Civil Appeal Nos. 6400/2016 and 6420/2016 This matter concerns two Civil Appeals filed by Union of India against Pradeep Vinod Construction Company arising from arbitration of disputes under Railway contracts. Northern Railways awarded two contracts for miscellaneous civil engineering works; after completion, the contractor claimed further sums, which were acknowledged in a final bill and a supplementary agreement recording accord and satisfaction. The contractor invoked arbitration in respect of post-final-bill claims, and the Railways rejected the claims as referable to “excepted matters.” The High Court appointed an independent arbitrator under Section 11, bypassing Clause 64 of the General Conditions of Contract (GCC) which prescribes appointment by the General Manager (or via a prescribed panel) when named arbitrators are provided in the contract. On appeal, the Court held that when the agreement specifically provides for named arbitrators, the appointment must be in terms of the contract and the High Court’s appointment of an independent arbitrator was unjustified, citing M.P. Gupta, V.S. Engineering, and Parmar Construction Company. The Court also noted that the Amendment Act, 2015 and Section 21 considerations apply only to proceedings begun after the amendment’s effective date. It directed the General Manager to appoint an arbitrator under Clause 64(3) within one month, with a sequence of steps for filing and replying and a speedy adjudication of the claims, ideally within four months.
Civil Appeal No. 1690 of 2010 Gangaram v. State of Rajasthan deals with the legality of a projectionist appointment under the Rajasthan Cinemas (Regulation) Rules, 1959. An advertisement by Dr. S.N. Medical College and Associated Group of Hospitals in Jodhpur invited applications for a Projectionist post, requiring qualifications including a cinema projector license. Gangaram and the third respondent were the sole applicants; Gangaram was appointed. The third respondent challenged the appointment via a writ petition claiming Gangaram lacked the required license. The Single Judge dismissed the petition, but the Division Bench quashed the appointment. The core issue is whether Rule 68(2-A) permits obtaining a license within three months after appointment, or requires possession of a license on the date of appointment, for eligibility. The Supreme Court analyzed Rule 68, which provides: (1) a qualified operator must hold a certificate; (2) an operator may obtain a certificate from the Electrical Inspector within three months from appointment (with possible extension of up to two months); and (3)-(5) related formalities. The Court held that sub-rule (2-A) does not require license at the appointment date; acquiring the license within three months suffices. Since Gangaram obtained the license after appointment, his compliance was valid. The Court noted the interim status quo and that Gangaram had continued in service for years. It allowed the appeal, set aside the High Court’s judgment, and dismissed the third respondent’s writ petition without costs.
Civil Appeal Nos. 2582-2583 of 2011 This is a Civil Appeals arising from O.S.A. Nos. 299 and 300 of 2006 in the Madras High Court concerning redemption of mortgage and a permanent injunction. The original plaintiff, G. Ratna Raj, filed suit against Sri Muthukarumasamy Permanent Fund Ltd. and others. The trial court framed issues, the plaintiff examined himself as PW-1, and after his evidence the defendants were proceeded ex parte for failing to appear when the case was fixed for recording their evidence, resulting in a preliminary decree against the defendants. The defendants moved under Order 9 Rule 13 to set aside that decree, but the Single Judge dismissed the applications as not maintainable since the decree was not ex parte. The Division Bench reversed, holding the preliminary decree to be ex parte and restoring the suit, directing payment of costs. The defendants filed special leave, challenging the Division Bench order. The Supreme Court examined the applicability of the Explanation to Order XVII Rule 2, Orders 17 Rules 2 and 3, and Order IX Rule 13, noting that the Rule 2 Explanation allows discretionary action only when substantial evidence has already been recorded and a party fails to appear, and that in the present case the defendants had not led any evidence. The Court ultimately held that the Division Bench was justified, dismissed the appeals, and directed the trial court to decide the suit on merits with amendments to the cause title."
Criminal Appeal Nos.1416-1417 of 2017; with Cr. Appeal Nos.300-301/2018, 1418-1419/2017, 298-299/2018 This Supreme Court judgment pertains to Criminal Appeal Nos.1416-1417 of 2017 and connected appeals arising from the gruesome murder of Chirag Rajput, a two-year-old child, allegedly killed as a human sacrifice by the accused, Ishwari Lal Yadav and his wife Kiran Bai, who were accused of tantric practices. The prosecution’s case rests on independent witnesses who testified that, upon entering the house of the main accused following a missing child report, they found a puja area with fresh mounds of earth, a body buried in the house in two parts with severed head and missing tongue, and discs of accompanying worship items; the witnesses stated the accused confessed to the murder in the presence of the crowd. The trial court convicted the main accused under sections 364/34 r/w 120B, 302/34 r/w 120B and 201 IPC, sentencing them to death for the murder and imposing related punishments for other offences. The High Court upheld the death sentence for the two main accused and altered the sentences of other co-accused to life imprisonment. The Supreme Court, applying the Bachan Singh–Machhi Singh framework and Sushil Murmu guidelines, held that the common intent was proved only for the main accused; reliance on extra-judicial confessions was upheld when corroborated by other evidence. It set aside 364/34 and 120B convictions for the others, confirmed the 302/34 and 201 IPC convictions against the main accused, and averred that this is a rare, brutal case meriting capital punishment for the two principals, while releasing other co-accused from those convictions.
Civil Appeal No. 7939 of 2019 This Supreme Court decision addresses the policy of Institutional Preference in Post Graduate (PG) Medical admissions in Gujarat. The Gujarat University framed rules under the Gujarat University Act, 1949 to allocate 50% of PG seats as All India Quota and the remaining seats to be filled by the Admission Committee, with 4.1 giving preference to Gujarat University graduates, and 4.3 allowing other Gujarat-based graduates to be considered. The petitioners challenged these rules as violative of the Medical Council Act, 1956 and the Post Graduate Medical Education Regulations, 2000, especially in light of NEET introducing a uniform entrance test. They argued that NEET centralizes admissions and that the rules permitting Institutional Preference (50% of seats) are inconsistent with the MCI Act and NEET. The respondents contended that Institutional Preference has been repeatedly sanctioned by this Court, most notably in Dr. Pradeep Jain v. Union of India, Saurabh Chaudhri v. Union of India, and Saurabh Dwivedi v. Union of India, and remains valid even after NEET, with admissions for PG courses to be based on NEET merit while the State/University seats can still reflect institutional preference. The Court ultimately held that Institutional Preference to the extent of 50% is permissible and shall not be ultra vires to Section 10D of the MCI Act, and NEET does not affect this precedent; the matter is dismissed with no costs.
Civil Appeal No.10596 of 2010 The Goa State Cooperative Bank Ltd., acting as liquidator, challenged a Goa-based cooperative society’s winding up under the Maharashtra Co-operative Societies Act, 1960. The Registrar had ordered winding up due to misfeasance and non-recovery of loans, with the liquidator bank filing numerous recovery actions against defaulting members. The High Court of Bombay at Goa issued a writ petition declaring termination of liquidation proceedings on expiry of the fixed period under Section 109, effectively pausing recovery actions. The Supreme Court, by a Division Bench, held that termination of winding up under Section 109 cannot be read to defeat the recovery of dues; interim stays and the interim period cannot prejudice the bank. It emphasized that the recovery of public money is essential, and when a final report is submitted, the Registrar must act on it, including notifying creditors. The court clarified that even after liquidation, member liabilities and recovery actions may continue; there is no automatic termination of pending recovery proceedings upon winding up termination. The decision reinforces the restitution principle, ensuring that any interim gain from stay orders is neutralized and that the bank, as prime lender-cum-liquidator, may continue with recovery actions to safeguard public money. The High Court’s contrary view is set aside, and the appellant bank’s appeal is allowed to the extent of permitting continuation of recovery proceedings.
Civil Appeal No. 116 of 2019 This Civil Appeal arises from a partition suit instituted on 9 May 1985 in Ranchi, where a preliminary decree (1990) and a final decree (1991) confirmed the appellant’s 1/4 share. A supplementary final decree was issued in 2013 after changes in the family due to death. On 12 May 2014, the appellant sought execution of these decrees; in March 2015 the first respondent objected under Section 47 CPC, claiming the decrees were without jurisdiction and a nullity. The executing court dismissed the objection, while the High Court held that the executing court erred in not entertaining the objection and remanded for disposal. The Supreme Court, in a divided judgment, clarifies that objections to territorial jurisdiction do not travel to the root of a civil court’s inherent jurisdiction and must be raised in the court of first instance at the earliest opportunity, and only if there is a consequent failure of justice may such objections be entertained. In execution, a territorial objection does not lie, and the executing court cannot go behind the decree. The Court emphasizes that Section 21 CPC and related provisions aim to prevent merits-based reversals on technical grounds. Accordingly, the High Court’s remand is set aside, the appeal is allowed, and the executing court is directed to conclude execution expeditiously with no costs.
Civil Appeal Nos. 5753-5754 of 2011 These appeals arise from a lease dispute concerning land situated in the Bombay Suburban District. The plaintiff, Shree Krishna Woolen Mills Pvt. Ltd., claimed specific performance of a lease-deed dated 20.06.1958 and sought conveyance of the suit land. The defendant, Mahadev P. Kambekar (represented by his legal heirs), counter-claimed for eviction and arrears of rent. The Single Judge, in a decree dated 24.12.1998, granted the plaintiff’s relief for specific performance and also allowed the counter-claim, directing eviction and awarding arrears of rent for three years. The Division Bench, by its impugned judgment, set aside the decree on the counter-claim, holding it not maintainable under Section 41 of the Presidency Small Cause Courts Act, 1882. The defendant appealed, while the plaintiff challenged this aspect. The Supreme Court, in a decision authored by Justice Sapre and with Justice Reddy concurring, held that the Division Bench was correct: counter-claims of this nature are not maintainable under Section 41(1). Relying on Mansukhlal Dhanraj Jain & Ors. v. Eknath Vithal Ogale (1995) 2 SCC 665 and Prabhudas Damodar Kotecha & Ors. v. Manhabala Jeram Damodar & Anr. (2013) 15 SCC 358, the Court explained that Section 41(1) vests exclusive jurisdiction in the Small Causes Court for suits between licensor-licensee or landlord-tenant relating to possession or rent. It affirmed that the suits fall within Section 41 and rejected the counter-claim as not maintainable, directing the parties to raise factual issues before the competent court on merits. The appeals were dismissed. The decision emphasizes the exclusive jurisdiction of Small Causes Courts in Bombay for possession/rent disputes and leaves factual issues to be determined by the appropriate forum, ensuring due process for the parties.
Civil Appeal No.4282 of 2019 This Civil Appeal concerns a family property dispute in Jalna, where Shankarlal (the Karta) allegedly sold the suit house in 1965 to Bansilal Shivlal. After Bansilal’s death, the property passed to his heirs (defendants 1 and 2). In 1971, they sued Shankarlal for a declaration of title; the Trial Court, by 31 January 1975 decree, held that defendants 1 and 2 were the owners of the suit property, a decree which became final. Subsequently, two sisters of Shankarlal (the plaintiffs) filed a suit alleging that the 1975 decree and the 1965 sale were not binding on them, arguing the property was ancestral and they were entitled to a share. The plaintiffs claimed the 1965 sale lacked their consent and that the earlier decree did not bind them. All three Courts below dismissed the suit, finding the suit to be collusive, raised at the behest of Shankarlal through family members to avoid execution of the 1975 decree. The Supreme Court held that concurrent findings by the Trial Court, First Appellate Court, and High Court were binding on this Court and properly supported by evidence. It also held that the sale by the Karta for legal necessity and for the family’s benefit binds all family members, including the plaintiffs. The appeal was dismissed, with no merit found in challenging the decree or the sale.
Civil Appeal No. 2713 of 2019 This Civil Appeal arises from the arbitration clause embedded in the notice inviting tender for extension and augmentation of water supply and sewerage works. The appellant challenged clause 25(viii) of the tender, which required a deposit-at-call of 10% of the amount claimed to be deposited with the Arbitrator to enable invocation of arbitration, ostensibly to deter frivolous claims. The High Court's refusal to strike down the clause was upheld by the appellate court. The Supreme Court, however, held that the 10% deposit-at-call provision is arbitrary and violates Article 14 of the Constitution because it imposes an upfront, automatic financial burden on a party invoking arbitration, irrespective of whether the claim is frivolous. The Court emphasized arbitration as a preferred ADR mechanism to de-clog courts and reduce litigation costs, and it noted that the refundable/refundable-proportionate nature of the deposit, combined with the possibility of majority/minority awards, undermines fairness. The judgment cites numerous precedents on judicial review of tenders, the nature of arbitration, and the autonomy of contracting parties while affirming that the terms of invitation to tender are ordinarily not scrutinized unless arbitrary or mala fide. Clause 25(viii) is severed from clause 25, the High Court’s judgment is set aside, and the appeal is allowed."
Civil Appeal No. 7315 of 2016 This case concerns a claim under an insurance policy for a road resurfacing project in Nashik where the appellant undertook resurfacing, metalling and asphalting works. The policy provides ‘material damage’ cover with exclusions, including normal wear and tear, gradual deterioration due to atmospheric conditions, rust, scratching and breakage. The appellant claimed loss and damage to the roads between 25 June 2007 and 5 July 2007, later stating that heavy rainfall on 29 June 2007 caused inundation and top-layer washout. The insurer rejected the claim, citing that the loss occurred due to defective workmanship and materials and due to traffic movement on wet roads, and ultimately that the loss stemmed from monsoon rains and wear-and-tear, not an insured event. The National Consumer Disputes Redressal Commission (NCDRC) rejected the complaint, noting inconsistencies in dates of alleged damage, delay in notifying the insurer, and evidence showing only surface damage with no indication of flood-related destruction. The Surveyor’s report concluded there was surface damage with no evidence of road washing out due to floodwaters, and meteorological data indicated minimal rainfall on the claimed dates. The Supreme Court held that the appellant failed to establish a non-excluded cause of damage, and that the evidence did not contradict the policy exclusions. Consequently, the appeal was dismissed and the NCDRC’s order upheld, with no error found in the findings.
Civil Appeal No. 8349 of 2017 This appeal concerns whether the Bagyammal Trust, in relation to the Sri Swamiya Dhamodara Perumal Temple, constitutes a ‘specific endowment’ under the Tamil Nadu Hindu Religious and Charitable Endowments Act, 1959, and thus would be governed by the Act’s provisions for endowments and religious institutions. The appellant contends that the Deed of Settlement (4 June 1926) created a private/family arrangement rather than a public or specific endowment, arguing that the trust’s terms do not vest a dedicated endowment for a religious charity or for a public service under Section 6(19). The Deputy Commissioner had declared the trust a public endowment; the trial court decreed in the appellant’s favor, but the High Court reversed; a Special Leave Petition was granted to challenge the High Court’s order. The Supreme Court examines the Act’s definitions: “specific endowment” includes property endowed for a specified service or charity in a math/temple or for any other religious charity; “religious charity” means a public charity associated with Hindu festivals or religious observances. It analyzes the Deed of Settlement showing that the choultry was to be constructed for pilgrims and for public use, with encumbrance restrictions and maintenance obligations limited to the donor or her heirs. The Court ultimately holds that the choultry meets the Act’s definition of a specific endowment and dismisses the appeal, reinforcing the High Court’s reversal of the trial court.
Civil Appeal No. 3529 of 2008 This Civil Appeal concerns the proper appellate forum post repeal of the Foreign Exchange Regulation Act, 1947 (FERA) for an adjudication order under Section 51 of FERA. The appellants challenge High Court rulings that upheld the Special Director (Appeals) as the competent forum for appeals against the 05.12.2003 adjudication order, and contend that such appeals should lie before the Appellate Tribunal under FEMA (Section 19). The Supreme Court undertakes a purposive reading of the repealing legislation—FEMA and the saving and transfer provisions, especially Sections 49(5)(b) and 81(c), to determine whether pending and post-repeal appeals against orders under Section 51 of FERA must be heard by the Appellate Tribunal or by the Special Director (Appeals). It surveys the dissolution of the Appellate Board under FERA and why pending appeals were transferred to FEMA’s Appellate Tribunal to preserve a single appellate mechanism. The Court concludes that all such appeals, whether filed before or after 01.06.2000, should be adjudicated by the Appellate Tribunal under FEMA to avoid logical anomalies and ensure uniformity. Consequently, the appeals filed before the Special Director (Appeals) are transferred to the Appellate Tribunal for disposal on merits; the appeal is allowed and the impugned order set aside.
Civil Appeal No. 12251 of 2018 This decision concerns challenges to the grant of environmental clearance (EC) for a greenfield international airport at Mopa, Goa. The National Green Tribunal (NGT) upheld the EC but directed additional environmental safeguards. The appellants—Hanuman Laxman Aroskar and the Federation of Rainbow Warriors—contend that the environmental impact assessment (EIA) process under the 2006 EC Notification was flawed, relying on disclosures that were incomplete or misleading and failing to consider critical ecological concerns such as forests, wetlands, and Ecologically Sensitive Zones (ESZs) within the study area, including parts in Maharashtra. They contend that Form 1 disclosures were inadequate, that data on ESZs and forest land within 15 km were omitted, and that the Expert Appraisal Committee (EAC) abdicated its mandate by deferring to the EC decision instead of conducting a rigorous merits review under the NGT Act. The Union of India and Goa government defend the process, arguing the airport is a matter of policy and public interest, and that the EIA, ToR, and public consultations were conducted in accordance with law, with ESZ considerations addressed through guidance and Kasturirangan reports. The Court emphasizes the environmental rule of law, the primacy of transparency, accountability, and participatory decision-making, and the need for a balanced approach to development and environmental protection. It instructs the EAC to revisit EC conditions within a set timetable and suspends the EC pending further proceedings, underscoring that the means of decision-making are as crucial as the ends.
Civil Appeal No. 8766-67 of 2019 This Supreme Court decision addresses multiple Civil Appeals and Writ Petitions arising from the National Company Law Appellate Tribunal’s orders in Essar Steel’s Corporate Insolvency Resolution Process (CIRP). The Court reaffirms that the Committee of Creditors (CoC) wields commercial wisdom in deciding the viability and distribution of a resolution plan, including how funds are apportioned among creditors—secured and unsecured financial creditors, and operational creditors—while keeping the corporate debtor alive as a going concern. It rejects the NCLAT’s approach of equal treatment across different creditor classes and clarifies that equality must be interpreted within the class framework (secured/unsecured, financial/operational) and in light of Regulation 38 and related provisions. The judgment upholds the constitutionality of the Insolvency and Bankruptcy Code (Amendment) Act, 2019 (Sections 4 and 6), which modify timelines and minimum payments to operational creditors and dissentient financial creditors to ensure timely resolution and asset maximisation. The court also elaborates on the role of the resolution professional (administrative, not adjudicatory), the permissible use of sub-committees (only as delegates of the CoC and subject to final ratification), and maintains that claims decided by the resolution professional and affirmed by the adjudicating authorities are binding. The decision directs that the corporate debtor’s CIRP proceed in accordance with ArcelorMittal’s resolution plan as amended and accepted by the CoC on 27 March 2019, and it sets aside several NCLAT directions, while dismissing or partly allowing specific appeals in line with the majority’s commercial decision.
Civil Appeal No. 117 of 2019 The appellant, Sushil Thomas Abraham, filed a civil suit as an indigent person under Order XXXIII Rule 1 CPC for recovery of Rs. 74,66,107/-. The trial court rejected the plea to sue as an indigent person, and the appeal before the Kerala High Court was likewise dismissed, with a direction to pay ad valorem court fees. Subsequently, the appellant sought to file an appeal under Order XLIV Rule 1 as an indigent person, but the High Court refused. The Supreme Court held that although the trial court and High Court denied indigent status in the earlier round, this does not bar the appellant from seeking indigent status in an appeal under Order XLIV. The Court clarified that Rules 3(1) and 3(2) of Order XLIV authorize re-examination of indigence at the appellate stage, and in cases where the applicant had been declined indigent status, an inquiry can still determine whether he has become indigent since the decree. The Court remanded to the Appellate Court to conduct a fresh inquiry under Order XLIV Rule 3(2) (or via the Trial Court as directed) to decide whether the appellant should be allowed to prosecute the appeal as an indigent person. The decision emphasizes the interplay between Orders XXXIII and XLIV and the need to assess indigence afresh while ensuring payment of admissible court fees if necessary.
Special Leave Petition (Civil) No. 30335 of 2017 This Special Leave Petition concerns the legality and sequencing of compassionate appointment schemes in Indian public banking institutions. The respondent sought compassionate appointment on the death of the SBI employee in harness in 2004, but the bank introduced an ex gratia lumpsum payment scheme in 2005, declaring that compassionate appointments were abolished. The petitioned issue is whether pending applications under the old compassionate appointment scheme can still be entertained or must be governed by the new ex gratia scheme. The Supreme Court notes two conflicting lines of authority: (i) decisions holding that the scheme in force when the application is actually considered governs, effectively allowing application of the newer scheme to pending cases; and (ii) decisions holding that the governing scheme is the earlier one, with the older framework applying to pending claims unless saved otherwise. The Court observes that these principles are not reconciled and require a larger Bench to decide definitively. It also cites related cases such as SBI v. Raj Kumar (2010), MGB Gramin Bank v. Chakrawarti Singh (2014), Canara Bank v. M. Mahesh Kumar (2015), and Jaspal Kaur (2007), indicating a broader policy dispute about whether compassionate appointment is a right or a concession, and how changes in policy affect pending claims. The Registry was directed to place the papers before the Chief Justice of India for constituting a Bench of appropriate strength.
Civil Appeal No. 7130 of 2010 Syed Zainul Abedeen challenged the Rajasthan Board of Muslim Wakf's declaration that the subject Dargah property is Wakf-Al-Allah and sought a declaration that it is Wakf-Alal-Aulad. The Wakf Survey Commissioner, during the survey of wakfs under the Wakf Act, 1954, examined rival claims and concluded on 2 January 1965 that the wakf included the property and its attached lands, to be entered as Wakf-Al-Allah; the Board published the list in the Official Gazette on 2 December 1965. The appellant then filed suit on 17 January 1967 under Section 6 of the Act to obtain declarations (i) that the property is not Wakf Allah but Wakf Alal-Aulad; (ii) a Hukum Imtanai directing the Wakf Board to register the property (excluding mosque and mazar) as Wakf Alal-Aulad; and (iii) costs. All three courts held the suit barred by the statutory one-year period from Gazette publication, a finding the appellant did not dispute in pleadings. The appellant argued that the suit concerns Wakf Alal-Aulad and therefore Section 6 limitation should be governed by Article 113 of the Limitation Act (three years), and that Section 56 cannot defeat a suit. The Court held that once the property is registered as Wakf-Al-Allah, disputes about its nature must be decided within Section 6's four corners, and the proviso imposes a one-year limit; Section 113 does not apply. The appeal was dismissed.
Civil Appeal No. 6878 of 2018 This Supreme Court appeal arises from a National Consumer Disputes Redressal Commission order that dismissed the consumer complaint in limine under the Consumer Protection Act, 1986. The appellant, M/S AnjaneYa Jewellery, brought a consumer case against New India Assurance Co. Ltd. and other respondents alleging deficiency in service or unfair practice by the insurer. The Commission dismissed the complaint in limine without issuing notice to the opposite party. The appellant challenged the order under Section 23 of the Act, arguing that the matter required consideration on merits with the opportunity for the respondents to respond. The Court scrutinized whether dismissal in limine could be justified, acknowledging that post-amendment of Section 13 (as of 15.03.2003) the Commission can dismiss in limine, but such power must be exercised with regard to the facts of each case. In the instant case, the Supreme Court found that the facts did not warrant dismissal at the limine. It set aside the impugned order, admitted the complaint under Section 13, and granted the respondents one month to file their reply so that the Commission could decide the case on merits in accordance with law, avoiding prejudice from observations in prior orders. The Court emphasized fair procedure and directed remand for merits.
Civil Appeal No. 937 of 2019 This is a group of connected appeals challenging demolition notices issued by the Nagpur Improvement Trust (NIT) in the Abhyankar Road widening and Buty Mahal Street Scheme. The Scheme, framed in 1960 under the Nagpur Improvement Trust Act, provided for a 15-metre wide internal road. After the Maharashtra Regional Town Planning Act (MRTP Act), 1966 came into force, Development Plans (DPs) sanctioned under the MRTP Act did not include a 15-metre internal road. The NIT sought to implement its pre- MRTP Scheme; the State Government allotments and subsequent development approvals followed the NIT Scheme’s terms. The High Court quashed demolition notices issued by the NIT, holding that the DP under MRTP Act takes precedence and that any variation to align the Scheme must occur under the MRTP Act’s provisions (Sections 39 and 92) and/or the NIT Act’s procedures. The Supreme Court, in a common judgment on Civil Appeal No. 937 of 2019 (and related matters), held that the MRTP Act DP prevails over the NIT Scheme when in conflict, though the MRTP Act also provides for variation to harmonize the Scheme with the DP (Section 39 read with Section 92). The Court quashed the High Court’s order, allowed the appeals, and dismissed the connected transferred case and a related SLP appeal, with no costs. The decision elaborates a harmonized reading of MRTP Act Sections 39, 43, 46, 59 and NIT Act Sections 31, 39, 44(1), 45, 46.