Tenetowl LogoTenetowl
Supreme Court of IndiaSupreme Court · 2010Division BenchDisposed of; award made a rule of the Court; ob...

STATE OF RAJASTHAN v NAV BHARAT CONSTRUCTION COMPANY

Case / Petition Number:
Civil Appeal No. 2500 of 2001; Civil Appeal No. 2501 of 2001
Neutral Citation:[2010] 1 S.C.R. 312

Case Synopsis & Summary

This is a Supreme Court judgment in a dispute arising from a government contract for construction of the Bhimsagar Dam. The contract provided for arbitration in case of disputes. Delays led the State to terminate the contractor’s work and reassign the remaining tasks to others. The contractor claimed several amounts; the disputes were referred to two arbitrators, who differed, and an umpire passed an award. The State filed objections under Sections 30 and 33 of the Arbitration Act, 1940, which were dismissed by the trial and appellate courts. In 2005, this Court set aside the umpire’s award and directed the appointment of a new umpire, holding that the proceedings were a continuation of the earlier reference and that the Arbitration Act would continue to apply. The new umpire awarded on 9 September 2006. The State then sought to have the award made a rule of the Court, while the respondent challenged under Sections 30 and 33. The Court ultimately held that it had jurisdiction to entertain the application and the objections, that the award should be filed in this Court, and that the objections should be overruled. The Court also clarified that this was not a fresh reference but a continuation of the prior proceedings and that the Arbitration Act, 1940 applies throughout. It disposed of the matter by making the award a rule of the Court with no costs awarded to either side.

Precedent Explorer

Find Cases Like This

Explore other judgments dealing with similar legal situations, facts, or statutory provisions.

Case Details & Bench

Court
Supreme Court of India
Hon'ble Judges
  • Tarun Chatterjee
  • R. M. Lodha
Judgment Date
2010-01-08
Court Decision / Holding
The Court allowed the application for making the award a rule of the Court and rejected the objections filed under Sections 30 and 33 of the Arbitration Act, 1940. There will be no order as to costs.
Final Disposition
Disposed of; award made a rule of the Court; objections under Sections 30 and 33 overruled; no costs.

Parties to the Case

Appellants / Petitioners

  • State of Rajasthan

Respondents

  • Nav Bharat Construction Company

Legal Representation & Advocates

Counsels for Petitioners

  • • Pallav Shishodia
  • • Mool Chand Luhadia

Provisions of Law Cited

Arbitration Act, 1940 – Section 30Arbitration Act, 1940 – Section 33Arbitration Act, 1940 – Section 20Arbitration Act, 1940 – Section 11

Legal Doctrines & Maxims

  • The jurisdiction of the court under Section 30 of the Arbitration Act, 1940 is not appellate in nature; an award cannot be set aside on the grounds that it is erroneous and the court cannot re‑appreciate the evidence or substitute its own view.
  • The court may set aside an award if the arbitrator mis-conducted the proceedings or ignored the terms of the contract or acted beyond the four corners of the contract.
  • Not a new reference but continuation of the earlier proceedings; the Arbitration Act, 1940 continues to apply.

Submissions & Arguments

Contentions of Appellants / Petitioners

The State of Rajasthan argued that the award of the Umpire—after the earlier award was set aside and a new Umpire appointed—must be filed in this Court, as held in the 2005 judgment, and that the Arbitration Act, 1940 continues to apply to this proceeding rather than being a new reference. The Court’s jurisdiction to entertain the application for making the award a rule of the Court and to consider the objections under Sections 30 and 33 was pressed as a continuation of the proceedings. The Court was urged to uphold the validity of the new Umpire’s award and to decide the disputes on their merits, including the claims that were already adjudicated in earlier proceedings.

Contentions of Respondents

Nav Bharat Construction Company contended that the matter was not a new reference and that the Court should decline to entertain the applications; the objections under Sections 30 and 33 were argued to be unsustainable or not properly entertained; they argued that the matter should be referred back to a competent forum; they also contested the earlier findings on certain claims as binding on the new umpire and sought to reopen those issues.

Legal Doctrine & Issue Explorer

Explore This Legal Issue

Find relevant judgments and authoritative positions on the legal questions discussed here.

Cited Precedents (6)

Case NameCitationTreatmentExplanation
Garwal Manda/ Vikas Nigam Ltd. vs. Krishna Travel Agency2008 (6) SCC 741Mentioned OnlyCited as part of the doctrinal backdrop; not a binding precedent for the decisive outcome.
Bharat Coking Coal Ltd. vs Annapurna Construction2008 (6) SCC 732Mentioned OnlyCited for general doctrinal context; not controlling in the present decision.
McDermott International Inc. vs. Burn Standard Co. Ltd and Others2005 (10) SCC 353PositiveThree-judge bench held that the umpire must file the award in Court and that objections and entertainability lie in this Court; directly supports the Court’s jurisdiction in this case.
Bhagwati Oxygen Ltd. vs. Hindustan Cooper Ltd.2005 (6) SCC 462PositiveCited for the principle that Section 30 does not permit appellate re‑view; supports non‑appellate nature of the jurisdiction.
Food Corporation of India vs. Chandu Construction2007 (4) SCC 697PositiveCited for upholding that ignoring the contract terms or misapplying them can lead to setting aside the award.
Tarapore & Co. v. State of M.P.1994 (3) SCC 521PositiveCited to illustrate the effect of contract terms on claims related to wage increases.
Case Applicability Diagnostic

Apply This to My Facts

Share your situation and test whether this judgment governs, supports, or challenges your case.

Official Judgment Record
•4,580 words•~21 min read

In The Court Record

STATE OF RAJASTHAN v NAV BHARAT CONSTRUCTION COMPANY

## [2010] 1 S.C.R. 312 A ## STATE OF RAJASTHAN _V._ ## M/S. NAV BHARAT CONSTRUCTION COMPANY (Civil Appeal No. 2500 of 2001} ## **B** ## JANUARY 8, 2010 ## **[TARUN CHATTERJEE AND R.M. LODHA, JJ.)** _Arbitration Act, 1940: s.30_ - _Jurisdiction of Court to set aside the award_ - _Held: The jurisdiction of the Court under_ C _s.30 is not appellate in nature_ - _Court is not empowered to re-appreciate the evidence and examine the correctness of conclusions arrived at by the Umpire in considering an application for setting aside the award_ - _It is also not open to the court to interfere with the award merely if in its opinion,_ D _another view was possible_ - _On facts, no reason to differ from_ aw<~rd _of Umpire as he rightly considered the entire evidence._ _Jurisdiction: Supreme Court appointing new arbitrator and dimcted him to file award before it_ - _New arbitrator filing award_ E _in Supreme Court_ - _Jurisdiction of Supreme Court to entertain_ · _the application for making the award a rule of the cowt as well_ - _as the objections, challenged Held: Supreme Court has the jurisdiction._ **Dispute arose between the parties and the matter F was referred to arbitration. There was difference of opinion between the arbitrators and matter was referred to an Umpire. The Umpire entered into reference and passed an award. The appellant filed objections under Sections 30 and 33 of the Arbitration Act, 1940 which** G **wine dismissed. In appeal, respondent also filed cross appeals claiming compound interest. High Court dismissed both the appeals.** **Both the parties came up before this Court. This** **H** 312 STATE OF RAJASTHAN _v._ NAV BHARAT CONST. 313 COMPANY Court by judgment dated 4.10.2005 set aside the award A of the Umpire and the judgment of High Court, and appointed new Umpire and also clarified that it was not a new reference but continuation of the earlier proceeding and the Arbitration Act, 1940 would continue to apply. The new arbitrator passed an award. Before this B Court, appellant filed an application for making the award a rule of Court and at the same time the respondent filed an objection under Sections 30 and 33 of the Act. An Interlocutory Application was also filed by the respondent challenging the jurisdiction of this Court to make the C award absolute and also to consider the objections raised by the respondent. B Dismissing the IA and objections filed under Sections 30 and 33 and allowing the application for making the award a rule of the Court, the Court D HELD: 1. The judgment of this Court dated 4.10. 2005 made it clear in its operative part, that the award that would be passed by the Umpire must be filed in this Court. It was also clarified in the judgment itself that it was not a case of a new reference but a continuation of the earlier proceeding and thus the Act would continue to apply. Therefore, this Court had the jurisdiction to entertain the application of the appellant and also the -objectfons filed by the respondent. [Para 4] [319-F-H] _Garwal Manda/ Vikas Nigam Ltd. vs. Krishna Travel Agency_ 2008 (6) SCC 741; _Bharat Coking Coal Ltd. vs. Annapurna Construction_ 2008 (6) SCC 732; _Mcdermott International Inc. vs. Burn Standard_ Co. _Ltd and Others_ 2005 (10) sec 353, referred to. E F G 2. Under Section 30 of the Arbitration Act, 1940, the Court is not empowered to re-appreciate the evidence and examine the correctness of the conclusions arrived at by the Umpire in considering an application for setting H 314 SUPREME COURT REPORTS [201 O] 1 S.C.R. - A aside the award. The jurisdiction of the court under Section 30 of the Act is not appellate in nature and the award passed by the Umpire cannot be set aside on the ground that it was erroneous. It is also not open to the court to interfere with the award merely because in the - B opinion of the court, another view is equally possible. [Paras 6 and 7) (322-E-F; 323-D-E] 3.1. Perusal of judgment dated 4.10. 2005 shows that the claim Nos. 2 and 26 were elaborately considered and this Court in the said judgment came to a clear finding C with regard to Claim No.2 and 26 that the respondent would not be entitled to such claims. In this view of the matter, the Umpire was fully justified in not reconsidering the same while passing an award. [Para 5] (322-8-C] D _Bhagwati Oxygen Ltd. vs. Hindustan Cooper Ltd._ 2005 (6) SCC 462; _Food Corporation of India vs. Chandu Construction_ 2007 (4) SCC 697, relied on. 3.2. Since Claim Nos.4, 6, 9, 13, 23, 32, 33, 36 and 38 E of the respondent were accepted by the Umpire and the Award has been passed in respect of the said claims in favour of the respondent, it is held not necessary to deal with this part of the award any further. So far as Claim Nos. 1,3,5, 7,8,10, 11, 12, 14-22,24,25,27,28, 29,30,31, 34, 35, 37 and 39 are concerned, the Umpire after going F through the objections of the respondent and after hearing the parties in respect of these claims rightly rejected the same and there is no reason to set aside the said award on the ground that the jurisdiction of the court is not appellate in nature nor such an award could be G found to be erroneous. Accordingly, the objections are overruled. [Para 8] [323-F-H; 324-A-B] 4. The respondent had claimed compound rate of interest which was not granted by the Umpire. The H claimant had claimed compound interest with quarterly STATE OF RAJASTHAN _v._ NAV BHARAT CONST. 315 COMPANY rest while the respondent had opposed the said rate of A interest. While rejecting the said claim of the claimant, the Umpire had rightly observed that there was no necessity for him to fix any other rate of interest because on the basis of the award passed by the Umpire, the claimant had to return the substantial amount received by him. In B view of that, the Umpire in his award directed that difference of amount which has now become refundable by virtue of the award would be returned back to the State of Rajasthan with interest from the date of recovery by the claimant and the same was allowed by the c previous Umpire till the date of repayment/recovery. There is no reason to differ from the award of the Umpire on this score, because the Umpire rightly considered the entire aspect of interest and passed an award. [Paras 9 and 10) [324-B-F] D |and10)[324-B-F]|[324-B-F]|[324-B-F]||D| |---|---|---|---|---| ||Case Law Reference :|||| |2008|(6)sec741|referred to|Para4|| |2008|(6)sec732|referred to|Para4|E| |2005|(10)sec353|referred to|Para4|| |2005|(6Jsec462|relied on|Para6|| |_,12001_|(4)sec697|relied on|Para7|| |CIVIL|CIVILAPPELLATEJURISDICTION|JURISDICTION: Civil Appeal No.|: Civil Appeal No.|F| CIVIL APPELLATE JURISDICTION : Civil Appeal No. 2500 of 2001. From the Judgment & Order dated 10.12.1999 of the High Court of Judicature for Rajasthan at Jaipur Bench, Jaipur in S.B. Civil Misc. Petition No. 1091 of 1996. G WITH C.A. No. 2501 of 2001. Pallav Shishodia, ~ ,.. :! Kumar, Mool Chand Luhadia-inH 316 SUPREME COURT REPORTS (2010] 1 S.C.R. A person, for the appearing parties. The Judgment of the Court was delivered by **TARUN CHATTERJEE, J.** 1. The appellant, State of Rajasthan, invited tenders for construction of Bhimsagar Dam B in which one of the tenderer was the respondent. The tender of the respondent was accepted. Accordingly, a contract was awarded to the respondent and under the contract the work was to be started on 16th of November, 1978 and the date of completion was fixed on 15th of May, 1981. One of the terms C of the contract was that if any difference or dispute arises between the parties, such dispute or difference shall be referred to arbitration. However, the work was not completed within the time allotted and time was thereafter extended. lnspite of extension of time, the work was not completed. For that reason, D the State of Rajasthan terminated the contract and got the remaining work done from some other contractor. 2. The respondent raised various claims which were rejected by the State of Rajasthan. The respondent, therefore, E moved an application under Section 20 of the Arbitration Act, 1940 (in short the 'Act') for referring the claims mentioned therein to arbitration. The District Judge, Jhalawar by an order dated 11th of November, 1982 held that only one claim was referable to arbitration and refused to refer the other three F claims to arbitration. The respondent filed an appeal before the High Court of Rajasthan at Jaipur and the High Court by its order dated 7th of June, 1984 held that it was for the Arbitrator to de~cide whether the claims were to be awarded or not and accordingly directed that all the four claims be referre0 to arbitration. The disputes were referred to two Arbitrators. The G respondent, however, filed 39 claims amounting to Rs.42,59, 155.56 before the /1.rbitrators. The parties led oral and documentary evidence. There was a difference of opinion between the two Arbitrators. Therefore, the Arbitrators referred the dispute to an Umpire. The State of Rajasthan. the appellant H herein, thereafter filed an application under Section 11 of the ## STATE OF RAJASTHAN _v._ NAV BHARAT CONST. 317 COMPANY [TARUN CHATTERJEE, J.] Act for removal of the Umpire on the ground of bias. This A application was dismissed on 16th of November, 1993. The appellants filed a revision case which also came to be dismissed by the High Court in January, 1995. The Umpire entered into the reference and passed an award on 29th of May, 1995. B B 3. The State of Rajasthan, the appel!ant herein, filed objections under Sections 30 and 33 of the Act which were dismissed by the trial court and in appeal the respondent filed a cross appeal claiming compound interest. The High Court by a judgment dismissed both the appeals. Feeling aggrieved, C both the parties approached this Court and two Civil Appeals were registered. C.A.No.2500 of 2001 was by the State of Rajasthan which was aggrieved by the dismissal of their objection filed under Sections 30 and 33 of the Act and C.A.No.2501 of 2001 was by the respondent against the D dismissal of their claim for compound interest. By a judgment and order dated 4th of October, 2005 passed in the aforesaid two appeals, this Court had set aside the award of the Umpire and the judgment of the High Court by the following directions: E "Under the circumstances and .for reasons set out hereinabove, we set aside the award and appoint Justice N.Santosh Hegde, a retired Judge of this Court as the Umpire. The Umpire, Mr.V.K.Gupta st1all forthwith forward all papers and documents to Justice N.Santosh Hegde at F his residence i.e. 9, Krishna Menon Marg, New Delhi. The parties shall appear before Justice N.Santosh Hegde on 6.10.2005 at 5.p.m. at 9, Krishna Menon Marg, New Delhi. Justice N.Santosh Hegde shall fix his fees which shall be borne by both the parties equally. Justice N.Santosh Hegde G is requested to fix the schedule and give his award with a period of 4 months from the date of receipt of all the papers and documents from the outgoing Umpire Mr.V.K.Gupta. _The award to be filed in this Court._ We leave the question of grant of interest open to be decided by the Umpire in accordance with law. H H 318 SUPREME COURT REPORTS (2010] 1 S.C.R. A Lastly, it is clarified that _this is not_ a _new reference but_ a _continuation of the earlier proceeding_ and thus the Arbitration Act, 1940 shall continue to apply. 4. Accordingly, in compliance with the judgment of this Court as aforesaid, Mr.Justice N.Santosh Hegde, (as His 8 Lordship then was), entered into reference and passed his award on 9th of September, 2006. Now the State of Rajasthan has filed an application for making the award a rule of the Court and at the same time the respondent filed an objection under Sections 30 and 33 of the Act. An Interlocutory Application was C also filed by the respondent challenging the jurisdiction of this Court to make the award absolute and also to consider the objections raised by the respondent against the award passed by the Umpire in pursuance of the order passed on 4th of October, 2005. According to the respondent, who appeared in D person, the application and objections filed by the parties must be sent back to the court of competent jurisdiction for deciding the same in accordance with law, because after the judgment was passed and the earlier award was set aside by the impugned judgment, this Court had become functus officio to E entertain such applications. Therefore, before we go into the question regarding the objections raised by the respondent under Sections 30 and 33 of the Act and the application for making the award a rule of the Court, we must first deal with the Interlocutory application, that is to say, whether this Court F still retains the jurisdiction to entertain the award passed by the Umpire or to consider the objections to the same or the matter should go back to the court of competent jurisdiction for considering the said application and objections in accordance with law. According to Mr. Mool Chand Luhadia, appearing in G person, this Court is ceased to have jurisdiction after the appeal was disposed of and a new Umpire was appointed who passed an award on 9th of September, 2006. In support of this contention that this Court cannot have the jurisdiction to entertain the application filed by the appellant to make the award a rule H of the court and also the objection filed under Sections 30 and ## STATE OF RAJASTHAN _v._ NAV BHARAT CONST. 319 COMPANY [TARUN CHATTERJEE, J.] 33 of the Act, he had relied on certain decisions of this Court A out of which strong reliance was placed on the decision in _Garwal Manda/ Vikas Nigam Ltd. vs. Krishna Travel Agency_ (2008 (6) SCC 741) and also the decision in _Bharat Coking Coal Ltd. vs Annapurna Construction_ (2008 (6) SCC 732). This submission of Mr.Luhadia, who appeared in person was B contested by Mr.Pallav Shishodia, learned senior counsel appearing on behalf of the State of Rajasthan. According to Mr.Shishodia, in view of the decision of a three-Judge Bench of this Court in _Mcdermott International Inc. vs. Burn Standard Co. Ltd and Others_ [2005 (10) SCC 353), this question is no C longer res integra. In our view, the submission of Mr.Shishodia must be accepted. From the judgment of this Court dated 4th of October, 2005, it has been made clear by this Court in the operative part of the same, as noted herein earlier, that the award that would be passed by the Umpire must be filed in this 0 Court and secondly it was clarified in the judgment itself that this was not a case of a new reference but a continuation of the earlier proceeding and thus the Act shall continue to apply. In _Mcdermott International Inc._ (supra), a three-Judge Bench decision of this Court clearly observed that since the Arbitrator E was directed to file his award in this Court, the objections as well as the entertainability of the application of the appellant for making the award a rule of the Court must be filed in this Court alone and, therefore, this Court has the jurisdiction to entertain the application of the appeflant and also the objections filed by the respondent. In view of the discussions made herein above F and in view of the three-Judge Bench decision of this Court, namely, _Mcdermott International_ (supra), it would not be necessary for us to deal with the other two decisions as referred to herein earlier. That apart, in the judgment dated 4th of October, 2005, it has been made clear that the award was to G be filed in this Court and that this was not to be taken as a new reference but a continuation of the earlier proceeding, thus the Act shall continue to apply. Accordingly, the question regarding entertainability of the aforesaid two applications namely, the application for making the award a rule of the court and the H [2010] 1 S.C.R. ## 320 SUPREME COURT REPORTS - A objections under Sections 30 and 33 of the Act filed in this Court could not arise at all. 5. Let us now consider the objections filed by the respondent against the award passed by the Umpire under Sections 30 and 33 of the Act. Since we have already overruled 8 the objections raised by the respondent about the entertainability of the two applications by this Court, we now deal with the objections filed by the respondent in respect of thE~ various claims made by them for passing an award in their C favour. According to Mr.Luhadia, since the first award of the Umpire Mr.V.K.Gupta was set aside, and a new Umpire was appointed after setting aside the said award it would be evident from the judgment of this Court that the intention of this Court was to permit the respondent to raise all their objections to the clc:1ims put forward by it including the claim No.2 and 26. We D am unable to accept this contention of Mr.Luhadia. So far as Claim No.2 and 26 are concerned, on a perusal of the judgment of this court, it is difficult to accept the argument of Mr.Luhadia as we find from the said judgment that the claim Nos. 2 and 26 were elaborately considered in the judgment and - E this Court in the said judgment came to a clear finding with regard to Claim No.2 and 26 that the respondent would not be entitled to such claims. While rejecting Claim Nos. 2 and 26, this Court categorically made the following observations which we reproduce herein below : F - "As regards claim No. 2 Mr. Luhadia fairly admitted - that Clause 5.11 (iii) of the Contract requires chiseling of stones on all sides. He however submitted that the rates given in Schedule G were only for chiseling of stones on one side. He submitted that this was clear from Note 1 - G under Schedule G which stated that Schedule G was based on B.S.R. 1975. He submitted that B.S.R. 1975 showed that such rates were only for chiseling stones on one side. He submitted that when the stone has to be chiseled on all sides the rates given in B.S.R. 1975 were H ## STATE OF RAJASTHAN _v._ NAV BHARAT CONST. 321 COMPANY [TARUN CHATTERJEE, J.] to be applied. He submitted that claim No. 2 was based A . on those rates. We are unable to accept this submission of Mr. Luhadia. The Contract is very specific. The work specified in the Contract has to be done at the rates specified in Schedule 'G'. Even though Schedule G may be based on B.S.R. 1975 it is not exactly as B.S.R. 1975. B Where in respect of a work specified in the contract the rate has been given in Schedule G that work could only be done at that rate. Works specified in the Contract does not become extra work. It is. only in respect of extra work that rates specified in B.S.R. 1975 can be applied. _To us_ c _it is clear that the claim No. 2 is contrary to the terms of the Contract. It is barred by Clauses_ 57, _60 and 61 of the Contract._ As regards claim No. 26, Mr. Luhadia relied upon the case of _Tarapore_ & Co. _v. State of M.P._ [1994 [3] sec 521]. In this case, the question was whether the 0 contractor was entitled to claim extra amounts because he had to pay increased wages to his workers. This Court has held that the contractor would have tendered on the basis of the then prevailing wages and as the contract required the contractor to pay the minimum wages if the minimum wages increased it was an implied term of the contract that E he would not be entitled to claim the additional amount. However, it must be noted that, in this case, there was no term in the contract which prohibited any extra claims being made because of the increase in WC1ges. Clause 31 of the Special Conditions of the Contract, which has been F reproduced hereinabove, specifically bars the contractor from claiming any compensation or an increase in rate under such circumstances. Not only that but the Respondent had with their initial tender put in a term which provided that if there was any increase in the minimum G wages by the Government the rates quoted by him would be increased by the same percentage: At the time of negotiation this clause was dropped. _Thus, the Respondent had themselves specifically agreed not to claim any compensation or increase by reason of_ H [201 OJ 1 S.C.R. 322 SUPREME COURT REPORTS A _increase in wages. This claim could therefore not have been granted."_ From a reading of this paragraph 30 of the judgment of this Court, it is clear that this Court in the judgment has, in detail, B considered Claim Nos.2 and 26 and on consideration of the materials on record and the terms of the contract between the parties rejected the aforesaid two claims. In this view of the matter, we must accept the finding of the Umpire that since these two claims were clearly and elaborately considered and C thereafter rejected by this Court in the said judgment, it was not open for him to reconsider the same while passing the award. In view of this conclusion arrived at by this Court in the aforesaid judgment, the Umpire was fully justified in not reconsidering the same while passing an award. D 6. The jurisdiction of the court to set aside an award under Section 30 of the Act has now been settled by catena of decisions of this Court as well as by the different High Courts in India. Taking those principles into consideration, it would thus be clear that under Section 30 of the Act it must be said that E the court is not empowered to re-appreciate the evidence and examine the correctness of the conclusions arrived at by the Umpire in considering an application for setting aside the award. In this connection, we may refer to a decision of this Court in the case of _Bhagwati .Oxygen Ltd. vs. Hindustan_ F _Cooper Ltd._ [2005 (6) SCC 462]. In that decision, this Court observed in paragraph 25 .as follows :- G H "This Court has considered the provisions of Section 30 of the Act in several cases and has held that the court while exercising the power under Section 30, cannot reappreciate the evidence or examine correctness of the conclusions arrived at by the Arbitrator. The jurisdiction is not appellate in nature and an award passed by an Arbitrator cannot be set aside on the ground that it was erroneous. It is not open to the court to interfere with the STATE OF RAJASTHAN _v._ NAV BHARAT CONST. 323 COMPANY [TARUN CHATTERJEE, J.] award merely because in the opinion of the court, another A view is equally possible. It is only when the court is satisfied that the Arbitrator had mis-conducted himself or the proceedings or the award had been improperly procured or is "otherwise" invalid that the court may set aside such award." B 7. Similarly in the case of _Food Corporation of India vs. Chandu Construction_ [2007 (4) SCC 697) in which one of us (Chatterjee,J.) was also a party, it was held that when the Arbitrator or the Umpire as the case may be, had ignored the C specific terms or had acted beyond the four corners of the contract, it was open for the court in the exercise of its power under Section 30 of the Act to set aside the award on the ground that the Arbitrator could not ignore the law or misapply the terms of the contract in order to do what he thought was just and reasonable. That apart, the law is also settled as D referred to herein earlier that the jurisdiction of the court under . Section 30 of the Act is not appellate in nature and the award passed by the Umpire cannot be set aside on the ground that it was erroneous. It is also not open to the court to interfere with the award merely because in the opinion of the court, another E view is equally possible. Keeping these principles as lait:I down by this Court in the aforesaid two decisions, let us now consider the award passed by the Umpire in respect of the claims of the respondent excluding Claim Nos. 2 and 26. F 8. Since Claim Nos.4, 6, 9, 13, 23, 32, 33, 36 and 38 of the respondent were accepted by the Umpire and the Award has been passed in respect of the said claims in favour of the respondent, it would not be necessary for us to deal with this part of the award any further. So far as Claim Nos. 1, 3, 5, 7, G 8, 10, 11, 12, 14-22, 24, 25, 27, 28, 29,30, 31, 34, 35, 37 and 39 are concerned, we find that the Umpire after going through the objections of the respondent and after hearing the parties in respect of these claims rejected the same and we do not find any reason to set aside the said award on the ground that H SUPREME COURT REPORTS [2010] 1 S.C.R. 324 - A the jurisdiction of the court is not appellate in nature nor such an award could be found to be erroneous. Accordingly, we do not find any reason to accept the objections of the respondent in this regard. The objections are overruled. 9. Before parting with this judgment, there is another 8 aspect to be considered at this stage. As noted herein earlier, the respondent has claimed compound rate of interest which was not granted t:iy the Umpire. The claimant had claimed compound interest with quarterly rest while the respondent had C opposed the said rate of interest. While rejecting the said claim of the claimant, the Umpire had rightly observed that there was no necessity for him to fix any other rate of interest because on the basis of the award passed by the Umpire, the claimant had to return the substantial amount received by him. In view of that, the Umpire in his award directed that difference of D amount which has now become refundable by virtue of the award would be returned back to the State of Rajasthan with interest from the date of recovery by the claimant and the same was allowed by the previous Umpire till the date of repayment/ recovery. E 10. We do not find any reason to differ from the award of the Umpire on this score, because the Umpire has rightly considered the entire aspect of interest and passed an award which can never be said to be erroneously rejected by him. F 11. For the reasons aforesaid, we allow the application for making the award a rule of the court and reject the objections filed under Sections 30 and 33 of the Act by the respondent. There will be no order as to costs. G D.G. Matters disposed of.
End of Judgment Record
Browse All Supreme Court of India (2010) Decisions
2010-09-24

Department of Telecommunications v. Gujarat Co-operative Milk Marketing Federation Ltd.

This Supreme Court decision concerns a billing dispute arising from two bi-monthly telephone bills totaling Rs. 4,54,652 raised against the Managing Director of the Gujarat Co-operative Milk Marketing Federation Ltd. for calls categorized as international “party” or “sex talk” calls. The respondent subscriber alleged mischarging and that calls were made from another number, prompting a complaint to the Department. Verification upheld the bills; an administrative appeal was dismissed; the matter was referred to arbitration under section 7B of the Indian Telegraph Act, 1885, following a High Court direction. The arbitrator, Vineet Bhatia, concluded the bills were proper. The respondent challenged this award by writ petition, which the High Court (Single Judge) quashed, holding that the arbitrator was junior to the appellate authority, and proceeded to find the award invalid on presumptions and inferences unsupported by evidence; a Letters Patent Appeal was dismissed. The Supreme Court reversed, holding that the High Court exceeded its judicial review scope, misapplied the standard for review of arbitral awards under section 7B, and erred in imputing bias based on rank. It affirmed that the arbitrator’s findings were grounded in the department’s records and meters, and that independence was maintained. The appeal is allowed and the writ petition dismissed, with the High Court orders set aside.

2010-11-23

BHAGWAN BUDHA PRATHMIK TECHNICAL TRAINING COLLEGE NIRMALI v. STATE OF BIHAR

This is a consolidated Supreme Court decision in Civil Appeal Nos. 9896 and 9897 of 2010 arising out of Bihar. Bhagwan Budha Prathmik Technical Training College, Nirmali, a minority Buddhist institution established in 1987, challenged Bihar’s and other authorities’ recognition/approval decisions for its teacher-training course in light of the National Council for Teacher Education Act, 1993 (NCTE Act). The central issue is whether, after the NCTE Act’s appointed day (1 July 1995), State Governments retain power to grant recognition to teacher-education institutes and whether students of unrecognized colleges may sit for qualifying examinations. The matter traces a long litigation history: initial directions in the early 1990s required the Government to decide recognition while allowing students to appear at their own risk; subsequent orders and representations culminated in a 16 March 2007 order recognizing the college from 1987-89 on the ground that inspection warranted it, followed by a 2 September 2008 order withdrawing that recognition in light of NCTE’s sole jurisdiction post-appointed day. The High Court affirmed the sequence, but this Court held that a power to issue an order includes a power to withdraw it for valid reasons, and that recognition is vested in the NCTE after the appointed day. The judgment emphasizes that the NCTE Act must be implemented with full force to protect standards in teacher education. Ultimately, the Supreme Court dismissed the appeals, modified a cost order, and held there should be no further costs in these appeals, while acknowledging the students’ plight and the need for orderly implementation of the regulatory regime.

2010-06-03

State of Punjab & ors. v. G.S. Randhawa

This Civil Appeal arises from a petition challenging a demand for additional price under the Punjab Urban Estate (Sale of Sites) Rules, 1965. The Supreme Court hears counsel for the appellant and notes that the respondent did not enter appearance. Relying on the decision in Smt. Fuljit Kaur v. State of Punjab & Ors., (2010) 7 SCR 317, the Court states that, for the reasons recorded in Civil Appeal No. 5292 of 2004 (the Fuljit Kaur decision) decided on this date, the appeal must be allowed. The High Court’s December 6, 2006 order is set aside and the Demand Notice is upheld. The appellant is entitled to recover the additional price in accordance with law. The decision clarifies that liability to pay additional price under the Punjab Urban Estate Rules can be enforced consistent with the Fuljit Kaur framework, upholding the validity of the demand and permitting recovery by the State. The judgment thus resolves the previous split on allotment price adjustments and prescribes a uniform approach for enforcing such recoveries in analogous cases going forward.

2010-07-15

Harish Singh Nagra & Ors. v. Kapil Sibal & Ors.

Mehfil-e-Wukala, a Supreme Court cultural-literal association of lawyers, published a souvenir containing messages, articles, and poems by judges and senior advocates. Kapil Sibal, a senior advocate and then a candidate for President of the Supreme Court Bar Association, sent a message criticizing the junior Bar and urging reforms, which was circulated within Mehfil’s members but not released to the press or sold publicly. Petitioners, five practicing advocates from the Punjab and Haryana High Court, filed criminal contempt proceedings under Article 215 of the Constitution alleging that Sibal conspired with others to bring the administration of justice into disrepute. The High Court transferred the case to this Court. The central issue was whether the message, read in its proper context, amounted to contempt under Section 2(c) of the Contempt of Courts Act, 1971. The Court held that the message, read in its prospective context, did not scandalize or tend to scandalize any court, nor obstruct the administration of justice; it was a fair critique aimed at improving the system. Citing P.N. Duda, Mulgaokar, Ambard, Vishwanath, and others, the Court reaffirmed that freedom of expression under Article 19(1)(a) protects fair, reasoned criticism of judgments and judicial institutions. It noted that the Times of India article excerpt misrepresented the message, but the souvenir’s limited internal distribution and the respondent’s apology supported dismissal. Accordingly, the contempt petition was dismissed and notices discharged.