TENCO PRIVATE LIMITED v. THE KERALA STATE ELECTRICITY BOARD and others

Case / Petition Number:
A.S. No: 507 of 1998 (B)

Case Synopsis & Summary

This Kerala High Court appeal arises from a suit filed by TENCO Private Limited for recovery of money arising from a contract to supply RCC/PSC poles to the Kerala State Electricity Board (KSEB). The trial court dismissed the suit. The appellant contends that the respondents breached the contract by delaying supply of raw materials, resulting in loss of potential profits and additional costs, and disputes the liability to pay excise duty (ED) on the poles, arguing that ED was to be borne by the Board or adjusted through advance payments. Clause 14 of Ext.A5 (the tender/contract) purportedly bars any compensation for delay, while Clause 6(b) claimed the contract price was inclusive of all taxes and duties. The appellant also alleges that the board’s advances for ED and Ext.A12 evidence show ED payments were to be refunded or credited to the board, implying liability on the respondents. The respondents counter that the suit is barred by limitation, that compensation is barred by Clause 14, and that the contract price was inclusive of taxes; they rely on statutory contract terms and precedent to argue ED was the contractor’s liability or, at best, circumstances did not entitle the appellant to damages for delay. The court ultimately upholds the trial court’s view and dismisses the appeal, holding no merit in the appellant’s claims for compensation, ED liability, or rent. The final order: appeal dismissed with no order as to cost.

Precedent Explorer

Find Cases Like This

Explore other judgments dealing with similar legal situations, facts, or statutory provisions.

Case Details & Bench

Court
High Court of Kerala
Hon'ble Judges
  • K. M. Joseph
  • M. L. Joseph Francis
Judgment Date
2009-12-23
Court Decision / Holding
The appeal is dismissed. There is no order as to cost.
Final Disposition
Appeal dismissed

Parties to the Case

Appellants / Petitioners

  • TENCO PRIVATE LIMITED

Respondents

  • The Kerala State Electricity Board
  • The Executive Engineer, Kerala State Electricity Board Circle Office, Kasaragod
  • Deputy Chief Engineer, Office of the Chief Engineer, K.S.E.B., Kasaragod

Legal Representation & Advocates

Counsels for Petitioners

  • • Sri. Kodoth Sreedharan

Counsels for Respondents

  • • Sri. C K Karunakaran, SC, KSEB

Provisions of Law Cited

Indian Contract Act, 1872 – Section 23Indian Contract Act, 1872 – Section 55Indian Contract Act, 1872 – Section 56Indian Contract Act, 1872 – Section 73Central Excise Act, 1944APDSS Clause 59Ext.A5 Clause 14Ext.A5 Clause 6(b)

Legal Doctrines & Maxims

  • Time is of the essence
  • Damages for loss of the whole transaction
  • Loss of profit as measure of damages in contract breach (General principle)
  • Damages depend on facts and circumstances
  • Contract price inclusive of taxes and duties (construction/oral contracts)
  • Judicial approach to enforceability of contract clauses restricting compensation (ext. Clauses)
  • Chitty on Contracts (28th Edn.), para 22-015 (reference to loss of profit measure)

Submissions & Arguments

Contentions of Appellants / Petitioners

The appellant contends there is breach by the respondents in not supplying raw materials timely, leading to a loss of opportunity to undertake other contracts and losses due to delay. It asserts the board’s liability to pay excise duty and argues that Ext.A12 shows the board’s responsibility for ED payments; the ad hoc advance of Rs.1,39,196/- for ED should be refunded or reconciled. Clause 14 of Ext.A5 bars compensation for delay, but the appellant argues such a clause cannot override Section 23 and 73 of the Indian Contract Act, and that the measure of damages for loss of profit should be considered under Section 55 and 56, as clarified by the Apex Court decisions (e.g., General Manager Northern Railway v. Sarvesh Chopra) and State Kerala v. Mathai. It asserts that ED and rent claims are recoverable and that the trial court misapplied contractual clauses.

Contentions of Respondents

The respondents submit that the suit is barred by limitation and that compensation is barred by Clause 14 of Ext.A5, which makes the contract price inclusive of all taxes, duties, etc. They emphasize that ED is to be paid by the contractor where the contract indicates such, and reference Ext.A5 and Ext.B3/Ext.A18 communications to show ED-related adjustments were not the Board’s liability. They contend there is no unused right to claim compensation for delayed performance, as the contract did not permit such recovery and the appellant has not shown a consistent reservation of rights or notice of intention to claim compensation. They argue the tenants’ rent claim is unsupported absent a contract right and that ED was appropriately sought/paid within the contract framework.

Legal Doctrine & Issue Explorer

Explore This Legal Issue

Find relevant judgments and authoritative positions on the legal questions discussed here.

Cited Precedents (5)

Case NameCitationTreatmentExplanation
General Manager, Northern Railway and another v. Sarvesh Chopra2002(4) SCC 45PositiveCited and applied to support the proposition that delay/damages and the effect of contract terms on compensation are governed by the clarified principles in Sections 55, 56, and 73; the Supreme Court reiterated the need to assess compensation under contract terms when time is not necessarily of the essence.
State of Kerala v. Mathai2007(2) KLT 513 (SC)PositiveReiterates the above principles from General Manager v. Sarvesh Chopra and applies them to contract delay and compensation issues as clarified by Supreme Court precedent.
M/s. Associated Engineering Enterprises, Hyderabad v. State of Andhra PradeshAIR 1990 AP 294PositiveCited to discuss clause-based limitations (e.g., clause 59) on compensation; used to illustrate when delays and hindrances may bar claims for compensation under standard terms and conditions.
M/s. A.T. Brij Paul Singh and Others v. State of Gujarat1984(4) SCC 59DistinguishedThe court explicitly states that the principle from this case is not applicable to the facts before it, distinguishing the scenario involving loss of profit/damages from the present case.
State of Andhra Pradesh v. Associated Engineering Enterprises, HyderabadAIR 1990 AP 294Mentioned OnlyReferenced in the context of contract clauses affecting compensation; used as supportive discussion of the approach without being a binding conclusion in this case.
Case Applicability Diagnostic

Apply This to My Facts

Share your situation and test whether this judgment governs, supports, or challenges your case.

Official Judgment Record
•5,504 words•~26 min read

In The Court Record

TENCO PRIVATE LIMITED v. THE KERALA STATE ELECTRICITY BOARD and others

IN THE HIGH COURT OF KERALA AT ERNAKULAM PRESENT : THE HONOURABLE MR. JUSTICE K.M.JOSEPH & THE HONOURABLE MR. JUSTICE M.L.JOSEPH FRANCIS WEDNESDAY, THE 23RD DECEMBER 2009 / 2ND POUSHA 1931 AS.No. 507 of 1998(B) -------------------OS.38/1994 of SUB COURT, KASARAGOD .................... APPELLANT: -------------TENCO PRIVATE LIMITED REPRESENTED BY THE MANAGING DIRECTOR M C MOHAMMAD KUNHI, R/AT MUNDOL THEKKIL VILLAGE KASARAGOD DISTRICT. BY ADV. SRI.KODOTH SREEDHARAN RESPONDENTS --------------- 1. THE KERALA STATE ELECTRICITY BOARD REPRESENTED BY THE SECRETARY VIDYUTH BHAVAN, THIRUVANANTHAPURAM 2. THE EXECUTIVE ENGINEER KERALA STATE ELECTRICITY BOARD CIRCLE OFFICE KASARAGOD 3. DEPUTY CHIEF ENGINEER OFFICE OF THE CHIEF ENGINEER, K.S.E.B, KASARGOD BY ADV. SRI. C K KARUNAKARAN, SC, KSEB THIS APPEAL SUITS HAVING BEEN FINALLY HEARD ON 23/12/2009, THE COURT ON THE SAME DAY DELIVERED THE FOLLOWING: ## **K. M. JOSEPH & JOSEPH FRANCIS JJ.,** **- - - - - - - - - - - - - - - - - - - - - - - - - - - - A. S. NO: 507 OF 1998** **- - - - - - - - - - - - - - - - - - - - - - - - - - - - - Dated this the 23[rd] of December, 2009.** ## **JUDGMENT** ## **K. M. Joseph J.,** The appellant is the plaintiff in a suit for recovery of money. The Trial court has dismissed the suit. 2. The brief case of the appellant is as follows: The appellant has entered into an agreement on 9.2.1987 for the supply of 1,500 numbers 8 metre long RCC poles and 1,000 numbers 9 metre long R.C.C poles to the first respondent. The poles were to be exclusively used by the respondents. The steel and cement for manufacturing the poles were to be supplied by the respondents. Ext.A5 is an agreement and it was executed on 9.2.1987. The respondents were liable to pay excise duty for lifting the poles. It is the further case of the appellant that the estimate made by the defendant would indicate that excise duty would not be included in ## **A. S. NO: 507 OF 1998** **==> picture [14 x 9] intentionally omitted <==** the tender amount. The casting work was to be completed within three months. But the respondents were not able to supply the materials in time and there was some delay in completing the work. 3. The respondents demanded the appellant to pay the excise duty. From time to time the respondents made some payment to the appellant to be paid to the government to pay excise duty. An amount of Rs.1,39,196/- was paid, and out of that the appellant remitted only Rs.1,03,901/-. The balance amount (Rs.35,295/-) is with the appellant and this is to be adjusted towards the amount due from the respondents to the appellant. In view of the delay in supplying the materials by the respondents, the work could not be completed in time. It also took almost three years to supply the materials. The appellant/ plaintiff could have undertaken similar works if the work was completed in time. Plaintiff estimated Rs.8,000/- per month under this head and the damages caused to him on account of the delay in the supply of raw materials was claimed at Rs.3,00,000/-. ## **A. S. NO: 507 OF 1998** **==> picture [14 x 9] intentionally omitted <==** 4. It is the further case of the plaintiff that the gross value of the work done by the appellant in casting the poles was Rs.9,19,595/-, after providing cost of materials, the sales tax etc. The balance due to the appellant towards value of the work is Rs.2,10,213/-. Out of the same, the respondents paid Rs.71,017/-. After adjusting Rs.35,295/- the appellant claimed the gross value of the balance work at Rs.1,03,901/- and interest at 12½% per annum. It is the further case of the appellant that it disputed the liability to pay the excise duty to the government and had incurred Rs.11,000/as expenses for conducting the case for the purpose of avoiding payment of excise duty. It is said that this was incurred on behalf of the respondents. It is stated that the respondents have not paid the amount so far. The claim is not barred by limitation. 5. Another claim is that the respondents did not remove the poles in time and the appellant was not able to use the yard for any other purpose. The rent for such yard would not be less than Rs.1,000/- per month. Accordingly they have claimed damages of ## **A. S. NO: 507 OF 1998** **==> picture [14 x 9] intentionally omitted <==** Rs.36,000/-, at the rate of Rs.1,000/- per month for three years immediately proceeding the suit. 6. The respondents contended inter alia that the suit is barred by limitation. The appellant quoted labour portion of the expenses at the rate of 3% below the estimate and the agreement is thus for Rs.4,46,584/-. It is contended that the excise duty is to be paid by the contractor. The contract specifically states that the contract amount is inclusive of all taxes, duties etc. The Excise authorities charged excise duty for the poles cast at the yard and the appellant disputed the demand. The excise department issued show cause notice to the board which was withdrawn. The Apex Court held that the contractor should be regarded as the manufacturer and the duty is to be demanded from them. The specific case of the respondents is that the advance amount payable towards excise duty was a temporary arrangement and was subject to the final decision. The delay in supplying materials for the work was not much. The work was completed on 30.3.89. They paid the net amount payable ## **A. S. NO: 507 OF 1998** **==> picture [14 x 9] intentionally omitted <==** to the plaintiff. The lifting of the balance poles was prevented by the plaintiff, it is contended. The court raised six issues, including the question as to whether the suit is barred and found that there was no merit in the suit and accordingly it was dismissed. 7. We heard the learned counsel for the appellant, Sri. Kodoth Sreedharan and the learned counsel appearing on behalf of the respondents. 8. Learned counsel for the appellant would submit that the trial court erred in dismissing the suit. He would contend that there was a breach of contract by the defendants in not supplying the raw materials. There was much delay in supplying the raw materials. On account of the delay, clearly the appellant is entitled to compensation, as there is admitted breach by the defendants in supplying the raw materials. He further contended that the trial court has clearly erred in not finding that excise duty was payable by the board. In this context he would take us through the documentary evidence. In particular, he relied on Ext.A12. He ## **A. S. NO: 507 OF 1998** **==> picture [14 x 9] intentionally omitted <==** would point to the admitted fact that the excise duty was paid by the respondents. He further contended that Rs.11,000/- was incurred by him as expenses and this was on the basis of the direction by the respondents to ventilate the grievance regarding payment of excise duty before the authorities. Lastly he contended that several poles were not removed and the appellant is entitled to compensation. 9. Learned counsel for the respondents, on the other hand, contended that there is no merit in the appeal. He would further contend that as far as the delay in supply of raw materials is considered, apart from Clause 14 of the Contract, this is a case whether at the time when the performance of the reciprocal obligation was accepted by the appellant, there was no indication that the appellant will claim compensation for the belated performance of obligation by the department. He would also submit that actually the suit is barred by limitation. He would support the findings. 10. The appellant/ plaintiff has filed the suit claiming money ## **A. S. NO: 507 OF 1998** **==> picture [14 x 9] intentionally omitted <==** under four different heads. The first claim was for compensation of lumpsum amount of Rs.3,00,000/- (Rs. Three lakhs only). Rs.3,00,000/- is apparently arrived at by claiming compensation at the rate of Rs.8,000/- per month for a period of three years. This claim has been rejected by the court below on account of two grounds. Firstly it was found that Clause 14 stands as an obstacle for the appellant claiming compensation. Secondly it is found that the appellant has not proved his claim. 11. We will examine the claim of the appellant for compensation. The contract provided for making of the poles within a period of three months. The respondent undertook the liability of supplying the steel and cement. Therefore there was a reciprocal obligation on the part of the respondents to supply these materials. There is a delay on the part of the respondents in supplying the materials. But the question arises as to whether the appellant is entitled for compensation as claimed by the appellant. Clause 14 of the Ext.A5 agreement reads as follows: :8: ## **A. S. NO: 507 OF 1998** “Various facilities and departmental supply of materials proposed to be supplied by the department as stipulated in the tender conditions are strictly subject to the condition that the contractor will have no claim for any compensation on account of failure or delay on the part of the Board in rendering these facilities or supplying these materials, tools and plant etc.” 12. Learned counsel for the appellant would contend that the said clause which bars the claim for compensation is against the provision of Section 23 of the Contract Act, in so far as such Clause is against the mandate of Section 73 of the Contract Act. He would also rely upon the following two decisions, namely **General** **Manager, Northern Railway and another v. Sarvesh Chopra** (2002(4) SCC 45) and **State of Kerala v. Mathai** (2007(2) KLT 513 (SC)). 13. He also relied on the judgment of the Apex court in **M/s. A.T. Brij Paul Singh and Others v. State of Gujarat** (1984(4) SCC 59), wherein the Apex Court held as follows: :9: ## **A. S. NO: 507 OF 1998** “Ordinarily, when a contractor submits his tender in response to an invitation to tender for a works contract, a reasonable expectation of profit is implicit in it and its loss has to be compensated by way of damages if the other party to the contract is guilty of breach of contract. Where, therefore, the party entrusting the work commits breach of the contract, the contractor would be entitled to claim damages for loss of profit which he expected to earn by undertaking the works contract. What would be the measure of profit would, however, depend upon facts and circumstances of each case. While estimating the loss of profit for the breach of contract it would be unnecessary to go into the minutest details of the work executed in relation to the value of the works contract. A broad evaluation would be sufficient.” 14. Per contra the learned counsel for the respondent would bring to our notice the judgment in **State of Andhra Pradesh v.** ## **M/s. Associated Engineering Enterprises, Hyderabad** (AIR 1990 AP 294). In this judgment, the Division bench of the Andhra Pradesh High Court considered Section 55 of Contract Act and also ## **A. S. NO: 507 OF 1998** **==> picture [20 x 9] intentionally omitted <==** the effect of Clause 59 of APDSS, which barred the claim for compensation “on account of delays and hindrances to work from any cause whatever”. The delays and hindrances included were the stoppage, hindrances and delays on the part of the department. The Division Bench upheld the case of the respondents that the claim of the contractor was barred. 15. In the case before the Apex Court, namely, **General Manager, Northern Railway and another v. Sarvesh Chopra** (2002(4) SCC 45), the Apex Court, after referring to the aforesaid decision of the Andra Pradesh High Court, held as follows: “13. A Division Bench decision of the High Court of Andhra Pradesh in **State of A.P. v. Associated Engineering Enterprises, Hyderabad** is of relevance. Jeevan Reddy, J (as His Lordship then was), speaking for the Division Bench, held that where clause 59 of the standard terms and conditions of the contract provided that neither party to the contract shall claim compensation “on account of delays or hindrances to the work from ## **A. S. NO: 507 OF 1998** **==> picture [20 x 9] intentionally omitted <==** any cause whatever”, an award given by an arbitrator ignoring such express terms of the contract was bad. We find ourselves in agreement with the view so taken”. Thereafter the Apex Court held as follows: “In our country question of delay in performance of the contract is governed by Section 55 and 56 of the Indian Contract Act, 1872. If there is an abnormal rise in prices of material and labour, it may frustrate the contract and then the innocent party need not perform the contract. So also, if time is of the essence of the contract, failure of the employer to perform a mutual obligation would enable the contractor to avoid the contract as the contract becomes voidable at his option. Where time is “of the essence” of an obligation. Chitty on Contracts (28[th] Edn., 1999, at p.1106, para 22-015) states. a failure to perform by the stipulated time will entitle the innocent party to (a) terminate performance of the contract and thereby put an end to all the primary obligations of both parties :12: ## **A. S. NO: 507 OF 1998** remaining unperformed: and (b) claim damages from the contract-breaker on the basis that he has committed a fundamental breach of the contract (a breach going to the root of the contract') depriving the innocent party of the benefit of the contract ('damages for loss of the whole transaction') If, instead of avoiding the contract, the contractor accepts the belated performance of reciprocal obligation on the part of the employer, the innocent party i.e, the contractor, cannot claim compensation for any loss occasioned by the nonperformance of the reciprocal promise by the employer at the time agreed, “unless, at the time of such acceptance, he gives notice to the promisor of his intention to do so”. Thus, it appears that under the Indian law, in spite of there being a contract between the parties where under the contractor has undertaken not to make any claim for delay in performance of the contract occasioned by an act of the employer, still a claim would be entertainable in one of the following situations: (i) if the contractor repudiates the contract exercising his right to do so ## **A. S. NO: 507 OF 1998** **==> picture [20 x 9] intentionally omitted <==** under Section 55 of the Contract Act, (ii) the employer gives an extension of time either by entering into supplemental agreement or by making it clear that escalation of rates or compensation for delay would be permissible, (iii) if the contractor makes it clear that escalation of rates or compensation for delay shall have to be made by the employer and the employer accepts performance by the contractor in spite of delay and such notice by the contractor putting the employer on terms.” 16. The Apex Court, in **State of Kerala v. Mathai** (2007(2) KLT 513 (SC)), has reiterated whatever has been stated by it in para 15 of the judgment in **General Manager, Northern Railway** **and another v. Sarvesh Chopra (Supra)** . Therefore, on the one hand, we notice that the judgment of the Division Bench of the Andhra Pradesh High court in regard to Clause 59 has been approved as noted in paragraph 13. The Apex court has further found that in case there is delayed performance of contract in three contingencies, in view of the Section 55 of the Contract Act, the ## **A. S. NO: 507 OF 1998** **==> picture [20 x 9] intentionally omitted <==** contractor will be enabled to compensation as referred to in para 15 of the judgment in **General Manager, Northern Railway and** . **another v. Sarvesh Chopra (Supra)** 17. This is the state of the law. If we apply the aforesaid principles to the facts of the case, we must ask whether the appellant falls in any of the three categories mentioned above. There is no dispute that the appellant has not repudiated the contract. Equally there is no agreement executed between the parties, under which the defendants have agreed to pay the compensation at higher rates on account of the delayed performance of reciprocal obligation in supplying steel and cement. The appellant brought Ext.A18 to our notice. In Ext.A18, which is dated 15.1.1990, the appellant complains of the retention of the final amount due. There is no claim or reservation of the claim the appellant would be making on account of delayed performance of obligations by the respondents. As a matter of fact, Ext.A18 is not issued at the time of acceptance of delayed performance. But even on a perusal of Ext.A18, we **A. S. NO: 507 OF 1998** **==> picture [20 x 9] intentionally omitted <==** cannot make out any case of the appellant reserving a right to claim compensation or giving notice to the defendants that it will make a claim for compensation on account of delayed supply of the steel and cement. In fact the claim itself is only for the demand of the balance value, which is withheld by the defendant, in view of the payment of Rs.1,39,196/- by them as advance for the payment of the excise duty. Therefore, we would think that even going by the decisions of the Apex court relied on by the learned counsel for the appellant, we cannot hold that the appellant falls in any of the three categories which have been declared by the Apex court. 18. We notice that there is no scope for applying the principle mentioned in **M/s.A.T. Brij Paul Singh and others v. State of Gujarat** (1984 (4) SCC 59). In this case, one of the claims raised by the contractor was that on account of breach of the contract by the employer, there was a reduction in profit. There is no such claim in this case. The claim of the appellant as already noted was that only because of the delayed performance by way of delay in ## **A. S. NO: 507 OF 1998** **==> picture [20 x 9] intentionally omitted <==** supplying the raw materials, the appellant could not take up other work. Apart from the statements of the appellant as PW1 that he lost Rs.8,000/- per month and then he could not take up any contract, as correctly noticed by the Court below, there are no materials to show that there was loss to the appellant. The trial court has correctly negatived the claim for compensation of Rs.3,00,000/. 19. The further question to be considered is whether the appellant is justified in contending that the appellant was not liable to pay the excise duty. We would at once notice Clause 6 (b) of the Notice for Inviting Tenders for Work in Ext.A5, which reads as follows: “The tenderers are bound to study the estimate rates from their own rates for their own information only, work out the net PAC after deducting the cost of Departmental supply of materials, work out relation between the Departmental net PAC and Tenderer's net PAC by percentage which may either fall above or below the departmental PAC. After :17: ## **A. S. NO: 507 OF 1998** this, the tenderers need quote only a single rate as a percentage, above or below or at the rates as given in additional conditions of contract in the form furnished below the schedule of work. Contract amount is inclusive of all taxes, duties, seigniorage etc, which are or may become payable by the contractor under the existing or future laws or rules of the country during the course of execution of the contract.” 20. A perusal of the Clause appears to us to be unambiguous that what the parties have agreed to be the accepted PAC, was to be inclusive of all taxes and duties under any other existing laws or future laws. The contention of the learned counsel for the appellant however is that the conduct of the parties is also relevant to determine the question is to who is liable to pay the excise duty. He would submit that the parties actually contemplated the payment of excise duty by the defendants. He would point out that this was clear from Ext.A12. This is a letter addressed by the Executive :18: ## **A. S. NO: 507 OF 1998** Engineer to the Managing Director of appellant company dated 21.8.89. It reads as follows: “As you know, K.S.E. Board had made a temporary arrangement for the payment of Excise duty for R.C.C. poles cast by you at Kanhangad consequent on the award of the customs, excise and gold (control) Appellate Tribunal, New Delhi vide its order dated 1.2.'88. Your status as the manufacturer of the posts stands decided by the Tribunal under the said order. But pending detailed examination of all the aspects connected with the issue and to ensure steady flow of poles from the casting yard, this division has been providing you the required funds as advance for payment of Excise duty subject to certain conditions. The position being so, you will take notice that refund of Excise duty on any account out of the payment made by you to the Central Excise Department from the advance made available to you from time to time since 1.2.1988 is due to the K.S.E. Board. Excess amount of Excise duty if any, levied by the local officers of the Central Excise **A. S. NO: 507 OF 1998** :19: Department, over and above the rate applicable to an SSI unit is to be got refunded by filing refund applications as per rules. So if you have remitted Excise duty for poles cast at any time at a rate higher than that would have been admissible under the concessions granted to SSI Units by the Central Excise Department, be it on whatever basis of objection and mode of assessment. You will immediately file refund application with the Central Excise department as per rules, if not already done, under intimation to this office. This procedure should be followed strictly in respect of all payment of Excise duty by you out of the advance provided by the K.S.E. Board. Please note that any loss to the K.S.E. Board on account of your failure to comply with the above said directions would be recoverable from you. Please also ensure that all payments of Excise Duty, the assessment of which is not in conformity with your status as a local SSI Unit under the relevant rules of the Central Excise Department, is made under protest only as per the procedure prescribed for it, as already instructed”. :20: ## **A. S. NO: 507 OF 1998** 21. If it were not that respondents were liable, what was the reason for the board to ask the plaintiff to take up the matter with the authority and to seek refund and make over the amount, which may be received by way of refund to the board. He would further contend that if the appellant is shouldered the liability under Central Excise Act, it will be unjust, and it is pointed out that the parties have not reckoned the excise duty payment as appellant's liability and it was complained that the respondent is liable in this regard. 22. Ext.B3 is the excise duty file. Undoubtedly, the defendant have paid a sum of Rs.1,39,196/- as payment for excise duty to the appellant. The case of the respondent is that the said conduct is justified with reference to the emergent need for the board to get delivery of the poles as the clearing of the poles was being held up on account of non payment of excise duty. The communication dated 1.11.91 issued by the board reads inter alia as follows : “The Board after considering the issue in details :21: ## **A. S. NO: 507 OF 1998** orders that - (1) The PSC/RCC Pole Casting contracts be categorised as follows: - (i) Cases where there is no mention about payment of Excise Duty. (ii) Cases where it is mentioned that Excise Duty be paid as an Extra payment. (iii) Cases where it has been specifically mentioned that the rates are inclusive of Excise duty. (2) The amount paid towards Excise duty be adjusted as below: (i) Where there is no mention about payment of Excise Duty, the amount paid be debited to the Contractor's account. (ii) Where it is mentioned that Excise duty will be paid as Extra payment, Board will meet the expense and will reimburse the expenditure incurred by the contractor. (iii) Where it is mentioned that the rates quoted are inclusive of Excise duty, the amount advanced to the contractors be debited to the Contractor's account. (3) Any amount paid in excess over the prescribed rate mentioned under 2(ii) above be got :22: ## **A. S. NO: 507 OF 1998** refunded and in such cases contractors be held liable for such amount.” 23. We further notice that the Excise authorities have withdrawn show cause notice issued against the respondent demanding payment of excise duty for the poles. A letter dated 7.5.93 is addressed by the Chief Engineer to the Deputy Chief Engineer. It reads as follows: “..... I am to inform you that as per the latest B.O. dt.1.11.91 regarding the payment of E.D. in respect of PSC/RCC Poles casting contractor's under the various Ele.Circles, the subject case comes under item 1(i) of the B.O. dated 1.11.91, in which the E.D. has to be paid by the contractor. As such the amount deducted cannot be refunded until further specific orders from the Board. The fact may be intimated to the concerned firm and necessary steps may be taken to lift the poles stacked in their yard.” ## **A. S. NO: 507 OF 1998** **==> picture [20 x 9] intentionally omitted <==** 24. By letter dated 5.10.1990 from the Deputy Chief Engineer addressed to the MD of the plaintiff, it is noticed that even though Rs.1,39,196/- was advanced, the appellant has not remitted the final spell of the amount of Rs,35,295/-. (Apparently in protest against the deducting the full advance of Rs.1,39,196/- from the final bill). 25. Ext.B6 is a copy of the judgment in Civil Appeal No.140/1989. It is evident that thereunder the Apex Court confirmed the view taken by the Authority that it is the contractor, who is the manufacturer and not the board. 26. Further the two claims, namely expenses incurred, Rs.11,000/- towards litigation and also the claim for rent for three years also falls to be decided on the basis as to who has the liability to pay the excise duty. We are of the view that the learned Sub Judge is correct in finding that it is the appellant who is liable to pay the excise duty. Apparently the appellant was running a Small Scale unit. Under The Central Excise Act, exemption is granted under various notifications. We notice that there was proceedings ## **A. S. NO: 507 OF 1998** **==> picture [20 x 9] intentionally omitted <==** before the Excise authorities. Claim was raised apparently that the board was entitled to exemption under two notifications. It is the plaintiff who is found liable to pay the excise duty being the manufacturer. Apparently there was some understanding that for small scale unit, the appellant may not exigible to pay the excise duty. We are of the view that what was paid by the defendants was as an advance, in view of the urgent need to clear the poles. Apparently some ambiguity may have been there at that stage regarding the exigibility to excise duty itself. But obviously there was emergent need to ensure the prompt supply of the poles. Already there was a delay on account of the delayed supply of the raw material. It appears, in such circumstances, that the board decided to advance the amount with the specific understanding that payment is to be made as excise duty. No doubt it was understood that the appellant should make application for refund. We would think that this can be understood as meaning that if any amount is received by way of refund, it was to be paid over to the respondents ## **A. S. NO: 507 OF 1998** **==> picture [20 x 9] intentionally omitted <==** and if not so received, will be treated as paid on account of the contract. It is true that in Clause 6(b), the words “Excise Duty” is not used. But we would think that when parties had agreed that what the board is liable to pay is only the contract amount and the contract amount will apprehend not only tax, but duties and wording does not appear to exclude the excise duty, the appellant was liable to pay Excise duty as per the said clause. 27. We would take the view that parties understood that no further amount is payable by the defendants under the head of excise duty. In other words, the acceptance of the argument of the learned counsel for the appellant may result in the court making a new contract between the parties by substituting the terms of Clause 6(b) by alteration. We think it is impermissible. When the matter reaches the court, and the understanding between the parties is reduced to writing, the court has to interrupt the contract. We are not persuaded to accept the contentions of the learned counsel for the appellant that with reference to the communication between the ## **A. S. NO: 507 OF 1998** **==> picture [20 x 9] intentionally omitted <==** parties the terms of Clause 6(b) should be understood differently. In such situation, we confirm the finding of the trial court that it is the plaintiff who is liable to pay the excise duty. 28. The next question to be considered is the claim of Rs.11,000/- as litigation expenses. According to the appellant, the appellant proceeded to spend money towards litigation as directed by the board. It may be true that the appellant spent Rs.11,000/-. But the question, is once we have decided that the appellant was liable under the contract to pay the excise duty, whether the appellant could be entitled to get amount claimed. We are of the view that the appellant cannot be given a decree for Rs.11,000/When the matter was before this court, the Court finds that under the terms of the Contract, it is the appellant who is liable to pay the excise duty and we find no reason to direct the board to pay the litigation expenses, which we feel that the appellant must bear. We also notice the fact that the show cause notice against the board :27: ## **A. S. NO: 507 OF 1998** was also withdrawn. It is the case that excise duty was actually paid out of the advance given by the appellant. On the facts present, it is clear that, in view of Clause 6(b) and Ext.B6 judgment it is the appellant who would have to pay the duty. We reject the said contention. 29. Lastly the appellant submitted that 400 poles were not removed by the respondent and the appellant is entitled for rent for the period of 3 years at the rate of Rs.1,000/- per month. The trial court found there is no contract to decree any rent. There is no dispute that out of Rs.1,39,196/- the appellant has not paid Rs.35,295/- as excise duty. If the appellant had paid an amount of Rs.35,295/- the excise authorities would not have obstructed the removal of the poles. According to the appellant, the appellant did not pay Rs.35,295/- as further amount were due from the board towards the final bill. We have already found that the appellant is liable to shoulder the excise duty. If the appellant had paid over **A. S. NO: 507 OF 1998** **==> picture [20 x 9] intentionally omitted <==** the balance of excise duty, certainly the excise authorities would not have obstructed the removal of the poles and it would have been possible for the board to remove the poles. The appellant did not pay the whole amount given as advance for payment of excise duty. Therefore the non removal on the part of the respondent of the 400 poles cannot be attributed to the fault of the respondents. We find that the reasoning of the trial court is unexceptional and we affirm it. We see no merit in the appeal. Accordingly, the appeal is dismissed. There is no order as to cost. ## **K. M. JOSEPH, JUDGE** ## **M. L. JOSEPH FRANCIS, JUDGE.** dl/
End of Judgment Record
Browse All High Court of Kerala (2009) Decisions
2009-06-26

Nishana Mol.N v Alappuzha Municipality & Secretary, Alappuzha Municipality

This writ petition concerns the registration of a marriage under the Kerala Registration of Marriages (Common) Rules, 2008 (Common Rules). The petitioner Nishana Mol.N, whose marriage was solemnized on 8 March 2009, sought registration of her marriage by the Local Registrar. Her husband was abroad, and she submitted Form No. 1 along with documents; however, the Local Registrar demanded the presence of both spouses for registration, a point contested by the petitioner. The court recalls the apex court’s directions in Seema v. Ashwani Kumar (2006) to frame rules ensuring compulsory registration to protect women and provide evidence of marriage, while noting that registration under the Rules does not itself create a marriage but evidences one solemnized otherwise. The Rules specify that registration is mandatory for marriages solemnized within the state, with various procedural requirements (Rules 5, 6, 9, 10, 11, 13, 16, 17) and mechanisms for correction, appeal, and re-registration. The court clarifies that the presence of both parties is not ordinarily required; the registrar may require appearance only in cases where there is reasonable doubt about identity, and even then as an exception rather than a rule. Ultimately, the court directs that registration and certificate issuance be completed within one month from copy of the judgment, without insisting on joint appearance, provided the memorandum is in order.

2009-07-27

Abdul Majeed Kalathil v. District Collector, Malappuram & Others

This batch of writ petitions concerns the constitutional validity of Section 17 of the Kerala Anti-Social Activities (Prevention) Act, 2007, and the power of District Magistrates to confiscate vehicles used in anti-social activities. The petitions challenge the absence of a substantive prohibition against using vehicles for anti-social activities and the lack of a defined procedure for confiscation or an appellate remedy. In W.P.C. No. 9925 of 2009 (the lead case), Abdul Majeed Kalathil contends that his goods carriage KL 11-B/6651 was seized by the Sub Inspector of Pandikkad Police and reported to the District Collector, Exts.P1–P2. The court scrutinizes Section 17's scope, defining anti-social activity (Section 2(a)) and whether the District Collector’s power to confiscate is constitutionally tenable. It finds Section 17 to be vague and violative of Articles 14, 19(1)(g) and 21, as it rests on subjective police satisfaction with no clear standards or process. It also notes environmental objectives but concludes that fundamental rights must prevail. The court does not sustain confiscation under Section 17; instead, it directs that such vehicles be dealt with under the Kerala Protection of River Banks and Regulation of Removal of Sand Act, 2001 and Rules, with interim release under specified conditions. It further directs initiation of Sand Act proceedings within a month and finalization within another month. The writ petitions are disposed of accordingly, preserving the rule of law and environmental protection.

2009-06-11

WA No. 671 of 2006 (Fertilizers and Chemicals Travancore Ltd v Union of India)

This writ appeal concerns the pay revision and pensionary benefits of employees of the Fertilizers and Chemicals Travancore Ltd (FACT). The long-term settlement covering terms of employment expired on 31 December 1996. A fresh settlement was concluded (notified 28 August 2001) and made retroactive to 1 January 1997, with revisions in wages and benefits. Clause 29 of Ext. P1 provides that arrears relating to wage revision and dearness allowance for the period 1 January 1997 to 30 June 2001 will be reviewed and decided by management/government only when the company earns profits for at least three consecutive years; Clause 33.1 provides that employees who retired on or after 1 January 1997 will be eligible for arrears calculated from 1 January 1997 to the date of retirement, subject to adjustments for interim relief already paid, with any unclaimed amount transferred to a Welfare Fund. The appellants—the retirees who fall in the 1 January 1997 to 1 July 2001 window—argue that they were denied arrears and were paid pensionary benefits at pre-revised rates, creating discrimination. Respondents contend Ext. P1 binds the parties and arrears depend on profits, and that pay revision administered to others does not compel retroactive change. The court held that Ext. P1 terms survive as terms of employment and directed the management to consider terminal benefits at revised rates within two months and to release arrears when paid to current workers, with connected matters following."

2009-05-29

M/S. Palm Fibers & Yars Trading Co. v. State of Kerala & Others

The petitioner, a Small Scale Industrial unit, ran two LT power connections (No.13070 and No.13427) with commercial production starting in July 1994 and July 1995. On 06/02/1992, the Government issued Ext.P1 guaranteeing concessional tariffs (pre-1992 tariff) for five years from the date of commencement or substantial capacity expansion, certified by the District Industries Centre. Ext.P2 certified eligibility for this concession. Subsequently, the petitioner increased power demand to 300 KVA and was reclassified/advised to HT status from 15/05/1998, converting LT supply to HT. The petitioner argued that Ext.P1 benefits should extend for the full five-year period, covering the LT quantities certified in Ext.P2, and that the HT conversion was a mere reclassification directed by the Board, not a cessation of eligibility. The Board argued Ext.P1 targets only those who commenced production during 1992–1996 and that HT conversion from 15/05/1998 falls outside the Ext.P1 window, rendering the petitioner eligible only up to 15/05/1998. Earlier orders (Ext.P3) had set aside a cut-off date for merits, and Ext.P6/Ext.P4 handled appeals. Ultimately, the Court held that the HT conversion was outside Ext.P1’s period, but directed that the LT benefits for the two LT connections be extended only until 23/05/1998 (LT dismantling date) and without reimbursement from the Industries Department, as held in OP No.7622/1998. The petition was disposed of as above.