Supreme Court of IndiaSupreme Court · 2016Division BenchAppeal disposed of.

The Electricity Department, Rep. by its Superintending Engineer, Port Blair and Anr. v. M/s Suryachakra Power Corporation Limited

Case / Petition Number:
1652 of 2015
Neutral Citation:[2016] 9 S.C.R. 68

Case Synopsis & Summary

The Electricity Department, Port Blair, along with another, challenged the Appellate Tribunal for Electricity’s order allowing, suo moto, an enhanced project-cost computation by increasing the JDC (interest during construction), financing charges and incidental expenses during construction attributable to a delay in commissioning the Port Blair project. The dispute centered on whether such increases should form part of the completed cost under the Power Project Agreement (PPA) and the Techno-Economic Clearance issued by the Administrations. Expert committees — including MIS K.P.C.L. and MIS Tamil Nadu Electricity Generation and Distribution Corporation Ltd. (TANGEDCO) — were engaged to determine the project cost. A five-member committee ultimately fixed the cost at Rs. 70.61 crores after reconciling multiple reports, with a broader exercise on interlinked items. The five-member report, accepted by Administration, was placed before the Commission for acceptance. The appellants argued that the Tribunal’s suo moto addition of IDC, FC and IEDC for delays beyond the respondent’s control was not part of the appeal and inconsistent with the pleadings, and that the computed Rs. 78.29 crore figure did not reliably reflect the costs. The respondents contended that the delay, attributable to the appellants for failure to evacuate power, justified additional charges, and relied on the accepted committee reports. The Supreme Court held that the appeal is allowed only to the limited extent that the Appellate Tribunal’s order to increaseIDC/FC/IEDC is set aside; other issues were dismissed, and the matter was disposed of.

Precedent Explorer

Find Cases Like This

Explore other judgments dealing with similar legal situations, facts, or statutory provisions.

Case Details & Bench

Court
Supreme Court of India
Hon'ble Judges
  • Justice Kurian Joseph
  • Justice R. F. Nariman
Judgment Date
2016-09-22
Court Decision / Holding
The appeal is disposed of; it is allowed only to the limited extent that the judgment of the Appellate Tribunal is set aside insofar as it permitted an increase in interest during construction (IDC), financing charges (FC) and incidental expenses during construction (IEDC) incurred for the delay in the project for reasons beyond the respondent's control. On other points, the appeal is dismissed. No costs.
Final Disposition
Appeal disposed of.

Parties to the Case

Appellants / Petitioners

  • The Electricity Department, Rep. by its Superintending Engineer, Port Blair and Anr.

Respondents

  • M/s Suryachakra Power Corporation Limited

Legal Representation & Advocates

Counsels for Petitioners

  • • Rakesh Khanna, Sr. Adv.
  • • Ms. Ruchi Singhwani
  • • Mohit Paul
  • • Ms. Megha Bharara
  • • Yikash Arora
  • • Ms. Diksha Jhingan

Counsels for Respondents

  • • Gurukrishna Kumar, Sr. Adv.
  • • Rohit Rao N.
  • • Mukund P. Unny
  • • Ananga Bhattacharyya

Submissions & Arguments

Contentions of Appellants / Petitioners

The appellants contended that the Appellate Tribunal's suo moto direction to pay additional IDC, FC and IEDC as a consequence of delay was beyond the scope of the appeal and not supported by the pleadings. They argued that the Rs. 78.29 crore project-cost figure started from Rs. 77.595 crore on a 'funds tied up' basis per CEA approvals, and that several items relied upon by the five-member committee were not included in the cost. They asserted that the delay in achieving COD arose from the respondent's failure to provide transmission lines under the PPA, and that deemed generation charges are higher than the additional IDC/FC/IEDC, so the tribunal's decision to grant the lower of the two should be re-evaluated. They urged strict adherence to the PPA and TEC framework and limited examination to the matters actually appealed.

Contentions of Respondents

The respondents argued that the delay in COD was attributable to the appellants, that the five-member committee report was accepted by the Administration and relied upon by the Commission, and that the inquiry properly allowed for IDC/FC/IEDC as a consequence of the delay. They contended that deemed generation charges for the period of delay were higher than the added IDC/FC/IEDC, and that the appellate tribunal’s direction fell within the scope of the case. They maintained that the cost figures were derived from the 'funds tied up' basis supported by the CEA and the referenced reports.

Legal Doctrine & Issue Explorer

Explore This Legal Issue

Find relevant judgments and authoritative positions on the legal questions discussed here.

Case Applicability Diagnostic

Apply This to My Facts

Share your situation and test whether this judgment governs, supports, or challenges your case.

Official Judgment Record
•2,004 words•~10 min read

In The Court Record

The Electricity Department, Rep. by its Superintending Engineer, Port Blair and Anr. v. M/s Suryachakra Power Corporation Limited

[2016] 9 S.C.R. 68 - A THE ELECTRICITY DEPARTMENT, REP. BY ITS SUPERINTENDING ENGINEER, PORT BLAIR AND ANR. v. B _MIS_ SURYACHAKRA POWER CORPORATION LIMITED (Civil Appeal No. 1652of2015) ## SEPTEMBER 22, 2016 ## [KURIAN JOSEPH AND R. F. NARJMAN, JJ.) - ·; .••. ·'-' dll t _<.:llC111 .1ur jJiiJ 111ea: uj l/t.hlitio11al costs_ - _and expenses_ - _Power Project Agreement (PPA)_ - _Delay in execution_ - c _of project_ - _Increase in various cost components, viz., illleresl during construction (JDC); financing charges (FC); and incidental expenses during construction (IEDC) incurred for the delay,_ suo moto _allowed in appeal by Appellate Tribunal_ - _Propriety of- Held: Appellants are on solid grou111;f in contending that an increase in_ - D _JDC, FC and IEDC was allowed in appeal by the Appellate Tribunal._ suo moto - _Appeal allowed only to this limited extent_ - _On other points, it is dismissed_ Disposing of the appeal, the Court HELD: 1.1 The appellants are on solid ground when they E contend that an increase in interest during construction, financing charges and incidental expenses incurred for the delay in the execution of the project due to reasons beyond the control of the respondent was allowed in appeal by the Appellate Tribunal _suo moto._ [Para 6] [72-A-Bl - F 1.2 The appellant argued that the tribunal directed a _suo moto_ payment of additional JDC, financing cost and incidental expenses during construction even though this was not the part of the appeal filed by the respondent (appellant therein) before the tribunal. The respondent contended that in any \:ase what G was referred to, in the Commission's judgment in order to arrive at the figure of Rs.78.29 Crores as the project cost in fact started with the figure of Rs. 77.595 Crores, being CEA approval as per "funds tied up" basis, which according to the respondent, included the aforesaid expenditure. It was argued by the respondent that certain figures which were referred to and relied upon by the H 68 ELECTRICITY DEPT., REP. BY ITS S.E., PORT BLAIR v. _MIS_ 69 SURYACHAKRA POWER CORPN. LTD. CEA to arrive at this figure specifically included the aforesaid. A No such figures were shown. [Paras 7, 8) [72-C; 73-B-C] 1.3 Therefore, the appeal is allowed only to this limited extent. Judgment of the Appellate Tribunal insofar as it allowed an increase in interest during construction (IDC), financing charges (FC) and incidental expenses during construction (IEDC) incurred for the delay in execution of the project for reasons beyond the control of the respondent, is set aside.[Para 8)(73-D] CIVILAPPELLATE JURISDICTION: Civil Appeal No. 1652 of 2015. From the Judgment and Order dated 28.11.2014 of the Appellate Tribunal for Electricity at New Delhi in Appeal No. 268 of2013. B c Rakesh Khanna, Sr. Adv., Ms. Ruchi Singhwani, Mohit Paul, Ms. Megha Bharara, Yikash Arora, Ms. Diksha Jhingan, Advs. for the Appellants. D Gurukrishna Kumar, Sr. Adv., Rohit Rao N., Mukund P. Unny, Ananga Bhattacharyya, Advs. for the Respondent. The Judgment of the Court was delivered by R. F. NARIMAN, J, I. We have heard Shri Rakesh Khanna, learned senior counsel appearing for the appellants for quite some time, and Shri. Gurukrishna Kumar, learned senior counsel appearing for the respondent in reply. Though Shri Rakesh Khanna has taken us through the PPA, various documents, and various orders in great detail, we do not find it necessary to go into any of these for the reason that we find that the appellants had set up various expert committees to go into the bone of contention in this appeal, namely, project cost and completed cost. E F 2. We find that _Mis._ K.P.C.L _(Mis._ Kamataka Power Corporation Ltd.) had been appointed by them in order to determine the project cost which was determined at Rs.73.40 crores. _Mis._ Tamil Nadu Electricity Generation and Distribution Corporation Ltd. (TANGEDCO), another expert, arrived at a finding of Rs. 82.11 crores, which was reconfirmed by a subsequent report, and ultimately arrived at a figure of Rs.79.439 crores with other issues which were to be decided separately. A joint exercise between the appellants and respondent, also carried out in April, 2010, where a figure of Rs. 76.14 crores was arrived at, and the balance G H ~ 70 SUPREME COURT REPORTS [2016] 9 S.C.R. - A of Rs. 8.82 crores in respect of roe, that is, interest during construction and preliminary expenses was left to be examined by the Central Electricity Authority. The Central Electricity Authority also came out with three separate reports in which it arrived at certain figures of project cost. Finally, the administration appointed a five member committee after all these reports, and in 2013, this five member committee ultimately arrived - B at Rs.70.61 crores as the final project cost. This was as follows : " |Descriptionofitems||Quantumof<br>Expenditure<br>Rs. C rores|ParaRef.of<br>Committee<br>Report| |---|---|---|---| |ApprovedCost||63.14|15,17,29&30| |JDC|(-)|3.00|| |Costexcluding!De|(+)|60.14|| |Increaseincostof<br>Establishmentdueto<br>extendedgestationperiod|(+)|3.30|17| |IncreaseduetoExchange<br>Rate variationconsidering<br>only 5.13MUS$ Rs.11.0445perdollar|(+)|5.67|Allowedas<br>peractual<br>utilization| |AdditionalTransformerand<br>BlackStartDGSet-Work<br>doneafterCOD|(+)|0.31|22| |HardCostexcl. IDC||69.42|| |ProportionateJDConthe<br>hardcostofRs.69.11Cr.|(+)|4.91|Revisedon<br>hardcost| |Completedcostincluding<br>JDC/Projectcost||74.33|| |Liquidateddamage@5%<br>onRs.74.33crores|(-)|3.72|| |ProjectCompletedCost||70.61|| 3. Subsequently, it has been stated that the said report of the five member committee has been accepted by the Administration. The Respondent had prayed that the Hon'ble Commission determine the H ELECTRICITY DEPT., REP. BY ITS S.E., PORT BLAIR v. MIS 71 SURYACHAKRA POWER CORPN. LTD. [R. F. NARIMAN, J.] project cost and tariff thereon in accordance with the provisions of PPA/ Techno Economic Clearance issued by A&N Administration and the report of the five members committee constituted by the A & N Administration for the purpose of determination of the cost of the project as Rs. 70.61 crores. 4. When we pointedly referred to these reports and the figures contained therein, together with the fact that the respondent itself accepted the five member committee report, which is then placed before the commission for acceptance, we find it a little difficult to now allow the respondent to go behind the said report. None of the expert committee reports allow certain amounts to be deducted from the project cost which would, ifthe appellants were to succeed before us, amount to a figure of Rs. 18.25 crores as is now argued before us by the appellants. Even the five member committee report, accepted by the Administration, does not include any figures to be minused on account of under utilization of foreign currency component of Rs. 4.149 crores; custom-duty concession of Rs. 2.80 crores; concession in Land Registration Charges availed by the respondent amounting to Rs.0.3234 crores; and cost for start-up fuel and LUBE oil for trial and test run amounting to Rs.0.1971 crores. 5. Shri Khanna took us through the memo of appeal filed before the Appellate Tribunal and referred specifically to ground (C) and question of law 8(b) I which read as follows: "The JERC has relied upon the reports of the 'experts' which are contrary to the PPA. JERC has erred in giving foreign exchange variation on 7 .96 MUSD. Documents submitted by the respondent clearly show that the respondent had utilised only 9472653 DEM (equivalent to 5 .13 MUSD) as foreign currency for the purpose of importing the equipment which is mandated by the PPA. A B c D E F "8(b) 1. Whether the JERC has not erred by following recommendations/reports which are in contravention of the provisions of PPA for computation of completed cost." 6. We are afraid that these grounds do not help the appellants' case. Nowhere has it been stated, in any of the grounds thatthe statement made by the commission that the five member committee report had been accepted by the Administration is said to be incorrect. On the contrary, the ground sought to be raised in the appeal is that the commission has relied upon these reports, which reports are contrary to G H 72 [2016] 9 S.C.R. SUPREME COURT REPORTS - A the Power Project Agreement. We are thus of the opinion that none of these aspects can be looked into by us in the present appeal. However, we find that the appellants are on solid ground when they contend that an increase in interest during construction, financing charges and incidental expenses incurred for the delay in the execution of the project due to reasons beyond the control of the respondent has been allowed in - B appeal by the Appellate Tribunal at para 23 and 36 suo moto. 7. Shri Rakesh Khanna has argued before us and shown us the ground taken in the present appeal that the tribunal has directed a suo moto payment of additional JDC, financing cost and incidental expenses duri11g construction even though this was not part of the appeal filed by c the appellant M/s. Suryachakra Power Corporation Limited before the Tribunal. Th is is sought to be answered by the respondent in its counter affidavit in this Court in paragraph (F) which reads as under: - "In the synopsis the appellant has sought to contend that the Tribunal has suo-moto directed payment ofadditional interest during - D construction (JDC), financing cost (FC) and incidental expenses during construction (IEDC) for the period of delay in achieving commercial operation. The appellants have also sought to contend that the said issue regarding additional JDC, FC and IEDC was not a part of the appeal filed before the Tribunal. In this contekt, - E it is respectfully submitted that the said contention of the appellants is incorrect and misleading. It is respectfully submitted that the issue regarding t~e delay in achieving commercial operation and to whom was the delay attributable was pleaded and considered in detail by both the Joint Electricity Regulatory Commission as well as the Tribunal. Additional JDC, FC and IEDC are only - F consequences that follow the delay in achieving the commercial operation. Both the Courts below have concurrently held that the delay in achieving commercial operation of more than a year was attributable to the appellants themselves as they did not provide the transmission lines to evacuate the power from the project - G within the time prescribed under the PPA. Therefore the Respondents herein had claimed deemed generation charges for the whole period of delay in achieving commercial operation. It is pertinent to mention that the deemed generation charges is higher than the additional IDC, FC and IEDC. Thus, the Tribunal has granted the Respondents the lower of the two. The deemed H 73 ELECTRlCITY DEPT., REP. BY ITS S.E., PORT BLAIR v. M/S SURYACHAKRA POWER CORPN. LTD. [R. F. NARIMAN, J.] generation charges have been awarded only for a period of four months out of the total delay of more than a year in achieving commercial operation. The Respondent is not claiming additional JDC, FC and IEDC for the said period of four months for which deemed generation charges have been granted." 8. In reply, Shri Gurukrishna Kumar, learned senior counsel appearing for the respondent, points out before us that in any case what was referred to in the commission's judgment in order to arrive at the figure of Rs. 78.29 crores as the project cost in fact started with the figure of Rs. 77.595 crores, being CEA approval as per "funds tied up" basis, which according to the lean.ed senior counsel, would include the aforesaid expenditure. He argued before us that certain figures which were referred to and relied upon by the CEA to arrive at this figure specifically included the aforesaid. We were not shown any such figures. · We, therefore, allow the appeal only to this limited extent and set aside the judgment of the Appellate Tribunal insofar as it allows an increase in interest during construction (!DC), financing charges (FC) and incidental expenses during construction (IEDC) incurred for the delay in execution of the project for reasons beyond the control of the respondent. To this limited extent alone the appeal stands allowed, and on other points it is dismissed. 9. We are also of the view that apart from the above, no substantial question of law is raised in this appeal. A B c D E JO. For the aforesaid reasons, we dispose of the appeal with no other costs. Divya Pandey Appeal disposed of. F
End of Judgment Record
Browse All Supreme Court of India (2016) Decisions
2016-03-16

Union of India v. Mis. Ambica Construction

This judgment addresses whether an arbitrator can award pendente lite interest when a contract expressly bars such interest, within the framework of Indian arbitration law. The Union of India approached this dispute after two arbitrators failed to publish an award and after a long procedural history in the Calcutta High Court and various SLPs. The core issue is whether pendente lite interest can be awarded where the contract contains explicit clauses barring such interest, and how this interacts with the implied terms of arbitration under the Arbitration Act, 1940 and, for post-1996 matters, the Arbitration and Conciliation Act, 1996. The Court traces a lineage of decisions (GC Roy; NC Budharaj; Sayeed Ahmed; Harish Chandra; Balimela; Engineers-De-Space-Age; Tehri Hydro) and clarifies that while arbitrators are generally creatures of the contract, their power to award pendente lite interest is bounded by express contractual bars. It concludes that no pendente lite interest can be awarded if the contract expressly prohibits it. The judgment also recognizes Tehri Hydro’s reasoning and clarifies the status of earlier decisions, holding certain observations as overruled or limited prospectively. The result is that the High Court and the award are to be modified to reflect the absence of pendente lite interest, with a reference answered and no costs awarded.”

2016-08-29

Madhya Pradesh State Road Transport Corporation v. Manoj Kumar & Anr.

This is a civil appeal challenging the voluntary retirement scheme (VRS) introduced by the Madhya Pradesh State Road Transport Corporation (MPSRTC) to downsize its workforce as the company faced losses and declining business. The scheme opened on July 1, 2005 and closed on August 1, 2005, with employees permitted to submit their option for voluntary retirement (VRS) within that window. The scheme included a clause stating that once an employee’s option was submitted it could not ordinarily be withdrawn, yet the scheme was a funded, time-bound arrangement requiring the employer to create a fund and to lay out a process for acceptance and settlement. In October 2006, the Corporation issued an amendment extending the period to October 28, 2006, prompting questions whether this extension created a new scheme or was merely an extension of the original. Several employees who had submitted applications sought withdrawal after August 1, 2005, and in some cases after the extension, while the Corporation accepted their VRS applications and disbursed terminal dues. The High Court of Madhya Pradesh upheld the employees’ right to withdraw within the relevant periods, but the Supreme Court concluded that VRS schemes, being contractual and funded, are invitations to offer governed by the Indian Contract Act, and withdrawals are permissible only within the valid period; the extension does not automatically grant a right to withdraw beyond the original window. The Court accordingly set aside some reinstatement orders and disposed of the appeals in favor of the Corporation in most respects.

2016-07-01

Mahipal Singh Rana, Advocate v. State of Uttar Pradesh

The appeal arises from a High Court of Allahabad judgment (Criminal Contempt Petition No.16 of 2004) finding the appellant, an advocate, guilty of criminal contempt for intimidating and berating a Civil Judge, Etah, on two dates (16 April 2003 and 13 May 2003). The Allahabad High Court sentenced him to two months’ simple imprisonment and imposed a fine, with a direction to Bar Council authorities to consider disciplinary action for professional misconduct. On admission to this Supreme Court, the matter was referred to a larger bench to decide whether a case of criminal contempt by a lawyer could also implicate professional misconduct beyond the contempt regime, and whether the Court could exercise suo motu jurisdiction under the Advocates Act if Bar Councils fail to act. The Court examined the separation of powers between contempt proceedings and Bar Council disciplinary processes, the scope of Article 142/129, and the ability to regulate appearance in courts (including the right to practice vs. the right to appear). It held that contempt conviction was justified and upheld the High Court’s finding, but set aside the imprisonment sentence due to the appellant’s advanced age. It sustained a two-year enrollment suspension under Section 24A of the Advocates Act and directed the Bar Councils to suspend the licence for an additional five years, with further appearance restrictions until the contemnor purges himself of contempt. The judgment emphasizes reform of regulatory mechanisms governing the legal profession and the State Bar Councils’ failings in acting on earlier notices.

2016-03-10

CHARANJIT KAUR v. BIKRAM SINGH & ANR.

Charanjit Kaur, wife of Bikram Singh, faced dowry-related harassment under sections 498A and 406 IPC. The trial court convicted the husband and imposed a one-year RI for each offence, with the sentences to run concurrently and a fine of Rs. 1,000/- with default imprisonment. The wife appealed against the conviction and also sought enhancement of punishment; the husband cross-appealed. The mother-in-law was acquitted; the father-in-law had died. The Sessions Court at Kapurthala modified the sentence by permitting the husband to deposit Rs. 2,50,000 payable to the appellant within one month, so that he could obtain the benefit of probation under Section 4(1) of the Probation of Offenders Act, 1958. The wife’s revision before the High Court of Punjab & Haryana at Chandigarh was dismissed in a summary manner, reportedly influenced by the deposit. The Supreme Court, noting the summary disposal and the deposit-driven rationale, held that the impugned order required setting aside so that the matter could be re-heard on merits. It directed remand to the High Court for a fresh decision strictly in accordance with law, without entering into the merits of rival submissions in this order. The decision was delivered by a Single Judge, Justice Shiva Kirti Singh, on March 10, 2016.