Case Synopsis & Summary

This is a Kerala High Court criminal revision petition by accused Nos. 2, 3 and 5 to 9 challenging an order of the Enquiry Commissioner and Special Judge, Kozhikode, in CC No.56 of 2004, which refused to discharge them in proceedings arising from alleged offences under the Prevention of Corruption Act (Sections 13(2) r/w 13(1)(c) and (d)) and Indian Penal Code (ss. 465, 468, 471, 420 and 120B). The prosecution contends that the accused conspired with contractors to obtain timbering/shoring work for the Karapuzha River Project by forging a measurement book and making false entries to cheat the government. The respondents claim the records do not prima facie establish any offence, and that the evidence is insufficient to frame charges. The judge reiterates the legal standard at the charge-framing stage: a grave suspicion suffices and the court should form a presumptive opinion that there is ground to proceed, without a deep probe into evidence’s probative value (citing Onkar Nath Mishra v. State, (2008) 1 SCC (Cri.) 507). The court analyzes that, although there were procedural irregularities (e.g., tender issued before technical sanctions), there exists material suggesting that timbering/shoring work may not have been properly justified and that the accused had a role in the process. After examining the record and witness material (C.W.1–C.W.14), the court held that there is enough ground to proceed to frame charges, and accordingly dismissed the revisions. The matter thus moves forward to trial.

Precedent Explorer

Find Cases Like This

Explore other judgments dealing with similar legal situations, facts, or statutory provisions.

Case Details & Bench

Court
High Court of Kerala
Hon'ble Judges
  • Thomas P. Joseph
Judgment Date
2009-09-23
Court Decision / Holding
Revision Petitions are dismissed.
Final Disposition
Revision petitions dismissed.

Parties to the Case

Appellants / Petitioners

  • T. Baburajan (Accused No.2)
  • Accused No.3
  • Accused No.5
  • Accused No.6
  • Accused No.7
  • Accused No.8
  • Accused No.9

Respondents

  • State of Kerala, rep. by the Public Prosecutor, High Court of Kerala, at Ernakulam

Legal Representation & Advocates

Counsels for Petitioners

  • • B. Raman Pillai
  • • R. Anil
  • • Anil K. Mohammed
  • • Sujesh Menon
  • • Joseph P. Alex
  • • Shyam Aravind
  • • T. Anil Kumar

Counsels for Respondents

  • • Public Prosecutor, Sh. P.N. Sukumar

Provisions of Law Cited

Section 13(2) read with Section 13(1)(c) and (d) of the Prevention of Corruption ActSections 465, 468, 471, 420 and 120B of the Indian Penal Code

Legal Doctrines & Maxims

  • Grave suspicion standard for framing charges (grave suspicion suffices to form a basis for proceeding)
  • Presumption, not full evaluation, at charge-framing stage; court should form presumptive opinion there is ground to proceed

Submissions & Arguments

Contentions of Appellants / Petitioners

The accused contended that the prosecution has not established, prima facie, the commission of any offence. They argued that records and standards under the PWD Manual and Kerala Standard Specifications do not necessarily require timbering/shoring in the given trench conditions beyond 2 metres, that essential data appeared only partially in the file, and that the trial court did not properly analyze the records before framing charges. They asserted procedural irregularities—such as inviting tenders before obtaining technical sanction—were not sufficient to prove guilt and that senior departmental officials bona fide carried out public interest work. Respondents argued that there is ample material on record showing sufficient ground to proceed and that the framing of charges was warranted; the court should not assess the full evidence at this stage.

Contentions of Respondents

The State, through the Public Prosecutor, maintained that there was substantial material indicating offence and collusion with contractors, justifying framing of charges.

Legal Doctrine & Issue Explorer

Explore This Legal Issue

Find relevant judgments and authoritative positions on the legal questions discussed here.

Cited Precedents (1)

Case NameCitationTreatmentExplanation
Onkar Nath Mishra and Others v. State(2008) 1 SCC (Cri.) 507PositiveCited to support the proposition that at the charge-framing stage the court need only form a presumptive opinion of ground to proceed, not conduct a full probative inquiry.
Case Applicability Diagnostic

Apply This to My Facts

Share your situation and test whether this judgment governs, supports, or challenges your case.

Official Judgment Record
•2,567 words•~12 min read

In The Court Record

T. Baburajan v. State of Kerala

## **IN THE HIGH COURT OF KERALA AT ERNAKULAM** **PRESENT :** **THE HONOURABLE MR. JUSTICE THOMAS P.JOSEPH WEDNESDAY, THE 23RD SEPTEMBER 2009 / 1ST ASWINA 1931** **CRL.REV.PET.NO. 1683 OF 2009()** **------------------------------------------AGAINST THE ORDER IN CMP.277/2006 IN CC.56/2004 OF ENQUIRY COMMR. & SPL.JUDGE, KOZHIKODE** **....................** ## **REVN. PETITIONER(S) – ACCUSED NO.2:** **-----------------------------------------------------** **T.BABURAJAN, S/O. THOMAS, AGED 69, THOTTATHIL HOUSE, CHENGAMANADU VILLAGE, NEDUMBASSARY P.O.** **BY ADV. SRI.B.RAMAN PILLAI SRI.R.ANIL SRI.ANIL K.MOHAMMED SRI.SUJESH MENON V.B. SRI.JOSEPH P.ALEX SRI.SHYAM ARAVIND SRI.T.ANIL KUMAR** ## **RESPONDENT(S) - COMPLAINANT:** **--------------------------------------------** **STATE OF KERALA, REP. BY THE PUBLIC PROSECUTOR, HIGH COURT OF KERALA, AT ERNAKULAM.** **BY PUBLIC PROSECUTOR SHRI P.N. SUKUMARAN** **THIS CRIMINAL REVISION PETITION HAVING BEEN FINALLY HEARD ON 25.8.2009 ALONG WITH CRRP NOS. 1779 & 1780 OF 2009, THE COURT ON 23.9.2009 PASSED FOLLOWING:** ## **THOMAS P.JOSEPH, J.** = = = = = = = = = = = = = = = = = = = = = = = = **CRL. R.P. NO.1683 of 2009, CRL.R.P. NO.1779 of 2009 AND CRL.R.P. NO.1780 of 2009** = = = = = = = = = = = = = = = = = = = = = = = = = Dated this the 23[rd] day of September, 2009 ## **O R D E R** -------------- Accused Nos.2, 3 and 5 to 9 in C.C. No.56 of 2004 of the court of Enquiry Commissioner and Special Judge, Kozhikode (for short, “the learned Special Judge”) are the petitioners in these revision petitions. They along with a few others are facing prosecution for offences punishable under Section 13(2) read with 13(1)(c) and (d) of the Prevention of Corruption Act and Sections 465, 468, 471, 420 and 120B of the Indian Penal Code. They pleaded for discharge which learned Special Judge by the impugned order refused. Hence these revisions. 2. Accused Nos.1 to 5 and 8 are Engineers connected with the work of Karapuzha River Project (for short, “the Project”) during the relevant periods. Case is that they while holding office as Engineers and working as such in the Project conspired and colluded with accused Nos.6, 7 and 9, contractors for obtaining the work of timbering/shoring in favour of accused Nos.6, 7 and 9 and without doing that work, forged the measurement book (M.Book) by making **CRL.RP.1683, 1779 & 1780 OF 2009** **-: 2 :-** false entries with reference to the measurement of the work which was actually not done, cheated the Government and made unlawful gain for themselves and thereby committed the offences. Accused No.1 was connected with the Project work from 25.2.1994 to 8.11.1996; accused No.2 from 9.1.1991 to 29.11.1993; accused No.3 from 14.2.1994 to 12.2.1997; accused No.4 from 3.1.1994 to 30.6.1995; accused No.5 from 1.4.1992 to 17.11.1998 and accused No.8 from 29.11.1993 to 25.2.1994. It is contended by learned counsel for accused that records do not even prima facie show that any offence is committed by these accused. Learned counsel contended that as per PWD manual and Kerala Standard Specifications timbering/shoring has to be done for trenches beyond the depth of two metres to prevent sliding of earth. It is also submitted by learned counsel that page 89 of the file produced by the prosecution would show that datas of timbering/shoring work given. Further contention is that learned Special Judge has not referred to the relevant records while holding that there is sufficient ground to proceed against these accused. At any rate so far as accused No.2, Executive Engineer is concerned he has only forwarded the estimate proposal for timbering/shoring work to his superior Officer, the Superintending Engineer and hence he cannot be prosecuted for any **CRL.RP.1683, 1779 & 1780 OF 2009** **-: 3 :-** of the offences. Learned counsel submitted that court cannot act as a Post Office and has to peruse records before concluding that there is sufficient ground to proceed against the accused. Learned Prosecutor appearing for respondent contend that there is sufficient materials on record to show that there is sufficient ground to proceed against the accused. 3. Charge is that timbering/shoring work was unnecessary and actually not done, but records were manipulated to make it appear that such work was done and the accused thus made unlawful gain to themselves, unlawful loss to the Government and cheated the Government. Now what is required to be considered is whether there is sufficient ground to proceed against these accused. 4. Relevant decisions on the point say that at the stage of framing charge court is not expected to go deep into the probative value or acceptability of the materials produced. Instead court has to form a presumptive opinion as to the existence of factual ingredients constituting the offences alleged (see **Onkar Nath Mishra and Others v. State** - (2008) 1 SCC (Cri.) 507). At the time of framing charge it is sufficient that a grave suspicion is made out against the accused. I shall consider whether such materials are available on **CRL.RP.1683, 1779 & 1780 OF 2009** **-: 4 :-** record to form a presumptive opinion that there is ground to proceed against these accused. 5. Accused No.1 was the Executive Engineer connected with the Project. He is stated to have executed the agreement with the contractors concerned for the impugned work. Accused No.2 is the Executive Engineer who along with his own report forwarded the estimate proposal for the impugned work. Accused No.3 is the Assistant Executive Engineer who is said to have checked the measurement. Accused No.5 is the Chief Engineer who approved the estimate and issued technical sanction (after quotations were invited). Accused No.8 is the Assistant Engineer who signed the quotation notice. It is not disputed that sealed quotations for the work was invited on 18.2.1994 even before granting technical sanction for the work on 19.2.1994. Official witnesses questioned by the Vigilance Officials have opined that quotations should have been invited only after obtaining technical sanction. It is not proper to have invited quotations even before technical sanction was obtained. 6. C.W.1 is the Assistant Engineer of P.W.D. who inspected the site along with the Deputy Superintendent of Police (Vig.) and others from chainage 184m to 219m on the right flank. After perusing the relevant file he sated that the file revealed that after calling tender **CRL.RP.1683, 1779 & 1780 OF 2009** **-: 5 :-** for the work Executive Engineer suo moto initiated a proposal to arrange the work departmentally on piece work basis 35% above the scheduled rate and accordingly quotations were invited on 18.2.1994. He also stated that the base width of the excavation trenches is about 30 metres and sides of trenches are sloped at 45 **[o ]** angles. According to the guidelines and specifications for timbering/shoring work the item of shoring work could not be paid in the present case. He stated that it is difficult to convince how bottom planks would support on both sides which is at 1:1 slope. If plank shoring is provided it would be the earth at slope that would be supporting the plank and not otherwise. As per the Kerala Standard Specifications timbering/shoring for trenches is to be provided only for sides of trenches that are vulnerable for collapse and sides of trenches are to be prevented from collapsing by stepping. C.W.1 found that the provision for timbering/shoring for a surface which is not expected to collapse is superfluous and absolutely not required and hence provision for timbering/shoring was considered unnecessary in this case. C.W.1 has also given a detailed report to that effect. In that report he has stated that the details observed during verification do not indicate any change in levels when compared to the actuals at site. It may be remembered that complaint was received and investigated **CRL.RP.1683, 1779 & 1780 OF 2009** ## **-: 6 :-** much after the entire work was completed and hence there was no possibility of physically verifying whether shoring/timbering work was actually done. That could be decided only from the facts and circumstances of the case. 7. C.W.2 is also an Engineer who had been with C.W1 for the purpose of excavation. He was also of the opinion that on inspection it was revealed that timbering/shoring work was not necessary. 8. C.W.4 is Executive Engineer of the Project. He, after referring to the files stated that the Tender Committee had recommended that shoring working has to be completed before monsoon of 1994. But the file does not show that work was done before monsoon. It is seen that no action was taken by the Engineers concerned against the contractor for non-completion of the work. 9. C.W.11 is the Assistant Executive Engineer of the P.W.D. building sub division. He examined the relevant file and stated that it related to the work on foundation excavation on the right flank from 184mt. to 219 mt. But the datas for timbering/shoring work are not seen mentioned (learned counsel for accused pointed out that in page 89 of the file datas for the shoring work are given). I have found in pages 89 and 90 of the file that datas of timbering/shoring work are given but I am unable to say that it is in connection with the work of **CRL.RP.1683, 1779 & 1780 OF 2009** ## **-: 7 :-** the right flank. It is stated by C.W.11 that what is stated in page 89 is the sub datas of foundation excavation work and that sub items (a) to (c) did not show that datas for shoring work were included. C.W.11 has also stated after referring to the file that the rate of foundation excavation work was fixed (page 105 of the file) as per the soil boring chart and as per that chart classification of the soil is made as ordinary soil, hard soil, ordinary rock, etc. File stated that nature of the soil was identified after soil testing. There is specification as per PWD manual (el. 4:1:2) for trenching beyond the depth of two metres and shoring work is needed. Estimate for the timbering/shoring work was prepared as per 1992 schedule. He stated that estimate proposal will be sent to the Tender Committee only after getting technical sanction (unlike in these cases where estimate was prepared and even tenders were invited before obtaining technical sanction). PWD manual does not show that timbering/shoring work is incidental to the main work. In these cases technical sanction was obtained only on 19.2.1994 after the Tender Committee approved the estimate. That is not the proper course or procedure. 10. C.W.14 is the Chief Engineer. He referred to the relevant file and stated that (in page 55 of the file) timbering/shoring work is shown as a separate item and rate of Rs.4546 per meter square is **CRL.RP.1683, 1779 & 1780 OF 2009** **-: 8 :-** fixed. For any work proposal will be sent to the Tender Committee only after obtaining technical sanction. In this case technical sanction was accorded on 19.2.1994. 11. Two other witnesses relied on by the prosecution are C.Ws.3 and 7. C.W.3 is a resident near the Project area and sated that he was engaged in the work of cement loading in the Project area during 1979-98. He was working on the left flank adjacent to the Dam. He was very much there during the time of earth work and used to watch the work on the right flank. He would say that during 1995-96 he had not seen any sliding of earth from the sides. He has never seen any timbering/shoring work done to prevent soil erosion. Concrete work was being done there. 12. C.W.7 is also a resident near the Project area. He stated that he used to graze his cattle in the Project area every day during 1996-97 when the work was in progress. He used to watch the progress of work. He would say that about 1.80 acres of land belonging to him had been acquired for the Project. There was concrete work being done at very depth of the trench but he had never seen timbering/shoring work to prevent soil erosion. 13. Learned counsel for the accused contends from the relevant provisions of the P.W.D manual and Kerala Standard **CRL.RP.1683, 1779 & 1780 OF 2009** ## **-: 9 :-** Specifications that in any case trenching beyond the depth of 2 metres timbering/shoring is necessary to prevent sliding and consequent danger. Learned counsel contends that it is in accordance with that stipulation that the work was done. Learned counsel submitted that senior officials of the department are being prosecuted for the work they have bona fide carried out in public interest. Learned counsel contends that statements of C.Ws.3 and 7 could not be taken for face value to prosecute senior officials of the department. 14. The circumstances that emerged from the materials on record are that according to C.Ws.1 and 2, Engineers of PWD department timbering/shoring was not essential in this case. They also stated that considering the slope at which the trenches were made, timbering/shoring work was not essential as there was no possibility of soil erosion. They have given reasons for concluding so. Another fact which is not disputed is that the estimate proposal should have been prepared only after technical sanction was obtained but in this case estimate was prepared, forwarded to the Tender Committee and the estimate was approved and even tender notice was issued before technical sanction was obtained. According to the learned counsel that is only a procedural irregularity. But the fact that **CRL.RP.1683, 1779 & 1780 OF 2009** ## **-: 10 :-** technical sanction was obtained only later is to be taken into account along with other facts and circumstances relied on by the prosecution. It is stated in the evidence of C.W.11 that datas for the timbering/shoring on the right flank is not contained in the file (I referred to page 89 of the file where there is some reference to the datas of timbering/shoring work). There is also statements of C.Ws.3 and 7 who had occasion to be at the Project area during the relevant time that no timbering/shoring work was actually done. 15. At this stage court is not required to consider the acceptability or probative value of the statements of C.Ws.3 and 7. That is a matter to be decided after examination of the witnesses. Now it is not as if there is no materials to prima facie show that timbering/shoring work was not done. 16. So far as Accused No.2 is concerned it is argued that he has only forwarded the estimate proposal to his Superior Officer and he has worked at the Project area only for a short period. I have gone through the file and find that it is not as if accused No.2 merely forwarded the estimate proposal. It is seen from the file that he has sent his own report while forwarding the estimate proposal. 17. I have gone through the records and I am unable to accept the contention that there is no sufficient ground to proceed against the **CRL.RP.1683, 1779 & 1780 OF 2009** **-: 11 :-** accused. As I stated above, it is sufficient that a strong suspicion is made out against these accused to frame charge. As such contention of learned counsel that learned Special Judge went wrong in framing charge against petitioners cannot be accepted. There is no merit in these revisions and they are liable to be dismissed. Revision Petitions are dismissed. **THOMAS P.JOSEPH, JUDGE.** vsv
End of Judgment Record
Browse All High Court of Kerala (2009) Decisions
2009-06-26

Nishana Mol.N v Alappuzha Municipality & Secretary, Alappuzha Municipality

This writ petition concerns the registration of a marriage under the Kerala Registration of Marriages (Common) Rules, 2008 (Common Rules). The petitioner Nishana Mol.N, whose marriage was solemnized on 8 March 2009, sought registration of her marriage by the Local Registrar. Her husband was abroad, and she submitted Form No. 1 along with documents; however, the Local Registrar demanded the presence of both spouses for registration, a point contested by the petitioner. The court recalls the apex court’s directions in Seema v. Ashwani Kumar (2006) to frame rules ensuring compulsory registration to protect women and provide evidence of marriage, while noting that registration under the Rules does not itself create a marriage but evidences one solemnized otherwise. The Rules specify that registration is mandatory for marriages solemnized within the state, with various procedural requirements (Rules 5, 6, 9, 10, 11, 13, 16, 17) and mechanisms for correction, appeal, and re-registration. The court clarifies that the presence of both parties is not ordinarily required; the registrar may require appearance only in cases where there is reasonable doubt about identity, and even then as an exception rather than a rule. Ultimately, the court directs that registration and certificate issuance be completed within one month from copy of the judgment, without insisting on joint appearance, provided the memorandum is in order.

2009-07-27

Abdul Majeed Kalathil v. District Collector, Malappuram & Others

This batch of writ petitions concerns the constitutional validity of Section 17 of the Kerala Anti-Social Activities (Prevention) Act, 2007, and the power of District Magistrates to confiscate vehicles used in anti-social activities. The petitions challenge the absence of a substantive prohibition against using vehicles for anti-social activities and the lack of a defined procedure for confiscation or an appellate remedy. In W.P.C. No. 9925 of 2009 (the lead case), Abdul Majeed Kalathil contends that his goods carriage KL 11-B/6651 was seized by the Sub Inspector of Pandikkad Police and reported to the District Collector, Exts.P1–P2. The court scrutinizes Section 17's scope, defining anti-social activity (Section 2(a)) and whether the District Collector’s power to confiscate is constitutionally tenable. It finds Section 17 to be vague and violative of Articles 14, 19(1)(g) and 21, as it rests on subjective police satisfaction with no clear standards or process. It also notes environmental objectives but concludes that fundamental rights must prevail. The court does not sustain confiscation under Section 17; instead, it directs that such vehicles be dealt with under the Kerala Protection of River Banks and Regulation of Removal of Sand Act, 2001 and Rules, with interim release under specified conditions. It further directs initiation of Sand Act proceedings within a month and finalization within another month. The writ petitions are disposed of accordingly, preserving the rule of law and environmental protection.

2009-06-11

WA No. 671 of 2006 (Fertilizers and Chemicals Travancore Ltd v Union of India)

This writ appeal concerns the pay revision and pensionary benefits of employees of the Fertilizers and Chemicals Travancore Ltd (FACT). The long-term settlement covering terms of employment expired on 31 December 1996. A fresh settlement was concluded (notified 28 August 2001) and made retroactive to 1 January 1997, with revisions in wages and benefits. Clause 29 of Ext. P1 provides that arrears relating to wage revision and dearness allowance for the period 1 January 1997 to 30 June 2001 will be reviewed and decided by management/government only when the company earns profits for at least three consecutive years; Clause 33.1 provides that employees who retired on or after 1 January 1997 will be eligible for arrears calculated from 1 January 1997 to the date of retirement, subject to adjustments for interim relief already paid, with any unclaimed amount transferred to a Welfare Fund. The appellants—the retirees who fall in the 1 January 1997 to 1 July 2001 window—argue that they were denied arrears and were paid pensionary benefits at pre-revised rates, creating discrimination. Respondents contend Ext. P1 binds the parties and arrears depend on profits, and that pay revision administered to others does not compel retroactive change. The court held that Ext. P1 terms survive as terms of employment and directed the management to consider terminal benefits at revised rates within two months and to release arrears when paid to current workers, with connected matters following."

2009-05-29

M/S. Palm Fibers & Yars Trading Co. v. State of Kerala & Others

The petitioner, a Small Scale Industrial unit, ran two LT power connections (No.13070 and No.13427) with commercial production starting in July 1994 and July 1995. On 06/02/1992, the Government issued Ext.P1 guaranteeing concessional tariffs (pre-1992 tariff) for five years from the date of commencement or substantial capacity expansion, certified by the District Industries Centre. Ext.P2 certified eligibility for this concession. Subsequently, the petitioner increased power demand to 300 KVA and was reclassified/advised to HT status from 15/05/1998, converting LT supply to HT. The petitioner argued that Ext.P1 benefits should extend for the full five-year period, covering the LT quantities certified in Ext.P2, and that the HT conversion was a mere reclassification directed by the Board, not a cessation of eligibility. The Board argued Ext.P1 targets only those who commenced production during 1992–1996 and that HT conversion from 15/05/1998 falls outside the Ext.P1 window, rendering the petitioner eligible only up to 15/05/1998. Earlier orders (Ext.P3) had set aside a cut-off date for merits, and Ext.P6/Ext.P4 handled appeals. Ultimately, the Court held that the HT conversion was outside Ext.P1’s period, but directed that the LT benefits for the two LT connections be extended only until 23/05/1998 (LT dismantling date) and without reimbursement from the Industries Department, as held in OP No.7622/1998. The petition was disposed of as above.