Case Synopsis & Summary

This writ petition challenges Ext.P4, the Sub Judge, Koyilandy's order in O.S.7/2008 directing the plaintiffs to value the reliefs sought for partition on the market value of the entire property and to pay court fee accordingly, including the value of two registered documents sought to be declared void. The petitioners, Thayyankhannapoyil Ayissa and Nabeesa, are the plaintiffs; the respondents are Cheruvalath Ammath and his sisters Pathumma, Jameela, and Subaida. The issue of valuation and court fee was treated as a preliminary issue. The Sub Judge held that Sub Section (2) of Section 40 of the Kerala Court Fees and Suits Valuation Act applies only when liability cannot be split, and that the relief to set aside those documents requires valuation of the whole property and payment of court fee on that value. The petitioners argued that Sub Section (2) enables limiting valuation to their share (2/7th) of the property. The High Court rejected this interpretation, citing Pachayammal v. Dwaraswamy Pillai (2006) 3 KLT 527 as controlling authority. It granted one month to amend the plaint and remit the court fee from the date of judgment, and closed the writ petition, upholding the court's approach to valuation while allowing the amendment.

Precedent Explorer

Find Cases Like This

Explore other judgments dealing with similar legal situations, facts, or statutory provisions.

Case Details & Bench

Court
High Court of Kerala
Hon'ble Judges
  • S.S.SATHEESACHANDRAN
Judgment Date
2009-07-30
Court Decision / Holding
Writ petition disposed; the High Court rejected the petitioners’ interpretation of Sub Section (2) of Section 40, upheld the need for valuation for the whole property, cited Pachayammal; the court directed the petitioners to amend the plaint within one month and remit court fee from the date of the judgment; the writ petition is closed.
Final Disposition
Writ petition disposed/closed with directions to amend and remit court fee

Parties to the Case

Appellants / Petitioners

  • Thayyankhannapoyil Ayissa
  • Nabeesa

Respondents

  • Cheruvalath Ammath
  • Sister Pathumma
  • Sister Jameela
  • Sister Subaida

Legal Representation & Advocates

Counsels for Petitioners

  • • T.G. Rajendran

Counsels for Respondents

  • • K.P. Sudheer
  • • N.N. Praseeda
  • • Cibi Thomas

Provisions of Law Cited

Article 227 of the Constitution of IndiaSection 37(2) of the Court Fees ActSection 40(2) of the Kerala Court Fees and Suits Valuation Act

Submissions & Arguments

Contentions of Appellants / Petitioners

Petitioners argued that Sub Section (2) of Section 40 enables valuation and court fee to be computed on the plaintiff's share or on a specific item; for setting aside the two void documents, they contended court fee should be payable on 2/7th share of the market value, not on the entire property. They sought one month to amend the plaint and remit court fee.

Contentions of Respondents

Respondents contended valuation must be on the market value of the whole property for the relief to set aside the two documents, as liability cannot be split; Sub Section (2) is not applicable; the court should insist on remittance of court fee for the entire property.

Legal Doctrine & Issue Explorer

Explore This Legal Issue

Find relevant judgments and authoritative positions on the legal questions discussed here.

Cited Precedents (1)

Case NameCitationTreatmentExplanation
Pachayammal v. Dwaraswamy Pillai2006 (3) KLT 527PositiveCited as authority supporting the principle that, for a declaration to set aside documents, valuation and court fee must be computed for the whole property, not merely the plaintiff's share.
Case Applicability Diagnostic

Apply This to My Facts

Share your situation and test whether this judgment governs, supports, or challenges your case.

Official Judgment Record
•1,022 words•~5 min read

In The Court Record

Thayyankhannapoyil Ayissa and Nabeesa v. Cheruvalath Ammath and Sisters Pathumma, Jameela and Subaida

**IN THE HIGH COURT OF KERALA AT ERNAKULAM** **PRESENT :** **THE HONOURABLE MR. JUSTICE S.S.SATHEESACHANDRAN** ## **THURSDAY, THE 30TH JULY 2009 / 8TH SRAVANA 1931** **WP(C).No. 37172 of 2008(A)** **--------------------------------------** **OS.7/2008 of SUB COURT, KOYILANDY. ....................** ## **PETITIONER(S):** - **---------------------** **1. THAYYANKHANNAPOYIL AYISSA, D/O. KUNHAMI UMMA, NAMBITHOOR HOUSE, SWASTHAM, MENHANNIAM AMSOM, MARUTHERI DESOM, KOYILANDY TALUK, MENHANNIAM.P.O.** **2. NABEESA, D/O. KUNHAMI UMMA, KALAKUTTIKUNI HOUSE, KUNNATHARA, ULLIYERI AMSOM, AANAVATHIL DESOM, KANNOOR.P.O, ULLIYERI VIA, KOYILANDY.** **BY ADV. MR.T.G.RAJENDRAN** ## **RESPONDENT(S):** **-------------------------** **1. CHERUVALATH AMMATH, S/O. KUNHAMI UMMA, AGRICULTURIST, CHERUVALATH MEETHAL HOUSE, MENHANNIAM AMSOM, MARUTHERI DESOM, KOYILANDY.** **2. SISTER PATHUMMA, D/O. KUNHAMI UMMA, NHERAPOYIL HOUSE, CHERUVANNUR AMSOM DESOM, KOYILANDY TALUK, CHERUVANNUR.P.O.** **3. SISTER JAMEELA, D/O. KUNHAMI UMMA, VALLUPARAMBIL HOUSE, NOCHAD AMSOM, CEHNOLI DESOM, KOYILANDY TALUK, PERAMBRA.P.O.** **4. SISTER SUBAIDA, D/O. KUNHAMI, OZHAKKERIPARAMBA HOUSE, KIDAVOOR AMSOM, PALLIPURAM DESOM, THACHAMPOYIL.P.O, THAMARASSERY.** **R1 BY ADV. MR.K.P.SUDHEER , SMT.N.N.PRASEEDA . R2 TO R4 BY ADV. MR.CIBI THOMAS.** **THIS WRIT PETITION (CIVIL) HAVING BEEN FINALLY HEARD ON 30/07/2009, THE COURT ON THE SAME DAY DELIVERED THE FOLLOWING:** **WP(C) NO. 37172/2008-A** ## **APPENDIX** ## **PETITIONER'S EXHIBITS:** **EXT.P1: COPY OF THE PLAINT IN O.S.7/2008 ON THE FILE OF THE SUBORDINATE JUDGE, KOYILANDY.** **EXT.P2: COPY OF THE ORDER IN O.S.7/2008 ON THE FILE OF THE SUBORDINATE JUDGE, KOYILANDY.** **EXT.P3: COPY OF THE JUDGMENT IN WP(C) NO. 30029/2008 OF THIS HONOURABLE COURT.** **EXT.P4: COPY OF THE ORDER OF THE SUB JUDGE, KOYILANDY IN O.S.7/2008.** ## **RESPONDENT'S EXHIBITS: NIL** ## **//TRUE COPY//** **P.A. TO JUDGE** **rs.** ## **S.S.SATHEESACHANDRAN, J.** ## **------------------------------W.P.(C).NO.37172 OF 2008 (A) ----------------------------------Dated this the 30[th] day of July, 2009** ## **J U D G M E N T** The writ petition is filed seeking the following reliefs: i. to issue a writ of certiorari or any other appropriate writ order or direction, quashing Ext.P4 order of the Sub Judge, Koyilandy. ii. to grant such other reliefs prayed for from time to time including cost of these proceedings. 2. Petitioners are the plaintiffs in O.S.No.7 of 2008 on the file of the Sub Court, Koyilandy and respondents are the defendants. Suit is one for partition. On the basis of the contentions raised by the defendants in their written statement, among other issues, valuation of the suit and also sufficiency of the court fee paid on the reliefs claimed was also raised by the court. That issue was considered as a preliminary issue and after hearing the counsel on both sides, the court below passed Ext.P4 order. Propriety and correctness of Ext.P4 order to the extent the plaintiffs are WPC.37172/08 2 aggrieved is challenged in this writ petition invoking the supervisory jurisdiction vested with this Court under Article 227 of the Constitution of India. 2. I heard the counsel on both sides. So far as the challenge raised as to the court fee paid under Section 37 (2) of the Court Fees Act for getting the relief of partition, the contentions raised by the defendants were negatived by the learned Sub Judge, but, with respect to the valuation and court fee paid in respect of two registered documents which are sought to be declared as void, the court below accepting the contentions of the defendants directed the plaintiffs to value the suit and pay the court fee therein with respect to the market value of the property covered by those deeds. Correctness of that decision is impeached by the plaintiffs/petitioners in the present writ petition. Setting aside the two documents, the plaintiffs would get only[2] /7th shares, and as such in respect of the valuation for setting aside those documents and also the court fee payable thereon, plaintiffs need pay only[2] /7th of the market value of the whole property covered by the deeds, and accordingly, the valuation WPC.37172/08 3 has been correctly made and court fee paid, is the submission of the learned counsel. Sub Section (2) of Section 40 of the Kerala Court Fees and Suits Valuation Act is also relied by the learned counsel for the petitioners to contend that it enables the plaintiffs to assess the valuation and pay the court fee as canvassed. On the other hand, the learned counsel for the respondents submitted that valuation has to be made in respect of the market value for the whole property and not in respect of the share alone of the plaintiffs over the property, covered by the two deeds which are sought to be set aside, and court fee on the market value for the whole property has to be remitted. 3. I do not find any merit in the submissions of the learned counsel for the plaintiff that valuation and court fee in the present case falls under Sub Section (2) of Section 40 of the Kerala Court Fees and Suits Valuation Act. Sub Section (2) of Section 40 of the Kerala Court Fees and Suits Valuation Act, makes it clear that the document or decree should be one in which the liability under it cannot be split up, and, further, the relief claimed must relate only to a particular item of WPC.37172/08 4 property belonging to the plaintiff or to the plaintiff's share in any such property. That is not the case here. When that be so, for a declaration to set aside those documents, plaintiffs are bound to value the suit for the whole property in accordance with the market value and remit the court fee thereof and not in respect of their share alone. That position is concluded by the decision rendered by the Division Bench of this Court in **Pachayammal v. Dwaraswamy Pillai (2006 (3) KLT 527)** . 4. The learned counsel for the petitioners sought for one month's time to amend the plaint to correct the valuation and pay the court fee payable. The court below is directed to grant the petitioners/plaintiffs one month's time to to carry out the amendment and remit the court fee from the date of this judgment. Subject to the above observations, this writ petition is closed. Handover a copy of this judgment to the counsel on both WPC.37172/08 5 sides on usual terms, and transmit a copy of this judgment to the court below forthwith. **S.S.SATHEESACHANDRAN JUDGE** prp
End of Judgment Record
Browse All High Court of Kerala (2009) Decisions
2009-06-26

Nishana Mol.N v Alappuzha Municipality & Secretary, Alappuzha Municipality

This writ petition concerns the registration of a marriage under the Kerala Registration of Marriages (Common) Rules, 2008 (Common Rules). The petitioner Nishana Mol.N, whose marriage was solemnized on 8 March 2009, sought registration of her marriage by the Local Registrar. Her husband was abroad, and she submitted Form No. 1 along with documents; however, the Local Registrar demanded the presence of both spouses for registration, a point contested by the petitioner. The court recalls the apex court’s directions in Seema v. Ashwani Kumar (2006) to frame rules ensuring compulsory registration to protect women and provide evidence of marriage, while noting that registration under the Rules does not itself create a marriage but evidences one solemnized otherwise. The Rules specify that registration is mandatory for marriages solemnized within the state, with various procedural requirements (Rules 5, 6, 9, 10, 11, 13, 16, 17) and mechanisms for correction, appeal, and re-registration. The court clarifies that the presence of both parties is not ordinarily required; the registrar may require appearance only in cases where there is reasonable doubt about identity, and even then as an exception rather than a rule. Ultimately, the court directs that registration and certificate issuance be completed within one month from copy of the judgment, without insisting on joint appearance, provided the memorandum is in order.

2009-07-27

Abdul Majeed Kalathil v. District Collector, Malappuram & Others

This batch of writ petitions concerns the constitutional validity of Section 17 of the Kerala Anti-Social Activities (Prevention) Act, 2007, and the power of District Magistrates to confiscate vehicles used in anti-social activities. The petitions challenge the absence of a substantive prohibition against using vehicles for anti-social activities and the lack of a defined procedure for confiscation or an appellate remedy. In W.P.C. No. 9925 of 2009 (the lead case), Abdul Majeed Kalathil contends that his goods carriage KL 11-B/6651 was seized by the Sub Inspector of Pandikkad Police and reported to the District Collector, Exts.P1–P2. The court scrutinizes Section 17's scope, defining anti-social activity (Section 2(a)) and whether the District Collector’s power to confiscate is constitutionally tenable. It finds Section 17 to be vague and violative of Articles 14, 19(1)(g) and 21, as it rests on subjective police satisfaction with no clear standards or process. It also notes environmental objectives but concludes that fundamental rights must prevail. The court does not sustain confiscation under Section 17; instead, it directs that such vehicles be dealt with under the Kerala Protection of River Banks and Regulation of Removal of Sand Act, 2001 and Rules, with interim release under specified conditions. It further directs initiation of Sand Act proceedings within a month and finalization within another month. The writ petitions are disposed of accordingly, preserving the rule of law and environmental protection.

2009-06-11

WA No. 671 of 2006 (Fertilizers and Chemicals Travancore Ltd v Union of India)

This writ appeal concerns the pay revision and pensionary benefits of employees of the Fertilizers and Chemicals Travancore Ltd (FACT). The long-term settlement covering terms of employment expired on 31 December 1996. A fresh settlement was concluded (notified 28 August 2001) and made retroactive to 1 January 1997, with revisions in wages and benefits. Clause 29 of Ext. P1 provides that arrears relating to wage revision and dearness allowance for the period 1 January 1997 to 30 June 2001 will be reviewed and decided by management/government only when the company earns profits for at least three consecutive years; Clause 33.1 provides that employees who retired on or after 1 January 1997 will be eligible for arrears calculated from 1 January 1997 to the date of retirement, subject to adjustments for interim relief already paid, with any unclaimed amount transferred to a Welfare Fund. The appellants—the retirees who fall in the 1 January 1997 to 1 July 2001 window—argue that they were denied arrears and were paid pensionary benefits at pre-revised rates, creating discrimination. Respondents contend Ext. P1 binds the parties and arrears depend on profits, and that pay revision administered to others does not compel retroactive change. The court held that Ext. P1 terms survive as terms of employment and directed the management to consider terminal benefits at revised rates within two months and to release arrears when paid to current workers, with connected matters following."

2009-05-29

M/S. Palm Fibers & Yars Trading Co. v. State of Kerala & Others

The petitioner, a Small Scale Industrial unit, ran two LT power connections (No.13070 and No.13427) with commercial production starting in July 1994 and July 1995. On 06/02/1992, the Government issued Ext.P1 guaranteeing concessional tariffs (pre-1992 tariff) for five years from the date of commencement or substantial capacity expansion, certified by the District Industries Centre. Ext.P2 certified eligibility for this concession. Subsequently, the petitioner increased power demand to 300 KVA and was reclassified/advised to HT status from 15/05/1998, converting LT supply to HT. The petitioner argued that Ext.P1 benefits should extend for the full five-year period, covering the LT quantities certified in Ext.P2, and that the HT conversion was a mere reclassification directed by the Board, not a cessation of eligibility. The Board argued Ext.P1 targets only those who commenced production during 1992–1996 and that HT conversion from 15/05/1998 falls outside the Ext.P1 window, rendering the petitioner eligible only up to 15/05/1998. Earlier orders (Ext.P3) had set aside a cut-off date for merits, and Ext.P6/Ext.P4 handled appeals. Ultimately, the Court held that the HT conversion was outside Ext.P1’s period, but directed that the LT benefits for the two LT connections be extended only until 23/05/1998 (LT dismantling date) and without reimbursement from the Industries Department, as held in OP No.7622/1998. The petition was disposed of as above.