Tenetowl LogoTenetowl
High Court of KeralaKerala High Court · 2009Single JudgeWrit Petition dismissed.

Suresh Babu v. Mohammed Aseem, Haleema Naina, VK Haris and Aluva Municipality

Case / Petition Number:
WP(C).No. 37163 of 2008(Y)

Case Synopsis & Summary

The writ petition challenges Exts. P10 and P11, orders passed in Execution Petition No. 4/08 in O.S. No. 278/02 of the Munsiff Court, Aluva. The original suit, filed in 2002, sought both prohibitory and mandatory injunctions against the demolition of a bunk shop placed illegally on A schedule property, owned or claimed by the decree holders; the decree directed the first judgment debtor (the Aluva Municipality) to demolish the bunk shop and to restrain the defendants from operating it after demolition. When the Municipality failed to comply, the decree holders sought to enforce the decree by demolition through the Amin, and the execution court appointed a commissioner to identify and supervise the demolition (EA 161/08, P7; P8 order). The second judgment debtor argued that the B schedule bunk shop identified in the plaint and decree bears a specific number, while the shop placed for demolition under Exts. P10 and P11 is of a different number or location; he also highlighted related litigations asserting his alleged rights to a different bunk shop. He sought appointment of a commission to determine identity before demolition. The High Court rejected these objections, holding that the purpose of execution is to obtain the fruits of the decree and that technical identity disputes cannot defeat the decree; the petition is dismissed. The court relies on a liberal interpretation of execution to prevent futile proceedings and to ensure enforcement of the decree.” ,

Precedent Explorer

Find Cases Like This

Explore other judgments dealing with similar legal situations, facts, or statutory provisions.

Case Details & Bench

Court
High Court of Kerala
Hon'ble Judges
  • S.S. Satheesachandran
Judgment Date
2009-08-10
Court Decision / Holding
Writ Petition is devoid of any merit, and it is dismissed.
Final Disposition
Writ Petition dismissed.

Parties to the Case

Appellants / Petitioners

  • SURESH BABU

Respondents

  • SRI. MOHAMMED ASEEM
  • SMT. HALEEMA NAINA
  • SRI.V.K. HARIS
  • THE ALUVA MUNICIPALITY

Legal Representation & Advocates

Counsels for Petitioners

  • • A. Jayasankar
  • • Manu Govind

Counsels for Respondents

  • • A. Vijayakumar
  • • V. M. Kurian

Provisions of Law Cited

Article 227 of the Constitution of IndiaCode of Civil Procedure, Order XXI Rule 97

Legal Doctrines & Maxims

  • The purpose of execution proceeding is to enable the decree holder to obtain the fruits of his decree.
  • The policy of law is to give a fair and liberal and not a technical construction enabling the decree holder to reap the fruits of his decree.

Submissions & Arguments

Contentions of Appellants / Petitioners

The petitioner contends that the identity and number of the bunk shop to be demolished under the decree are disputed. The B schedule bunk shop described in the plaint and the decree is alleged to differ from the structure proposed for demolition under Exts. P10 and P11, and an independent determination of identity is essential before execution. The petitioner seeks appointment of a commission (EA 161/08) to identify the correct shop and challenges Exts. P8, P10 and P11 in light of a prior Writ Petition (W.P.C. 30104/08) and the ongoing dispute over his alleged rights to another bunk shop. He argues that without a clear identity, demolition would be improper or pointless.

Contentions of Respondents

The decree holders argue that the decree is enforceable against the first judgment debtor (the Municipality) and that the second judgment debtor cannot resist execution simply by disputing identity. They emphasize that the identity dispute cannot defeat the fruits of the decree and that the execution court correctly ordered demolition or removal of the bunk shop under the decree, with appropriate supervision. They contend that Ext.P8 was rightly upheld earlier and that any further scrutiny should not impede the enforcement of the decree.

Legal Doctrine & Issue Explorer

Explore This Legal Issue

Find relevant judgments and authoritative positions on the legal questions discussed here.

Cited Precedents (1)

Case NameCitationTreatmentExplanation
Deep Chand and others v. Mohan Lal(2000) 6 S.C.C. 259PositiveCited to illustrate that execution should enable the decree holder to obtain the fruits of the decree and that the policy of law favors a fair, liberal interpretation over technicalities.
Case Applicability Diagnostic

Apply This to My Facts

Share your situation and test whether this judgment governs, supports, or challenges your case.

Official Judgment Record
•2,173 words•~10 min read

In The Court Record

Suresh Babu v. Mohammed Aseem, Haleema Naina, VK Haris and Aluva Municipality

## **IN THE HIGH COURT OF KERALA AT ERNAKULAM** **PRESENT :** **THE HONOURABLE MR. JUSTICE S.S.SATHEESACHANDRAN** **MONDAY, THE 10TH AUGUST 2009 / 19TH SRAVANA 1931** **WP(C).No. 37163 of 2008(Y)** **-------------------------OS.278/2002 of MUNSIFF COURT,ALUVA** **....................** ## **PETITIONER(S):** **-------------------------** **SURESH BABU, S/O. KUMARAN, THACHETTU HOUSE, ASOKAPURAM, ALUVA.** **BY ADVS. MR.A.JAYASANKAR, MR.MANU GOVIND.** **RESPONDENT(S):** **----------------------------** **1. SRI. MOHAMMED ASEEM, S/O. KUNJALI NAINA, VEZHAPPILLY HOUSE, PALACE ROAD, ALUVA.** **2. SMT. HALEEMA NAINA, W/O. KUNJALI NAINA, VEZHAPPILLY HOUSE, PALACE ROAD, ALUVA.** **3. SRI.V.K. HARIS, VEZHAPPILLY HOUSE, PALACE ROAD, ALUVA.** **4. THE ALUVA MUNICIPALITY, REPRESENTED BY ITS SECRETARY, ALUVA - 683 102.** ## **R1 TO R3 BY ADV.MR.A.VIJAYAKUMAR** - **R4 BY ADV.MR.V.M.KURIAN** **THIS WRIT PETITION (CIVIL) HAVING BEEN FINALLY HEARD ON 03/08/2009, THE COURT ON 10/08/2009 DELIVERED THE FOLLOWING:** _Kss_ ## **WPC.NO.37163/2008 Y** ## **APPENDIX** ## **PETITIONER'S EXHIBITS:** - **P1: COPY OF JUDGMENT DTD. 30/09/2004 IN O.S.278/02.** - **P2: COPY OF DECREE IN O.S.278/02.** - **P3: COPY OF EXECUTION PETITION 4/08 IN O.S.278/02.** - **P4: COPY OF OBJECTION DTD. 14/03/08 BY PETITIONER (JD2) TO EXHIBIT P3.** - **P5: COPY OF COMMISSION APPLICATION DTD. 28/08/08 MADE BY COUNSEL FOR R1-R3 (DH) AS EA 151/08 IN EP 4/08.** - **P6: COPY OF OBJECTION DTD. 29/08/08 BY PETITIONER (JD2)TO EXHIBIT P5.** - **P7: COPY OF COMMISSION APPLICATION DTD. 22/09/08 IN E.A.161/08 IN EP 4/08.** - **P8: COPY OF ORDER DTD. 29/09/08 IN EP 4/08 IN O.S.278/02.** - **P9: COPY OF JUDGMENT DTD. 24/11/08 IN WPC. 30104/08.** - **P10: COPY OF ORDER DTD. 02/12/2008 IN E.A.161/08 IN EP 4/08 IN O.S.278/02.** - **P11: COPY OF ORDER DTD. 02/12/08 IN E.P.4/08 IN O.S.278/02.** ## **RESPONDENT'S EXHIBITS:** - **R1(A): COPY OF THE PLAINT IN O.S.278/02 OF MUNSIFF'S COURT, ALUVA.** - **R1(B): COPY OF THE CERTIFICATE ISSUED BY THE 4TH RESPONDENT REGARDING THE OLD WARD NO. AND THE PRESENT SY.NO.** - **R1(C): COPY OF .A.226/08 IN E.P.4/08 FILED BY THE OBSTRUCTOR UNDER O.21 R.97.** **R1(D): COPY OF THE W/S. IN O.S.278/02 BY THE WRIT PETITIONER.** **/TRUE COPY/** **P.S.TO JUDGE** _Kss_ ## **S.S. SATHEESACHANDRAN, J.** **- - - - - - - - - - - - - - - - - - - - - - - - -** W.P.(C) No. 37163 of 2008 **- - - - - - - - - - - - - - - - - - - - - - - - -** Dated: 10[th] August, 2009 ## **JUDGMENT** The Writ Petition is filed seeking the following relief: “To quash Ext.P10 and P11 orders dated 2.12.2008 in E.P.4/08 in O.S.No.278/02 and direct the same to be reconsidered in accordance with law.” 2. Petitioner is the 2[nd] judgment debtor in E.P.No.4 of 2008 in O.S.No.278 of 2002 on the file of the Munsiff Court, Aluva. The respondents 1 to 3 are the plaintiffs/decree holders, and the 4[th] respondent is the first defendant/first judgment debtor, which is a local authority. The above suit was for injunction both prohibitory and mandatory. Mandatory injunction was sought for to demolish B schedule structure, a bunk shop, alleged to have been illegally put up by the second defendant in a portion of A schedule belonging to the plaintiff, and prohibitory injunction was sought for to restrain the defendants from operating that bunk shop after such demolition. Both the defendants resisted the suit claim filing separate written statements. Suit after trial was decreed and the first defendant/local authority was directed by a decree of mandatory injunction to remove the illegally constructed B schedule bunk shop, and both the W.P.C.No.37163/08 - 2 - defendants by a decree of prohibitory injunction from operating that bunk shop after such demolition. The decree, on failure of the first defendant to demolish the structure, allowed the plaintiffs to get it removed through the process of court and realise the cost. The aforesaid execution petition was filed on default of the first defendant-local authority to comply with the decree of mandatory injunction directing the removal of the structure. The second judgment debtor resisting the execution petition filed objections and moved a commission application as E.A.No.161 of 2008 to determine certain matters. P7 is the copy of that application. The decree holder moved an application for appointment of a commission as E.A.No.151 of 2008 to oversee the demolition of the structure in execution of the decree with the assistance of the Amin. The execution court allowed the application of the decree holder for appointment of a commission to supervise the demolition. P8 is the copy of that order. The application moved by the second judgment debtor for appointment of a commission was dismissed by Ext.P10 order. P11 order was passed by the court deputing the Amin to demolish the structure under the supervision of the Advocate Commissioner. The 2[nd] judgment debtor has filed the Writ Petition challenging the propriety and correctness of P10 and P11 orders invoking the supervisory jurisdiction vested with this court under Article 227 of the Constitution of India. W.P.C.No.37163/08 - 3 - 3. I heard the learned counsel for the petitioner and also the respondents 1 to 3, the decree holders. Learned counsel for the petitioner/2[nd] judgment debtor canvassed arguments before me impeaching the propriety and correctness of P10 and P11 orders with reference to the identity of B schedule bunk shop contending that under the decree executed another bunk shop having a different number as distinct from the number shown in the B schedule in the plaint and also in the decree is proceeded to be demolished by virtue of P11 order passed by the executing court. Determination of the identity of the bunk shop under the decree by allowing P7 commission application by the 2[nd] judgment debtor is essential before any further step is taken for execution of the decree, according to the counsel. Reference is also made to some other litigations pending in which right, title and possession of 2[nd] judgment debtor over a bunk shop having a different number other than that stated in 'B' schedule, and that is yet to be adjudicated, is also highlighted by the counsel to contend that appointment of a commission as sought for under P8 application to identify the decree schedule bunk shop earmarked for demolition before the decree is being executed is essential to advance the ends of justice. Learned counsel for the decree holders, on the other hand, contended that there is no merit in the objections raised by the 2[nd] judgment debtor and he is incompetent even to resist the W.P.C.No.37163/08 - 4 - decree as the decree of mandatory injunction is issued against the first judgment debtor, the local authority, to demolish the bunk shop which had been illegally put up in a portion of A schedule property belonging to the decree holders. 4. Though the reliefs in the petition are confined to challenges against P10 and P11 orders as referred to above, it is surprising to note that the attempt of the petitioner/2[nd] judgment debtor is to reopen P8 order passed earlier by the execution court which had been challenged before this court by him and found against in W.P.C.No.30104/08. Disposing of that Writ Petition of the 2[nd] judgment debtor, this court has held thus: “Second judgment debtor has no voice in the matter to resist execution of the executable portion of the decree which is as against the first judgment debtor only. All the same, if he is still unauthorisely conducting business in the structure illegally constructed in 'B' schedule property, he has to be removed forcibly if need be while demolishing the building. There is absolutely no merit in this Writ Petition praying for Ext.P8 order being quashed. The petitioner/second judgment debtor is not entitled to any relief and this Writ Petition deserves only to be dismissed.” W.P.C.No.37163/08 - 5 - Pursuant to the dismissal of that Writ Petition upholding Ext.P8 order passed by the court below, it is seen, as ground No.B in the Writ Petition the petitioner/2[nd] judgment debtor has raised a challenge as follows: “Exts.P8, P10 and P11 orders are against facts, law and circumstances of the case. The findings entered into are factually incorrect and legally inadmissible. Same are based on surmises and conjunctures.” Needless to point out, whatever be the challenge of the petitioner against Ext.P8 order, it cannot be countenanced and deserve to be taken note of only for its rejection in the light of P9 judgment rendered by this court. Though the learned counsel for the petitioner/2[nd] judgment debtor made strenuous and forcible arguments to canvass that the conclusion formed in P9 judgment in the previous Writ Petition will no way affect that judgment debtor in challenging P10 and P11 orders, I am not persuaded to accept the submission. It is interesting to note that in the plaint, a copy of which is produced by the decree holders, B schedule is described as a bunk shop bearing No.XVIII/433 taking an approximate area of about 8 square metre. The allegations raised in the plaint would show that it is placed in plaint A schedule property over which the plaintiffs claimed title and possession to seek decree of mandatory and W.P.C.No.37163/08 - 6 - prohibitory injunction for removal of the bunk shop and to restrain the defendants from putting up any bunk after removal of B schedule bunk shop. However, in the light of the defence canvassed by the second judgment debtor setting up right, title and possession over 200 square links contending that his bunk shop with different number is situate therein, it appears, in the judgment while negativing and ruling out his contentions, plaint B schedule had been described as a portion of the property taking in a bunk shop as situate in 8 square metres of land in a portion of A schedule. P1 is the copy of the judgment. However, it is noticeable from P2 decree, B schedule is a the bunk shop, taking an approximate area of 8 square metres, bearing AMC 18/433. Any dispute over the identity of the bunk shop by the second judgment debtor raking up the contentions advanced earlier in his written statement which were found against him and negatived by the court after trial on the plea that the bunk shop with a different number as situate in 200 square metres property on which he has got absolute title and possession is bereft of any value and, further, cannot at all be countenanced. He is bound by the decree and it is not open to him to set forth challenges as to the identity of the bunk shop showing that he is in possession of a different bunk shop in a property under his ownership to resist the decree. Whatever be the litigations pending in respect of his claim W.P.C.No.37163/08 - 7 - over the bunk shop in which he has put up a right of ownership, that will not enable him to resist the execution of the present decree and prevent the decree holders from enjoying the fruits of that decree. In this context, it is appropriate and profitable to refer to the decision rendered by the apex court in **Deep Chand and others v. Mohan Lal** [ (2000) 6 S.C.C. 259] which read thus: “The purpose of execution proceeding is to enable the decree holder to obtain the fruits of his decree. In case where the language of the decree is capable of two interpretations, one of which assists the decree holder to obtain the fruits of the decree and the other prevents him from taking the benefits of the decree, the interpretation which assists the decree holder should be accepted. The execution of the decree should not be made futile on mere technicalities which does not, however, mean that where a decree is incapable of being executed under any provision of law it should, in all cases, be executed notwithstanding such bar or prohibition. A rational approach is necessitated keeping in view the prolonged factum of litigation resulting in the passing of a decree in favour of a litigant. The W.P.C.No.37163/08 - 8 - policy of law is to give a fair and liberal and not a technical construction enabling the decree holder to reap the fruits of his decree.” The executable decree passed by the court, as pointed out by the court, is against the first judgment debtor to the local authority mandating it to remove the bunk shop placed illegally in a portion of the A schedule property of the decree holders. Even assuming that the number of the bunk shop in that property is found to be different, as and when Amin visits the property, it is liable to be demolished and removed in the light of the decree passed by the court. The execution court has to take appropriate and necessary steps to execute the decree, if essential by ordering police aid, if applied for by the decree holders, where it is prima facie shown that the local authority, despite a decree of mandatory injunction being passed against it has not complied with the decree. Writ Petition is devoid of any merit, and it is dismissed. srd ## **S.S. SATHEESACHANDRAN, JUDGE**
End of Judgment Record
Browse All High Court of Kerala (2009) Decisions
2009-06-26

Nishana Mol.N v Alappuzha Municipality & Secretary, Alappuzha Municipality

This writ petition concerns the registration of a marriage under the Kerala Registration of Marriages (Common) Rules, 2008 (Common Rules). The petitioner Nishana Mol.N, whose marriage was solemnized on 8 March 2009, sought registration of her marriage by the Local Registrar. Her husband was abroad, and she submitted Form No. 1 along with documents; however, the Local Registrar demanded the presence of both spouses for registration, a point contested by the petitioner. The court recalls the apex court’s directions in Seema v. Ashwani Kumar (2006) to frame rules ensuring compulsory registration to protect women and provide evidence of marriage, while noting that registration under the Rules does not itself create a marriage but evidences one solemnized otherwise. The Rules specify that registration is mandatory for marriages solemnized within the state, with various procedural requirements (Rules 5, 6, 9, 10, 11, 13, 16, 17) and mechanisms for correction, appeal, and re-registration. The court clarifies that the presence of both parties is not ordinarily required; the registrar may require appearance only in cases where there is reasonable doubt about identity, and even then as an exception rather than a rule. Ultimately, the court directs that registration and certificate issuance be completed within one month from copy of the judgment, without insisting on joint appearance, provided the memorandum is in order.

2009-07-27

Abdul Majeed Kalathil v. District Collector, Malappuram & Others

This batch of writ petitions concerns the constitutional validity of Section 17 of the Kerala Anti-Social Activities (Prevention) Act, 2007, and the power of District Magistrates to confiscate vehicles used in anti-social activities. The petitions challenge the absence of a substantive prohibition against using vehicles for anti-social activities and the lack of a defined procedure for confiscation or an appellate remedy. In W.P.C. No. 9925 of 2009 (the lead case), Abdul Majeed Kalathil contends that his goods carriage KL 11-B/6651 was seized by the Sub Inspector of Pandikkad Police and reported to the District Collector, Exts.P1–P2. The court scrutinizes Section 17's scope, defining anti-social activity (Section 2(a)) and whether the District Collector’s power to confiscate is constitutionally tenable. It finds Section 17 to be vague and violative of Articles 14, 19(1)(g) and 21, as it rests on subjective police satisfaction with no clear standards or process. It also notes environmental objectives but concludes that fundamental rights must prevail. The court does not sustain confiscation under Section 17; instead, it directs that such vehicles be dealt with under the Kerala Protection of River Banks and Regulation of Removal of Sand Act, 2001 and Rules, with interim release under specified conditions. It further directs initiation of Sand Act proceedings within a month and finalization within another month. The writ petitions are disposed of accordingly, preserving the rule of law and environmental protection.

2009-06-11

WA No. 671 of 2006 (Fertilizers and Chemicals Travancore Ltd v Union of India)

This writ appeal concerns the pay revision and pensionary benefits of employees of the Fertilizers and Chemicals Travancore Ltd (FACT). The long-term settlement covering terms of employment expired on 31 December 1996. A fresh settlement was concluded (notified 28 August 2001) and made retroactive to 1 January 1997, with revisions in wages and benefits. Clause 29 of Ext. P1 provides that arrears relating to wage revision and dearness allowance for the period 1 January 1997 to 30 June 2001 will be reviewed and decided by management/government only when the company earns profits for at least three consecutive years; Clause 33.1 provides that employees who retired on or after 1 January 1997 will be eligible for arrears calculated from 1 January 1997 to the date of retirement, subject to adjustments for interim relief already paid, with any unclaimed amount transferred to a Welfare Fund. The appellants—the retirees who fall in the 1 January 1997 to 1 July 2001 window—argue that they were denied arrears and were paid pensionary benefits at pre-revised rates, creating discrimination. Respondents contend Ext. P1 binds the parties and arrears depend on profits, and that pay revision administered to others does not compel retroactive change. The court held that Ext. P1 terms survive as terms of employment and directed the management to consider terminal benefits at revised rates within two months and to release arrears when paid to current workers, with connected matters following."

2009-05-29

M/S. Palm Fibers & Yars Trading Co. v. State of Kerala & Others

The petitioner, a Small Scale Industrial unit, ran two LT power connections (No.13070 and No.13427) with commercial production starting in July 1994 and July 1995. On 06/02/1992, the Government issued Ext.P1 guaranteeing concessional tariffs (pre-1992 tariff) for five years from the date of commencement or substantial capacity expansion, certified by the District Industries Centre. Ext.P2 certified eligibility for this concession. Subsequently, the petitioner increased power demand to 300 KVA and was reclassified/advised to HT status from 15/05/1998, converting LT supply to HT. The petitioner argued that Ext.P1 benefits should extend for the full five-year period, covering the LT quantities certified in Ext.P2, and that the HT conversion was a mere reclassification directed by the Board, not a cessation of eligibility. The Board argued Ext.P1 targets only those who commenced production during 1992–1996 and that HT conversion from 15/05/1998 falls outside the Ext.P1 window, rendering the petitioner eligible only up to 15/05/1998. Earlier orders (Ext.P3) had set aside a cut-off date for merits, and Ext.P6/Ext.P4 handled appeals. Ultimately, the Court held that the HT conversion was outside Ext.P1’s period, but directed that the LT benefits for the two LT connections be extended only until 23/05/1998 (LT dismantling date) and without reimbursement from the Industries Department, as held in OP No.7622/1998. The petition was disposed of as above.