Subodh Singh v. Union of India and Others

Case / Petition Number:
Civil Appeal No. 6458 of 2024
Neutral Citation:[2024] 6 S.C.R. 708 : 2024 INSC 458

Case Synopsis & Summary

Subodh Singh v. Union of India and Others deals with compensation for a "left out" portion of land acquired under the Indian Railways Act, 1989. The land parcel admeasuring 0.0624 hectare was left out from an award declared on 8 February 2010 for land acquired under Notifications dated 10 June 2008 and 16 December 2008. The Allahabad High Court directed payment of compensation for this left out land along with additional compensation. The respondents initially calculated delay compensation for only two months, while the appellant urged that delay should be payable for a period of 84 months, citing a prior decision in Kamla Devi & Ors. The Supreme Court, invoking its 2011 ruling, reiterated that the second proviso to section 20F(2) of the Act requires payment of additional compensation at not less than 5% of the award value for each month of delay, and that such compensation should not be arbitrarily capped. The Court discussed that the assessment in the Kamla Devi decision and the 2011 judgment show there can be extended compensation for delay where left out land is concerned. Consequently, the Court held that the appellant is entitled to additional compensation for the left out land at least @ 5% of the value of the award for 84 months, with the amount already paid for two months to be adjusted, and the balance plus 7% simple interest to be released within eight weeks, while each side bears its own costs.

Precedent Explorer

Find Cases Like This

Explore other judgments dealing with similar legal situations, facts, or statutory provisions.

Case Details & Bench

Court
Supreme Court of India
Hon'ble Judges
  • Hima Kohli
  • Ahsanuddin Amanullah
Judgment Date
2024-05-16
Court Decision / Holding
Appeal allowed. The appellant Subodh Singh is entitled to additional compensation for the left out portion of land at not less than 5% of the value of the award for a period of 84 months. The amount already paid towards the delay (two months) shall be adjusted. The remaining amount shall be released within eight weeks from today. In addition, the appellant shall be entitled to simple interest at 7% per annum on the outstanding amount from the date the amount became due and payable until realization. Costs to be borne by each party.
Final Disposition
Appeal allowed; parties to bear their own expenses; directions issued for payment of the remaining compensation along with interest within eight weeks.

Parties to the Case

Appellants / Petitioners

  • Subodh Singh

Respondents

  • Union of India and Others

Legal Representation & Advocates

Counsels for Petitioners

  • • S. B. Upadhyaya
  • • Aftab Rasheed
  • • Aftab Ali Khan
  • • M. Z. Chaudhary
  • • Mansur Ali Khan
  • • Rahat Ali Chaudhary
  • • M.A. Mansoori

Counsels for Respondents

  • • K M Nataraj
  • • A.S.G.
  • • Amrish Kumar
  • • Mrs. Indira Bhakar
  • • Anuj Udupa
  • • Manoj Mishra
  • • Chitvan Singhal
  • • Padmesh Mishra
  • • Saurabh Mishra
  • • Shrimay Mishra
  • • Abhinav Pandey
  • • Rakesh Chander
  • • Nirbhaya S Tewari

Provisions of Law Cited

Section 20(E)(1) of the Indian Railways Act, 1989Section 20F(2) of the Indian Railways Act, 1989Second proviso to Section 20F(2) of the Indian Railways Act, 1989Section 20F(1) of the Indian Railways Act, 1989

Submissions & Arguments

Contentions of Appellants / Petitioners

The appellant contends that after initial award, a left out portion of land (0.0624 hectare) remained for which compensation along with additional sum should be paid. He asserts the delay in payment merits compensation for 84 months at not less than 5% per month, referencing the Kamla Devi matter and the 2011 Supreme Court order clarifying the mechanism for calculating delay compensation rather than restricting it to two months. The appellant therefore seeks the full 84 months of delay plus interest.

Contentions of Respondents

The respondents contend that no direction existed to award additional compensation beyond two months and that the payment period of two months was only for the actual payment, not an entitlement cap. They rely on the High Court order guiding payment and suggest that any further calculation should occur through the appropriate proceedings/arbitration under Section 20F(1) (and the provisos), not by ad hoc extension of the delay period.

Legal Doctrine & Issue Explorer

Explore This Legal Issue

Find relevant judgments and authoritative positions on the legal questions discussed here.

Cited Precedents (1)

Case NameCitationTreatmentExplanation
Dedicated Freight Corridor Corporation of India v. Subodh Singh[2011] 3 SCR 1160 : (2011) 11 SCC 100PositiveDirectly supports the principle of not less than 5% per month as additional compensation for delay and was used to justify the extended compensation period in this case.
Case Applicability Diagnostic

Apply This to My Facts

Share your situation and test whether this judgment governs, supports, or challenges your case.

Official Judgment Record
•2,158 words•~10 min read

In The Court Record

Subodh Singh v. Union of India and Others

[2024] 6 S.C.R. 708 : 2024 INSC 458 ## **Subodh Singh** ## **v.** ## **Union of India and Others** (Civil Appeal No. 6458 of 2024) 16 May 2024 ## **[Hima Kohli and Ahsanuddin Amanullah, JJ.]** ## **Issue for Consideration** Whether the appellant is entitled to additional compensation for the left out portion of land at least @ 5% of the value of the award for a period spreading over 84 months. ## **Headnotes** **Compensation – Additional compensation for the left out portion of land – Payment towards the delay only to two months – Appellant claimed payments towards delay of 84 months – Correctness:** **Held:** Respondents had acquired a land by Notifications issued u/s. 20(E)(1) of the Indian Railways Act, 1989 – An award was declared on 08.02.2010 in respect of land that respondent acquired – A parcel of land admeasuring 0.0624 Hectare was left out – The High Court vide order dated 20.09.2016 directed the respondents to provide compensation to the appellant for 0.0624 Hectare of land, which was left out, along with additional compensation – While calculating the additional compensation, respondent confined the same to a period of two months for delayed period – Appellant claimed that he was entitled to compensation for a period of 84 months and relied on one Kamla Devi & Ors. – This Court noted that an order dated 18.09.2017, passed by the Competent Authority refers to an order dated 19.07.2017, passed by the High Court in a Writ Petition filed by Kamla Devi and others and goes on to record that after completion of formalities of publication, some portion of the land admeasuring 0.0890 Hectare had been left out, as the same was not required for the subject project – Subsequently, another award was declared in respect of the left out area and additional compensation was paid to the land owners @ 5% per month of the award for a period of 66 months, i.e. from 19.04.2012 to 12.09.2017 – In light of the above, the appellant herein cannot be treated differently in his case, the respondents ought not to have confined the delayed payment on the [2024] 6 S.C.R.  709 ## **Subodh Singh v. Union of India and Others** awarded amount for the left out portion of land to only two months – Thus, the appellant is held entitled to additional compensation for the left out portion of land at least @ 5% of the value of the award for a period spreading over 84 months. [Paras 3, 4, 9, 12] ## **Case Law Cited** _Dedicated Freight Corridor Corporation of India v. Subodh Singh_ **[2011] 3 SCR 1160 : (2011) 11 SCC 100 – referred to.** ## **List of Acts** Indian Railways Act, 1989. ## **List of Keywords** Compensation; Additional compensation; Award; Delay in payment; Payment of additional compensation; Additional compensation for left out portion of land. ## **Case Arising From** CIVIL APPELLATE JURISDICTION: Civil Appeal No. 6458 of 2024 From the Judgment and Order dated 31.08.2017 of the High Court of Judicature at Allahabad in WC No. 39875 of 2017 ## **Appearances for Parties** S. B. Upadhyaya, Sr. Adv., Aftab Rasheed, Aftab Ali Khan, M. Z. Chaudhary, Mansur Ali Khan, Rahat Ali Chaudhary, M.A. Mansoori, Advs. for the Appellant. K M Nataraj, A.S.G., Amrish Kumar, Mrs. Indira Bhakar, Anuj Udupa, Manoj Mishra, Chitvan Singhal, Padmesh Mishra, Saurabh Mishra, Shrimay Mishra, Abhinav Pandey, Rakesh Chander, Nirbhaya S Tewari, Advs. for the Respondents. ## **Judgment / Order of the Supreme Court** ## **Order** **1.** Leave granted. **2.** The present appeal is directed against the order dated 31[st] August, 2017, passed by the Division Bench of the High Court of Judicature at Allahabad whereby, the Writ Petition filed by the appellant herein praying _inter alia_ for issuing directions to the respondents to pay [2024] 6 S.C.R. 710 ## **Digital Supreme Court Reports** additional compensation for the entire land area, subject matter of the Notification dated 12[th] December, 2008, issued under Section 20(E)(1) of the Indian Railways Act[1] , 1989, at the rate higher than 5% per month and further pay interest @ 18% per annum for delay in payment from 30[th] March, 2011, i.e. the date on which this Court had passed an order in Civil Appeal No. 2794 of 2011[2] titled “ _Dedicated Freight Corridor Corporation of India Vs. Subodh Singh_ ”, till the actual date of payment in respect of the award dated 08[th] February, 2010. **3.** It is submitted on behalf of the appellant that the respondents had acquired land in Village Kakrahi, Tehsil and District Auriya, Uttar Pradesh _vide_ Notifications dated 10[th] June, 2008 and 16[th] December, 2008 issued under Section 20(E)(1) of the Act. An award was declared on 08[th] February, 2010 only in respect of the land that the respondents required. As a result, a parcel of land admeasuring 0.0624 Hectare was left out. Aggrieved by the said action, the appellant filed a Writ Petition[3] before the High Court for quashing the award dated 08[th] February, 2010, which was allowed _vide_ order dated 12[th] May, 2010. Challenging the said order, the respondents filed a Petition for Special Leave to Appeal[4] before this Court, which was allowed _vide_ judgment dated 30[th] March, 2011 holding _inter alia_ that the acquisition in question had not lapsed and having regard to the second proviso to section 20F(2) of the Act, the land owners would be entitled to an additional compensation for the delay in making the payment in terms of the award dated 08[th] February, 2010, at a rate not less than 5% of the value of the award for each month of delay. **4.** Pursuant to the aforesaid order, the respondent no.2 issued a certificate in respect of the entire parcel of land in terms of the Notification dated 12[th] December, 2008, again leaving an area of 0.0624 Hectare as free from acquisition proceedings. Being aggrieved by the said decision, the appellant filed another petition[5] before the High Court, which was allowed _vide_ order dated 20[th] September, 2016 and the respondents were directed to provide compensation - 1 For short the ‘Act’ > 2 [2011] 3 SCR 1160 : (2011) 11 SCC 100 > 3 Writ C. No. 14945/2010 > 4 SLP(Civil) No. 26410 of 2010 (i.e. Civil Appeal No. 2794/2011) - 5 Writ C. No. 63467/2011 [2024] 6 S.C.R.  711 ## **Subodh Singh v. Union of India and Others** to the appellant for 0.0624 Hectare of land along with additional compensation within a period of two months. **5.** On 19[th] November, 2016, the respondents prepared a bank draft for a sum of ₹ 2,74,56,000/- (Rupees Two Crores Seventy Four Lakh Fifty Six Thousand) stating that the same was in respect of the compensation payable to the appellant in terms of the order passed by the High Court on 20[th] September, 2016. While calculating the additional compensation, the respondent no.2 confined the same to a period of two months for the delayed period. **6.** Aggrieved by the compensation offered by the respondents limiting the delay to only two months, the appellant approached the High Court by filing yet another petition[6] claiming that he was entitled to compensation for a period of 84 months, which would come to Rs.10,23,28,000/- (Rupees Ten Crores Twenty Three Lakh and Twenty Eight Thousand), on which the impugned order dated 31[st] August, 2017, has been passed observing that the appellant ought to approach the Arbitrator for determining the additional compensation, by invoking Section 20F (1) of the Act. **7.** It is submitted on behalf of the appellant that the respondents have adopted a pick and choose policy in the instant case. While they have paid additional compensation for a period of delay of 66 months to one Smt. Kamla Devi & Ors., who were similarly situated persons like the appellant and their land was also acquired under the very same award, in the case of the appellant the respondents have arbitrarily confined the payment towards the delay only to two months, instead of 84 months. **8.** We have perused the record and heard the arguments advanced by learned counsel for the parties. **9.** At the outset, we may note that the order dated 18[th] September, 2017, passed by the Competent Authority refers to an order dated 19[th] July, 2017, passed by the High Court in a Writ Petition[7] filed by Kamla Devi and others and goes on to record that after completion of formalities of publication, some portion of the land admeasuring 0.0890 Hectare had been left out, as the same was not required for > 6 Writ C No. 39875/2017 > 7 WP No. 65267 of 2012 [2024] 6 S.C.R. 712 ## **Digital Supreme Court Reports** the subject project. Subsequently, another award[8] was declared in respect of the left out area and additional compensation was paid to the land owners @ 5% per month of the award for a period of 66 months, i.e. from 19[th] April, 2012 to 12[th] September, 2017. In the light of the above, the appellant herein is justified in arguing that he cannot be treated differently and in his case, the respondents ought not to have confined the delayed payment on the awarded amount for the left out portion of land to only two months. **10.** The aforesaid submission is disputed by learned counsel for the respondents on a plea that no such direction was issued either by this Court or the High Court permitting compensation for the delayed period beyond two months, for which reliance is sought to be placed on the order dated 20[th] September, 2016 passed by the High Court. **11.** The aforesaid submission is taken note of only to be turned down. The period of two months referred to by the High Court in its order dated 20[th] September, 2016 was only for making payment of the amount. Not that any direction was issued to the respondents to confine the payment of additional compensation only to a period of two months. In fact, the order passed by this Court on 30[th] March, 2011 is crystal clear and needs no interpretation. Highlighting certain anomalies noticed in Chapter IV A of the Act, particularly Section 20F, this Court referred to the proviso to Section 20F (2) and observed as follows: - “12. (iii) The second proviso to section 20F (2) requires payment of additional compensation for the delay in making of the award, at the rate of not less than five percent of the value of award, for each month of delay. This vests unguided discretion in the competent authority or the Arbitrator to award additional compensation at any higher rate and gives room for unnecessary litigation at the instance of “entitled persons” claiming higher percentages as additional compensation. It is necessary to consider whether specifying a fixed monthly rate of increase would serve the ends of justice better instead of indicating a minimum rate per month. xxxx xxxx xxxx 8 Award No. 1/2011-12, dated 19th April, 2012 [2024] 6 S.C.R.  713 ## **Subodh Singh v. Union of India and Others** “13. In view of our finding that the acquisition has not lapsed, we allow this appeal, set aside the judgment of the High Court, and dismiss the challenge to the acquisition. It is however made clear that in view of the delay in making the award beyond one year, the first respondent shall be entitled to additional compensation as provided under the second proviso to section 20F (2) of the Act. Parties to bear their respective costs.” **12.** It is apparent from the above that the appellant would be entitled to additional compensation for the delay in making the award @ not less than 5% of the value of the award for each month’s delay. In our opinion, there was no reason for the High Court to have relegated the appellant to initiate any arbitration proceedings for determining the additional compensation when the order passed by this Court had clarified the manner in which compensation would be calculated and paid for the delay in making the award for the left out parcel of land. **13.** In view of the above discussion, the present appeal succeeds. The appellant is held entitled to additional compensation for the left out portion of land at least @ 5% of the value of the award for a period spreading over 84 months. Needless to state that the amount already paid by the respondents towards the delay, i.e., for a period of two months, shall be duly adjusted. The remaining amount shall be released by the respondents within eight weeks from today. Besides the aforesaid amount, the appellant shall also be entitled to simple interest on the outstanding amount calculated @ 7% per annum from the date the said amount became due and payable, till the same is realized. **14.** The appeal is allowed on the above terms while leaving the parties to bear their own expenses. _Headnotes prepared by:_ Ankit Gyan _Result of the case:_ Appeal allowed.
End of Judgment Record
Browse All Supreme Court of India (2024) Decisions
2024-04-09

Kizhakke Vattakandiyil Madhavan (Dead) Thr. Lrs. v. Thiyyurkunnath Meethal Janaki and Ors

This appeal concerns partition of a family property in Eravattur, Kozhikode, governed by pre-1956 Mitakshara succession. Madhavan died before 1910; his widow Chiruthey remarried Neelakandan, triggering Section 2 of the Hindu Widow’s Remarriage Act, 1856, which extinguishes a widow’s rights in her deceased husband’s property on remarriage. Chiruthey’s second marriage, and a sequence of instruments dated 1910–1925—back-to-back deeds creating a lease in favour of Cheriyamma and her son (Exhibits A-20 and A-1) and an assignment (Exhibit A-2)—formed the basis for Chandu (the plaintiff) and Sankaran’s successors-in-interest to seek partition in OS 157/1985. The Trial Court granted partition to the plaintiff; the First Appellate Court dismissed; the Kerala High Court restored the Trial Court’s decree. The Supreme Court, however, allowed the appeal. It held that on remarriage the widow’s title over Madhavan’s property stood lapsed under Section 2; yet the back-to-back deeds involved Nangeli (Madhavan’s mother) and Sankaran, who retained an interest. Exhibit A-20 was treated as a valid conveyance, but Chiruthey’s own title did not survive; the lease purportedly created by A-1 could not extend beyond its 12-year term. Consequently, the plaintiff’s claim for partition could not be sustained, and the appeal was allowed with the trial/decree of the lower courts set aside.

2024-10-04

Banshidhar Construction Pvt. Ltd. v. Bharat Coking Coal Limited & Others

Banshidhar Construction Private Limited (the appellant) challenged Bharat Coking Coal Limited’s tender for a mega project to salvage, develop, and operate a coal mine under a revenue-sharing arrangement for 25 years. The tender NIT dated 16.08.2023 imposed stringent eligibility criteria, including Clause 10 requiring financial capacity documentation and a Power of Attorney for signing bids. The appellant contended that its Power of Attorney (dated 07.11.2023 and notarised 14.11.2023) was valid, and its bid documents were uploaded before the last submission date (01.12.2023). Technical bids opened on 04.12.2023, yet the appellant was declared technically disqualified on 06.05.2024 on grounds that it did not meet Clause 10. Meanwhile, Respondent No.8 was declared technically qualified and later found to be the successful bidder after financial bids were opened on 07.05.2024, despite non-compliance with the “mandatory” Clause 10 documents, including delayed Audited Balance Sheets. The High Court dismissed the writ petition. The Supreme Court, while acknowledging limited review in mega-project tenders, held that public authorities must act with fairness, transparency, and without arbitrariness or malafides. It held that the Power of Attorney requirement was satisfied and that accepting the non-compliant Respondent No.8 while rejecting the appellant was arbitrary. The Court set aside the impugned decision and permitted a fresh tender process in accordance with law, reaffirming that Article 14 requires equal treatment and non-arbitrariness in public procurement.

2024-03-21

Union of India v. M/s Indian Oil Corporation Ltd.

This Supreme Court judgment concerns an appeal by the Union of India challenging a batch of Allahabad High Court orders that directed refunds to IOCL for a difference of approx. 110 km in freight charges on the Baad–Hisar route. IOCL had been charged on the basis of a distance of 444 km under the old Local Distance Table; following Railway Ministry circulars in 2004 and 2005 rationalizing the rounding-off of chargeable distance, the distance was reduced to 333.18–334 km in practice. IOCL issued notices under Section 106 of the Railways Act, 1989 (formerly Section 78-B of the Railways Act, 1890) seeking refunds of the alleged overcharge, and 122 consignments were paid at the old distance before the authorities corrected the distance. The Railway Claims Tribunal dismissed most claims as time-barred, while the Allahabad High Court allowed IOCL’s appeals, holding that the original 444 km charge was an “illegal charge” rather than an overcharge, and thus protected by equity. The Union of India challenged this, arguing that Section 106(3) only covers refunds of overcharges and not illegal charges; that the change in distance stemmed from policy rationalization and circulars, not an erroneous charge. The Court distinguishes Hindustan Petroleum, clarifies the overcharge/illegal charge distinction, and ultimately holds that the 444 km distance was illegal. As a result, the Union’s appeals are dismissed, and IOCL’s refunds for the difference would be payable to IOCL. The matter underscores the nuanced interplay between statutory time limits, chargeable distance, and the nature of the charge in refund claims.

2024-07-23

Gene Campaign & Anr. v. Union of India & Ors.

This is a batch of writ petitions initiated in 2004–2005 addressing the environmental and regulatory treatment of GM crops, specifically the environmental release of transgenic mustard DMH-11 (Dhara Mustard Hybrid-11). The Supreme Court examined whether GEAC’s 18.10.2022 conditional approval and the 25.10.2022 decision were legally sound, whether they violated Article 21 (right to a safe environment) and whether the precautionary principle was properly applied. The court undertook a comprehensive review of the regulatory framework under the Environment Protection Act, 1986 and the 1989 Rules, as well as the Technical Expert Committee (TEC) reports and Parliamentary Standing Committee recommendations. A key feature is the dual opinions: Justice Nagarathna (with Justice Karol concurring but delivering a separate opinion) upheld a robust judicial review of executive policy in GM regulation and found serious irregularities in the decision-making process, quashing the impugned approvals and directing a national policy on GM crops, greater public transparency, and safe-guarded field testing. Justice Karol, in a separate opinion, while endorsing the need for precaution, cautioned against an outright ban on HT crops and emphasized policy matters be left to the legislature. The judgment thus emphasizes environmental rule of law, public trust, intergenerational equity, and a precautionary approach, while mandating further regulatory reform and public participation.