Supreme Court of IndiaSupreme Court · 1997Division BenchAppeals allowed; award set aside; costs borne b...

Tamil Nadu Electricity Board v. Bridge Tunnel Constructions and Ors.

Case / Petition Number:
Civil Appeal Nos. 1766-1767 of 1997

Case Synopsis & Summary

This Supreme Court decision deals with a dispute arising from an inter-connecting tunnel contract for the Suruliyar Hydroelectric Project, where the Tamil Nadu Electricity Board (appellant) invoked arbitration under a clause with a dispute as to compensation for work performed after expiry. The respondents claimed Rs 2.10 crores, of which Rs 70.83 lakh was awarded by an umpire in a non-speaking award consolidating all claims. The core issue was whether the umpire correctly decided arbitrability—the question whether certain claims fell within the arbitration clause and contract—and whether a non-speaking award can validly include both arbitrable and non-arbitrable items. The Madras High Court had affirmed the award, but the Supreme Court held that arbitrability is a jurisdictional issue to be decided by the court and that the arbitrator cannot clothe himself with jurisdiction to decide arbitrability or issue a non-speaking award without addressing how particular items are arbitrable. It referred to multiple precedents on the limits of arbitrator’s jurisdiction, the necessity (or not) of speaking awards, and the proper treatment of disputed arbitrability under the 1996 Act. Ultimately, the Court set aside the award and allowed the appeals, directing the parties to bear their own costs and ordering refund of security/Bank guarantees if no dues remain.

Precedent Explorer

Find Cases Like This

Explore other judgments dealing with similar legal situations, facts, or statutory provisions.

Case Details & Bench

Court
Supreme Court of India
Hon'ble Judges
  • K. Ramaswamy
  • Saghir Ahmad
Judgment Date
1997-02-18
Court Decision / Holding
Appeals allowed. The award of the arbitrator/umpire is set aside. The Court held that arbitrability is a jurisdictional issue and the arbitrator cannot issue a non-speaking award or consolidate sums without addressing which items are arbitrable. The Court remitted no part of the award and ordered the parties to bear their own costs. If there are no outstanding dues, the security deposit and bank guarantee should be refunded to the respondent.
Final Disposition
Appeals allowed; award set aside; costs borne by the parties; refund of security deposit and bank guarantees if no outstanding dues remain.

Parties to the Case

Appellants / Petitioners

  • Tamil Nadu Electricity Board

Respondents

  • Bridge Tunnel Constructions
  • Ors.

Legal Representation & Advocates

Counsels for Petitioners

  • • V. R. Reddy, Additional Solicitor General
  • • N. C. Ramesh
  • • V. B. Ramasubramaniam
  • • V. Krishnamurthy

Counsels for Respondents

  • • P. S. Poti
  • • Ms. Malini Poduval

Provisions of Law Cited

Arbitration Act, 1940, Section 33Arbitration and Conciliation Act, 1996, Section 31(3)Arbitration and Conciliation Act, 1996, Section 30

Legal Doctrines & Maxims

  • Arbitrability is a jurisdictional issue to be decided by the court, not by the arbitrator.
  • An arbitrator cannot enlarge his jurisdiction by deciding arbitrability.
  • Error of jurisdiction vs error apparent on the face of the award.
  • Speaking vs non-speaking awards; Section 31(3) requires award to state reasons unless parties agree otherwise or the award is under Section 30.
  • Governments/instrumentalities may require speaking awards in private arbitration where public interest is involved.

Submissions & Arguments

Contentions of Appellants / Petitioners

The appellant argued that the umpire’s non-speaking award of Rs. 70,83,793 was illegal because the arbitrator failed to decide the arbitrability of several items within the contract. The arbitrator, empowered to decide arbitrability, awarded a consolidated sum without clarifying which items were arbitrable or non-arbitrable and did not provide reasons on the arbitrability issue. This amounted to an error of jurisdiction and invalidates the award. The contract and prior court direction required a determination of arbitrability; without such a decision, the award cannot stand and must be set aside or remitted for proper adjudication.

Contentions of Respondents

The respondents contended that the umpire’s non-speaking award is legally permissible; the arbitrator, though not expressly stating the arbitrability conclusions, had jurisdiction to decide the disputes on merits within the scope of the contract. They argued that the award reflects the arbitrability finding, and any absence of explicit reasoning on arbitrability should not void the award; even if some items were non-arbitrable, the arbitrator could still award a consolidated sum within his jurisdiction. They cited Tarapore and Co., and other authorities to contend that examining the arbitration clause is permissible to test jurisdiction, and the court ultimately decides arbitrability under Section 33.

Legal Doctrine & Issue Explorer

Explore This Legal Issue

Find relevant judgments and authoritative positions on the legal questions discussed here.

Cited Precedents (10)

Case NameCitationTreatmentExplanation
Raipur Development Authority v. Chokhamal Contractors(1989) 2 SCC 121DistinguishedHeld inapplicable in the present context; court distinguished it on grounds relevant to the speaking/non-speaking award and arbitrability issues.
Tarapore & Co. v. Cochin Shipyard Ltd., Cochin(1984) 2 SCC 680PositiveCited to discuss arbitrability and the limits of an arbitrator's jurisdiction; supports the proposition that arbitrability must be determined within the contractual framework and by the court when necessary.
Managing Director, J & K Handicraft v. Good Luck Carpets(1990) 4 SCC 740PositiveCited for the principle that the arbitration agreement can be looked into to test the scope of arbitrability and jurisdiction; supports the court’s role in determining arbitrability.
U.P. Rajkiya Nirman Nigam Ltd. v. Indure Pvt. Ltd.(1996) 2 SCC 667PositiveArbitrability depends on the construction of the arbitration clause; court decides; arbitrator cannot conclusively decide arbitrability.
Union of India v. G.S. Atwal & Co. (Asansole)(1996) 3 SCC 568PositiveArbitrator’s finding on arbitrability is not conclusive; court must decide arbitrability.
Champsey Bhara & Co. v. Jivraj Balloo Spinning & Weaving Co. Ltd.LR (1922) 50 IA 324; AIR (1923) PC 66PositiveError in law on the face of the award concept, guiding the distinction between jurisdictional error and error on the face of the record.
Hindustan Construction Co. Ltd. v. State of J & K(1992) 4 SCC 217PositiveCited for the treatment of error on the face of the award and jurisdictional limits.
M/s Sudarsan Trading Co. v. State of Kerala(1989) 2 SCC 38PositiveDistinguishes jurisdictional errors from errors on the face of the award; supports the need to test jurisdictional boundaries.
Gujarat Water Supply and Sewerage Board v. Unique Erectors(1989) 1 SCC 532PositiveArbitrator’s obligations on arbitrability and the requirement to show applicability of clause to disputes.
State of A.P. v. R. V. Raya11im & Ors.(1990) 1 SCC 433PositiveArbitrability depends on contract construction; ultimate decision lies with the court.
Case Applicability Diagnostic

Apply This to My Facts

Share your situation and test whether this judgment governs, supports, or challenges your case.

Official Judgment Record
•8,072 words•~37 min read

In The Court Record

Tamil Nadu Electricity Board v. Bridge Tunnel Constructions and Ors.

A B # TAMIL NADU ELECTRICITY BOARD _v. MIS._ BRIDGE TUNNEL CONSTRUCTIONS AND ORS. FEBRUARY 18, 1997 [K. RAMASWAMY ANDS. SAGHIR AHMAD, JJ.) _Arbitratio11 Act, 1940/A1bitratio11 a11d Co11ciliatio11 Act, 1996._ S. _33/s. 31(3)-Arbitrability of claims-Arbitrator asked by this Court_ C _to decide arbitrability of claims-171e Umpire without goi11g i11to the details, awarded a co11solidated amount by a 11011- speaki11g award--Held, the Arbitrator, having bee11 i11vested with the jurisdictio11 to decide the arbitrability of certain claims, has committed error of jurisdiction i11 not considering the arbitrability of the claims and passed a 11on-speaki11g ordel"-lt cannot be ascertained as to what extent he has awarded the claims withi11 the co11tract_ D _·or the claims outside the contract-!11 the circumstances the award cannot be accepted-A11 illegal award cwmot be upheld to be valid or withi11 jurisdictio'n-The award of the Arbitrator is set aside._ _Raipur Development Authority_ v. _Chokhamal Contractors,_ (1989) 2 E sec 121, held inapplicable. _Tarapore and Co_ v. _Cochin Shipyard Ltd. Cochi11,_ [1984) 2 SCC 680; _Managing Director, J & K Handicraft_ v. _Good Luck Carpets,_ (1990) 4 SCC 740; _U.P. Rajkiya Ninna11 Nigam Ltd._ v. _llldure Pvt. Ltd.,_ (1996) 2 SCC 667; _U11ion of India_ v. G.S. _Atwal & Co. (Asa11sole),_ [1996) 3 SCC 568; _Champsey_ F _Bhara & Co._ v. _Jivraj Ba/loo Spin11i11g & Weavi11g Co. Ltd.,_ LR (1922) 50 IA 324 =AIR (1923) PC 66; _Hi11dusta11 Co11structio11 Co. Ltd._ v. _State of J & K,_ (1992) 4 SCC 217; _M/s. Sudarsan Trading Co._ v. _State of Kera/a,_ [1989) 2 SCC 38; _Gujarat Water Supply and Sewerage Board_ v. _Unique Erectors,_ [1989] 1 SCC 532 and _State of A.P. & Ors._ v. _R. V. Rayanim & Ors.,_ (1990) G 1 sec 433, referred to. _State of A.P.V.R.V. Rayanim,_ (1990] 1 SCC 433, cited. _"Russel 011 Arbitration" (Ni11etee11th Edition) by Antho11y Walton,_ page 99 and _"Law of Arbitration"_ by _R.S. Bachawat_ (2nd (1987) Edition) referred ,H to. 132 TAMIL NADU ELECTRICITY BD. _v._ BRIDGE TUNNEL CONSNS. 133 CIVIL APPELLATE JURISDICTION: Civil Appeal Nos. 1766-67 A of 1997. From the Judgment and order dated 20.12.90 of the Madras High Court in 0.S.A. Nos. 109-110of1988. V.R. Reddy, Additioqal Solicitor General, N.C. Ramesh, V. B Ramasubramaniam and V. Krishnamurthy for the Appellant. - P.S. Poti, Ms. Malini Poduval for the Respondents. The following Order of the Court was delivered : c Leave granted. Substitution allowed. These appeals, by special leave, arise from the judgment of the Madras High Court, dated December 20, 1990, made in O.S.A..No. 109 and 110 of 1988. D The admitted facts are that the respondents had entered into an agreement with the appellant to construct inter-connecting tunnels for Suruliyar Hydroelectric Project as per specification No 1138 - Schedule-B to the agreement. The initial value of the tender to be awarded was Rs. 47 lakhs and it was revised to Rs. 69 lakhs on January 16, 1975. In the course E of execution of the contract, a sum Rs. 92 lakhs was paid to the respondent. The contract was to be completed within a period of 24 months from the date of taking over of the site, i.e., January 18, 1975; thus, it was completed after the expiry of the term, on August 25, 1978. Resultantly, there had arisen a dispute as to the entitlement to further amount towards the work done by the respondent. F On a notice issued by respondent for appointment of an arbitrator in terms of clause _50_ of the contract (arbitration clause), there was a delay on the part of the appellant in nomination of the arbitrator. When the respondent exercised the power, after expiry of the prescribed in the notice, appointing a sole arbitrator, proceedings under Section 33 of the G Arbitration Act, 1940 were initiated by the appellant. One of the objections raised by the appellant in the proceedings under Section 33 was that under the terms of the conti:act the claim sought to be put up in the notice given by the respondent was not arbitrable. The. question was gone into and the court recorded a finding as under : H 134 (1997] 2 S.C.R. SUPREME COURT REPORTS A B c D "If the petitioner had come forward to raise dispute and if it is outside the scope of clause 50, the first respondent itself would come forward with such a reservation. It is not as if all disputes would come within the scope of clause 50 and only those that would. come within the ambit of clause 50 alone can be decided by the Arbitrators when such is the clear position in this aspect; enabling the petitioner Board to raise a objection regarding disputes which_ may not come within the scope of clause 50 is not a concession, but a recognition of a right, which is available not only to the petitioner Board but also the first respondent in the event of the Board raising any dispute as against it. Therefore, the first stipula- . tion is dependent upon the Arbitrators deciding as no whether a particular dispute would come with in the scope of Section 50 or not, and only if they consider that it falls within the scope of ' Arbitration clause, they would have the jurisdiction to decide the same. In the event of the Arbitrators holding that any particular dispute is outside the Arbitration clause, it is not as if the first respondent is deprived of remedies by agitating the same in Courts." It is also further Held that : E "After the award is made, as the petitioner Board has already reserved its right, it would enable the Board to raise this point, in the event of any need arising for setting aside the award in Court." Pursuant thereto, condoning the delay, liberty was given to the appellant to nominate an Arbitrator on its behalf which accordingly was F done and dispute was referred to arbitration. Arbitrability of some of the claims _was disputed as part of Ito_ liability. Since the two Arbitrators differed, an umpire was selected by the Arbitrators and he had gone into the q ucstion. At this stage, it is relevant to mention that some of the claim made by the respondents relate to excavation of hard rock in the tunnel G and the rate of claims. The relevant clauses of the Contract postulate thus : _22. Matelial to be excavated_ : H The character of the material through which the tunnel is to be ## TAMIL NADU ELECTIUCITY BD. _v._ BRIDGE TUNNEL CONSNS. 135 A excavated is indicated in the report of the Geologist of the GeologiA cal Survey of India, attached of this specification as an appendix. The probable nature of materials to be excavated is given in the above report. It is expressly to be understood, however, t.hat the purchaser does not guarantee the accuracy of the information and should the conditions be found to differ from those indicated, the **B** contractor shall have no claim against the purchaser on the grounds of misrepresentation. Moreover, the price to be given in the schedule of prices for excavation work is to. be inclusive and to be held to cover excavation in the actual materials e~countered. ## 23. _Tunnel Excavation_ : c (a) The tunnel is to be excavated to such dimensions as to give the minimum thickness of concrete lining specified and to suit the shape and size of cross section of the tunnel shown on drawing. (b) Excavation is to be carried out as far as feasible, simultaneously **D** on all fages. It is expected, that more of the ground along the tunnel will be hard rock requiring no supports. Except where t~e materials penetrated is hard rock and will safely stand by itself, the tunnel is to be lined temporarily with timber supports and shoring. The timbering is to be kept as close to the face of the **E** · heading as possible. Any shoring or protective arrangements considered inadequate by the Engineer is to be strengthened immediately. (g) The type of tunnel section to be constructed shall be as directed or approved by the Engineer. Measurement for payment of tunnel **F** excavation, will be limited to the special sectional dimensions and will be made along the established centre line of the tunnel and payment therefore will be made at the unit bid in the schedule for excavation of all classes of tunnel. No additional allowance above the unit price bid in the schedule for excavation of all classes of G tunnel will be made on account of. the class, nature or condition of any of the material encountered." The rates were mentioned in the Schedule and the respondent had set **up** the claims raised at rates higher than the contracted rates and twice the rate for the work done after the expiry of the contract period. **H** (1997) 2 S.C.R. 136 SUPREME COURT REPORTS A B Against the claims, objections were raised by the appellant. They have disputed the claim set up by the respondents and requested the Arbitrators to decide on the arbitrability of the items mentioned in the claims of the respondents. The umpire, without going into the details, in a non-speaking award as again~t the claim of Rs. 2 crores 10 lakhs, has awarded a consolidated sum of Rs. 70.83 lakhs as under : "I hereby award and direct as follows : c (1) The Respondent shall pay the claimant a sum of Rupees Seventy Lakhs eighty three thousand seven hundred and ninety three only (Rs. 70,83, 793) and release the earnest money deposit and Bank Guarantees furnished by the claimant in lieu of Security Deposit, in full settlement of all claims and counter-claims." Calling the award in question, an application to set it aside has been filed. The respondent filed an application to make the award the rule of D the Court. The Civil Court dismissed the petition of the appellant and made the award the rule of the· court.. On appeal, the Division Bench of the High Court has confirmed the same. Thus these appeals, by special leave. E Shri V.R. Reddy, the learned Additional Solicitor General, contends that the award is illegal on account of omission on the part of the Umpire to give the findings and reasons in support thereof of the arbitrability of the claims. He contends that arbitrability of claim a jurisdictional issue. The arbitrator cannot clothe himself with the power, in a non-speaking award to award a consolidated sum, without deciding the ·arbitrability of F the claims set up by the respondents including those which are not part of the contract. Shri Poti, learned senior counsel for the respondents has contended that the award being a non-speaking one in the absence of specific reference directing the Arbitrators to decide the arbitrability of some of the G items in the claims set up by the respondent, Umpire was not called upon or obliged to decide the dispute by a speaking order on arbitrability. He reached the conclusion whether or not the dispute or the claim is arbitrable and obviously he was of the opinion that all the claims are arbitrable and he is empowered to decide it either rightly or wrongly. He may be wrong H in not expressly giving his decision on arbitrability of some of the claims. ## TAMIL NADU ELECTRICITY BD. _v._ BRIDGE TUNNEL CONSNS. 137 However, his decision is within his jurisdiction. He is not required to give A any reasons in the award for reaching that decision. When the arbitrator had given a consolidated sum towards all the claims, it would mean that he had considered the arbitrability of some of the claims in terms of the contract and that, therefore, he has not committed any error in reaching that conclusion which is apparent on the face of the record. In the absence B of any specific reference for deciding that dispute, even if incidentally he reaches that ,decision, he gets the jurisdiction and power to decide the question. Even otherwise also, the award cannot be assailed on the ground that he reached a wrong decision without any reasons in support thereof. In that event, it must be deemed that he had considered the non-arbitrability of the items in a non-speaking award given by him. He also C further contends that in the absence of any agreement between the parties that the arbitrator would give reasons in support of his decision on the arbitrability of the dispute, he is not called upon to decide the dispute by a speaking award. What is required, therefore, is to be considered is whether the arbitrator reached the decision as to the entitlement to for a D specified sum or disentitlement thereof, in his award. Once he specifies the amount to which the respondent is entitled, it must be deemed that he had taken into consideration the arbitrability of all the claims including the claim relating to non-arbitrability of some of the items and had given the award. Thereby, consolidated sum in the award is not subject to attack that the award made by the Arbitrator is vitiated by any error of jurisdiction or E error of law apparent on the face of the record. Shri Poti further contends that the contract of arbitration is not part of the record and the umpire had not referred to the agreement as part of the award and that, therefore, it is not open to the court to look into the contract to find out whether the contractor claimed at the rates higher than what were contracted and the F umpire has omitted to consider the non-arbitrability of the claim in respect of some of the items. In support thereof, he places strong reliance• on the decision of this Court in _Tarapore and Co._ v. _Cochin Shipyard Ltd., Cochin,_ [1984] 2 SCC 680, iµ particular, paragraphs 10, 12, 33 thereof, and _State of A.P._ v. _R.V. Rayanim,_ [1990] 1 SCC 433 at 435, para 5. G In view of the respective contentions, the question that arises for consideration is : whether the Un!Pire was required to give a: decision supported by reasons on the non-arbitrabilit y of some of the items in terms of the contract. It is already seen that the Court prior to the proceedings under Section 33 had gone into the question as to the right of the appellant H _:_ ## 138 ## SUPREME COURT REPORTS [1997] 2 S.C.R. A to question the arbitrability of some of the items and had expressly recorded, as seen hereinbefore, that if any objection regarding the dispute is raised, either parties is at liberty to raise the same and avail of decision by the arbitrator and the arbitrator is required to decide the arbitrability of the claim and if he considers that it falls within the scope of the B[arbitration clause/arbitrability, then he would have the jurisdiction to ] decide the same. If the decision has been. reached by the arbitrator against the appellant, it would be open to the Board to raise that point, in case any need arises for setting aside the said award in the court. Thus, it could be seen that prior to the proceedings under Section 33, the_ court had left open the point of the non-arbitrability of the dispute and the umpire had C to decide the dispute. In the event of the decision going against the Board, the same is also entitled to question the correctness of the award in a court of law. That order has become final. In the light of the above facts, the question arises : whether the D arbitrator was not obliged to decide the non-arbitrability of some of the items claimed by the respondents before/while giving a non-speaking award and whether a deemed decision could be given credence. In _Tarapore Co. 's_ case relied on by Shri Poti, a Bench of two Judges of this Court had gone into the question of jurisdiction of the arbitrator to decide the arbitrability of the dispute. In para 10 thereof, it is stated thus : E "What is the effect of referring the specific question of law to arbitration without prejudice to one's right to contend to the contrary will be presently examined." F G H "If this issue specifically raises a question as to jurisdiction of the arbitrator to arbitrate upon the dispute set out in Point No. 2, it appears to have been specifically referred to the arbitrator for his decision. Parties, therefore, agreed to submit the specific question even with regard to the scope, ambit width and the construction of the arbitration clause so as to define its parameters and contours with a view to ascertaining whether the claim advanced by the appellant and disputed by the respondent would be covered by the arbitration clause. Whether upon its true construction the arbitration clause would include within its compass the dispute thus raised between the parties was specifically put in issue because parties were at variance about it." ## TAMIL NADU ELECTRICITY BD. _v._ BRIDGE TUNNEL CONSNS. 139 -- "The arbitrator was thus required and called upon first to A decide whether the dispute is arbitrable as falling within the width and answer is in the affirmative, then alone the second point need be examined. If the answer to the first point of reference is in the negative in that if the arbitrator were of the opinion that the dispute is not arbitrable' as it would not fall within the scope, width B and ambit of the arbitration a1:,1feement, it would not be necessary for him to determine whether the appellant was entitled to recover anything by way of compensation. This aspect is being analysed in depth to point out that the parties spe"Cifically referred the question of construction of arbitration agreement, its width, ambit and parameters vis"a"vis the dispute raised so as to decide whether the C dispute would fall within the purview of the arbitration agreement, in other words the jurisdiction of the arbitrator." Thus, it could be seen that therein that when the question is specifi" cally referred to the arbitrator, the arbitrator is required to decide the question referred to him and decide the point on the question. Then only D he gets the jurisdiction to go into the merits. Iii para 12 of the judgment that point was elaborated holding that : "The first point extracted hercinbefore would clearly show that the specific question about jurisdiction of the arbitrator to arbitrate E upon the dispute set out in Points Nos. 2, 3 and 4 was specifically referred to the arbitrator. On the first point, the arbitrator had to decide whether the claim made by the appellant and disputed by the respondent would be covered by clause 40, i.e. the arbitration clause. In other words, the specific question referred to the ar" hitrator was about his jurisdiction to arbitrate upon the disputes F covered by Points Nos. 2, 3 and 4, if and only if, upon a true construction of the arbitration clause that is first paragraph of Clause 40, would cover the disputed claim for compensation he can enter into the merits of the dispute and decide it." This ratio clearly establishes that the arbitrator gets jurisdiction to <leci<lt: the dispute on merits only when he is specifically called upon to decide the dispute in terms of the contract. G In _Managing_ Dir~ctor, _J & K Handicraft v. Good Luck Carpets,_ [1990) 4 SCC 740, the questton arose·: whether the court could look into the H _y_ _I_ 140 SUPREME COURT REP-ORTS (1997] 2 S.C.R. - A arbitr;1tion agreement, find out whether the arbitrator has jurisdiction to decide the dispute though it was not formed part of the award? In para 5, this Court had held that : - " ... Here we may point out that the learned counsel for the respondent has urged that the agreement containing the arbitration clause - B cannot be looked into even to find out as to what was the nature of the dispute. contemplated by it with regard to which a reference to an arbitrator was contemplated, more so when the award was a non-speaking one. We find it difficult to agree with this submis- . sion for two reasons : Firstly, the award is not a totally non-speak- - c ing one inasmuch as it gives a resume of the incentive scheme and· the agreement between the parties as also the items of .the claim ·I· - made by the respondent Of course, while fixing the amount found payable by the appellant, no reasons are recorded. Secondly, if there is any challenge to the award on the ground that the ar-· - . bitrator had not jurisdiction to make the award with regard to a - D · particular item inasmuch as it was beyond the scope of refererlce, . the only way to test the correctness of such a challenge is to look into the agreement itself. In our opinion, looking into the agree- ' ment for this limited purpose is neither tantamount to going into the evidence produced by the parties nor into the reasons which - E weighed with the arbitrator in making the award." In fact this Court had gone into merits while deciding the question as to whether the arbitrator was justified in making the award in excess of the jurisdiction with reference to the arbitration agreement and deciding p the dispute on that basis. In _U.P. Rajkiya Ni1111a11 Nigam Ltd._ v. _Indure Pvt. Ltd.,_ [1996) 2 SCC 667 a Bench of three Judges (to which both of us were members) had gone into the question whether the arbitrator can go into the question whether there emerged any concluded contract and whether he can get exclusive G jurisdiction to decide that question by himself? In an application under Section 33, the learned Single Judge of the High Court had held that the <J.rbitrator had exclusive jurisdiction to decide that question. Reversing that jhdgment this Court in para 13 had held that "the arbitrability of a claim depends on the construction of the clause in the contract. The finding of H the arbitrator/arbitrators on arbitrability of the claim is not conclusive as TAMIL NADU ELECTRICITY BD. _v._ BRIDGE TUNNEL CONSNS. 141 under Section 33, ultimately it is the court that decides the controversy. It A being a jurisdictional iswe, the arbitrator/arbitrators cannot clothe themselves with jurisdiction to conclusively decide the issued." In para 15 it is held thus : "The clear settled law thus is that the existence or validity of an arbitration agreement shall be decided by the court alone. ArB bitrators,. therefore, have no power ·or jurisdiction to decide or adjudicate conclusively by themselves the question since it is the very foundation on which the arbitrators proceed to adjudicate the disputes. Therefore, it is rightly pointed out by Shri Adarsh Kumar Goe~ learned counsel for the appellant that they had by mistake C agreed for reference and that arbitrators could not decide the existence of the arbitration agreement or arbitrability of the disputes without prejudice to their stand that no valid agreement . existed. Shri Nariman contended that having agreed to refer the dispute, the appellant had acquiesced to the jurisdiction of the arbitrators and, therefore, they cannot exercise the right under D Section 33 of the Act. We find no force in the contention. As seen, the appellant is claiming adjudication under Section 33 which the court alone has jurisdiction and power to decide whether any valid agreement is existing between the parties. Mere acceptance or acquiescing to the jurisdiction of the arbitrators for adjudication E of the disputes as to the existence of the ar~itration agreement or arbitrability of the dispute does not disentitlc the appellant to have the remedy under Section 33 through the court. In our considered .view the remedy under Section 33 is the only right royal way for deciding the controversy." B F Accordingly, it was held that the controversy of arbitrability requires to be decided by the court and not by the arbitrator himself. In _Union of India_ v. _G.S. Atwal_ & _Co. (Asa11sole),_ [1996] 3 SCC 568 a Bench o~o Judges, to which one of us, K. Ramaswamy, J. was a G member, was to consider the question whether the arbitrator, when he enlarged his scope of award in a non-speaking award, can conclusively decide the dispute and give an award in that behalf? It was held in paragraph 6 that: "To constitute an arbitration agreement, there must be an agree- H _I_ 142 SUPREME COURT REPORTS (1997J 2 S.C.R. A ment that is to say the parties must be _ad idem._ Arbitrability of a claim depends upon the dispute between the parties and the reference to the arbitrator. On appointment, he enters upon that dispute for adjudication. The finding of the arbitrator on the arbitrability of the claim is not conclusive, as under Section 33 ultimately it is the court that decides the controversy. It can hardly B be within the arbitrator's jurisdiction to decide whether or not a condition precedent to his jurisdiction has been fulfilled. The arbitrator had no power to decide his own jurisdiction. The arbitrator is always entitled to inquire whether or not he has jurisdiction to decide the dispute. He can refuse to deal with the matter c at all and leave the parties to go to the court if he comes to the conclusion that he has no power to deal with the matter, or he can consider the matter and if he forms the view that the co~tract upon which the claimant is relying on and from which, if established, he alone has jurisdiction, he can proceed to decide the dispute accordingly. Whether or not the arbitrator has jurisdiction and D whether the matter is referred to or is within the ambit ;if clause for reference of any difference or dispute which may arise between the parties, it is for the court to decide it. The arbitrator by a wrong decision cannot enlarge the scope of the submission. It. is for the court to decide finally the arbitrability of the claim in E dispute or any clause or a matter or a thing contained therein or the construction thereof." B c D In _Cllampsey Bhara & Co._ v. _Jivraj Ba/loo Spinning & Weaving Co. Ltd.,_ LR (1922) 50 IA 324 : AIR (1923) PC 66 Lord Dunedin had laid down the dictum as to an error in law on the face of the award, _which was_ F _accepted and fallowed_ by this court in _Hindustan ConstJUction Co. Ltd._ v. _State of J & K,_ (1992) 4 SCC 217. Therein it was held that : - "An error in law on the face of the award means, in their Loardships' view, that you can find in the award or a document - G actually incorporated thereto, as for instance a note appended by the arbitrator stating the reasons for his judgment some legal proposition which is the basis of the award and which you can then say is erroneous. It docs not mean that if in a narrative a reference is made to a contention of one party, that opens the door to seeing - H first what that contention is, and then goijig to the contract on ## TAMIL NADU ELECTRICITY BD. _v._ BRIDGE TUNNEL CONSNS. 143 which the parties' right depend to see if that contention is sound. A Here it is impossible to say, from what is shown on the face of the award, what mistake the arbitrators made. The only way that the learned judges have arrived at finding what the mistake was is by saying : 'inasmuch as the arbitrators awarded so and so, and inasmuch as the letter shows that the buyer rejected the cotton, B the arbitrators ca.n only have arrived at that result by totally misinterpreting Rule _52':_ But they were entitled to give their own interpretation to Rule 52 or any other article, and the award will stand unless, on the face of it, they have tied themselves down to some special legal proposition which then, when examined, appears to be unsound." C This decision has been followed by this Court in all subsequent judgments and the precise scope of the law as to error apparent on the face of the award has been crystalised. But there is a distinction between an error apparent on the face of the award and jurisdictional error in D passing the award. In that behalf, in _Mis. Sudarsan Trading Co._ v. _State of Kera/a,_ [1989) 2 SCC 38 Justice Sabyasachi Mukherji, as he then was, had pointed out the distinction on the jurisdictional error and the error on the face of the award. It was stated thus : "An award may be remitted or set aside on the ground that the E arbitrator in making it, had exceeded his jurisdiction and evidence of matters not appearing on the face of it, will be admitted in order to establish whether the jurisdiction had been exceeded or not, because the nature of the dispute is something which has to be determined outside the award - whatever might be said about it in F the award or by the arbitrator. It has to be reiterated that an arbitrator acting beyond his jurisdiction - is a different ground from the error apparent on the face of the award. In Hal5bury's Laws of England II, 4th edn., Vol. 2 para 622 one of the misconducts enumerated, it the decision by the arbitrator on a matter which is not included in the agreement or reference. But in such G a case one has to determine the distinction between an error within the jurisdiction and an error in excess of the jurisdiction. WhBther a particular amount was liable to be paid of damages liable to be sustained, was a decision within the competency. of the arbitrator in this case. By purporting to construe the contract the court could H _y_ _J_ 144 (1997] 2 S.C.R. ## SUPREME COURT REPORTS A B not take upon itself the burden of saying that this was contrary to the contract and, as such, beyond jurisdiction. It has to be determined that there is a distinction between disputes as to the jurisdiction of the arbitrator and the disputes as to in what way that jurisdiction should be exercised. There may be a conflict as to the power of the arbitrator to grant a particular remedy." In "Russel on Arbitration" (Nineteenth EditiOn) by Anthony Walton, page 99, it is stated as under : c D E "It can hardly be within the arbitrator's jurisdiction to decide whether or not a condition precedent to his jurisdiction has been fulfilled. It has indeed several times been said bluntly that an arbitrator has no power to decide his own jurisdiction and in one case where rules of an institution prepared to conduct arbitrations gave the arbitrator such power, the court will ignore this when asked to enforce the award, and decide the question itseif. However, an arbitrator is always entitled to inquire whether or not he has jurisdiction. An umpire faced with a dispute whether or not there was a contract from which alone his jurisdiction, if any, can arise can 11¥tter at all and lease the parties to go to court, or he can consider the matter and if he forms the view that the contract upon which the claimant is relying and from which, if established, alone his jurisdiction can arise is in truth the contract, he can proceed accordingly." In "Law of Arbitration" by R.S. Bachawat (2nd (1987) Edition) at pages 154-55, it is stated thus : F G H "An arbitrator cannot by mistake assume jurisdiction over a matter on which he has no jurisdiction. If it is shown by the terms of the submission or by extrinsic evidence th~t the arbitrator has adjudicated upon matters outside the scope of his authority the award cannot stand, however well meaning and honest the mistake might have been. An arbitrator cannot give himself jurisdiction by a wrong decision collateral to the merits as to facts on which the limits of his jurisdiction depends. Where it was a condition precedent to his jurisdiction that the dispute should have arisen during a tenancy between the plaintiff and the defendant or in the event of a collusion if certain works had been completed, the arbitrator TAMIL NADU ELECTRICITY BD. _v._ BRIDGE TUNNEL CONSNS. 145 "' B - " ... Disputes about the existence or validity of the contract and C as to the existence orJacts which render it illegal must be determined by the court and not by tpe arbitrator. The arbitrator cannot by his own finding clothe himself with jurisdiction. Supposing he finds that the arbitration agreement is valid such a finding cannot bind the parties". D It would thus be seen that the arbitrator, while deciding the admitted dispute, subject matter of adjudication, may decide the dispute in reference to the agreement. That would be within his jurisdiction. In such jurisdictional issue, even if an error is committed that may not be an error apparent on the face of the recored because the arbitrator, the chosen E forum, may commit an error in exercising his jurisdiction. However, if he, by a speaking award, decides it on a wrong proposition of law, it will be an error apparent on the face of record and liable to correction. If the arbitrator decides a dispute which is beyond the scope of his reference or beyond the subject matter of the reference or he makes the award disregarding the terms of reference or the arbitration agreement or terms of F the contract, it would jurisdictional error beyond the scope of reference, he cannot clothe himself to decide conclusively that dispute as it is an error of jurisdiction which requires to be ultimately decided by the court. This Court has pointed out the distinction between latent and patent error of jurisdiction in _Tarapore Co. 's_ case thus : G "It has to be seen whether the term of the agreement permitted entertainment of the claim by necessary implication. It may be stated that we do not accept the broad contention of Shri Nariman that whatever is not .excluded specifically by the contract can be subject-matter of claim by a contractor. Such a proposition will H 146 [1997) 2 S.C.R. A ## SUPREME COURT REPORTS • mock at <he terms agreed upon. Parties cannot be allowed to · depart from what they had agreed. Of course, if something flows as a necessary concomitant to what was agreed upon, courts can assume that too as a part of the contract between the parties." It would thus be clear that the arbitrator cannot clothe himself B conclusively with the jurisdiction to decide or omit to decide the arbitrability of a particular item odhe claim made by the parties. When a specific reference has been made to the arbitrator and the parties raise the dispute of arbitrability, with the leave of the court/by a direction of the court in a proceedings under Section 33, he is to decide the arbitrability of C the dispute and make a decision while giving reasons in support thereof. The decision of the arbitrator in granting a particular sum by a non-speaking award, therefore, hinges upon the arbitrability of a dispute arising under the contract or upon a particular item claimed thereunder. He is required to give the decision thereon. The question of decision by implication does not arise since his jurisdiction to decide the dispute on merits D hinges upon his jurisdiction to decide the arbitrability of the dispute. In this case, in view of the finding recorded by the court, which has become final, as referred to earlier, the arbitrator/umpire was enjoined to decide the arbitrability of the claims set up by the respondent and disputed by the appellant. Admittedly, the award of the umpire does not contain any E decision on arbitrability of the claims. In _Gujarat Water Supply and Sewerage Board_ v. _Unique Erectors,_ [1989] 1 SCC 532 one of the questions referred was arbitrability of a particular item. It was by the Court stated thus : - F "In the instant case, the arbitrator by virtue of the terms mentioned in the order of this Cou;t had to decide which of the disputes were arbitrable and which were not. It is true that the arbitrator hjis not specifically stated in the award that he had to decide the question of arbitrability. The arbitrator has rested by stating that he had heard the parties on the point of arbitrability of the claim and the - G counter-claim. He has further stated that after 'considering all the above aspects' and 'the question of arbitrability or nonarbitrability' he had made the award on certain aspects." It could be seen that if the arbitrator has indicated his mind in the H award that he in fact adverted to the arbitrability or non-arbitrability of the ## TAMILNADU ELECfRICJTY BD. _v._ BRIDGE TUNNEL CONSNS. 147 claim and then made the award, it would be indicative of the fact that he A had, in fact, applied his mind, considered that question and reached the decision in awarding certain amounts by a non-speaking award including the claim in respect of which arbitrability was in issue. In _Raipur Developme11t Authority_ v. _Chokhamal Contractors,_ (1989] 2 SCC 721, a Constitution Bench of this Court had gone into the question B whether the arbitrator is required to give reasons in a non-speaking award. The Constitution Bench h~d pointed out in para 35 thus : - "We do not appreciate the contention, urged on behalf of the parties who contend that it should be made obligatory on the part C of the arbitrator to give reasons for the award, that there is no justification to leave the small area covered by the· law of arbitration out of the general rule that the decision of every judicial and quasi-judicial body should be supported by reasons. But at the same time it has to be borne in mind that what applies generally to settlement of disputes by authorities governed by public law D need not be extended to all cases arising under private law such as those arising under the Jaw of arbitration which is intended for settlement of private disputes." ln para · 37 thereof, this Court emphasised the need to make a speaking award and the terms in the contract should postulate such a need when the contract in entered into by State or its instrumentalities. It was held thus : "The trappings of a body which discharges judicial functions and is required to act in accordance with law with their concomitant p obligations for reasoned decisions, are not attracted to a private adjudication of the nature of arbitration as the latter, as we have noticed earlier, is not supposed to exert the State's sovereign judicial power. But arbitral awards in disputes to which the State and its instrumentalities are parties affect public interest and the matter of the manner in which government and its instrumentalities G allow their interest to be affected by such arbitral adjudications involve larger questions of policy and public interest. Government and its instrumentalities cannot simply allow large financial interests of the State to be prejudicially affected by non-reviewable - except in the limited way allowed by the statute - non-speaki.ng H 148 [1997] 2 S.C.R. SUPREME COURT REPORTS A B c arbitral awards. Indeed, this branch of the system of dispute resolution has, of late, acquired a certain degree of notoriety by the manner in which in many cases the financial interests of government have come to suffer by awards which have raised eyebrows by doubts as to their rectitude and propriety. It will not be justifiable for governments or their instrumentalities to enter into arbitration agreements which do not expressly stipulate the rendering of reasoned and speaking awards. Governments and their instrumentalities should, as a matter of policy and public interest - if not as a compulsion of law - ensure that wherever they enter into agreements for resolution of disputes by resort to private arbitrations, the requirement of speaking awards is expressly stipulated and ensured." > In _State of A.P. & Ors._ v. _R. V. Raya11im & Ors.,_ [1990] 1 SCC 433, relied on by Shri Poti, the question arose whether the award of escalation charges in a non-speaking award is vitiated by any error apparent on the D face of the record? Therein the question -of jurisdictional issue had not arisen. On the other hand, on merits, it was contended that there was an ' error in that behalf. In para _5_ it was held that "it was then contended that the award has purported to grant damages on the basis of escalation of cost and p~ices and such escalation was not a matter within the domain of E the bargain between the parties and having taken that factor into consideration the award was bad. II Therefore, the ratio there is an authority supporting the contention on the need of an arbitrator to give a reasoned decision on arbitrability of the contract or claim in dispute. In this regard, Section 31(3) of the Arbitration and Conciliation Act, F 1996, provides thus : "(3) The arbitral ward shall state the reasons upon which it is based, unless - G (a) the parties have agreed that no reasons are to be given, or (b) the award is an arbitral award on agreed terms under Section 30." The Parliament has expressed the legislative judgment that the award H shall state reasons upon which it is based unless parties have agreed ~ - ## TAMIL NADU ELEcmICITY BD. _v._ BRIDGE TUNNEL CONSNS. 149 otherwise or the award is covered on agreed terms under Section 30 of the A new Act. Thus, the law on the award, as governed by the new Act, is other way about of the pre-existing law; it mandates that the award should state the reasons upon which it is based. In other words, unless (a) the parties have agreed that no reasons are to be given or (b) the award is an arbitral award B on agreed terms under Section 30 of the new Act, the award should state the reasons in support of determination of the liability/non-liability. Thereby, legislature has not accepted the ratio of the Constitution Bench in the _Chokhamal Contractor's_ case that the award, being in the private law field, need not be a speaking award even where the award relates to the contract C of private parties or between person and the Government or public sector undertakings. The principle is the same, namely the award is governed by Section 31(3). We have set out the relevant portions of the award. From a reading D thereof, it is clear that the· arbitrator had considered the claims made on the basis of escalation and damages, in a ·non-speaking award of the disputes consisting of arbitrable and non-arbitrable claims. He awarded a lumpsum amount of Rs. 70,83, 793. It is difficult to discern as to what extent the umpire had considered the admissible and inadmissible claims which he adjudged. In such a situation, it is notpossible to discern to what extent E he had exercised his jurisdiction vis-a-vis of the admissible claims and disallowed the non-arbitrable claims, So, it is not clear whether he exercised his authority either beyond his jurisdiction or in abdication thereof. In either case, it is an error of jurisdiction, the very four1dation for his decision. F It is well settled that in the matter of challenge to the award there are two distinct and different grounds, viz., that there is an error apparent . on the face of the record and that the arbitrator has exceeded his jurisdiction. In the latter case, the court can look into the arbitration agreement but under the former it cannot do so unless the agreement was incor- G porated or cited in the award or evidence was made part of the agreement. In the case of jurisdictional error, there is no embargo on the power of the court to admit the contract into evidence and to consider whether _ot_ not the umpire had exceeded the jurisdiction because the nature of the dispute is something which has to be determined, outside the award, whatever H 150 [1997] 2 $.C.R. ## SUPREME COURT REPORTS A might be said about it in the award or by the arbitrator. In the case of non-speaking award, it is not open to the court to go into the merits. Only in a speaking award the court can look into the reasoning in the award and correct wrong proposition of law or error of law. It is not open to the court to probe the mental process of the arbitrator and speculate, when no reasons have been given by the arbitrator, as to what impelled the arB bitrator to arrive at his conclusion. But in the later case the court, with reference to the terms of the contract/arbitration agreement, would consider whether or not the arbitrator/umpire has exceeded his jurisdiction in awarding or refusing to award the sum of money awarded or omitted a consolidated lumpsum. - c In fact, in _G.S. Atwal & Co. 's_ case, having noticed that the arbitrator had exceeded his jurisdiction to grant amount _de hors_ the terms of the contract and being a non-speaking award, the C,0Urt was unable to speculate as to what extent the award was within the terms of the contract or D claims made and to what extent the amount awarded was in respect of non-arbitrable dispute. Accordingly, the order of the civil court was set aside reversing the judgment of the Division Bench of the Calcutta High Court. Thus considered, . we hold that the arbitrator, having been invested E with the jurisdiction to decide the i.rbitrability of certain claims, has committed error of jurisdiction in not considering the arbitrability of the daims and passed a non-speaking award, awarding a sum of Rs. 70.83 lakhs and odd. It is difficult to ascertain as to what extent he has awarded the claim within the contract or the claims outside the contract, of a total claim F of Rs. 2.10 crores. Under those circumstances, we are constrained tu hold that it is difficult to give acceptance to the award made by the umpire as upheld by the courts below. Equally, we find it difficult to accept the contention that out of a claim of Rs. 2.10 crores, only a sum of Rs. 70.83 and odd was awarded. So, it is not a fit case for interference on the basis of the mere fact that a lesser sum than was claimed has been awarded. An G illegal award cannot be upheld to be valid or within jurisdiction. The question then is : what procedure should be adopted in this behalf? The contention of Shri Poti is that it may be remitted to the umpire for fresh consideration. On the other hand, the contention of Shri V.R. H Reddy is that in the event of the conclusion that the arbitrator has exceeded ## TAMIL NADU ELECTRICITY BD. _v._ BRIDGE TUNNEL CONSNS. 151 -- - his jurisdiction, the entire award would become invalid and it has to be set A at naught. Having given due consideration to the respective contentions, we find force in the contention of Mr. V.R. Reddy. Mr. Poti has stated that though it is found that the award is not valid in law, the party cannot be made to suffer on account of the illegality committed by the umpire. We find no force in the contention. Once a finding recorded that the umpire/arbitrator has committed error of jurisdiction, as stated earlier, two B courses are open, viz., either to remit the award to the umpire for reconsideration or to set aside the award _in toto._ We think that the latter course would be appropriate in the facts and circumstances in this case. C Accordingly, we allow the appeals set aside the award of the arbitrator anq leave the parties to bear their own costs. If there are no outstanding dues recoverable from the respondents, the security deposit and bank guarantee is required to be refunded to the respondent. R.P. Appeals allowed. -
End of Judgment Record
Browse All Supreme Court of India (1997) Decisions
1997-12-17

Sharad Vasant Kotak and Ors. v. Ramniklal Mohanlal Chawda and Anr.

This Supreme Court judgment concerns the maintainability of a suit for dissolution of partnership and accounts under the Indian Partnership Act, 1932, as amended by the Maharashtra Amendment of 1984 (Section 69(2A)). The Paramount Builders partnership, registered in 1980 with seven partners (Kotak family and Chawda family), underwent changes after the death of partner Mohanlal Chawda in 1986, when his widow was inducted as a partner. A series of deeds (1986, 1992) reconstituted the firm without informing the Registrar of Firms, raising questions about registration and the applicability of Section 69(2A), which restricts suits to registered firms where the suing partner is shown in the Register of Firms. The Bombay High Court Division Bench held that reconstitution does not cancel registration and that amendments to pleadings were permissible; it concluded that Section 69(2A) does not bar the suit. The appellants argued that induction of a new partner dissolves the old firm and requires a fresh registration, while the respondents contended that dissolution and reconstitution are distinct concepts and that registration continues despite changes. The Supreme Court ultimately held that the firm was merely reconstituted, not dissolved; non‑compliance with registration provisions may attract penalties, but does not erase registration. The Special Leave Appeal was dismissed, with no costs.

1997-11-18

National Insurance Co. Ltd. v. Santro Devi and Ors.

National Insurance Co. Ltd. v. Santro Devi deals with a motor-accident compensation claim under the Motor Vehicles Act. A Tribunal found that the offending vehicle was driven by a person who held a valid driving licence, which had been renewed on the date of the accident, and the claimants were accordingly awarded compensation. The Punjab and Haryana High Court affirmed this finding on appeal but then referred the matter to a full Bench to decide a legal question: whether a forged or fake licence, if renewed, would be treated as a valid licence for purposes of liability. The full Bench answered that a forged licence would not become valid under the Motor Vehicles Act and that an insured, bonafide believing in the licence’s validity, would still incur liability toward third parties under the policy; several related conclusions regarding insurer liability were laid down. The Insurance Company challenged these High Court observations. The Supreme Court allowed the appeal in part, holding that the claimants were rightly granted compensation on the facts, and that the High Court’s observations on forged licences were obiter and not binding precedents since there was concurrent factual finding that the driver held a valid licence renewed on the date of the accident. The Court affirmed the substantive order and dismissed the related Special Leave Petition.

1997-02-03

JAIPUR DEVELOPMENT AUTHORITY v. SITA RAM AND ORS.

This appeal concerns the validity of notifications under Section 52 of the Rajasthan Urban Improvement Act, 1959, by which the Jaipur Development Authority sought to continue land acquisition even after the repeal of the 1959 Act, and after a fresh notification was issued in 1984 under the Jaipur Development Authority Act. The Rajasthan High Court had held that unless the master plan scheme under the JDA Act had been properly framed, the notification issued under Section 52 was not valid in law. The appellants challenge this proposition, contending that framing of a scheme is not a mandatory pre-condition for acquisition and that the 1984 notification cannot be quashed solely for lack of a sanctioned scheme. The matter traces several precedents: Pratap v. State of Rajasthan; State of Tamil Nadu v. Mohd. Yousef; Narain v. State of Rajasthan; and Urban Improvement Trust v. State of Rajasthan. The decision ultimately clarifies that framing of a scheme is not a required pre-condition for land acquisition; overruled or distinguished interpretations in earlier decisions, especially Tamil Nadu Yousef, Krishnan’s later formulation and Narain’s approach. The Court endorses the view that the notification for acquisition cannot be invalidated on account of non-framing of a scheme, and thus allows the appeals, setting aside the High Court’s judgment and dismissing the writ petitions, with no costs to either side.

1997-07-07

Delhi Administration (Now Govt. of N.C.T. Delhi) through the Chief Secretary, Delhi and Ors. v. Nand Lal Pant and Anr.

Delhi Administration v. Nand Lal Pant concerns the scope of promotion from the cadre of Trained Graduate Teachers (TGT) to Post-Graduate Teachers (Sanskrit) in the Delhi education cadre, and the remedy when a sanctioned channel does not exist. Pant, appointed as a TGT in 1974 and confirmed, was asked to officiate in the PGT (Sanskrit) post when it became vacant after the retirement of S.N. Sastri, a Sanskrit-qualified officer. He repeatedly sought promotion to the PGT position, which the Delhi High Court granted in 1996, directing promotion with effect from 1986 and ordering payment of consequential benefits. The Delhi Administration appealed on the ground that there was no direct promotional channel from TGT (General) to PGT (Sanskrit), and that the SC caste reservation for the post should be respected. The Supreme Court accepted that there is no direct channel, but noted Pant’s extended officiation in the PGT post since 1986. It held that justice required a workable remedy: creation of a supernumerary PGT (Sanskrit) post in any school or directorate, allowing Pant to continue there until retirement, with pay from the date of creation. The decision clarifies it as a discretionary remedy and not a general precedent, and it disposed of the appeal with no costs.