STATE OF RAJASTHAN AND ANR. v. M/S. NA V BHARAT CONSTRUCTION CO.

Case / Petition Number:
Civil Appeal No. 8115 of 2001
Neutral Citation:2001 (Supp.) 5 S.C.R.

Case Synopsis & Summary

This Supreme Court decision concerns a dispute arising from an arbitration award in a government contract between the State of Rajasthan (and an additional respondent) and M/s Na V Bharat Construction Co. The arbitrator awarded 18% interest on the principal. The District Court fixed 15% from decree; the Rajasthan High Court confirmed the arbitrator’s award. On appeal, the State contends that the award is illegal for three reasons: (i) the arbitrator failed to consider a counter-claim or set-off raised by the State; (ii) a second reference to the arbitrator under Order 2 Rule 2 CPC was not maintainable; and (iii) the arbitrator granted interest contrary to the agreement’s terms. The Court rejects the first two objections, noting that no counter-claim or set-off was filed, and that the second reference pertained to claims arising after final bill and is not actionable under Order 2 Rule 2 CPC. On the third point, the Court observes that the contention about Clause 23 of the contract was not raised before the arbitrator and therefore not decided. The Court holds that the award is a reasoned one and within the scope of review under the Arbitration Act, and accordingly reduces the interest to 6% per annum. The SLP by the contractor seeking higher interest is dismissed, and the parties bear their own costs. The appeal is disposed of.

Precedent Explorer

Find Cases Like This

Explore other judgments dealing with similar legal situations, facts, or statutory provisions.

Case Details & Bench

Court
Supreme Court of India
Hon'ble Judges
  • M.B. Shah
  • B.N. Agrawal
Judgment Date
2001-11-27
Court Decision / Holding
The Court held that there was no counter-claim or set-off raised, and the second reference was not maintainable under Order 2 Rule 2 CPC. The contention regarding Clause 23 was not raised before the arbitrator and need not be decided in this appeal. The award, being reasoned, falls within the narrow review permissible under the Arbitration Act. The Court modified the rate of interest to 6% per annum on the principal amounts and dismissed the Special Leave Petition seeking higher interest. The appeal is disposed of, with parties bearing their own costs.
Final Disposition
Appeal disposed of; award modified to 6% interest; SLP dismissed; costs to both sides.

Parties to the Case

Appellants / Petitioners

  • State of Rajasthan and Anr.

Respondents

  • M/S. NA V BHARAT CONSTRUCTION CO.

Legal Representation & Advocates

Counsels for Petitioners

  • • Ashwani Kumar (Senior Counsel)

Counsels for Respondents

  • • G.L. Sanghi (Senior Counsel)

Provisions of Law Cited

Code of Civil Procedure, 1908, Order 2 Rule 2Arbitration Act (general reference to grounds for setting aside/arbitration awards)

Legal Doctrines & Maxims

  • Scope for setting aside the award is limited to the grounds available under the Arbitration Act.
  • A reasoned award is proper and review is confined to statutory grounds.

Submissions & Arguments

Contentions of Appellants / Petitioners

The State contends that the arbitrator erred by not considering a counter-claim/set-off raised on the ground that Accountant General’s objection to labour charges was raised after a long lapse; that a second reference under Order 2 Rule 2 CPC was not maintainable since post-bill claims were not admissible under that Rule; and that the arbitrator granted interest despite a contract clause (Clause 23) prohibiting or limiting such payment. It further argues that the award should be set aside on these grounds and that the contract terms should govern recovery of interest.

Contentions of Respondents

The contractor contends that no counter-claim was pleaded before the arbitrator, hence no set-off could be considered; the second reference concerns post-final-bill claims and is not actionable under Order 2 Rule 2 CPC; and while Clause 23 could affect interest, it was not argued before the arbitrator, so the issue was not decided here. The respondent also relies on this Court’s decisions interpreting similar clauses to permit interest where due. The award is argued to be reasoned and within permissible limits under the Arbitration Act.

Legal Doctrine & Issue Explorer

Explore This Legal Issue

Find relevant judgments and authoritative positions on the legal questions discussed here.

Cited Precedents (1)

Case NameCitationTreatmentExplanation
State of U.P. v. Harish Chandra and Co.[1999] 1 SCC 63Mentioned OnlyCited for persuasive consideration of contractual interest issues, but not relied upon as binding or decisive in the present appeal.
Case Applicability Diagnostic

Apply This to My Facts

Share your situation and test whether this judgment governs, supports, or challenges your case.

Official Judgment Record
•1,591 words•~8 min read

In The Court Record

STATE OF RAJASTHAN AND ANR. v. M/S. NA V BHARAT CONSTRUCTION CO.

A # STATE OF RAJASTHAN AND ANR. _v._ ## M/S. NA V BHARAT CONSTRUCTION CO. ## NOVEMBER 27, 2001 ## B [M.B. SHAH AND B.N. AGRAWAL, JJ.] ## _Arbitration :_ c _Arbirration Award-Interest on delayed payment-Claim for-Award passed by_ arbitrator~Con.finned _by High Court-On appeal, held, Arbitrator_ _**passed a reasoned av.[1] ard-Non-consideration of counter clailn and grant o.f** interest of delayed payment by Arbitrator justified-Order 2 Rule 2 not applicable to the second_ r~ference _to the Arbitrator-Code o,f Civil P."ocedure, 1908 Order 2 Rule_ 2. D E Respondent-contractor claimed interest on delayed payment from the appellants. Arbitrator passed an award and granted interest @ 18 % on the principal amount claimed. District Court awarded interest at the rate of 15% from the date of decree. High Court confirmed the award made by the Arbitrator. In this appeal, it was contended that the Award made by the Arbitrator was illegal because Arbitrator failed to consider counter-claim; and that the second reference to Arbitrator was not maintainable under Order 2 Rule 2 of CPC and that the Arbitrator awarded interest despite the .contrary condition in the agreement. F ## Disposing of the appeal, the Court G HELD **1.** As no set off or any counter claim was filed by the appellant for the alleged amount due and payable by the contractor on the alleged ground that Accountant General's Officer has raised objection for payment of labour charges at accelerated rate, Arbitrator has rightly not considered the same which was sought to be raised after lapse of 4 years of reference. (352-G; **H;** 353-A] 2. With regard to subsequent claims arising after the first reference, H that is after the bill was prepared, second reference to tbe Arbitrator was 350 STATE _v._ NA V BHARAT CONSTRUCTISJN CO. [SHAH. J.] 351 not maintainable under Order 2 Rule 2 CPC as rightly held by the Arbi· tration and the courts below. [353-B; C] A 3. The appellant did not raise the contention before the arbitrator or at any stage thereafter that under Clause 23 of the Agreement between the parties, contractor was not entitled to recover any interest on delayed payment. Thus, it cannot be held that arbitrator has committed any error apparent on the face of the record or has misconducted himself in passing the impugued award. Further as the contention was not raised before the arbitrator or at any stage thereafter, it is not necessary to deal with or decide the same in the present appeal. [353-C; F) B c _State of U.P._ v. _Harish Chandra and Co.,_ [1999] l SCC 63, referred to. 4. The Award is modified qua the rate of interest considering the dispute involved and overall circumstances of the case. Respondent-claimant is entitled to recover the said amount with interest at the rate of 6% only. [353-G; H; 354-A) D CIVIL APPELLATE JURISDICTION : Civil Appeal NO. 8115 of 200 !. From the Judgment and Order dated 4.12.2000 of the Rajasthan High Court in S.B.C.M.A. No. 6.59 of 1999. ## WITH Special Leave Petition (C) No. 6172 of 2001. Javed Mahmud Rao and V. Krishna Murthy for the appearing parties. In-person for the Petitioner in S.L.P. (C) No. 6172 of 2001. The Judgment of the Court was delivered by SHAH, J. _CA. No. 8JJ5 of 2001_ @ _S.L.P. (C) No. 7192 of 2001._ G Leave granted. Learned Senior Counsel Mr. Ashwani Kumar appearing for the appellant contended that the judgment and decree passed by the High Court confirming H 352 (2001] SUPP. 5 S.C.R. ## SUPREME COURT REPORTS A the award made by the arbitrator is on the face of it illegal because : - (a) Arbitrator has failed to consider counter-claim. - (b) second reference to arbitrator was not maintainable under Order 2 Rule 2 CPC, and B - (c) the arbitrator has awarded interest despite the contrary condition in the agreement. c D E As against this, Mr. G.L. Sanghi learned senior counsel for the respondent as well as the respondent who is appearing in person submitted that in the written statement, counter-claim or set off was neither pleaded nor proved by the appellant before the arbitrator. He also contended that in case of claims raised by the respondent after preparation of final bill, there is no question of application of Order 2 Rule 2 CPC as rightly held by the arbitrator and the Courts below. For the contention based on clause 23 of the Agreement, it is submitted that the appellant never contended before the arbitrator that clause 23 provides for non-payment of interest in such cases. It is pointed out that neither befcre the arbitrator nor before the courts below, it was contended that arbitrator had no authority to grant interest in view of clause 23. Only contention which was raised with regard to grant of interest _pendente lite_ for which reliance was placed on various decisions of this Court. F We would state that the respondent who is appearing in person has in the alternative referred to the decision rendered by this Court in _State qf U.P._ v. _Harish Chandra_ & _Co.,_ [1999] l SCC 63 and submitted that similar clause is interpreted by this Court and it is held that there is no such prohibition on granting interest. He further pointed out that if such plea was raised, he would have produced the necessary documentary evidence or the letters written by the concerned officers and proved that interest was payable for wrongfully withholding the amount due and payable. G H In our view, it has been rightly pointed out that in the written statement, appellants have not claimed any set off or title counter claim for the alleged amount due and payable by the contractor on the alleged ground that Accountant General's Office has raised objection for payment of labour charges at accelerated rate. In our view as no such set off or claim nor any counter claim was filed by the appellant, arbitrator has rightly not considered the same which STATE _v._ NA V BHARAT CONSTRUCTION CO. [SHAH, J.] 353 • was sought to be raised after lapse of 4 years of reference. Further the High A Court has noted that the learned Additional Advocate General was unable to point out any legal basis to support the contention that arbitrator was required to go into the counter-claim in the circumstances of the present case. There is also no substance in the contention raised by Mr. Ashwani Kumar, learned senior counsel for the appellant that the second reference was barred by Order 2 Rule 2 CPC. As such the contention was not raised before the High Court. In any case, the dispute with regard to the subsequent claims arose after the first reference, that is, after the final bill was prepared and this aspect is rightly dealt with by the Additional District Judge. . B c Lastly, in the present case, the award passed by the arbitrator is reasoned one. The contention raised by the learned counsel for the appellant that under Clause 23 of the Agreement between the parties, contractor was not entitled to recover any interest on delayed payment was neither raised before the arbitrator, the District Court or before the High Court. This question depends upon the evidence which may be led by the parties as well as interpretation of clause 23 by the parties and the arbitrator. The parties have understood that there is no bar on granting interest on delayed payments. It appears that no such contention was raised on behalf on behalf of the State of Rajasthan. In this view of the matter, it cannot be held that arbitrator has committed any error apparent on the face of the record or has misconducted himself in passing the impugned award. It is settled law that scope for setting aside the award is limited to the grounds available under the Arbitration Act which have been well defined by long line of decided cases. In this view of the manner, it is not necessary for us to consider the contention of the contractor that similar clause is interpreted by this Court in _Harsish Chandra and Company's_ case (supra) and it is held that there is no bar on granting iilterest. In our view as the contention was not raised before the arbitrator or at any stage thereafter, it is not necessary for us to deal with or <lecide the same in this appeal. D E F G However, considering the dispute involved and overall circumstances of the case. we modify the award qua the rate of interest and reduce the same at the rate of 6% per annum. The arbitrator in paragraph 2 l.8.1. of the award has granted interest on the principal amount of claims no 1 to 8 from l.7.1990 to 30.4.1998 and 10 to 18 from 29.4.1991 to 30.4.1998 at the rate of 18% and the District Court has awarded interest at the rate of 15% from the date of H 354 SUPREME COURT REPORTS [2001] SUPP. _5_ S.C.R. - A decree. That part of the award and decree is modified and it is held that respondent-claimant is entitled to recover the said amount with interest at the rate of 6% only. The appeal is disposed of accordingly. Parties to bear their own cost of litigation all throughout. - _S.L.P. (C) No. 6172 of 2001_ - B In view of the aforesaid order, the S.L.P. filed by the contractor for - enhancement of interest rate from 15% to 18% would not survive and is dismissed. N.J. Appeal disp?sed of.
End of Judgment Record
Browse All Supreme Court of India (2001) Decisions
2001-08-07

Sajan Abraham v. State of Kerala

On 7 August 2001, the Supreme Court rendered its judgment in Sajan Abraham v. State of Kerala arising from a Narcotic Drugs and Psychotropic Substances Act case. The appellant was charged under Section 21 for possession of Buprenorphine and three syringes near Palluruthy, after information from a Head Constable led to seizure by a Special Squad and arrest following an on-site search. The Trial Court acquitted due to inconsistencies; the Kerala High Court, on reappraisal, convicted and sentenced the appellant to ten years’ rigorous imprisonment and a Rs 1 lakh fine. The prosecution contended violations of Sections 42, 50 and 57: failure to record information in writing and communicate it to the immediate superior before arrest; failure to inform the accused in writing of the right to be searched in the presence of a Magistrate or Gazetted Officer; and non-submission of a full report within 48 hours. The Supreme Court adopted a pragmatic approach to mandatory provisions in the NDPS Act, recognizing the stringent nature of the statute but allowing substantial compliance to suffice when it results in no prejudice and promotes timely action to prevent escape. It held that the information was conveyed promptly, the Section 50 right was validly communicated orally, and that copies of FIR and seizure records were sent to the superior, satisfying substantial compliance with Section 57. Citing State of Punjab v Baldev Singh and Balbir Singh, the Court dismissed the appeal, upholding the conviction and sentence.

2001-08-08

P. C. Joshi v. State of U.P. and ORS.

This Supreme Court appeal concerns a judicial officer challenged termination following disciplinary proceedings. The Allahabad High Court had dismissed a writ petition filed by the appellant after the Enquiry Officer held him guilty of several charges, including missteps in bail orders. The central issue was whether initiation of disciplinary action is warranted where an order is faulty or where a different action could have been taken. The Court emphasized that a bona fide erroneous exercise of judicial powers cannot be treated as misconduct and warned against a chilling effect on judicial independence: if every faulty judgment triggered a disciplinary inquiry, subordinate judges would fear writing judgments. It relied on established constitutional principles that safeguard the independence of the judiciary and prevent routine harassment through disciplinary machinery over minor or non-mala fide errors. The Court referred to the tests laid down in Union of India v. A.N. Saxena and Union of India v. K.K. Dhawan for determining when disciplinary action may be initiated. In evaluating the bail-related charges, the Court found that the Enquiry Officer’s conclusions rested on inferences rather than legally tenable evidence, rendering substantial parts of the findings vitiated. Consequently, the judgment of the High Court was set aside and the appellant was reinstated with continuity of service and arrears of salary, with no costs.

2001-04-09

Bank of India v. Secretary, Bank of India Staff Union and Anr.

Bank of India v. Secretary, Bank of India Staff Union and Anr. concerns entitlement to special 'Special Assistant' allowances for staff serving as clearing-house representatives. The Industrial Tribunal-cum-Labour Court at Kanpur held that the concerned workmen were entitled to special assistant allowances for the number of days they worked at various collection centres and clearing-house duties, with payment to be made for the days actually worked from the date of reference. The Bank challenged the award on two fronts: first, that the duties performed by the workers did not require the greater skill and responsibility of a Special Assistant, being largely clerical in nature; and second, that the Special Assistant duties were defined by the Bipartite Settlements (1966 and its modifications, including 1984) and awards (Sastry and Desai). The workers contended that they performed duties as authorised representatives at clearing houses of RBI and State Bank of India and carried out routine bank duties connected with clearing. On appeal, the Supreme Court found that the Tribunal had not adjudicated the precise duties and responsibilities with reference to the parties’ contentions and evidence, and there was no concrete finding that the workers discharged duties warranting Special Assistant status. The Court set aside the Tribunal’s award and remitted the matter for fresh consideration, directing examination of the exact duties in light of the Bipartite Settlements and Sastry/Desai framework.

2001-09-13

KANHAIYALAL AGRAWAL AND ORS. v. THE FACTORY MANAGER, GWALIOR SUGAR CO. LTD.

These cross-appeals arise from termination of employees by the Gwalior Sugar Company. The Labour Court held that three workmen—Kanhaiyalal Agrawal and two others—had contravened prescribed procedures and, on the basis of evidence, found loss of confidence in them, denying reinstatement and awarding half salary with full retirement benefits. The Industrial Court, by contrast, held that the employees had not committed misappropriation of money but were negligent in performing their duties, and directed reinstatement without back wages. A Single Judge of the Madhya Pradesh High Court upheld the Industrial Court’s order. A Division Bench of the High Court dismissed the writ appeals on the ground that they arose under Article 227 (revisional jurisdiction) and were not maintainable. The present appeals before the Supreme Court, by management and workmen, focus on whether loss of confidence can be reversed and whether back wages should be payable. The Supreme Court held that the Industrial Court was correct in reversing the Labour Court’s finding of loss of confidence since such loss must be based on objective facts rather than subjective managerial belief. It affirmed the permissibility of reinstatement without back wages and declined to disturb the earlier orders, dismissing the appeals with no costs.