Two million residents in western Rajasthan rely on a river system comprising Jojari, Bandi and Luni, which have suffered catastrophic pollution from textile, dyeing and steel industries and municipal sewage over decades. The Supreme Court, taking suo moto cognizance on 16 September 2025 after a documentary, broadened the inquiry to include Bandi and Luni in addition to Jojari, noting prior National Green Tribunal orders and Civil Appeals pending before this Court (Civil Appeal Nos. 5517-5519 of 2022; 8748 of 2022; 9057-9058 of 2022; 9010-9011 of 2022). The judgment underscores that environmental degradation imperils life and health and affronts constitutional guarantees, especially Article 21, and that safeguarding the environment is a constitutional duty under Articles 48A, 47 and 51A(g). It criticizes two decades of regulatory laxity and administrative inaction even as belated measures were undertaken after the Court’s intervention. It rejects the continued stay of National Green Tribunal orders as a barrier to remedial action and directs a High-Level Ecosystem Oversight Committee to supervise implementation, prepare a River Restoration Blueprint for Jojari, Luni and Bandi, map discharge points, and ensure SCADA-enabled monitoring of CETPs/STPs, Zero Liquid Discharge, and Polluter Pays enforcement. The Court requires periodic status reports, expert audits, and direct submission of plans by IITs and other institutions to the Committee, with full cooperation of authorities.
Find Cases Like This
Explore other judgments dealing with similar legal situations, facts, or statutory provisions.
Case Details & Bench
- Court
- Landmark Cases
- Hon'ble Judges
- Mehta, J.
- Judgment Date
- 2025-11-21
- Court Decision / Holding
- The interim stay on the National Green Tribunal’s final order dated 25 February 2022 is modified and clarified; the substantive remedial and regulatory directions of the Tribunal shall be implemented in full, and the stay shall continue only in respect of (i) remarks against RIICO and other authorities/ Corporations and (ii) the direction imposing environmental compensation of Rs. 2 Crores. The Court constitutes a High-Level Ecosystem Oversight Committee to supervise, coordinate and oversee the river restoration and pollution-control measures, with broad Terms of Reference to map discharge points, audit CETPs/STPs, ensure SCADA integration, enforce Polluter Pays, and coordinate expertise from IITs and other institutions. The Committee shall submit its first status report within eight weeks and thereafter every eight weeks; all affiliated authorities and units must cooperate, and expenditure incurred shall be recoverable from culpable officials or industries. All plans and audits from IITs and other institutions shall be presented directly to the Committee for implementation, with a phased, time-bound blueprint for River Restoration and Rejuvenation across Jojari, Luni and Bandi.
- Final Disposition
- Interim stay on NGT order modified/ lifted to the extent described; substantive NGT directions to be implemented; High-Level Ecosystem Oversight Committee to oversee and report; mapping of discharge points, audits, and expert plans to be channelled through the Committee; status reports due every eight weeks; compliance to be ensured with penalties for non-cooperation.
Parties to the Case
Respondents
- State of Rajasthan
- Rajasthan State Industrial Development and Investment Corporation Ltd. (RIICO)
- Municipal Council, Pali
- Municipal Council, Balotra
- Nagar Nigam, Jodhpur (Jodhpur Municipal Corporation)
- Gram Panchayat Araba
Legal Representation & Advocates
Counsels for Respondents
- • Shri Shiv Mangal Sharma, Additional Advocate General for the State of Rajasthan
Provisions of Law Cited
Legal Doctrines & Maxims
- Precautionary principle
- Sustainable development
- Inter-generational equity doctrine
- Polluter Pays principle
- Right to healthy environment as part of right to life
Submissions & Arguments
Contentions of Appellants / Petitioners
This suo moto petition represents a constitutional imperative to protect the fundamental right to life by ensuring a clean, safe and healthy environment. The Applicants (the Court as the instrumentality of justice) urge immediate, robust, science-driven remedial action. The focus is on expediting the implementation of the National Green Tribunal’s directions, enabling a unified oversight mechanism, and mandating the strengthening of pollution-control infrastructure, strict enforcement against violators, adoption of Zero Liquid Discharge where feasible, and ensuring that all plans and audits from technical institutions are rapidly operationalized. The relief sought includes lifting procedural delays, comprehensive monitoring, and ensuring Polluter Pays liability is meaningfully enforced to restore ecological integrity and public health.
Contentions of Respondents
The Respondents, led by the State of Rajasthan through the Additional Advocate General, contend that while past failures are acknowledged, corrective steps have begun and must be implemented with due regard to local administrative constraints. They seek to preserve certain interim protective features and environmental compensation as directed, while urging a staged, technically sound rollout of CETPs/STPs, robust audits, and cooperation with authorities. They emphasize deference to expert institutions, phased capacity augmentation, and a balanced approach to avoid disruption to industry, while committing to comply with constitutional obligations and to cooperate with the Court’s oversight framework.
Explore This Legal Issue
Find relevant judgments and authoritative positions on the legal questions discussed here.
Cited Precedents (5)
| Case Name | Citation | Treatment | Explanation |
|---|---|---|---|
| Subhash Kumar v. State of Bihar | 1991 (1) SCC 598 | Positive | Cited for establishing that right to life under Article 21 includes the right to a pollution-free environment; forms a foundational premise for environmental rights. |
| Virender Gaur v. State of Haryana | 1995 (2) SCC 577 | Positive | Cited for recognizing the right to a clean and hygienic environment as an integral facet of the right to life and for constitutional duties to safeguard environment. |
| M.C. Mehta v. Kamal Nath | 2000 (6) SCC 213 | Positive | Cited to link Articles 48A and 51A(g) with Article 21, emphasizing that disturbance of basic environmental elements harms life. |
| A.P. Pollution Control Board II v. Prof. M.V. Nayudu | 2001 (2) SCC 62 | Positive | Cited for evolving concept of right to healthy environment as part of right to life; recognition of third-generation environmental rights. |
| Bandhua Mukti Morcha v. Union of India | 1984 (3) SCC 161 | Positive | Cited as precedent recognizing environmental protection and livelihoods as integral to human dignity and life. |
Apply This to My Facts
Share your situation and test whether this judgment governs, supports, or challenges your case.
In The Court Record
Suo Mot0 Writ Petition (Civil) No. 8 of 2025, In re: 2 Million Lives at Risk, Contamination in Jojari River, Rajasthan
Related Decisions & Precedents from Landmark Cases
State of Himachal Pradesh & Anr. v. Pinju Ram & Others; State of Himachal Pradesh & Ors. v. Ganesh Dutt & Anr.
This batch of appeals concerns regularisation and monetary benefits of part‑time employees in Himachal Pradesh who were converted to daily‑wage status. The State had issued a policy on 27 February 2004: part‑time Class‑IV employees who had completed ten years of continuous service as on 31 December 2003 would be made daily wagers with prospective effect, and posts vacated by such employees would stand abolished; Education and Ayurveda were excluded from the policy. Revenue Chowkidars, engaged by Panchayats, were not covered by that policy and received separate treatment. Following writ petitions and an order of the Himachal Pradesh High Court and in light of later developments, the State drew‑up directions in 2011 (22 September) to give seniority to Revenue Chowkidars on the basis of ten years of service, but with wages from the date of actual appointment and without back‑dated monetary benefits; 7 July 2012 further instructions reiterated this stance for remaining part‑time employees, with monetary benefits not guaranteed in the interregnum. The respondents pressed for back wages dating from 1 January 2007 and broader coverage. The Supreme Court held that the 2007 back‑pay direction was unsustainable, clarified that seniority would count from ten years without past benefits, and that the 2011 policy and Moti Singh principle should guide the approach. The appeals are allowed; no costs. The related writ petitions are to be disposed of consistent with these directions.
Union Bank of India and Others v. C.G. Ajay Babu and Anr.
This is a Supreme Court of India appeal concerning the forfeiture of gratuity under the Payment of Gratuity Act, 1972. The respondent was a branch manager of the appellant bank and was dismissed on 3 June 2004 after disciplinary proceedings. A show-cause notice sought to forfeit gratuity due to misconduct involving moral turpitude, which was ordered on 20 April 2004. The High Court upheld the dismissal but held that gratuity could be paid since there was no financial loss to the bank, and that a bipartite settlement between the bank and employees permitted forfeiture only where misconduct caused financial loss. The Division Bench, however, held that forfeiture under Section 4(6) must be read together with Section 4(5) and that no loss was proven, thus entitling the employee to gratuity in accordance with the bipartite settlement. The Supreme Court agreed with the High Court that forfeiture is not automatic; it is controlled by Sections 4(5) and 4(6) of the Act and by the bipartite settlement, which requires loss to justify forfeiture. The Court emphasized that an act must constitute an offence involving moral turpitude and that conviction is generally required for forfeiture under 4(6)(b)(ii). The appeal is dismissed with no costs.
Reema Salkan v. Sumer Singh Salkan
This is a Supreme Court of India criminal appeal under the Criminal Appellate Jurisdiction arising from a maintenance dispute under Section 125 Cr.P.C. The parties, married in 2002, had a protracted litigation history. The Family Court granted maintenance to the wife from 17 July 2003 to 8 December 2010, and held no maintenance thereafter. The High Court, in revision, partly allowed the application, directing Rs.9,000 per month from 9 December 2010 onward, while upholding the earlier period’s Rs.10,000 per month. This Court had earlier granted interim maintenance of Rs.20,000 per month in 2014 (Criminal Appeal Nos. 2347-2349 of 2014). The appellant contends there has been no change in circumstances since the interim order and that the respondent’s substantial assets, education, and overseas earnings establish the capacity to pay higher maintenance. The respondent defends the High Court’s reasoning, arguing that the Family Court’s assessment, demeanor observations, and the principle that maintenance should not be perpetual require careful scrutiny, and that the notional minimum wage approach used by the High Court is flawed. The overarching issue is the quantum of monthly maintenance payable to the appellant and whether the interim amount should be augmented beyond the period up to 2010.”
M/s Embassy Property Developments Pvt. Ltd. v State of Karnataka & Ors.
This judgment concerns three Civil Appeals filed by a Resolution Applicant, the Corporate Debtor (through its Resolution Professional) and the Committee of Creditors, challenging an Interim Order of the Karnataka High Court staying an NCLT order in proceedings under the Insolvency and Bankruptcy Code, 2016. The NCLT Chennai had admitted an application under Section 7 of the IBC against M/s Tiffins Barytes Asbestos & Paints Ltd. and directed a moratorium under Section 14. The Interim Resolution Professional then sought a deemed extension of a mining lease under MMDR Act, 1957 and the Government of Karnataka rejected it. The NCLT, by an order dated 11.12.2018, set aside the Government’s order and directed execution of Supplement Lease Deeds for the period up to 31.03.2020. The Government of Karnataka challenged this in a High Court writ petition, which stayed the impugned NCLT order. The core issues were: (i) whether the High Court may interfere under Article 226/227 with an NCLT order in IBC when an appeal lies to the NCLAT, and (ii) whether fraud can be inquired into by NCLT/NCLAT in CIRP. The Court reiterates that IBC is a complete, umbrella code with a three‑tier mechanism (NCLT, NCLAT, Supreme Court) and that public‑law disputes arising from MMDR Act obligations lie outside IBC. It ultimately holds that while NCLT/NCLAT may inquire into fraud, they cannot adjudicate MMDR‑related public legal disputes; and the High Court’s writ jurisdiction in public‑law contexts remains permissible. The appeals are dismissed.