High CourtDivision BenchAppeal allowed; High Court order set aside; con...

T.C. GUPTA v. BIMAL KUMAR DUTTA & ORS.

Case / Petition Number:Civil Appeal No. 9476 of 2013
Neutral Citation:[2013] 12 S.C.R. 170

Case Details & Bench

Court
High Court
Hon'ble Judges
  • P. Sathasivam
  • Ranjan Gogoi
Judgment Date
2013-10-25
Court Decision / Holding
Appeal allowed. The Supreme Court set aside the High Court’s order dated 23 July 2012 finding the appellant guilty of contempt, held that the interim order’s language did not warrant the blanket interpretation that barred licensing as such, and thus the contempt charge could not be sustained. The High Court’s order was quashed; the appellant’s contempt conviction was set aside and the appeal was allowed.
Final Disposition
Appeal allowed; High Court order set aside; contempt conviction not sustained.

Parties to the Case

Appellants / Petitioners

  • T.C. Gupta

Respondents

  • Bimal Kumar Dutta and Others

Legal Representation & Advocates

Counsels for Petitioners

  • • Goolam E. Vahanvati (Attorney General for India)
  • • Anubha Agarwal

Counsels for Respondents

  • • Soli J. Sorabjee
  • • Arun Monga
  • • Aviral Dhirendra
  • • Tushar Bakshi
  • • Kamal Mohan Gupta
  • • Parmod K. Singh
  • • Jitender Bidhuri

Case Synopsis & Summary

This judgment concerns a contempt of court appeal arising from contempt proceedings initiated against the Director General, Town & Country Planning, Haryana (the appellant) for alleged disobedience of an interim order of the Punjab and Haryana High Court dated 18 August 2011. The High Court had directed status quo as to allotments in the Gurgaon-Manesar development area and had been petitioned for stay of the Final Development Plan 2025-AD. The appellant subsequently granted a licence on 28 December 2011 for a Residential Plotted Colony on land in Sector 63A, despite the interim order. The High Court found him guilty of contempt, holding that the interim order imposed a comprehensive embargo on issuing licences, and ordered personal appearance for sentencing. The Supreme Court, noting contempt as quasi-criminal and requiring proof beyond reasonable doubt, emphasized that the court’s order must be clear and unambiguous and that a charge cannot be sustained by reinterpreting the order when ambiguity exists. It observed that no allotments were made and that the instruction to maintain status quo did not proscribe licensing under the Haryana Act of 1975 for plotted colonies, and that the appellant had tendered an unconditional apology in bona fide terms. Relying on O.P. Sharma, the Court held the high court interpretation flawed and set aside the contempt finding, allowing the appeal. The writ petition’s later dismissal (30 Oct 2012) did not alter this outcome.

Provisions of Law Cited

Contempt of Courts Act, 1971; Section 12; Explanation to Section 12Haryana Development and Regulations of Urban Areas Act, 1975Punjab Scheduled Roads and Controlled Areas Restriction of Unregulated Development Act, 1963

Legal Doctrines & Maxims

  • Contempt is quasi-criminal; proof beyond reasonable doubt required for conviction
  • The order in contempt must be clear, unambiguous, and unequivocal on its face
  • An apparently ambiguous or unclear order should not be interpreted post hoc to sustain contempt
  • Bona fide apology under Section 12 of the Contempt of Courts Act should not be rejected merely because it is qualified or conditional if made bona fide
  • O.P. Sharma and Ors. Vs. High Court of Punjab and Haryana (on apology and bona fide considerations)

Submissions & Arguments

Contentions of Appellants / Petitioners

The appellant contended that the interim order dated 18 August 2011 restrained merely allotments and did not categorically prohibit licensing under the Haryana Development and Regulations of Urban Areas Act, 1975. No allotments had been made as of the interim order, and the grant of licence for a plotted colony on 28 December 2011 did not constitute a violation. The appellant argued that the High Court erred in interpreting the interim order to impose a blanket embargo on all licences, and relied on the factual context that the plot licences did not restrict plotted colonies beyond the absence of a ceiling, and that the cited apology was sincere and bona fide. The appellant urged that the contempt charge should fail as there was no clear violation and the apology should be considered under Section 12, with reliance on established jurisprudence that (i) contempt is quasi-criminal and (ii) a precise interpretation of the order is required before finding disobedience.

Contentions of Respondents

The respondents argued that the interim order of 18 August 2011 imposed a comprehensive embargo on issuing any licences and that the grant of a licence dated 28 December 2011 for a plotted colony violated the court’s order. They maintained that the High Court correctly held that the order, read in its full context, encompassed a blanket restriction on licences under the Haryana Act of 1975. The respondents emphasized that the contempt charge required a strict interpretation of the order, and that the plaintiff’s apologies, though tendered, did not exonerate the contemnor from responsibility given the clear terms of the interim order and the actions taken in disregard of the court’s directive.

Cited Precedents (1)

Case NameCitationTreatmentExplanation
O.P. Sharma and Ors. Vs. High Court of Punjab and Haryana2011 (6) SCR 301 = (2011) 6 SCC 86PositiveThe Court relied on this decision to affirm that an apology under Section 12 should not be rejected merely for being qualified if bona fide.

Diagnostic Tool

Beta

Does this judgment govern your specific facts?

Don't risk relying on a distinguishable precedent. Enter your facts or proposition below. We will test it against T.C. GUPTA v. BIMAL KUMAR DUTTA & ORS. and instantly map out authorities that support, challenge, or govern your position.

Extracted Judgment Text

Exact text extracted from official judgment records.

[2013] 12 S.C.R. 170 A ## T.C. GUPTA _v._ B BIMAL KUMAR DUTTA & ORS. (Civil Appeal No. 9476 of 2013) OCTOBER 25, 2013 **[P. SATHASIVAM, CJI AND RANJAN GOGOi, J.]** _CONTEMPT OF COURT:_ c _Contempt proceedings_ - _A contempt action being in the nature of quasi criminal proceedings, the degree of satisfaction that must be reached by the court to hold_ a _person guilty of commission of contempt would be akin to what is required to prove_ a _criminal charge, namely, proof beyond_ 0 _[reasonable doubt. ]_ -- _Contempt proceedings Alleging disobedience of order_ - _of High Court High Court holding the appellant guilty of commission of contempt of its order and ctirecting for his personal appearance for hearing on quantum of punishment_ - **E** _Held: Order of the court in respect of which violation is alleged must be clear, unambiguous and unequivocal and defiance thereof must be apparent on the very face of the action with which_ a _contemnor is charged_ -- _In the instant case, the interim order of the High Court had directed status quo to_ F _be maintained in respect of allotments_ -- _Admittedly, no allotments had been made by the appellant or any other_ -- - _authority Order of High Court set aside Haryana Development and Regulation of Urban Areas Act, 1975._ - G _Contempt proceedings Interpretation of the order_ - _alleged to have been disobeyed Held: Would not be appropriate while dealing with_ a _charge of contempt_ -- _In_ a _situation like the case in hand, where High Court had directed maintenance of. status quo as to allotment, it was not open_ **H** 170 T.C. GUPTA _v._ BIMAL KUMAR DUTTA & ORS. 171 _for High Court to hold the contemnor guilty by understanding_ A _the said order to mean status quo or_ a _restraint in respect of grant of licences under the Act._ ## _CONTEMPT OF COURTS ACT, 1971:_ - - _s.12, Explanation Unconditional apology Held: An_[8 ] _apology tendered by_ a _contemnor should not be rejected merely on the ground that it is qualified or conditional_ so _long_ -- _it is made bona fide There is nothing on record to suggest that the unqualified and unconditional apology tendered by appellant in his reply before the High Court was actuated by_ C _reasons that are not bona fide._ In a writ petition instituted in public interest before the High Court raising a grievance with regard to the Final Development Plan, on the application for stay of the o implementation of the Plan, the High Court on 18.8.2011 directed status quo as to allotment to be maintained. However, the appellant who was the Director General, Town and Country Planning, granted a licence dated 28.12.2011 for setting up of a Residential Plotted Colony E on 100.262 acres of land. This led to the institution of the contempt proceedings in which the appellant filed his response contending that no allotment was made by him or by any other authority so as to constitute violation of the order dated 18.08.2011. The appellant also tendered F his unqualified and unconditional apology. However, High Court by its order dated 23.7.2012 held the appellant guilty of commission of contempt and passed orders for his personal appearance for hearing on the quantum of punishment. Aggrieved, the Officer filed the appeal. None appeared on behalf of the first respondent i.e. writ G contempt petitioner. ## Allowing the appeal, the Court HELD: 1.1. A contempt action being in the nature of H 172 SUPREME COURT REPORTS [2013] 12 S.C.R. A quasi criminal proceedings, the degree of satisfaction that must be reached by the court to hold a person guilty of commission of contempt would be akin to what is required to prove a criminal charge, namely, proof beyond reasonable doubt. The order of the court in B respect of which violation is alleged must, therefore, be clear, unambiguous and unequivocal and defiance thereof must be apparent on the very face of the action with which a contemnor is charged. In the instant case, the interim order of the High Court had directed status C quo to be maintained in respect of allotments. Admittedly, no allotments had been made by the appellant or any other authority. [para 10) [177-F-H; 178-A] 1.2 An interpretation of the terms of court's order in respect of which disobedience is alleged would not be D appropriate while dealing with a charge of contempt. Such a charge cannot be brought home by unravelling the true meaning of the court's order by a subsequent order when there is an apparent ambiguity, lack of clarity or dichotomy in the initial order. In a situation like the E case in hand, where the High Court had directed maintenance of status quo as to allotment, it was not open for the High Court to hold the contemnor guilty of commission of contempt by understanding the order dated 18.08.2011 to mean status quo or a restraint in F respect of grant of licences under the Haryana Act of 1975. [para 10) [178-A-D] 1.3 Further, the Explanation to s. 12 of the Contempt of Courts Act, 1971 makes it clear that an apology tendered by a contemnor should not be rejected merely G on the ground that it is qualified or conditional so long it is made bona fide. The appellant, in his. reply, after offering his explanations, had tendered his unconditional and unqualified apology in the event the explanations did not commend for acceptance of the High Court. There is H 173 T.C. GUPTA _v._ BIMAL KUMAR DUTTA & ORS. nothing on record to suggest that the unqualified and A unconditional apology tendered by the appellant in his reply before the High Court was actuated by reasons that are not bona fide. The order dated 23.07.2012 passed by the High Court cannot be sustained and, as such, is set aside. [para 11 and 13] [178-E-F, G-H; 179-C] B B _O.P.Sharma and Ors. Vs. High Court of Punjab and Haryana_ 2011 (6) SCR 301 = (2011) 6 SCC 86, relied on. ## Case Law Reference: c 2011 (6) SCR 301 relied on para 11 CIVIL APPELLATE JURISDICTION : Civil Appeal No. 9476 of 2013. From the Judgment and Order dated 23.07.2012 of the High Court of Punjab and Haryana at Chandigarh in C.O.C.P. No. 120 of 2012. D Goolam E. Vahanvati, AG, Anubha Agarwal for the Appellant. E Soli J. Sorabjee, Arun Monga, Aviral Dhirendra, Tushar Bakshi, Kamal Mohan Gupta, Parmod K. Singh, Jitender Bidhuri for the Respondents. The Judgment of the Court was delivered by F RANJAN GOGOi, J. 1. Leave granted. 2. By its order dated 23.07.2012 the High Court of Punjab and Haryana has found the appellant guilty of commission of contempt in respect of an order dated 18.08.2011 passed in G Civil Misc. No.10994 of 2011 arising out of Writ Petition (C) No.11684 of 2011. Consequently, the appellant was summoned to appear before the High Court on 30.07.2012 for hearing before pronouncement of order on the punishment to be imposed. Aggrieved, the present appeal has been filed. H H 174 SUPREME COURT REPORTS (2013] 12 S.C.R. A 3. The facts that will be necessary to be noticed are as follows: The respondent No.1 herein, as the writ petitioner instituted a Public Interest Litigation before the High Court (C.W.P. No.11684 of 2011) raising a grievance with regard to 8 the Final Development Plan 2025-AD for Gurgaon-Manesar Urban Complex published vide Notification No. CCP (NCR)/ FDP(G)/2011/1386 dated 24.05.2011. Specifically, it wa:s contended that Sectors 63-A and Sector 67-A have been carved out in the Development Plan contrary to the Zoning C Regulations which are required to be followed. The Final Development Plan, it may be noticed, is prepared under the Punjab Scheduled Roads and Controlled Areas Restriction of Unregulated Development Act, 1963 (hereinafter referred to as the Act of 1963). D 4. Notice on the writ petition was issued by the High Court on 8.07.2011. Thereafter, on 11.08.2011 Civil Misc. Application No.10994 of 2011 was filed before the High Court for stay of the implementation of the Final Development Plan "in view of E contemplated grant of licence to the colonizers/developers/ societies." On 18.08.2011 the following order was passed by the High Court in C.M.No.10994 of 2011: ## "Notice for the date fixed. F Mr. Anil Rathee, Addi. A.G., Haryana, present in Court, accepts notice. In the meanwhile, there will be status quo as to allotment as on today." ## G 5. Though an application to vacate the aforesaid interim order was filed by the Respondents in the writ petition the interim order was neither vacated nor modified by the High . Court and continued to remain in force. While the matter was _so situated the appellant who then serving as the Director H General, Town & Country Planning, Haryana, had granted a 175 ## T.C. GUPTA _v._ BIMAL KUMAR DUTIA & ORS. [RANJAN GOGOi, J .] licence dated 28.12.2011 for setting up of a Residential Plotted Colony on land measuring 100.262 acres falling in Sector 63A of the Gurgaon-Manesar. The aforesaid grant of licence [under the Haryana Development and Regulations of Urban Areas Act, 1975] (hereinafter referred to as 'Haryana Act of 1975') by the appellant had led to the institution of the contempt proceeding in question which was registered as C.O.C.P. No.120 of 2012. The said action was initiated on the basis that the grant of the licence dated 28.12.2011 by the appellant is in violation of the order of the Court dated 18.08.2011. A B C 6. The appellant had filed his response in the contempt proceeding contending that no allotment was made by him or by any other authority so as to constitute violation of the order of the High Court dated 18.08.2011. The appellant, in his reply, further stated that in every residential sector, a maximum of 20% of the net planned area was earmarked for group housing and 3.5% for commercial purposes whereas for plotted residential colonies there was no restriction except the requirement of a minimum area of 100 acres. It was also stated that while the applications for group housing and commercial activities was to be accorded priority on the basis of date of application the same was not so in respect of applications for plotted colonies which are to be considered and licences are to be granted on fulfilment of the conditions prescribed. It was further stated by the appellant that though not specifically prohibited by the order dated 18.08.2011, out of sheer deference, no licence has been granted or contemplated for group h_ousing colony/commercial colony as such licences can be granted upto a maximum limit · of the net planned areas. Licences for plotted colonies, according to the appellant, stood on a different footing inasmuch as for grant of such licences no ceiling limit exists. After offering the aforesaid explanations, in the penultimate paragraph of the reply the appellant had tendered his unqualified and unconditional apology in the following terms: D E F G 'It is humbly submitted that the answering deponent H ## 176 SUPREME COURT REPORTS [2013] 12 S.C.R - A has unfailing regard for this Hon'ble Court and all othHrs courts of India and cannot think of disobeying any order passed by the Hon'ble Law Court. It is an article of faith for them to respect the orders passed by the Hon'ble Courts. However, if this Hon'ble Court still comes to the - B conclusion that the answering deponent has committed any contempt of court, the deponent tender unqualified and unconditional apology for the same.' 7. The High Court, on consideration of its interim order dated 18.08.2011 and response of the appellant referred to C above, came to the conclusion that its order dated 18.08.2011 has to be understood to have imposed a comprehensive embargo on issuance of all kinds of licences and, therefore, the grant of licence dated 28.12.2011, though for a plotted housing colony, amounted to violation of the order dated D 18.08.2011. Accordingly, the High Court held the appellant guilty of commission of contempt and passed orders for his personal appearance for hearing on the quantum of punishment. 8. We have heard Mr.Goolam E. Vahanvati, learned E Attorney General for India, appearing for the appellant, Mr. Kamal Mohan Gupta, learned counsel for the respondent No.2 and Mr. Soli J. Sorabjee, learned senior counsel for the respondent No.3. None has appeared on behalf of the first respondent i.e. writ contempt petitioner before the High Court. ## F 9. It is the common ground of the learned coi.nsels appearing for the contesting parties that the interim order of the High Court dated 18.08.2011 had only restrained the concerned authority from making any allotments. Admittedly, no allotment{s) were made. There was no specific order G prohibiting the implementation of the development plan, though such a relief was prayed for before the High Court. It is urged that the appellant, in his reply, had set out the manner in which he had understood the order dated 18.08.2011, namely, that the said order had not placed any kind of prohibition on grant H of licences under the Haryana Act of 1975. Yet, out of ## TC. GUPTA _v._ BIMAL KUMAR DUTIA & ORS. 177 [RANJAN GOGOi, J.] deference to the order of High Court, no licence either for group A housing or commercial activities in either Sector 63-A or 67-A was issued or granted and the entire of the earmarked land in both these sectors for Group Housing and Commercial purposes was kept vacant. Only in respect of plotted colonies for which there was no ceiling limit the licence dated 28.12.2011 B was issued. It is further urged that in the light of the specific order passed by the High Court it cannot be said that the appellant or any other person or authority had violated the same. It is also pointed out by the learned counsels that, in any view of the matter, the appellant had tendered his unqualified c and unconditional apology which, in fitness of things, ought to have been accepted by the High Court. Lastly, the learned Attorney General, by drawing the Court's attention to the counter affidavit filed before this Court by the second respondent, has submitted that the writ petition itself had been dismissed by the 0 High Court on 30.10.2012 holding that the validity of the development plan published by the Government in accordance with the relevant provisions of the Statute is not open to challenge by means of a Public Interest Litigation. It is also pointed out that the aforesaid order of the High Court has E attained finality in law. E 10. The terms of the order of the High Court dated 18.08.2011; the averments/statements made in the contempt petition and the reply thereto on behalf of the appellant as well as the subsequent facts placed before us have received our F due and anxious consideration. The interim order of the High Court had directed status quo to be maintained in respect of allotments. Admittedly, no allotments had been made by the appellant or any other authority. A contempt action being in the nature of quasi criminal proceeding the degree of satisfaction G that must be reached by the Court to hold a person guilty of commission of contempt would be akin to what is required to prove a criminal charge, namely, proof beyond reasonable doubt. The order of the Court in respect of which violation is alleged must, therefore, be clear, unambiguous and H [2013) 12 S.C.R. ## 178 SUPREME COURT REPORTS A unequivocal and defiance thereof must be apparent on the very face of the action with which a contemnor is charged. An interpretation of the terms of Court's order in respect of which disobedience is alleged would not be appropriate while dealing with a charge of contempt. Such a charge cannot be brought B home by unravelling the true meaning of the Court's order by a subsequent order when there is an apparent ambiguity, lack of clarity or dichotomy in the initial order. In a situation like the present where the High Court had directed maintenance of status quo as to allotment when the interim prayer was to stay c the implementation of the final development plan "in view of contemplated grant of licence to the colonizers/developers/ Societies" it was not open for the High Court to hold the contemnor guilty of commission of contempt by understanding the order dated 18.08.2011 to mean status quo or a restraint in respect of grant of licences under the Haryana Act of 1975. 0 11. In an earlier part of the present order, we have noticed the unqualified and unconditional apology tendered by the appellant before the High Court in the event his explanations were to be found unacceptable. The explanation to Section 12 E of the Contempt of Courts Act, 1971, makes it clear that an apology tendered by a contemnor should not be rejected merely on the ground that it is qualified or conditional so long it is made bona fide. In his reply, the appellant, after offering his explanations, had tendered his unconditional and unqualified F apology in the event the explanations did not commend for acceptance of the High Court. In the decision rendered in _O.P.Sharma and Ors. Vs. High Court of Punjab and Haryana',_ this Court has already held that in view of the explanation to Section 12 of the Contempt of Courts Act an apology ought not G to be rejected only on the ground that it is qualified so long as it is made bona fide. In the present case there is nothing on record to suggest that the unqualified and unconditional apology tendered by the appellant in his reply before the High Court was actuated by reasons that are not bona fide. - H 1. (2011)6SCC86[para34and35] T.C. GUPTA _v._ BIMAL KUMAR DUTTA & ORS. 179 [RANJAN GOGOi, J.] 12. It has also been noticed by us that the writ petition in A which the interim order dated 18.08.2011 came to be passed has been finally terminated by an order dated 30.10.2012 dismissing the writ petition and also that the said order has attained finality in law. This is another relevant circumstance that cannot be ignored though we should not be understood to be B saying that all cases of dismissal of the writ petition, by itself, would absolve a contemnor of the charge of commission of contempt in respect of an interim order passed while the writ petition had remained pending. 13. In view of the aforesaid, we are unable to sustain the C order dated 23.07.2012 passed by the High Court. We , accordingly set aside the said order dated 23.07.2012 and allow the appeal. R.P. AppeFtl allowed. D