Subhash Kumar filed a writ petition under Article 32 challenging pollution of the Bokaro river by slurry discharged from washeries operated by West Bokaro Collieries and Tata Iron and Steel Co. (TISCO). The petitioner alleged that the Water (Prevention and Control of Pollution) Act, 1974 and the State Pollution Control Board had failed to prevent pollution, and that the State of Bihar had granted leases for collection of slurry despite its adverse impact on health and agriculture. He sought directions to stop the discharge of slurry into the Bokaro and interim relief permitting him to collect slurry for sale. The respondents contended that steps had already been taken: the State Pollution Control Board had issued directions, sanctioned discharges under Sections 25 and 26 of the Act after reviewing effluents, and monitored compliance. The petition was vigorously opposed on grounds that it did not serve public interest but pursued personal gain, given the petitioner’s long-standing involvement in slurry transactions and criminal cases. The Court held that Article 32 is designed to enforce fundamental rights, notably the right to life under Article 21, which includes pollution-free water and air. However, public interest petitions must be genuinely for societal protection and not a vehicle for personal grievance. Intrinsic petition evidence suggested the petitioner acted from self-interest, and public-interest litigation should be discouraged to prevent abuse of the Court’s extraordinary jurisdiction. The petition was dismissed with costs.

Precedent Explorer

Find Cases Like This

Explore other judgments dealing with similar legal situations, facts, or statutory provisions.

Case Details & Bench

Court
Supreme Court of India
Hon'ble Judges
  • K.N. Singh
  • N.D. Ojha
Judgment Date
1991-01-09
Court Decision / Holding
Petition dismissed with costs of Rs. 5,000 to respondent Nos. 3, 4 and 5.
Final Disposition
Petitions dismissed.

Parties to the Case

Appellants / Petitioners

  • Subhash Kumar

Respondents

  • State of Bihar
  • Bihar State Pollution Control Board
  • Tata Iron & Steel Co. Ltd.
  • West Bokaro Collieries
  • Union of India

Legal Representation & Advocates

Counsels for Petitioners

  • • S.K. Sinha

Counsels for Respondents

  • • D. Goburdhan
  • • Ms. A. Subhashini
  • • K.K. Lahiri
  • • Ms. Lira Goswami
  • • D.N. Misra

Provisions of Law Cited

Water (Prevention and Control of Pollution) Act, 1974: Sections 17, 24, 25 and 26Constitution of India, 1950: Article 21Constitution of India, 1950: Article 32Constitution of India, 1950: Article 226Essential Commodities Act: Section 7Mines and Mineral (Regulation and Development) Act, 1957Indian Penal Code: Section 379Indian Penal Code: Section 411

Legal Doctrines & Maxims

  • Article 32 is an extraordinary remedy to enforce fundamental rights; right to life under Article 21 includes pollution-free water and air
  • Public Interest Litigation must be pursued by a person genuinely interested in protecting society and cannot be used to enforce a personal grievance or enmity
  • Public Interest Litigation contemplates vindication or enforcement of fundamental rights of a group or community unable to enforce them due to incapacity, poverty or ignorance of law
  • Courts have a duty to discourage unscrupulous litigants and to prevent abuse of the process and obstruction of justice

Submissions & Arguments

Contentions of Appellants / Petitioners

The petitioner contends that the respondents pollute the Bokaro river by discharging slurry from their washeries, endangering health and violating the Water Act and the right to life. He seeks directions to stop the discharge and interim relief to collect slurry. He invokes Article 32 to protect the right to pollution-free water and air, arguing for public interest relief to curb pollution.

Contentions of Respondents

The respondents argue that the Water Act and State Pollution Control Board controls discharge; the Board granted sanction under Sections 25 and 26 after monitoring effluent; the Board has ensured compliance and that the petition is not in public interest but personal interest, given the petitioner’s history of slurry dealings. They state steps were taken to prevent pollution and that there is no ongoing discharge into the river.

Legal Doctrine & Issue Explorer

Explore This Legal Issue

Find relevant judgments and authoritative positions on the legal questions discussed here.

Cited Precedents (6)

Case NameCitationTreatmentExplanation
Bandhua Mukti Morcha v. Union of India[1984] 2 SCR 67PositiveCited to outline the essential nature and limitations of public interest litigation and the need to avoid personal grievances.
Sachindanand Pandey v. State of West Bengal[1987] 2 SCC 295PositiveCited regarding the framework of public interest litigation and the requirement that petitions reflect genuine public interest.
Ramsharan Autyanuprasi & Anr. v. Union of India & Ors.[1989] Suppl. 1 SCC 251PositiveCited as authority on the use of Article 32 and the concept of public interest litigation.
Chetriya Pardushan Mukti Sangharsh Samiti v. State of U. P. & Ors.[1990] 4 SCC 449PositiveCited in the context of public interest litigation principles.
Kundori Labour Co-operative Society Ltd. & etc. v. State of Bihar & Ors.AIR 1986 Patna 242OverruledPatna High Court held slurry was not coal; Supreme Court later overruled this view in Bharat Coking Coal Ltd. v. State of Bihar & Ors., holding slurry on land remains coal and belongs to the Company.
Bharat Coking Coal Ltd. v. State of Bihar & Ors.[1990] SCR 744PositiveSupreme Court reversed Patna High Court, holding that slurry deposited on company land remains coal and belongs to the Company; used to frame the rights over slurry and compliance with the Act.
Case Applicability Diagnostic

Apply This to My Facts

Share your situation and test whether this judgment governs, supports, or challenges your case.

Official Judgment Record
•4,363 words•~20 min read

In The Court Record

Subhash Kumar v. State of Bihar and Ors.

SUBHASH KUMAR A C _v._ STATE OF BIHAR AND ORS. JANUARY 9, 1991 [K.N. SINGH AND N.D. OJHA, JJ.] B _Water (Prevention and Control of Pollution) Act, 1974: Sections 17, 24, 25 and 26._ _Constitution of India, 1950: Article 21-Right to live includes right to enjoyment of pollution free water and air-A citizen has a right to invoke Article 32 for removing pollution._ _Article 32-Writ petition in public interest-Allegation that West Bokaro Collieries and Tata Iron and Steel Company are polluting the river Bokaro by discharging slurry from their washeries into the riverNo material to substantiate the allegations-Held petition is not in public interest but for personal interest._ > _Public Interest Litigation-Should be ·resorted to by a person genuinely interested in the protection of society-Personal interest cannot be enforced in the garb of public interest litigation-Entertainment of petitions satisfying personal grudge is abuse of process of the CourtDuty of the court is to discourage such petitions._ The petitioner filed a writ petition in this court by way of public interest litigation alleging that the respondents, West Bokaro Collieries and Tata Iron and Steel Company (TISCO) were polluting the river Bokaro by discharging surplus waste in the form of sludge/slurry as effluent from their washeries into the river making the river water unfit for drinking and irrigation purposes thereby causing risk to the health of the people; the State of Bihar and the State Pollution Control Board have failed to take appropriate steps for prevention of the pollution and instead the State of Bihar has granted leases on payment of royalty to various persons for collection . of slurry. Accordingly the petitioner prayed for directions to the respondents to take immediate steps prohibiting the pollution of the river and to take legal action against TISCO under the Water (Prevention and Control of Pollution) Act, 1974. The petitioner also claimed interim relief from this Court that he should be permitted to collect sludge/slurry flowing out of washeries of the respondents. D E F G H 5 6 [1991] 1 S.C.R. SUPREME COURT REPORTS The respondents contested the petition denying the petitioner's A allegations. Bihar State Pollution Board asserted that directions have been issued to the Bokaro Collieries to take effective steps for improving the quality of the emuent going into the river Bokaro and that the TISCO Company has been granted permission to discharge their effluents from their outlets in accordance with sections 25 and 26 of the B 1974 Act. On behalf of TISCO and the Bokaro Collieries it was contended that all effective steps have been taken to prevent the pollution and they have complied with the instructions of the State Pollution Board. By an order dated 13.12.1990, this Court dismissed the writ petition'with costs. ,..\..__ ~ _-(_ ' c I Giving reasons for dismissal of the petition, this Court, HELD: 1. Article 32 is designed for the enforcement of Fondamental Rights of a citizen by the Apex Court. It provides for an extraD ordinary remedy to safeguard the fundamental rights of a citizen. Right to life is a fundamental right under Article 21 of the Constitution and it includes the right of enjoyment of pollution free water and air for full enjoyment of life. If anything endangers or impairs that quality of life in derogation of laws, a citizen bas right to have recourse to Article 32 of the Constitution for removing the pollution of water or air which E may be detrimental to the quality of life. A petition under Article 32 for the prevention of pollution is maintainable at the instance of affected persons or even by a group of social workers or journalists. But recourse to proceeding under Article 32 of the Constitution should be taken by a person genuinely interested in the protection of society on behalf of the community. Public interest litigation cannot be invoked by F a person or body of persons to satisfy his or its personal grudge and enmity. If such petitions under Article 32 are entertained it would amount to abuse of process of the Court, preventing speedy remedy to other genuine petitioners from this Court. Personal interest cannot be enforced through the process of this Court under Article 32 of the Constitution in the garb of a public interest litigation. Pllblic -interest G litigation contemplates legal proceeding for vindication or enforcement of fundamental rights of a group of persons or community which are not able to enforce their fundamental rights on account of their incapacity, poverty or ignorance of law. A person invoking the jurisdiction of this Court under Article 32 must approach this Court for the vindication of the fundamental rights of affected persons and not for the purpose of H vindication of his personal grudge -- or enmity. - It is duty of this Court to _T_ / ~ -1 " 7 SUBHASH _v._ STATE OF BIHAR _,.,..i,_ ~ discourage such petitions and to ensure that the course of justice is not obstructed or polluted by unscrupulous litigants by invoking the extraordinary jurisdiction of this Court for personal matters under the garb of the public interest litigation. [13C-H; 14A] A I ...._ _Bandhua Mukti Morcha_ v. _Union of India,_ [1984] 2 SCR 67; _Sachindanand Pandey_ v. _State of West Bengal,_ [1987] 2 SCC 295; _Ramsharan Autyanuprasi & Anr._ v. _Union of India & Ors.,_ [1989] Suppl. 1 SCC 251; _Chetriya Pardushan Mukti Sangharsh Sa.miti_ v. _State of U. P. & Ors.,_ [1990] 4 SCC 449, referred to. B _r_ 2. The present petition is not filed in public "interest inste~d the petition has been made by the petitioner in his own interest. lnfact there c is intrinsic evidence in the petition itself that the primary purpose of filing this petition is not to serve any public interest instead it is in self-interest. The petitioner has been purchasing slurry from the / respondents for the last several years. With the passage of time he T wanted more and more slurry but the Company refused to accept his request. He removed the Company's slurry in an unauthorised manner D for which criminal cases are pending against him and his brother. Since the respondent company refused to sell additional slurry he entertained a grudge against the company and in order to feed fat his personal grudge he resorted to several proceedings against the company includ~[ing ][the present one. The prayer for the interim relief made ][by ][the ] petitioner i.e. permittjng him to arrest/collect sludge/slurry flowing out E of the washeries of the respondents with a direction to the State of Bihar, its officers and other ·authorities for not preventing him from collecting the sludge jslurry and transporting the same also collecting the sludge /Slurry and transporting the saine clearly indicates that he is interested in collecting the slurry and transporting the same for the purposes of his business. Therefore, there is no good reason to accept F the petitioner's allegation that the water of the river Bokaro is being J polluted by the discharge of sludge or slurry into it from the washeries of the respondent-company. On the other hand it is evident from records that the State Pollution Contro! Board has taken effective steps to check the pollution. [14B; 12F-G] E .. ~ _/_ G _Kundori Labou_rs Cooperative Society Ltd. & etc. etc._ v. _State of Bihar & Ors.,_ AIR 1986.·Patna 242; _Bharat Coki":_g Coal Ltd._ v. Sta~e_of _Bihar & Ors.,_ f1990]} SCR 744 = Juclgrnents Today,_ Vol. 3, _1990 SC_C 533, referred to. ~----< ORIGINAL JURISDICTION: Writ Petiti<;>n (C) No. 381 of H 1988. 8 SUPREME COURT REPORTS [1991] 1 s.c.R. ## **A** (Under Article 32 of the Constitution of India). S.K. Sinha for the Petitioner. D. Goburdhan, Ms. A. Subhashini, K.K. Lahiri, Ms. Lira Goswami and D .N. Misra for the Respondents. **B** The Judgment of the Court was delivered by **SINGH, J.** We heard the arguments in detail on 13.12.1990 and dismissed the petition with costs amounting to Rs.5,000 with the direction that the reasons shall be delivered later on. We are, accordingly, delivering our reasons. c This petition is under Article 32 of the Constitution by Subhash . \Kumar for the issue of a writ or direction directing the director of Collieries, West Bokaro Collieries at Ghatotand, District Hazaribagh \ in the State of Bihar and the Tata from & Steel Co. Ltd. to stop **D** ·forthwith discharge of slurry/sludge from its washeries at Ghatotand in the District of Hazaribagh into Bokaro river. This petition is by way of public interest litigation for preventing the pollution of the Bokaro river water from the sludge/slurry discharged from the washeries of the Tata Iron & Steel Co. Ltd. The petitioner has alleged that the Parliament has enacted the Water (Prevention and Control of Pollution) E Act, 1974 (hereinafter referred to as 'the Act') providing for the prevention and control of water pollution and the maintaining or restoring ·of wholesomeness of water, for the establishment of Board for the prevention and control of water pollution. Under the provisions of the Act the State Pollution Control Board constituted to carry out functions prescribed under Section 17 oi-.the Act which among other things **F** provide that the Board shall inspect sewage or trade effluents and plants for the treatment of sewage and trade effluents and to review plans, specifications or other data set up for the treatment of water and to lay down standards to be co,iiplied with by the persons while causing discharge of sewage or sullage. Section 24 of the Act provides that no person shall knowingly cause or permit any poisonous, noxious or (} polluting matter to enter into any stream or well which may lead to a substantial aggravation of pollution. The petitioner has asserted that Tata Iron and Steel Co.-respondent No. 5 carries on mining operation in coal mines/washeries in the town of Jamshedpur. These coal mines and collieries are known as West Bokaro Collieries and the Collieries have two coal washeries where the coal after its extraction H from the mines is broug~t and broken into graded pieces and there- r 9 SUBHASH _v._ STATE OF BIHAR [SINGH, J.) _)_ _J,__ _-r_ c d.1 • ,;......, ~ f after it is processed for the purpose of reducing its ash contents. A A chemical process is carried out which is known as 'froth floatation process'. Under this process the graded coal is mixed with diesel oil, pine oil and many other chemical ingredients and thereafter it is washed with the lacs of gallons of water. The end water is washed coal with reduced quantity of ash content fit for high graded metallurgical process for the purposes of manufacture of steel. In the process of B washing large quantity of water is discharged through pipes which carry the discharged water to storage ponds constructed for the purpose of retaining the slurry. Alongwith ·the discharged water, small particles of coal are carried away to the pond where the coal particles settle down on the surface of the pond, and the same is collected after the p_ond is de-watered. The coal particles which are carried away by c the water is cafled-the slurry which is ash free, it contains fine quality of coal which is used as fuel. -----....;' The petitioner has alleged that the surplus waste in the form of sludge/slurry is discharged as an effluent from the washeries into the Bokaro river which gets deposited in the bed of the river and it also gets settled on land including the petitioner's land Searing Plot No. 170. He has further alleged that the sludge or slurry whicn gets deposited on the agricultural land, is absorbed by the land leaving on the top a fine carbonaceous product or film on the soil, which adversely affects the fertility of the land. The petitioner has further alleged that · the effluent in the shape of slurry is flown into the Bokaro river which is carried out by the river water to the distant places polluting the river water as a result of which the river water is· not fit for drinking purposes nor it is fit for irrigation purposes. The continuous discharge of slurry in heavy quantity by the Tata Iron & Steel Co. from its washeries posing risks to the health of people living in the surrounding areas and as a result of such discharge the problem of pure drinking water has become acute. The petitioner has asserted that inspite of several representations, the State of Bihar and State Pollution Control Board have failed to take any action against the Company instead they have permitted the pollution of the river water. He has further averred that the State of Bihar instead of taking any action against the Company has been granting leases on payment of royalty to various persons for the collection of slurry. He has, accordingly, claimed relief for issue of direction directing the respondents which include the State of Bihar, the Bihar Pollution Control Board, Union of India and Tata Iron & Steel Co. to take immediate steps prohibiting the pollution of the Bokaro river water from the discharge of slurry into the Bokaro river and to take further action under provisions of the Act againt the Tata Iron & Steel Co. D E F G H (1991] 1 S.C.R. 10 SUPREME COURT REPORTS A c B D F ':G .... The respondents have contested the petition and counteraffidavits have been filed on behalf of t_he respondent Nos. 2, 4 and 5-State of Bihar,' State Pollution Board, Directors of Collieries a_nd Tata Iron & Steel Co. Ltd. In the counter-affidavits filed on behalf of the respondents, the petitioner's main allegation that the sludge/slurry is being discharged into the river Bokaro causing pollution to the water and the land and that the Bihar State Pollution Board has not taken steps to prevent the same is denied. In the counter-affidavit filed on behalf of the Bihar State Pollution Board it is asserted that the Tata Iron & Steel Co. operates open case and underground mining. The Company in accordance to Sections 25 and 26 of the Water (Prevention and Control of Pollution) Act, 1974 applied for sanction from the Board to discharge their effluent from their outlets. The Board before granting sanction analysed their effluent which was being watched constantly and monitered to see that 'the discharge does not affect the water quality of the Bokaro river adversely. In order to prevent the pollution the Board issued direction to the Director of the Collieries to take effective steps for improving the quality of the effluent going into the Bokaro river. The State Pollution Board imposed conditions requiring the Company to construct two settling tanks for settlement ofsollds and rewashing the same. The Board directed for the' regular samples being taken and tested for suspended solids and for the communic~tion of the results of the tests to the Board each month. The State Board has asserted that the Company has constructed four ponds ensuring more- storing capacity of effluent. The Pollution Board has been monitoring the effluent. It is further stated that on the receipt of the notice of the instant writ petition the Board carried out an inspection of the settling tanks regarding the treatment of the effluent from the washeries on 20th June, 1988. On inspection it was found that all -the four settling tanks had already been completed and work for further strengthening _of_ the embankment of the tanks was in progress, and there was no discharge of effluent from the washeries into the river Boka:o except that there was negligible seepage from the embankment. It is further stated that the Board considered all the aspects and for further improvement it directed the management of the collieries for removal of the settled slurry from the tanks. The Board has directed that the washeries shall perform desludging of the settling tanks at regular intervals to achieve the proper req-uired retention time for _the separation of solids and to achieve discharge of effluents within the standards prescribed by the Board. It is further asserted that at present there is no discharge from any of the tanks to the Bokaro river and thei"e is no question of pollution of the river water or affecting the fertility of land. In their affidavits fiied on behalf of the respondent 11 SUBHASH _v._ STATE OF BIHAR [SINGH, J.) I ~ 1 Nos. 4-and 5, they have aiso denied the allegations made in the petition. They have asserted that the effective steps have betm taken to prevent the flow of the water discharge from the .washeries into the river Bokaro. It is stated that intact river Bokaro remains dry during 9 months in a year and the question of pollution of water by discharge of slurry into the river does not arise. However, the management of the washeries have constructed from different ponds to store the slurry. The slurry which settles in the ponds is collected for sale. The slurry contains highly carbonaceous materials and it is considered very valuable for the purpose of fuel as the ash contents are almost. nil in the coal particles found in the slurry. Since, it has high market value, the Company would not like it to go in the river water. The Company has taken effective steps to ascertain that no slurry escapes from its ponds as the slurry is highly valuable. The Company has been following the directions issued by the State Pollution Control Board constituted under the 1974 Act. On the facts as appearing from the pleadings and the specific averments contained in the counter-affidavit filed on behalf of the State Pollution Control Board of Bihar, _prima facie_ we do not find any good reason to accept the petitioner's allegation that the water of the river Bokaro is being polluted by the discharge of sludge or slurry into it from the washeries of the respondent-company. On the other hand we find that the State Pollution Control Board has taken effective steps to check the pollution. We do not consider it necessary to delve into greater detail as the present petition does not appear to have been filed in public interest instead the petition has been made by the petitioner in his own interest. On a perusal of the counter-affidavit filed on behalf. of the respondent Nos. 4 and 5 it appears that the petitioner has been purchasing slurry from the respondent Nos. 4 and 5 for the last several years. With the passage of time he wanted more and more slurry, but the respondent-company refused to accept his request. The petitioner is an influent•al businessman, he had obtained a licence for coal trading, he tried to put pressure through various sources on the respondent-company for supplying him more quantity of slurry but when the Company refused to succumb to the pressure, he started harassing the Company. He removed the Company's slurry in an unauthorised manner for which a Criminal Case No. 173 of 1987 under Sections 379 and 411 of the Indian Penal Code read with Section 7 of the Essential Commodities Act was registered against the petitioner and Pradip Kumar his brother at Police Station Mandu, which is pending before A B c D JE F G H [1991] 1 S.C.R. 12 SUPREME COURT REPORTS _T_ the Sub-Judge, Hazaribagh. One Shri Jugal Kishore Jayaswal also A filed a criminal complaint under Section 379 and 411 of the IPC against the petitioner and his brother Pradip Kumar in the Court of Judicial Magistrate, First Class, Hazaribagh, which is also pending before the Court of Judicial Magistrate, 2nd Class Hazaribagh. The petitioner initiated several proceedings before the High Court of Patna under B Article 226 of the Constitution for permitting him to collect slurry . from the Raiyati land. These petitions were dismissed on the ground of _existence of dispute relating to the title of the !_ancl.. The petitioner filed a writ petition C.W.J.C. No. 887 of 1990 in the High Court of Patna for taking actio-n against the Deputy Commissioner, Hazaribagh for implementing the Full Bench judgment of the Patna High Court in C - _Kundori Labours Cooperative Society Ltd. & etc. etc._ v. _State of B_ihar & Ors.,_ AIR 1986 Patna 242 wherein it was held that the slurry was neither coal nor mineral instead it was an industrial waste of coal mine, not subject to the provisions of the Mines and Mineral (Regulation and Development) Act, 1957. Consequently the collection of slurry which escaped from the washeries could be settled by the State Government I) with any person without obtaining the sanction of the Central Government. The petitioner has been contending before the High Court that the slurry which was discharged from washeries did not belong to the Company and he was entitled to collect the same. Since the respondent-company prevented the petitioner from collecting slurry from its land and as it further refused to sell any additional quantity of slurry E to him, he entertained grudge against the respondent-company. In order to feed fat his personal grudge he has taken several proceedings against the respondent-company including the present proceedings. These facts are quite apparent from the pleadings of the parties and the documents placed before the Court. Infact, there is intrinsic evidence in the petition itself that the primary purpose of filing this petiF tion is not to serve any public interest instead it is in self-interest as would be clear from the prayer made by the petitioner in the interim stay application. The petitioner claimed interim relief from this Court permitting him to arrest/collect sludge/slurry flowing ·out of the washeries of the respondent Nos. 4 and 5 and with a direction to the State of Bihar, its officers and other authorities for not preventing him G from collecting the sludge/slurry and transporting the same. The prayer_ for the interim relief made by the petitioner clearly indicates that he is interested in collecting- the slurry and transporting the same for the purposes of his business. As already stated a Full Bench of the Patna High Court held that the slurry was not coal and the provisions of the Mines and Mineral (Regulation and Development) Act, 19_57 H were not applicable, the State Government was free to settle the same 13 SUBHASH _v._ STATE OF BIHAR [SINGH, J.] l and the Tata Steel_& Iron Co. had no right to collect the slurry which escaped from its washeries. The respondent-company filed an appeal before this Court. During the pendency of the aforesaid appeal, the petitioner filed the present petition. The appeal preferred by the Tata Iron & Steel Co; Ltd. and Bharat Coking Coal Ltd. was allowed by this Court and the judgment of Patna High Court was set asid·e. The judgment of this Court-is reported in _Judgments Today Vol. 3 1990 SC 533_ wherein it has been held that the slurry/coal deposited on any land , continues to be coal and the State Government has no authority in law ~~-, .to deal with the same and the slurry deposited on the Company's land belongs to the Company and no other person had authority to collect the same. A B c Article 32 is designed for the enforcement of Fundamental Rights of a citizen by the Apex Court. It provides for an extraordinary procedure to safeguard the Fundamental Rights of a citizen. Right to live is a fu~damental r4ght under Art 21 of the Constitution and it includes the right of enjoyment of pollution free water and air for full enjoyment of lite. If anything endangers or impairs that quality of life D in derogation of law.s, a citizen has right to have recourse to Art. 32 of the Constitution for removing the pollution of water or air which may be detrimental to the quality of life~ A petition under Art. 32 for the prevention of pollution is maintainable at the instance of affected persons or even by a group of social workers or journalists. But recourse to preceeding under Art. 32 of the Constitution should be taken by a person genuinely interested in the protection of society on behalf of the ·community. Public interest litigation cannot be invoked by a person or body or person to satisfy his or its personal grudge and enmity. If such petitions under Article 32, are entertained it would amount to abuse of process of the Court, preventing speedy remedy to other genuine petitioners from this Court, Personal interest cannot be F enforced through the process of this Court under Art. 32 of the Constitution in the garb of a public interest litigation. Public interest litigation contemplates legal proceeding for vindication or enforcement of fundamental rights of a group of persons pr community which are not able to enforce their fundamental rights on account of their incapacity, poverty or ignorance of law. A person invoking the jurisdiction of this G Court under Art. 32 must approach this Court for the vindication of the fundamental rights of affected per11ons and not for the purpose of vindication of his personal grudge or enmity. It is duty of this Court to discourage such petitions and to ensure that the course of justice is not obstructed or polluted by unscrupulous litigants by invoking the extra~ ordinary jurisdiction of this Court for personal matters under the garb H D E [ 1991] 1 S.C.R. 14 SUPREME COURT REPORTS - A of t~e eublic interest litigatio? see _Bandhua Mukti Morcha_ v. _Union of India,_ [1984] 2 SCR 67; _Sachmdanand Pandey_ v. _State of West Bengal,_ [ 1987] 2 SCC 295 at 331; _Ramsharan Autyanuprasi & Anr._ v. _Union of India & Ors.,_ [ 1989] Suppl. 1 SCC 251 and _Chhetriya Pardushan Mukti Sangharsh Samiti_ v. _State of U. P. & Ors.,_ [ 1990] 4 SCC 449. B In view of the above discussion we are of the opinion that this petition has been filed not in any public interest but for the petitioner's personal interest and for these reasons we dismissed the same and directed that the petitioner shall pay Rs. 5,000 as costs. These costs are to be paid to the respondent Nos. 3, 4 & 5. ## T.N.A. ## Petitions dismissed. _T_ \ _(_
End of Judgment Record
Browse All Supreme Court of India (1991) Decisions
1991-04-16

Municipal Corporation, Raipur v. Ashok Kumar Misra

This Supreme Court decision concerns the termination of a probationer, Ashok Kumar Misra, who was appointed as a Lower Division Clerk in the Raipur Municipal Corporation for a two-year probation. Three months after the two-year period, he received a one-month termination notice, prompting a civil suit for declaration that the termination without enquiry violated Rule 9A of the Madhya Pradesh Civil Services Classification, Control and Appeal Rules, 1966, and that he became a permanent employee with continuity of service and arrears of salary. The Trial Court dismissed the suit; the first appellate court upheld the dismissal; the High Court, however, decreed the suit in the respondent’s favor. The appellant Corporation contends that a probationer attains permanent status only on express confirmation, and that termination before confirmation, drawn under Rule 8 of the Madhya Pradesh Government Servants’ General Conditions of Service Rules, 1961, is legally valid if effected with proper notice; the High Court incorrectly held that expiry of probation automatically confers deemed confirmation under Rule 14 (now superseded). The respondent argues that recruitment rules under the Central Provinces and Berar Municipality Act, 1922 (including Rule 14) applied, and absence of action at the end of two years implies deemed confirmation, hence an enquiry would be required for termination. The Supreme Court reverses, holding that deemed confirmation does not arise from mere expiry; confirmation requires express order following prescribed examinations; the appointed authority may terminate during probation with one month’s notice. The rules governing service, not the old Rule 14, apply after the Municipal Corporation adopted government rules.”

1991-07-09

B.P. Singh v. Director General, Ordnance Factories and Ors.

This Supreme Court case concerns the retirement age of teachers employed in central government schools run by Ordnance Factories under the Defence Department. The petitioners, led by B.P. Singh, challenged their retirement at 58 years, arguing that similarly situated teachers in other central government departments were retired at 60, and that such differential treatment violated Articles 14 and 16 of the Constitution. They relied on memoranda that had previously raised the retirement age to 60 for Delhi School Teachers and for Railway school teachers (Sept. 6, 1983 and March 9, 1984). The petition contended there was no rational justification to fix 58 years for Ordnance Factory teachers, and sought to fix the age at 60. The respondents presented an Office Memorandum dated March 10, 1989 issued by the Ministry of Personnel, which announced a de novo review and stated that the age of retirement for all central government employees would be uniformly fixed at 58, with limited exceptions. The memorandum explained that teachers who had joined before 1 April 1989 would continue to enjoy the existing benefit of 60, and that no new appointments to 60-year posts would be made between the memorandum date and 1 April 1989. On these grounds, the Court held there is a uniform policy fixing 58 for central government teachers and dismissed the petition, thus standardizing retirement at 58 across departments.

1991-04-03

Burn Standard Company Limited v. McDermott International Inc. and Another

This is a Supreme Court of India decision addressing whether a Technical Collaboration Agreement (TCA) between Burn Standard Company Ltd. (a Government of India undertaking) and McDermott International Inc. (foreign collaborator) is void ab initio for want of RBI permission under the Foreign Exchange Regulation Act, 1973 (FERA) and whether the arbitration clause can survive if the agreement itself is void. The agreement, executed after approvals by the Secretariat for Industrial Approvals (SIA) and later taken on record by the Government, involved payment in foreign exchange for technical know-how and services. The key dispute centers on what constitutes valid RBI permission under section 28(1) and whether the Exchange Control Manual provisions (paragraphs 24A.11 and 25A.2) can substitute for statutory RBI permission, or if failure to follow the prescribed forms invalidates the contract under section 28(2). The High Court held that the arbitration clause could survive even if the contract were void, and emphasized that RBI permission had been granted after due consideration. The Supreme Court ultimately held that RBI permission under section 28(1) had in fact been granted and that the agreement could not be voided under section 28(2); accordingly, the appeal was dismissed, and the arbitration clause remained enforceable. The decision underscores substance over form and the importance of the RBI’s substantive decision rather than mere procedural lapses.

1991-10-29

Sub-Committee on Judicial Accountability v. Union of India

These writ petitions address the constitutional framework for removal of a Judge under Articles 124(4) and 124(5) and the Judges (Inquiry) Act, 1968, in the wake of a notice of motion by 108 MPs for the removal of Justice V. RamamSwami. The Lok Sabha was dissolved shortly after the Speaker admitted the motion and constituted an Inquiry Committee. Petitioners contended that dissolution of the House lapses the motion and that courts should not intrude in a political process; they pressed for enforcement of the statute and, if required, restraint of the Judge from judicial functions during pendency. The Union of India argued that dissolution causes lapse of all pending business, including the motion, and that Parliamentalone can decide the matter; it also contended that Article 124(5) is merely enabling and that the prevailing parliamentary rules govern the process. The Court, by a majority, held that the motion does not lapse on dissolution and the Court retains jurisdiction to adjudicate the lawfulness of the Speaker’s action. It held that Article 124(5) creates a two-part process: investigation and proof outside Parliament under the statute, followed by a parliamentary motion; the Parliament’s enactment under Article 124(5) overrides the Rules framed under Article 118. The judgment clarifies standing, procedural propriety, and the constitutional balance between judicial independence and political accountability, while declining to grant interim restraining orders and disposing of the petitions accordingly.