This Supreme Court decision revolves around the arbitrator’s power to award interest under the Arbitration Act, 1940, in three phases: pre-reference, pendente lite, and post-award. The appellants contended that Section 29 limits interest and that a contractual clause stating “no interest is payable on amounts withheld” applied to retention money, not the balance due, thereby negating any interest on the final bill. The Court undertook a historical and doctrinal analysis of earlier decisions, including Abhaduta Jena and the Constitution Bench decision in Secretary, Irrigation Department, Government of Orissa v. G.C. Roy, to determine when interest can be awarded. It held that pre-reference interest is permissible for periods after the 1978 Interest Act became applicable (19-08-1981); for pre-1981 periods, absence of substantive law, contract, or usage bars interest. Pendente lite interest is permissible where not proscribed by contract; GC Roy recognized limitations on pendente lite, though later decisions clarified its scope. Post-award interest can be ordered by the court under Section 29 from decree to payment; where an award is filed in court, the court can modify the rate or award as per Section 29. The Appeals were dismissed, upholding the arbitrator’s jurisdiction to award interest for all three periods where permissible by law and contract constraints.
Find Cases Like This
Explore other judgments dealing with similar legal situations, facts, or statutory provisions.
Case Details & Bench
- Court
- Supreme Court of India
- Hon'ble Judges
- A.M. Ahmadi
- S.P. Bharucha
- B.N. Kirpal
- Judgment Date
- 1997-01-29
- Court Decision / Holding
- The Court held that the arbitrator may award pre-reference interest for periods after the 1978 Act’s applicability (19-08-1981) and not for earlier periods in the absence of a substantive right; pendente lite interest is available in appropriate cases following GC Roy’s principle, although its scope has been refined since Abhaduta Jena; for post-award interest, the court may determine the rate and date from which interest runs under Section 29. In Civil Appeal No. 9233, pre-reference interest was recognized from the 1981 threshold; in Civil Appeal No. 9234, pre-reference interest could be awarded from 19-08-1981, with post-award interest governed by the decree process. The appeals were dismissed. The contract’s “no interest” clause does not automatically bar interest, where the dispute on interest is referred to arbitration and supported by law or contract.
- Final Disposition
- Appeals dismissed
Parties to the Case
Appellants / Petitioners
- State of Orissa
- Orissa Government
- and others
Respondents
- B.N. Agarwall(a)
Legal Representation & Advocates
Counsels for Petitioners
- • G.L. Sanghi
- • S.B. Sanyal
- • H.N. Salve
- • D.V. Sehgal
- • R.N. Sachthey
Counsels for Respondents
- • R.K. Mehta
- • S.B. Upadhyay
- • Anil K. Jha
- • C.D. Singh
- • H. Munshi
Provisions of Law Cited
Legal Doctrines & Maxims
- Interest is compensation for deprivation of use of money (right to be compensated)
- An arbitrator is a creature of the parties’ agreement and must act within the law; the agreement may confer powers on the arbitrator provided they are not contrary to law
- If the agreement does not prohibit, pendente lite interest may be awarded; historical practice recognizes this, though it is not an absolute rule
- Pre-reference interest is a matter of substantive law and requires a contractual or legal basis; post-award interest is procedural and governed by Section 29
- Certificates of justice and certainty require that the arbitral process be predictable, and the court may adjust or confirm interest awards under statutory provisions
Submissions & Arguments
Contentions of Appellants / Petitioners
The applicants argued that the arbitrator lacked jurisdiction to award interest for post-award or post-decree periods and that the contract clause prohibiting interest on withheld amounts applied to retention money, not to interest on the final balance. They contended that pre-reference interest could not be awarded unless a substantive right existed under contract or law, and that pendente lite interest should be narrowly construed under Abhaduta Jena unless overruled by GC Roy. They urged adherence to the pre-1978 regime and that the court should not expand the arbitrator’s powers beyond the contract terms.
Contentions of Respondents
The respondents contended that the arbitrator had authority to award interest for pre-reference, pendente lite, and post-award periods; GC Roy (Constitution Bench) permits pendente lite interest and Abhaduta Jena’s reasoning on pre-reference was not absolute; post-award interest could be determined by the court under Section 29; the clause prohibiting interest did not bar the arbitrator’s power to award interest if the dispute was referred to arbitration and if law allowed it.
Explore This Legal Issue
Find relevant judgments and authoritative positions on the legal questions discussed here.
Cited Precedents (9)
| Case Name | Citation | Treatment | Explanation |
|---|---|---|---|
| Secretary, Irrigation Department, Government of Orissa & Ors. v. G.C. Roy | [1992] 1 SCC 508 | Positive | Constitution Bench decision followed; used to expand scope of pendente lite interest. |
| Executive Engineer (Irrigation) v. Abhaduta Jena | [1988] 1 SCC 418 | Overruled | Overruled by GC Roy on pendente lite (and related aspects). |
| Gujarat W.S. & S.B. v. Unique Erectors (Gujarat) (P) Ltd. | AIR (1989) SC 973 | Positive | Relied on; supports pre-reference interest depending on Act applicability. |
| Hindustan Construction Co. Ltd. v. State of J & K | [1992] 4 SCC 217 | Positive | Relied on; supports post-award mechanisms and pendente lite principles. |
| Seth Thawardas Phenchmal v. Union of India | [1955] 2 SCR 48 | Mentioned Only | Referenced for historical context on interest and arbitration. |
| Kishore Prabhatilal Sharma v. Vijayendra Prabhatilal Sharma & Anr. | [1993] 1 SCC 114 | Positive | Used to discuss pre-reference and pendente lite jurisprudence; supports pre-reference stance in some contexts. |
| State of Orissa v. Lal Chand Kapani | [1994] Supp. 1 SCC 68 | Positive | Relied on for pre-reference/in relation to interest principles. |
| Sudhir Brothers v. Delhi Development Authority & Anr. | [1996] 1 SCR 32 | Positive | Conveys interpretation of pendente lite and pre-reference in light of GC Roy and Jena line. |
| Santokh Singh Arora v. Union of India & Ors. | [1992] 1 SCC 492 | Mentioned Only | Referenced in discussing related line of authorities. |
Apply This to My Facts
Share your situation and test whether this judgment governs, supports, or challenges your case.
In The Court Record
State of Orissa v. B.N. Agarwall(a)
Related Decisions & Precedents from Supreme Court of India (1997)
Sharad Vasant Kotak and Ors. v. Ramniklal Mohanlal Chawda and Anr.
This Supreme Court judgment concerns the maintainability of a suit for dissolution of partnership and accounts under the Indian Partnership Act, 1932, as amended by the Maharashtra Amendment of 1984 (Section 69(2A)). The Paramount Builders partnership, registered in 1980 with seven partners (Kotak family and Chawda family), underwent changes after the death of partner Mohanlal Chawda in 1986, when his widow was inducted as a partner. A series of deeds (1986, 1992) reconstituted the firm without informing the Registrar of Firms, raising questions about registration and the applicability of Section 69(2A), which restricts suits to registered firms where the suing partner is shown in the Register of Firms. The Bombay High Court Division Bench held that reconstitution does not cancel registration and that amendments to pleadings were permissible; it concluded that Section 69(2A) does not bar the suit. The appellants argued that induction of a new partner dissolves the old firm and requires a fresh registration, while the respondents contended that dissolution and reconstitution are distinct concepts and that registration continues despite changes. The Supreme Court ultimately held that the firm was merely reconstituted, not dissolved; non‑compliance with registration provisions may attract penalties, but does not erase registration. The Special Leave Appeal was dismissed, with no costs.
National Insurance Co. Ltd. v. Santro Devi and Ors.
National Insurance Co. Ltd. v. Santro Devi deals with a motor-accident compensation claim under the Motor Vehicles Act. A Tribunal found that the offending vehicle was driven by a person who held a valid driving licence, which had been renewed on the date of the accident, and the claimants were accordingly awarded compensation. The Punjab and Haryana High Court affirmed this finding on appeal but then referred the matter to a full Bench to decide a legal question: whether a forged or fake licence, if renewed, would be treated as a valid licence for purposes of liability. The full Bench answered that a forged licence would not become valid under the Motor Vehicles Act and that an insured, bonafide believing in the licence’s validity, would still incur liability toward third parties under the policy; several related conclusions regarding insurer liability were laid down. The Insurance Company challenged these High Court observations. The Supreme Court allowed the appeal in part, holding that the claimants were rightly granted compensation on the facts, and that the High Court’s observations on forged licences were obiter and not binding precedents since there was concurrent factual finding that the driver held a valid licence renewed on the date of the accident. The Court affirmed the substantive order and dismissed the related Special Leave Petition.
JAIPUR DEVELOPMENT AUTHORITY v. SITA RAM AND ORS.
This appeal concerns the validity of notifications under Section 52 of the Rajasthan Urban Improvement Act, 1959, by which the Jaipur Development Authority sought to continue land acquisition even after the repeal of the 1959 Act, and after a fresh notification was issued in 1984 under the Jaipur Development Authority Act. The Rajasthan High Court had held that unless the master plan scheme under the JDA Act had been properly framed, the notification issued under Section 52 was not valid in law. The appellants challenge this proposition, contending that framing of a scheme is not a mandatory pre-condition for acquisition and that the 1984 notification cannot be quashed solely for lack of a sanctioned scheme. The matter traces several precedents: Pratap v. State of Rajasthan; State of Tamil Nadu v. Mohd. Yousef; Narain v. State of Rajasthan; and Urban Improvement Trust v. State of Rajasthan. The decision ultimately clarifies that framing of a scheme is not a required pre-condition for land acquisition; overruled or distinguished interpretations in earlier decisions, especially Tamil Nadu Yousef, Krishnan’s later formulation and Narain’s approach. The Court endorses the view that the notification for acquisition cannot be invalidated on account of non-framing of a scheme, and thus allows the appeals, setting aside the High Court’s judgment and dismissing the writ petitions, with no costs to either side.
Delhi Administration (Now Govt. of N.C.T. Delhi) through the Chief Secretary, Delhi and Ors. v. Nand Lal Pant and Anr.
Delhi Administration v. Nand Lal Pant concerns the scope of promotion from the cadre of Trained Graduate Teachers (TGT) to Post-Graduate Teachers (Sanskrit) in the Delhi education cadre, and the remedy when a sanctioned channel does not exist. Pant, appointed as a TGT in 1974 and confirmed, was asked to officiate in the PGT (Sanskrit) post when it became vacant after the retirement of S.N. Sastri, a Sanskrit-qualified officer. He repeatedly sought promotion to the PGT position, which the Delhi High Court granted in 1996, directing promotion with effect from 1986 and ordering payment of consequential benefits. The Delhi Administration appealed on the ground that there was no direct promotional channel from TGT (General) to PGT (Sanskrit), and that the SC caste reservation for the post should be respected. The Supreme Court accepted that there is no direct channel, but noted Pant’s extended officiation in the PGT post since 1986. It held that justice required a workable remedy: creation of a supernumerary PGT (Sanskrit) post in any school or directorate, allowing Pant to continue there until retirement, with pay from the date of creation. The decision clarifies it as a discretionary remedy and not a general precedent, and it disposed of the appeal with no costs.