |(Arising out of SLP(C) No. 14050/2022)| |CIVIL APPEAL NO.<br>OF 2024| |(Arising out of SLP(C) No. 12949/2022)| |CIVIL APPEAL NO.<br>OF 2024| |(Arising out of SLP(C) No. 13947/2022)| |CIVIL APPEAL NO.<br>OF 2024| |(Arising out of SLP(C) No. 10081/2022)| |CIVIL APPEAL NO.<br>OF 2024| |(Arising out of SLP(C) No. 10014/2022)| |CIVIL APPEAL NO.<br>OF 2024| |(Arising out of SLP(C) No. 2284/2023)| |CIVIL APPEAL NO.<br>OF 2024| |(Arising out of SLP(C) No. /2024)| |[Diary No(s).12213/2023]| |CIVIL APPEAL NO.<br>OF 2024| |(Arising out of SLP(C) No. /2024)| |[Diary No(s).13231/2023]| 3 | P a g e ## **JUDGEMENT** ## **SURYA KANT, J.** **1.** Permission to file special leave petition is granted in Diary No.12213/2023. **2.** Delay condoned. **3.** Leave granted. **4.** These civil appeals impugn the judgements dated 28.02.2017, 28.11.2017, 15.02.2018, 20.02.2018, 21.02.2018, 02.03.2018, 22.03.2018, 06.04.2018, 13.04.2018, 26.04.2018, 07.12.2018, 12.12.2018, 14.01.2020, 24.01.2020 and 03.03.2021, passed by the High Court of Karnataka at Kalaburagi Bench, whereby compensation for the acquired land was enhanced. The appellant-Karnataka Neeravari Nigam Limited (in short, “Corporation”) claims to be the beneficiary of the subjectacquisition. **5.** The Corporation has been entrusted with the assignment to plan, execute and operate drinking water and irrigation projects and schemes in the State of Karnataka. About 13000 acres of land was acquired by the State of Karnataka for the appellantCorporation for various projects like (1) Bennethora Project (2) Gandori Nala Project (3) Lower Mullamari Project and (4) Amarja 4 | P a g e Project. Certain civil appeals also refer to a fifth project, namely, the Upper Tunga Project. This huge chunk of land measuring 13000 acres also included the parcels of lands owned by the respondent-land owners of different villages. The acquisition was carried under the Land Acquisition Act, 1894 (in short, “Act”). The present civil appeals pertain to the Bennethora Project, Lower Mullamari Project and Amarja Project situated in Kalaburagi, Karnataka. **6.** The acquisition proceedings in these appeals, as per the project-wise classification, progressed as follows- ## **(i) Bennethora Project** a) Civil Appeal Nos.4053, 4054, 4055, 4956, 4061, 4064, 4065, 4066, 4067, 4068, 4069, 4070, 4071, 4072, 4073, 4074, 4075, 4076, 4077, 4078, 4079, 4080, 4081, 4082, 4083, 4085, 4086, 4087 of 2024 pertain to this project. In this batch of civil appeals coming under the Bennethora Project, land measuring a consolidated total of **131 acres and 451 guntas (Approx. 142 acres)** was acquired through different notifications issued under Section 4 of the Act followed by declarations under Section 6 of the Act. The Section 4 notifications and the Section 6 declarations were issued on the following dates- 5 | P a g e |**Date of Section 4**<br>**Notification**|**Date of Section 6**<br>**Notification**| |---|---| |18.02.1982|10.05.1984| |17.03.1983|23.02.1984| |05.04.1990|22.11.1990| |05.07.1990|09.05.1991| |23.08.1990|04.04.1991| |07.02.1991|28.11.1991| |16.05.1991|26.03.1992| |13.06.1991|20.12.1991| |19.06.1991|17.12.1992| |11.07.1991|27.08.1997| |06.08.1992|13.01.1994| b) The Special Land Acquisition Officer (in short, “SLAO”) passed the awards for the acquired lands on different dates, whereby compensations were granted at the following rates- |**Date of SLAO award**|**Compensation granted by SLAO**<br>**(Rupees/acre)**| |---|---| |23.01.1985|3,167| |28.02.1985|3,500| |08.01.1991|5,400| |20.05.1991|6,000for wetlands| |15.06.1992|9,800| |30.01.1993|28,000 for dry lands &<br>42,000for wetlands| |03.02.1993|15,000| |22.11.1993|15,000| |27.11.1993|15,000| |24.12.1993|15,000| |31.05.1994|9,000| c) The rates of compensation awarded by the SLAO were enhanced by the Reference Court, keeping in view the year when the acquisition process commenced. The enhanced 6 | P a g e compensation amounts granted by the Reference Court was further enhanced, upon appeal, by the District Court. d) The dissatisfied landowners further approached the High Court for a higher compensation, which was subsequently granted vide the impugned judgements. The original rates of compensation awarded by the SLAO, the enhanced compensation amounts granted by the Reference Court, the compensation amounts as further enhanced by the District Court and impugned compensation amounts granted by the High Court, vide the impugned judgements, can be understood as follows- |**Amount**<br>**granted by**<br>**SLAO**<br>**(Rupees/**<br>**acre)**|**Amount**<br>**granted by**<br>**Reference**<br>**Court**<br>**(Rupees/**<br>**acre)**|**Amount**<br>**granted by**<br>**District**<br>**Court**<br>**(Rupees/**<br>**acre)**|**Amount**<br>**granted by**<br>**the High**<br>**Court**<br>**(Rupees/**<br>**acre)**| |---|---|---|---| |3,167|11,000|19,000|1,09,034| |3,500|11,000|26,100|83,500| |5,400|25,500|50,500|1,52,059| |15,000|28,500|74,000|1,64,223| |15,000|32,000|74,000|1,64,223| |9,000|32,000|67,000|1,76,388| |15,000|32,000|81,400|1,76,388| |6,000|36,000|Rs.90,200|2,28,088 for<br>wetlands| |28,000 for<br>dry lands &<br>42,000 for<br>wet lands|42,000 for<br>limited extent<br>of land<br>instead of<br>28,000|55,888 for<br>dry lands<br>83,832 for<br>wet lands|1,52,059 for<br>dry lands<br>2,28,088 for<br>wet lands| |9,800|42,000|75,750|1,64,223 for| 7 | P a g e dry lands 2,46,334 for wet lands ## **(ii) Amarja Project** a) Civil Appeal Nos.4057, 4058, 4059, 4060 & 4062, 4084 of 2024 pertain to this Project. In the batch of civil appeals coming under the Amarja Project, land measuring a consolidated total of **15 acres 83 guntas (Approx. 17 acres)** was acquired through a notification issued under Section 4 of the Act followed by a declaration under Section 6 of the Act. The Section 4 notification and the Section 6 declaration were issued on the following dates- |**Date of Section 4**<br>**Notification **|**Date of Section 6**<br>**Notification **| |---|---| |07.04.1988|06.07.1989| b) Thereafter, the SLAO passed the award for the acquired lands whereby compensations was granted at the following rate- |**Date of SLAO award**|**Compensation granted by SLAO**<br>**(Rupees/acre)**| |---|---| |06.03.1990|7,000| c) The rate of compensation awarded by the SLAO was enhanced by the Reference Court, keeping in view the year when the acquisition process commenced. The enhanced 8 | P a g e compensation amount granted by the Reference Court was further enhanced, upon appeal, by the District Court. d) The dissatisfied landowners further approached the High Court for a higher compensation, which was subsequently granted vide the impugned judgements. The original rate of compensation awarded by the SLAO, the enhanced compensation amount granted by the Reference Court, the compensation amount as further enhanced by the District Court and impugned compensation amount granted by the High Court, vide the impugned judgements, can be understood as follows- |**Amount**<br>**granted by**<br>**SLAO**<br>**(Rupees/**<br>**acre)**|**Amount**<br>**granted by**<br>**Reference**<br>**Court**<br>**(Rupees/**<br>**acre)**|**Amount**<br>**granted by**<br>**District**<br>**Court**<br>**(Rupees/**<br>**acre)**|**Amount**<br>**granted by**<br>**the High**<br>**Court**<br>**(Rupees/**<br>**acre)**| |---|---|---|---| |7,000|30,000|79,200|1,78,429| ## **(iii) Lower Mullamari Project** a) Civil Appeal Nos. 4063, 4088, 4089 of 2024 pertain to this Project. In the batch of civil appeals coming under the Lower Mullamari Project, land measuring a consolidated total of **19 acres 59 guntas (Approx. 20 acres)** was acquired through notifications under Section 4 of the Act followed by declarations under Section 6 of the Act, which were issued on different dates. 9 | P a g e The Section 4 notifications and the Section 6 declarations were issued on the following dates- |**Date of Section 4**<br>**Notification**|**Date of Section 6**<br>**Notification**| |---|---| |30.05.1991|11.05.1992/<br>03.09.1992| |14.01.1993|07.04.1994| |04.03.1993|07.04.1994| b) Thereafter, the SLAO passed the awards for the acquired lands on different dates, whereby compensations were granted at the following rates- |**Date of SLAO award**|**Compensation granted by SLAO**<br>**(Rupees/acre)**| |---|---| |04.05.1983|8,000 for dry lands & 10,000 for<br>wetlands| |18.11.1995|10,000 for dry lands & 15,000 for<br>wet lands| |01.01.1996|8,000| c) The rates of compensation awarded by the SLAO were enhanced by the Reference Court, keeping in view the year when the acquisition process commenced. The enhanced compensation amounts granted by the Reference Court was further enhanced, upon appeal, by the District Court. d) The dissatisfied landowners further approached the High Court for a higher compensation, which was subsequently 10 | P a g e granted vide the impugned judgements. The original rates of compensation awarded by the SLAO, the enhanced compensation amounts granted by the Reference Court, the compensation amounts as further enhanced by the District Court and impugned compensation amounts granted by the High Court, vide the impugned judgements, can be understood as follows- |**Amount**<br>**granted by**<br>**SLAO**<br>**(Rupees/**<br>**acre)**|**Amount**<br>**granted by**<br>**Reference**<br>**Court**<br>**(Rupees/**<br>**acre)**|**Amount**<br>**granted by**<br>**District Court**<br>**(Rupees/**<br>**acre)**|**Amount**<br>**granted by**<br>**the High**<br>**Court**<br>**(Rupees/**<br>**acre)**| |---|---|---|---| |8,000 for dry<br>lands &<br>10,000 for<br>wetlands|70,000|-|1,15,086| |10,000 for<br>dry lands &<br>15,000 for<br>wetlands|50,000 for<br>dry lands<br>75,000 for<br>wetlands|-|1,24,992 for<br>dry lands<br>1,86,440 for<br>wetlands| |8,000|33,000|74,750/75,543|1,33,500| **7.** It may thus be seen that the enhancement in the compensation granted by the High Court varies from project to project and while the minimum amount is Rs.83,500/- per acre, the maximum amount is seen to have gone up to Rs.1,78,429/per acre for dry lands and Rs. 2,46,334/- for wet lands. **8.** Having regard to the big chunk of land acquired for 11 | P a g e different projects referred to above, at different points in time, the enhancement made by the High Court in a few cases, where the compensation of Rs.1,20,814/- per acre for dry lands and Rs.1,81,221/- per acre for wet lands was awarded, came to be challenged before this Court in a batch of appeals, including C.A. No.2591/2022 (The Executive Engineer, KNNL Vs. Annarao @ Anveerappa & Anr.), in which this Court, _vide_ Judgment dated 10.05.2022, having found that the High Court has not analyzed each case independently, much less notification wise, concerning particular village or area and that the parameters delineated in various decisions of this Court were not adverted to, held as follows: “In the impugned judgment(s) and order (s), the High court has made no effort to analyze the concerned case(s) either notification-wise or for that matter, village-wise, including the other parameters required to be observed for arriving at a just compensation amount. Further, in most of the appeals, the appellant (Karnataka Neeravari Nigam Limited} was not made party in the appeal proceeding before the High Court. It is also the grievance of the appellant that most of the cases, entertained at the instance of land owners, were grossly delayed and yet they have been granted enhancement, and in some cases along with interest. The fact remains that the High Court in the impugned judgment(s) and order(s} has not analyzed each case independently much less notification-wise concerning particular village or area and keeping in mind the 12 | P a g e parameters delineated in the reported decision, adverted to earlier. In our opinion, it is appropriate that the parties are relegated before the High Court for reconsideration of the entire matter afresh and in accordance with law. Learned counsel appear1ng for the land owners were at pains to point out that some matters pertaining to some of the notifications, referred to in the present appeal proceedings, have reached upto this Court and decided in favour of the land owners, including in some cases the appellants have acted upon the decision by paying compensation amount. Even the effect of such orders passed by this Court can be examined by the High Court on its own merits and in accordance with law. Accordingly, we keep all contentions available to both sides open, to be considered by the High Court on its own merits and in accordance with law. The impugned judgment(s) and order(s) are set aside and the concerned appeals/petitions are remanded to the High Court for reconsideration in the above terms. The parties to appear before the High Court on 11.07.2022, when the High Court may assign suitable date for hearing of the concerned batch of cases which, as aforesaid, must proceed notification-wise pertaining to concerned village as a separate group. Needless to observe that some of the notifications pertain to the year 1983, therefore, it would be appropriate that the High Court disposes of the appeal(s) expeditiously. The appeals are disposed of in the above terms.” **9.** The High Court judgments, which were set aside and the cases remanded back for fresh consideration, also included the judgments rendered by the High Court in MSA No.200020/2018 13 | P a g e (LAC) titled Rajshekhar s/o Sangappa deceased by Lrs. vs. The Special Land Acquisition Officer, MSA No.200014/2018 (LAC) titled Kalappa S/o Paudapppa v. The Special Land Acquisition Officer and MSA No.200147/2017 (LAC) titled Motibee W/o Mashak Patel v. The Spl. Land Acquisition Officer & Anr. decided on 19.02.2018, 21.02.2018 and 09.01.2018 respectively, awarding compensation of Rs.1,64,223/acre, Rs.1,64,223/acre and Rs.1,52,059/acre respectively for the dry lands. _’_ Consequently, _Rajshekhar s case_ (supra) has also been remanded to the High Court for fresh adjudication. The abovementioned judgements of the High Court had in turn placed reliance on MSA No. 200055/2016 (LAC) titled Malkajappa @ Mallikarjun vs. The Special Land Acquisition Officer & Anr, decided by the High Court on 13.03.2017, which has also been remanded to the High Court vide this Court’s order dated 10.05.2022 in _Annarao @ Anveerappa case_ (supra). **10.** We find that in the present batch of appeals, the brief impugned order passed by the High Court in CA No.4053/2024, _’_ has solely relied upon its own decision in _Rajshekhar s case_ (supra). In some of the other appeals, namely CA Nos. 4954, 4055, 4056, 4064, 4065, 4066, 4067, 4068, 4079, 4080, 4081, 4082, 4083, 4087 and 4088 of 2024, the High Court has relied upon its 14 | P a g e decision in _Malkajappa @ Mallikarjun_ (supra) _, Kalappa_ (supra) _(which placed reliance on Malkajappa @ Mallikarjun (supra))_ and Motibee (supra) _(which placed reliance on Malkajappa @ Mallikarjun (supra))_ . These judgments did not find favour with this Court in _Annarao @ Anveerappa case_ (supra), whereby the matters have been remanded to the High Court for reconsideration. **11.** Learned senior counsel for the appellant-Corporation, submits that after the remand, the matter has been heard in part by the High Court. **12.** On the other hand, learned senior counsel for the respondents-land owners submits that there are numerous cases in which similarly placed land owners have already been paid compensation at enhanced rate granted by the High Court. Those judgments of the High Court have attained finality and are not subject matter of these appeals. **13.** Learned senior counsel for the appellant(s), however, counters this submission, as according to him, those matters pertain to different villages and the respondents cannot claim parity with those cases. **14.** We have considered the rival submissions made by learned senior counsel for the parties. It is not in dispute that a batch of 15 | P a g e cases has been remanded by this Court for reconsideration by the High Court, as seen above. It is also an admitted fact that those matters pertain to the same broader acquisition, though they possibly pertain to different projects. In a peculiar situation where some of the judgments of the High Court attained finality as the compensation amount, as enhanced, stands paid whereas the others are still subject matter of adjudication, we deem it appropriate to remand these cases also to the High Court so that a holistic view pertaining to the subject acquisition, at least project wise, can be taken by the High Court. The High Court will make an endeavour to infuse uniformity in the matter of award of compensation, to the extent it is possible, in accordance with law. **15.** It goes without saying that the High Court, while undertaking this exercise, will not reduce the compensation to a rate which has already been paid to some of the land owners and which has attained finality. The rest of the contentions from both sides are kept open to be gone into by the High Court. **16.** It is clarified that we have not expressed any opinion on the merits of the case. **17.** The parties are directed to appear before the High Court of Karnataka at Kalaburagi Bench on 18.03.2024. We request the 16 | P a g e High Court to take up these matters also, along with the _’ Rajshekhar s case_ (supra) and other cases, which are already part heard before the High Court. Since the acquisition is more than three decades old, we request the High Court to decide the matters expeditiously and preferably within three months from the date of this judgement. **18.** The instant civil appeals are disposed of in the above terms. **...................................J. (SURYA KANT) ...................................J. (K.V. VISWANATHAN)** New Delhi; March 12, 2024. 17 | P a g e ``` ITEM NO.37 COURT NO.4 SECTION IV-A ``` ``` S U P R E M E C O U R T O F I N D I A RECORD OF PROCEEDINGS ``` ``` Petition(s) for Special Leave to Appeal (C) No(s).13065/2022 ``` ``` (Arising out of impugned final judgment and order dated 22-03-2018 in MSA No.200214/2017 passed by the High Court Of Karnataka At Kalaburagi) ``` ``` THE EXECUTIVE ENGINEER, KNNL Petitioner(s) ``` ``` VERSUS ``` ``` SUBHASHCHANDRA & ORS. Respondent(s) ``` ``` (IA No.77872/2022 - EXEMPTION FROM FILING O.T., IA No.88121/2023 - PERMISSION TO FILE ADDITIONAL DOCUMENTS/FACTS/ANNEXURES) ``` ``` WITH SLP(C) No.9897/2022 (IV-A) (FOR ADMISSION and I.R.) ``` ``` SLP(C) No.10982/2022 (IV-A) (FOR ADMISSION and I.R.) ``` ``` SLP(C) No.14054/2022 (IV-A) SLP(C) No.13826/2022 (IV-A) SLP(C) No.13864/2022 (IV-A) ``` ``` SLP(C) No.14053/2022 (IV-A) (IA No. 87862/2022 - EXEMPTION FROM FILING C/C OF THE IMPUGNED JUDGMENT) SLP(C) No.14055/2022 (IV-A) SLP(C) No.13876/2022 (IV-A) SLP(C) No.14048/2022 (IV-A) (IA No. 80940/2022 - EXEMPTION FROM FILING C/C OF THE IMPUGNED JUDGMENT) SLP(C) No. 13950/2022 (IV-A) (IA No.79667/2022 - EXEMPTION FROM FILING C/C OF THE IMPUGNED JUDGMENT) ``` ``` SLP(C) No. 13948/2022 (IV-A) ``` 18 | P a g e ``` SLP(C) No. 13827/2022 (IV-A) ``` ``` (IA No. 92277/2022 - EXEMPTION FROM FILING C/C OF THE IMPUGNED JUDGMENT) SLP(C) No. 14045/2022 (IV-A) ``` ``` SLP(C) No. 13949/2022 (IV-A) ``` ``` SLP(C) No. 13859/2022 (IV-A) ``` ``` SLP(C) No. 13873/2022 (IV-A) ``` ``` SLP(C) No. 13877/2022 (IV-A) ``` ``` SLP(C) No. 11398/2022 (IV-A) (FOR ADMISSION and I.R.) ``` ``` SLP(C) No. 10980/2022 (IV-A) (FOR ADMISSION) ``` ``` SLP(C) No. 10007/2022 (IV-A) (FOR ADMISSION and I.R.) ``` ``` SLP(C) No. 10176/2022 (IV-A) (FOR ADMISSION and I.R.) ``` ``` SLP(C) No. 9860/2022 (IV-A) (FOR ADMISSION and I.R.) SLP(C) No. 11163/2022 (IV-A) SLP(C) No. 10570/2022 (IV-A) (FOR ADMISSION and I.R.) SLP(C) No. 11170/2022 (IV-A) SLP(C) No. 14052/2022 (IV-A) SLP(C) No. 14046/2022 (IV-A) SLP(C) No. 13825/2022 (IV-A) SLP(C) No. 14050/2022 (IV-A) SLP(C) No. 12949/2022 (IV-A) SLP(C) No. 13947/2022 (IV-A) SLP(C) No. 10081/2022 (IV-A) (FOR ADMISSION and I.R.) ``` 19 | P a g e ``` SLP(C) No. 10014/2022 (IV-A) (FOR ADMISSION and I.R.) ``` ``` SLP(C) No. 2284/2023 (IV-A) ``` ``` Diary No(s). 12213/2023 (IV-A) (IA No.75815/2023-CONDONATION OF DELAY IN FILING and IA No.75814/2023-EXEMPTION FROM FILING C/C OF THE IMPUGNED JUDGMENT and IA No.75810/2023-PERMISSION TO FILE PETITION (SLP/TP/WP/..)) ``` ``` Diary No(s). 13231/2023 (IV-A) (IA No.70226/2023-CONDONATION OF DELAY IN FILING and IA No.70231/2023-EXEMPTION FROM FILING O.T. and IA No.70233/2023- PERMISSION TO FILE LENGTHY LIST OF DATES) ``` ``` Date : 12-03-2024 These matters were called on for hearing today. ``` ``` CORAM : HON'BLE MR. JUSTICE SURYA KANT HON'BLE MR. JUSTICE K.V. VISWANATHAN ``` ``` For Petitioner(s) Mr. Naveen R. Nath, Sr. Adv. Ms. Hetu Arora Sethi, AOR Mr. Abhimanyu Verma, Adv. Ms. Lalit Mohini Bhat, Adv. Ms. Disha Gupta, Adv. Ms. Hetu Arora Sethi, Adv. ``` ``` For Respondent(s) Mr. Anand Sanjay M Nuli, Sr. Adv. Mr. Suraj Kaushik, Adv. Mr. Agam Sharma, Adv. Mr. Nanda Kumar, Adv. Mr. Dharm Singh, Adv. Mrs. Kiran Suri, Sr. Adv. Mr. Sharanagouda Patil, Adv. Mr. Harshvardhan Malipatil, Adv. Mr. Jyotish Pandey, Adv. Ms. Supreeta Sharanagouda, AOR Mr. S. J. Amith, Adv. Mrs. S. Anuradha Bhat, Adv. ``` ``` UPON hearing the counsel the Court made the following ``` ``` O R D E R ``` ``` 1. Permission to file special leave petition is granted in Diary No.12213/2023. ``` 20 | P a g e **`2. Delay condoned.`** **`3. Leave granted.`** **`4. The civil appeals are disposed of in terms of the signed reportable judgment.`** **`5. All pending applications, if any, also stand disposed of.`** ``` (ARJUN BISHT) (PREETHI T.C.) COURT MASTER (SH) COURT MASTER (NSH) (signed reportable judgment is placed on the file) ``` 21 | P a g e
End of Judgment Record
Browse All Landmark Cases Judgments
2019-01-22

State of Himachal Pradesh & Anr. v. Pinju Ram & Others; State of Himachal Pradesh & Ors. v. Ganesh Dutt & Anr.

This batch of appeals concerns regularisation and monetary benefits of part‑time employees in Himachal Pradesh who were converted to daily‑wage status. The State had issued a policy on 27 February 2004: part‑time Class‑IV employees who had completed ten years of continuous service as on 31 December 2003 would be made daily wagers with prospective effect, and posts vacated by such employees would stand abolished; Education and Ayurveda were excluded from the policy. Revenue Chowkidars, engaged by Panchayats, were not covered by that policy and received separate treatment. Following writ petitions and an order of the Himachal Pradesh High Court and in light of later developments, the State drew‑up directions in 2011 (22 September) to give seniority to Revenue Chowkidars on the basis of ten years of service, but with wages from the date of actual appointment and without back‑dated monetary benefits; 7 July 2012 further instructions reiterated this stance for remaining part‑time employees, with monetary benefits not guaranteed in the interregnum. The respondents pressed for back wages dating from 1 January 2007 and broader coverage. The Supreme Court held that the 2007 back‑pay direction was unsustainable, clarified that seniority would count from ten years without past benefits, and that the 2011 policy and Moti Singh principle should guide the approach. The appeals are allowed; no costs. The related writ petitions are to be disposed of consistent with these directions.

2018-08-14

Union Bank of India and Others v. C.G. Ajay Babu and Anr.

This is a Supreme Court of India appeal concerning the forfeiture of gratuity under the Payment of Gratuity Act, 1972. The respondent was a branch manager of the appellant bank and was dismissed on 3 June 2004 after disciplinary proceedings. A show-cause notice sought to forfeit gratuity due to misconduct involving moral turpitude, which was ordered on 20 April 2004. The High Court upheld the dismissal but held that gratuity could be paid since there was no financial loss to the bank, and that a bipartite settlement between the bank and employees permitted forfeiture only where misconduct caused financial loss. The Division Bench, however, held that forfeiture under Section 4(6) must be read together with Section 4(5) and that no loss was proven, thus entitling the employee to gratuity in accordance with the bipartite settlement. The Supreme Court agreed with the High Court that forfeiture is not automatic; it is controlled by Sections 4(5) and 4(6) of the Act and by the bipartite settlement, which requires loss to justify forfeiture. The Court emphasized that an act must constitute an offence involving moral turpitude and that conviction is generally required for forfeiture under 4(6)(b)(ii). The appeal is dismissed with no costs.

2018-09-25

Reema Salkan v. Sumer Singh Salkan

This is a Supreme Court of India criminal appeal under the Criminal Appellate Jurisdiction arising from a maintenance dispute under Section 125 Cr.P.C. The parties, married in 2002, had a protracted litigation history. The Family Court granted maintenance to the wife from 17 July 2003 to 8 December 2010, and held no maintenance thereafter. The High Court, in revision, partly allowed the application, directing Rs.9,000 per month from 9 December 2010 onward, while upholding the earlier period’s Rs.10,000 per month. This Court had earlier granted interim maintenance of Rs.20,000 per month in 2014 (Criminal Appeal Nos. 2347-2349 of 2014). The appellant contends there has been no change in circumstances since the interim order and that the respondent’s substantial assets, education, and overseas earnings establish the capacity to pay higher maintenance. The respondent defends the High Court’s reasoning, arguing that the Family Court’s assessment, demeanor observations, and the principle that maintenance should not be perpetual require careful scrutiny, and that the notional minimum wage approach used by the High Court is flawed. The overarching issue is the quantum of monthly maintenance payable to the appellant and whether the interim amount should be augmented beyond the period up to 2010.”

2019-12-03

M/s Embassy Property Developments Pvt. Ltd. v State of Karnataka & Ors.

This judgment concerns three Civil Appeals filed by a Resolution Applicant, the Corporate Debtor (through its Resolution Professional) and the Committee of Creditors, challenging an Interim Order of the Karnataka High Court staying an NCLT order in proceedings under the Insolvency and Bankruptcy Code, 2016. The NCLT Chennai had admitted an application under Section 7 of the IBC against M/s Tiffins Barytes Asbestos & Paints Ltd. and directed a moratorium under Section 14. The Interim Resolution Professional then sought a deemed extension of a mining lease under MMDR Act, 1957 and the Government of Karnataka rejected it. The NCLT, by an order dated 11.12.2018, set aside the Government’s order and directed execution of Supplement Lease Deeds for the period up to 31.03.2020. The Government of Karnataka challenged this in a High Court writ petition, which stayed the impugned NCLT order. The core issues were: (i) whether the High Court may interfere under Article 226/227 with an NCLT order in IBC when an appeal lies to the NCLAT, and (ii) whether fraud can be inquired into by NCLT/NCLAT in CIRP. The Court reiterates that IBC is a complete, umbrella code with a three‑tier mechanism (NCLT, NCLAT, Supreme Court) and that public‑law disputes arising from MMDR Act obligations lie outside IBC. It ultimately holds that while NCLT/NCLAT may inquire into fraud, they cannot adjudicate MMDR‑related public legal disputes; and the High Court’s writ jurisdiction in public‑law contexts remains permissible. The appeals are dismissed.