High CourtSingle JudgeAppeal allowed; application under section 34 re...

STATE OF MAHARASHTRA AND ORS. v. ARK BUILDERS PVT. LTD.

Case / Petition Number:Civil Appeal No. 2152 of 2011
Neutral Citation:[2011] 4 SCR 432

Case Details & Bench

Court
High Court
Hon'ble Judges
  • Aftab Alam
  • R.M. Lodha
Judgment Date
2011-02-28
Court Decision / Holding
Appeal allowed. The judgments and orders of the Bombay High Court and the Principal District Judge, Latur, are set aside. The application under section 34 of the Act is restored before the Principal District Judge, Latur, who shall hear the matter on merits and pass an order in accordance with law, ideally within six months from the date of receipt of this order.
Final Disposition
Appeal allowed; application under section 34 restored for merit hearing by the Principal District Judge, Latur.

Parties to the Case

Appellants / Petitioners

  • STATE OF MAHARASHTRA AND ORS.

Respondents

  • ARK BUILDERS PVT. LTD.

Legal Representation & Advocates

Counsels for Petitioners

  • • Chinmoy A. Khaladkar
  • • Asha Gopalan Nair

Counsels for Respondents

  • • Shyam Diwan
  • • Shirish K. Deshpande

Case Synopsis & Summary

This appeal concerns the proper start point for the three-month period of limitation under section 34(3) of the Arbitration and Conciliation Act, 1996, for challenging an arbitral award. The State of Maharashtra and other appellants challenge a Bombay High Court decision that treated the limitation period as running from March 29, 2003, when a copy of the award was received by the Executive Engineer, arguing that the period began when the award was signed and delivered to the concerned party. The arbitrator had signed the award on March 20, 2003 and delivered a signed copy to the claimant on that date. A Xerox copy was later certified and sent to the arbitrator; the endorsement of January 19, 2004 and the applicant’s subsequent filing on January 28, 2004 form the factual backdrop. The appellants contended that the statute requires a signed copy to be delivered to each party, and that the limitation under section 34(3) must start from the date a signed copy is delivered to the party under section 31(5). The respondents contended that the copy of the award was received on March 29, 2003 and that limitation began then. The Supreme Court allowed the appeal, holding that the limitation clock starts only from the date a signed copy is delivered/received by the party, per sections 31(5) and 34(3), and relied on Union of India v. Tecco Trichy Engineers & Contractors and Dr. Sheo Shankar Sahay. The Court set aside the High Court and the lower court orders, restoring the application to be heard on merits by the Principal District Judge, Latur, with a six-month timeline to dispose the matter. This decision clarifies that delivery is a substantive act that triggers rights and the limitations period, not merely a formality, and underscores the need for a signed copy to be delivered to the parties before limitation commences.

Provisions of Law Cited

Arbitration and Conciliation Act, 1996, s.34Arbitration and Conciliation Act, 1996, s.31(5)Arbitration and Conciliation Act, 1996, s.31(1)Arbitration and Conciliation Act, 1996, s.33Arbitration and Conciliation Act, 1996, s.32

Legal Doctrines & Maxims

  • Delivery of arbitral award under Section 31(5) is not a mere formality but a matter of substance.
  • The period of limitation under Section 34(3) commences from the date a signed copy of the award is delivered to the party making the application under Section 34(1).
  • Delivery/receipt of the signed copy and the relationship between Section 31(5) and Section 34(3) must be read together to determine start of limitation.

Submissions & Arguments

Contentions of Appellants / Petitioners

The appellants argued that Section 34(3) begins only from the date a signed copy of the award is delivered to the party, per Section 31(5), and that the delivery must be of the signed copy, not merely a copy, and not by mere dispatch. They contended that although a copy of the award was supplied on March 29, 2003, the signed copy was delivered only on January 19, 2004, making January 19, 2004 the relevant starting point for limitation, with the application filed January 28, 2004 within time. They relied on Union of India v. Tecco Trichy Engineers & Contractors to support the interpretation that delivery is substantive and not merely procedural, and on Dr. Sheo Shankar Sahay as an authority on earlier limitation concepts.

Contentions of Respondents

The respondents argued that the copy of the award was received in the Office of the Executive Engineer on March 29, 2003 and acknowledged; they contended that the decision to challenge the award was taken in December 2003, well before January 2004, and that the appellants sought to manipulate the timeline by obtaining the arbitrator’s signature after the period had lapsed. They maintained that March 29, 2003, is the date from which the limitation should be calculated, and that Xerox copies exchanged later do not extend the period.

Cited Precedents (2)

Case NameCitationTreatmentExplanation
Union of India v. Tecco Trichy Engineers & Contractors(2005) 4 SCC 239PositiveCited to support that delivery of the signed copy, not mere dispatch, is the critical stage for triggering limitation under Section 34(3).
Dr. Sheo Shankar Sahay v. Commissioner, Patna Division & Ors.1965 BLJR 78PositiveApproved as supportive authority on the timing and delivery principles for limitations, reinforcing the need for a signed copy.

Diagnostic Tool

Beta

Does this judgment govern your specific facts?

Don't risk relying on a distinguishable precedent. Enter your facts or proposition below. We will test it against STATE OF MAHARASHTRA AND ORS. v. ARK BUILDERS PVT. LTD. and instantly map out authorities that support, challenge, or govern your position.

Extracted Judgment Text

Exact text extracted from official judgment records.

## [2011) 4 S.C.R. 432 ## A ## THE STATE OF MAHARASHTRA AND ORS. _v._ MIS. ARK BUILDERS PVT. LTD. (Civil Appeal No. 2152 of 2011) ## B ## FEBRUARY 28, 20fl ## [AFTAB ALAM AND R.M. LQDHA, JJ.) - _Arbitration and Conciliation Act, 1996: s.34_ - _Period_ - _of limitation for making an application uls.34 for setting aside_ - C _an arbitral award_ - _Held: Is to be_ reck~ned _from the date a signed copy of the award is delivered tQ the objector by the arbitrator and not from the date a copy of the award is received by him by any means and from any source_ - _Limitation._ - _Interpretation of statutes: If the_ l~w _prescribes that a_ - 0 _copy of the order/award is to be communicated, 'delivered, dispatched, forwarded, rendered or sent to the parties concerned in a patticular way and sets a period of limitation for challenging the order/award in question by the aggrieved_ - E _party, then the period of limitation can only commence from the date on which the order/award was received by the party concerned in the manner prescribed by 'fhe law_ - _Arbitration and Conciliation Act, 1996_ - _s.34._ - The question which arose for consideration in the - F instant appeal was whether the perlbd of limitation for making an application under section 34 of the Arbitration and Conciliation Act, 1996 for setting aside an arbitral award is to be reckoned from the date a copy of the award is received by the objector by any means and from - G any source, or it would start running from the date a signed copy of the award is delivered to him by the arbitrator. ## Allowing the appeal, the Court H 432 > . , • • - . • STATE OF MAHARASHTRA AND ORS. _v._ ARK 433 BUILDERS PVT. LTD. HELO: 1.1. Section 31 (1) of the Arbitration and A C<?nciliation Act,•1996 obliges the members of the arbitral tribunal/ arbitrator to mllke the award in writing and to sign it·and sub-section (5) then mandates that a signed copy of lhe awar~. woul'Ct be delivered to each party. A signed copy of the award would normally be delivered to the B par~y ~y the arbitrator himself. The High Court clearly overlooked that what was required by law was the delivery of a copy of the award signed by the members of the arbitral tribunal/ arbitrator and not any copy of the award. Section 34 of the Act then provides for filing an c application for setting aside an arbitral award, and subsection (3) of that section lays down the period of limitation for making the application. The expression " .. party making that application had received the arbitral award .. " appearing in sub-section (3) of Section 34 cannot 0 be read in isolation and it must be understood in light of what is said earlier in section 31(5) that requires a signed copy of the award to be delivered to each party. Reading the two provisions together would make it clear that the limitation prescribed under section 34(3) would E commence only from the date a signed copy of the award is delivered to the party making the application for setting it aside. [Para 10, 11) [439-F-H; 440-A-G] _Union of India_ v. _Tecco Trichy Engineers_ & _Contractors_ (2005) 4 sec 239 - relied on. F 1.2. The period of limitation prescribed under section 34(3) of the Act would start running only from the date a signed copy of the award is delivered to/received by the party making the application for setting it aside under G section 34(1) of the Act. If the law prescribes that a copy of the order/award is to be communicated, delivered, dispatched, forwarded, rendered or sent to the parties concerned in a particular way and in case the law also H ## 434 SUPREME COURT REPORTS [2011] 4 S.C.R. A sets a period of limitation for challenging the order/award in question by the aggrieved party, then the period of limitation can only commence from the date on which the order/award was received by the party concerned in the manner prescribed by the law. The High Court B overlooked that what section 31 (5) contemplated was not merely the delivery of any kind of a copy of the award but a copy of the award that is duly signed by the members of the arbitral tribunal. In the facts of the case, the appellants would appear to be deriving undue advantage c due to the omission of the arbitrator to give them a signed copy of the award coupled with the supply of a copy of the award to them by the claimant-respondent but that would not change the legal position and it would be wrong to tailor the law according to the facts of a D particular case. [Paras 13, 16,17) [441-F¢-H; 442-A; 443-EH] _Dr. Sheo Shankar Sahay_ v. _Commissioner, Patna_ - _Division and Ors._ 1965 BLJR 78 approved. E ## Case Law Reference: (2005) 4 sec 239 relied on Para 7, 12 1965 BLJR 78 approved Para 14 F CIVIL APPELLATE JURISDICTION : Civil Appeal No. 2152 of 2011. From the Judgment & Order 6.10.2009 of the High Court of Judicature of Bombay Bench at Aurangabad in Arbitration Appeal No. 2. G Chinmoy A. Khaladkar (for Asha Gopalan Nair) for the Appellants. H Shyam Diwan, Shirish K. Deshpande (for Anirudha P. Mayee) for the Respondent. • STATE OF MAHARASHTRA AND ORS. _v._ ARK 435 BUILDERS PVT. LTD. The Judgment of the Court was delivered by A **AFTAB ALAM,** J. 1. Leave granted. > 2. Whether the period of limitation for making an application under section 34 of the Arbitration and Conciliation Act, 1996 (hereinafter 'the Act') for setting aside an arbitral award is to be reckoned from the date a copy of the award is received by the objector by any means and from any source, or it would start running from the date a signed copy of the award is delivered to him by the arbitrator? This is the short question that arises for consideration in this appeal. 8 C 3. The material facts of the case are brief and admitted by both sides. These may be stated thus. On March 20, 2003 the arbitrator gave a copy of the award, signed by him, to the claimant (the respondent) in whose favour the award was made. No copy of the award was, however, given to the appellant, the other party to the proceedings, apparently because the appellant had failed to pay the costs of arbitration. The respondent submitted a copy of the award in the office of the Executive Engineer (appellant no.4) on March 29, 2003, claiming payment in terms of the award. On April 16, 2003, the Executive Engineer submitted a proposal to challenge the award before the Chief Engineer, and the Financial Advisor and Joint Secretary. The respondent sent a reminder to the Chief Engineer on June 13, 2003, for payment of the money awarded to him by the arbitrator and a second reminder to the Secretary and Special Commissioner on January 8, 2004. The Executive Engineer by his letter dated January 15, 2004, acknowledged all the three letters of the claimant and informed him that the government had decided to challenge the award before the appropriate forum. 0 E F G 4. According to the appellants, the decision to make an application for setting aside the award was taken on December 16, 2003, but no application could be made for want of a copy of the award from the arbitrator. Hence, on January 17, 2004, H ## 436 SUPREME COURT REPORTS [2011) 4 S.C.R. A a messenger was sent to the arbitrator wi•h a letter asking for a copy of the award. The arbitrator made an endorsement on the letter sent to him stating that on the req .. ;est of t_he claimant the original award was given to him and the Xerox· copy of the award (sent to him along with the letter), was being certified B by him as true copy of the award. The endorsement from the arbitrator along with the Xerox/certified copy of the award was received from the arbitrator on January 19, io04 and on January 28, 2004, the appellants filed the application under section 34 of the Act. ## c 5. The respondent raised an obje¢tion regarding the maintainability of the petition contending that it was hopelessly. barred by limitation. The Principal District Jiµdge, Latur, by order dated February 15, 2007 passed in Civil Application No.84 of 2005 (previously Suit No.1 of 2004) uphelld the respondent's D contention and dismissed the appellants' application as barred by limitation. 6. Against the order of the Principal District Judge, the appellants preferred an appeal (Arbitration Appeal No.2 of E 2008) before the Bombay High Court. 7. Before the High Court, the appellants contended that _ they were able to obtain a copy of the award duly signedlbY · the arbitrator only on January 19, 2004 and the peri8d of limitation prescribed under section 34 (l) of the Act would, F therefore, commence from that date. The application for setting aside the award was filed on January 20, 2004 and hence, there was no question of the applicatipn being barred by limitation. In support of the contention, the appellants relied upon the last order passed in the arbitral proc¢edings on February G 22, 2003 in which it was stated that the qase was closed and the arbitrator would proceed with the framing of the award which would be declared and _copies sent to both parties in due course._ On behalf of the appellants it was stated that contrary to the order passed on February 22, 2003, the arbitrator did H 437 •[STATE OF MAHARASHTRA AND ORS. ] _[v. ]_[ARK ] BUILDERS PVT. LTD. [AFTAB ALAM, J.] not send them a copy of the award even though a Xerox copy A of the award was sent to them by the claimant-respondent to whom the arbitrator had given a copy of the award duly signed by him. In support of the submission that the period of limitation prescribed under section 34(3) of the Act would start running . from the date they received a copy of the award duly signed B by the arbitrator, they also relied upon section 31 (5) read with section 34(3) of the Act. They also relied upon a decision of this Court in _Union of India_ v. _Tecco Trichy Engineers_ & _Contractors,_ (2005) 4 SCC 239. 8. On behalf the claimant-respondent it was pointed out that a copy of the award was undeniably received in the office of the Executive Engineer on March 29, 2003 and as a matter of fact the receipt of the copy of the award on that date was expressly acknowledged .in the letter of the Executive Engineer dated January 15, 2004 in which he told him that the appellants had decided to challenge the award. The respondent further pointed out that it was only on the basis of the copy of the award received from him that the office communications and deliberations were made and finally on December 16, 2003 the decision was taken to challenge the award when the matter had already become barred by limitation. It was submitted on behalf of the respondent that the appellants undertook the exercise of sending the Xerox copy of the award to the arbitrator for obtaining his signature on it (when the period for making an application to set it aside was long over) just to make out a case to overcome the bar of limitation prescribed by section 34 (3) of the Act. In the admitted facts of the case there should be no question of there being any other date for the computation of limitation than March 29, 2003, the date on which he supplied a-copy of the award to the Executive Engineer. 9. The High Court upheld the submissions made on behalf of the claimant-respondent, affirmed-the view taken by the Principal District Judge and by judgment and order dated October 6, 2009 dismissed the appeal filed by the appellants. C 0 E F G H • ## 438 SUPREME COURT REPORTS [2011] 4 S.C.R. ' - A It took note of section 31 (5) and section 34(3) of the Act and the decision of this Court in _Tecco Trfchy Engineers_ & _Contractors_ but rejected the appellant's contention highlighting that the word used in section 31(5) is 'delivered' and not 'dispatched'. The High Court held and observed as follows: - B "17. It is to be noted that sub-section (5) of Section 31 prescribes that after arbitral award is made, a signed copy shall be 'delivered' to each party. l"he word 'delivered' appearing in Section 31 (5) cann()t be equated with 'dispatched'. A distinction has to be made between these - c two words. The 'Shorter Oxford English Dictionary' gives meaning of the word 'delivered' as, "to bring and handover a letter, a parcel to the proper retipient or address". "Deliver" means: (i) bring and handover (a letter or goods) to the proper recipient; formally hand over (someone); and - D (iii) provide (something promised or expected). Thus, what is important is that the copy of the award should be handed over to the proper recipient or addressee. In this view of the matter, sub-section (5) of Section 31 does not require that a copy of the arbitral aw;!rd should be sent off - E by the Arbitrator to the concerned party, but it is required that copy of the arbitral award be handed over to the proper parties. F G H 18. In the instant matter, admittedly the copy of award was received by the Executive Engineer in the month of April 2003. However, appellants did not a¢t till January 2004 for about nine months. Thus, for their inaction, appellants have to blame only themselves. In the instant matter, it cannot be said that there is non compliance of sub-section (5) of Section 31 of the Act of 1996. There is sufficient compliance of the provisions of Section 31 (5), as admittedly, appellants received copy of the award in the month of April, 2003. Appellants thereafter did not take steps in respect of raising challenge to the award and allowed the matter to remain in col~ storage. The delay 439 •[STATE ][OF ][MAHARASHTRA ][AND ][ORS. ] _[v. ]_[ARK ] BUILDERS PVT. LTD. [AFTAB ALAM, J.) occasioned in presenting the application is essentially A because of the lapses committed by the appellants only." 10. The appellants are now before this court by grant of special leave. The two provisions of the Arbitration and Conciliation Act, 1996, relevant to answer the question raised 8 in the case are sections 31 and 34. Section 31 deals with 'form and contents of arbitral award; and in so far as relevant for the present provides as follows: "31. Form and contents of arbitral award.- (1) An arbitral award shall be made in writing and shall be signed by the C members of the arbitral tribunal. (2) xxxxxxxxxxx (3) xxxxxxxxxxx D (4) xxxxxxxxxxx (5) After the arbitral award is made, a _signed_ copy shall be delivered to each party. (6), (7), (8) xxxxxxxxxxx E (emphasis added) Section 31 (1) obliges the members of the arbitral tribunal/ arbitrator to make the award in writing _and to sign it_ and subF section (5) then mandates that a _signed_ copy of the award would be delivered to each party. A signed copy of the award would normally be delivered to the party by the arbitrator himself. The High Court clearly overlooked that what was required by law was the delivery of a copy of the award _signed_ by the G members of the arbitral tribunal/ arbitrator and not any copy of the award. 11. Section 34 of the Act then provides for filing an application for setting aside an arbitral award, and sub-section H 440 SUPREME COURT REPORTS [2011) 4 S.C.R. - A (3) of that section lays down the period of limitation for making the application in the following terms: - "34. Application for setting aside arbitral award.-(1) Recourse to a Court against an arbitral award may be made only by an application for setting aside such award - B in accordance with sub- section (2) and sub-section (3). ## (2) )()()()()()()( - (3) An application for setting aside may not be made after - c three months have elapsed from the date on which the party making that application had received the arbitral award or, if a request had been made under section 33, from the date on which that request had been disposed of by the arbitral tribunal: D - Provided that if the Court is satisfied that the - applicant was prevented by sufficient cause from making the application within the said period of three months it may entertain the application within a further period of thirty days, but not thereafter. E ## (4) xxxxxxx'' The expression " .. party making that application had **received** the arbitral award .. " can not be read in isolation and it must be F understood in light of what is said earlier in section 31 (5) that requires a signed copy of the award to be delivered to each party. Reading the two provisions together it is quite clear that the limitation prescribed under section 34 (3) would commence only from the date a signed copy of the award is delivered to the party making the application for setting it aside. G 12. We are supported in our view by the decision of this Court in _Union of India_ v. _Tecco Trichy Engineers_ & _Contractors,_ (2005) 4 SCC 239; in paragraph 8 of the decision it was held and observed as follows: H • STATE OF MAHARASHTRA AND ORS. MAHARASHTRA AND ORS. _v._ ARK OF MAHARASHTRA AND ORS. MAHARASHTRA AND ORS. _v._ ARK 441 BUILDERS PVT. LTD. [AFTAB ALAM, J.] "8. The delivery of an arbitral award under sub-section (5) A of Section 31 is not a matter of mere formality. It is a matter ·of substance. It is only after the stage under Section 31 has passed that the stage of termination of arbitral proceedings within the meaning of Section 32 of the Act arises. The delivery of arbitral award to the party, to be B effective, has to be "received" by the party. This delivery _by the Arbitral Tribunal and receipt by the party of the award sets in motion several periods of limitation such as_ an application for correction and interpretation of an award within 30 days under Section 33(1), an application c for making an additional award under Section 33(4) and _an application for setting aside an award under Section 34(3) and so on._ As _this delivery of the copy of award_ has the effect of conferring certain rights on the party as also bringing to an end the right to exercise those rights on 0 expiry of the prescribed period of limitation _which would be calculated from that date,_ the delivery of the copy of award by the Tribunal and the receipt thereof by each party constitutes an important stage in the arbitral proceedings." (emphasis added) E 13. The highlighted portion of the judgment extracted above, leaves no room for doubt that the period of limitation prescribed under section 34(3) of the Act would start running only from the date a signed copy of the award is delivered to/ received by the party making the application for setting it aside under section 34(1) of the Act. The legal position on the issue may be stated thus. If the law prescribes that a copy of the order/ award is to be communicated, delivered, dispatched, forwarded, rendered or sent to the parties concerned in a particular way and in case the law also sets a period of limitation for challenging the order/award in question by the aggrieved party, then the period of limitation can only commence from the date on which the order/award was F G H [2011] 4 S.C.R. 442 SUPREME COURT REPORTS - A received by the party concerned in the manner prescribed by the law. 14. We may here refer to a decision of the Patna High Court in _Dr. Shea Shankar Sahay_ v. _Commissioner, Patna_ B _Division and Ors.,_ 1965 BLJR 78. Section 18(1) of the Bihar Building (Lease, Rent and Eviction) Control Act, 1947 prescribed a period of limitation of 15 days for filing an appeal against an order of the House Controller and provided as follows: C "any person aggrieved by an order passed by the Controller may, within fifteen days from the date of receipt of such order by him, prefer an appeal in writing to the appellate authority" 0[It was contended ][on ][behalf of the petitioner before the High ] Court that the order-sheet of the House Controller was shown to the lawyer of the respondent on June 10, 1959 and therefore, that would be the starting point of limitation under section 18(1) of the Bihar Building (Lease, Rent and Eviction) Control Act, E 1947. A division bench of the High Court consisting of Chief Justice V. Ramaswami (as his Lordship then was) and Justice N.L. Untwalia (as his Lordship then was) rejected the submission observing as follows: "2 .... But we shall assume that the petitioner is right in F alleging that the order was shown to the lawyer on the 10th June, 1959. Even so, we are of opinion that the appeal preferred by respondent no.4 before the Collector of Shahabad was not barred by limitation. The reason is that Sec. 18(1) provides limitation of fifteen days "from the date G of receipt of the order" and not from the date of communication of the order. It is significant that Sec. 14 of the Bihar House Rent Control Order, 1942, had provided that "any person aggrieved by an order of the Controller may, within fifteen days from the date on which the order H is communicated to him, present an appeal in writing to •[STATE OF ][[MAHARASHTRA ][AND ORS. ]][[AND ORS. ]] _[[v. ]]_[[ARK ]] > [[MAHARASHTRA ][AND ORS. ]][[AND ORS. ]] _[[v. ]]_[[ARK ]] 443 BUILDERS PVT. LTD. [AFTAB ALAM, J.] the Commissioner of the division". Sec. 18(1) of Bihar Act A Ill of 1949 is couched in different language. _In our opinion,_ Sec. _18(1) implies that the Controller is bound, as_ a _matter of law, to send_ a _written copy of his order to the person aggrieved, and limitation for filing an appeal does not start unless and until the copy of the order is sent._ In B the present case it is not disputed that no copy of the order was sent to respondent no.4. It is true that the responderit' ·himself applied for a copy of the order on the 11th December, 1959, and obtained a copy on the 14th December, 1959. In any event, therefore, limitation will not C start running against respondent no.4 under Sec. 18(1) of the Act till the 14th December, 1959, and as the appeal was filed on the 26th December, 1959, there is no bar of limitation in this case ... ." (emphasis added) D 15. We are in respectful agreement with the view taken by the Patna High Court in the case of _Dr. Sheo Shankar_ Sahay. 16. In light of the discussions made above we find the impugned order of the Bombay High Court unsustainable. The High Court was clearly in error not correctly following the decision of this Court in _Tecco Trichy Engineers_ & _Contractors_ and in taking a contrary view. The High Court overlooked that what section 31 (5) contemplates is not merely the delivery of any kind of a copy of the award but a copy of the award that is duly signed by the members of the arbitral tribunal. E F 17. In the facts of the case the appellants would appear to be deriving undue advantage due to the omission of the arbitrator to give them a signed copy of the award coupled with G the supply of a copy of the award to them by the claimantrespondent but that would not change the legal position and it would be wrong to tailor the law according to the facts of a particular case. H 444 SUPREME COURT REPORTS [2011] 4 S.C.R. A 18. In the light of the discussion made above this appeal must succeed. We, accordingly, set aside the judgments and orders passed by the Bombay High Court and the Principal District Judge, Latur. The application made by the appellants under section 34 of the Act is restored before the Principal B District Judge, Latur, who shall now proceed to hear the parties on merits and pass an order on the application in accordance with law. Since the matter is quite old, it is hoped and expected that the Principal District Judge will dispose this matter preferably within 6 months from the date of receipt of this order. c D.G. allowed. Appeal allowed.