This Special Leave Petition challenges a High Court decision dismissing a second appeal on the ground of inordinate delay of 5 years 10 months in filing, without addressing the merits of a land dispute involving 1,300 hectares of government land at Majhganwa, Katni. The respondent had filed Civil Suit No.79A/2011 seeking declaration of title and permanent injunction over lands in Survey Nos. 107, 108, 115. The trial court dismissed the suit in 2013; the First Appellate Court reversed and allowed the respondent’s appeal in 2014, holding that the lands were not in possession of the respondent and right to leasehold was not granted by the Settlement Officer. The State thereafter filed Second Appeal No.2895/2019, with an interlinked delay-condonation application, which the High Court refused, noting extreme inordinate delay and lack of satisfactory explanation. The Supreme Court discusses the standard for condonation of delay, stressing that ‘sufficient cause’ must be shown and cannot be liberally construed, and that delay should not be excused as a matter of generosity. While upholding the need to consider delay, the Court still dismisses the SLP, directing the State to fix responsibility for the delay, and imposing a substantial cost order, with Rs. 1,00,000 to be deposited in two weeks.”

Precedent Explorer

Find Cases Like This

Explore other judgments dealing with similar legal situations, facts, or statutory provisions.

Case Details & Bench

Court
Landmark Cases
Hon'ble Judges
  • J. B. Pardiwala
  • R. Mahadevan
Judgment Date
2024-11-29
Court Decision / Holding
Special Leave Petition dismissed with costs of Rs. 1,00,000 to be deposited by the State within two weeks with the Supreme Court Mediation Centre; failure to deposit to be recovered as per law. Pending applications stand disposed of.
Final Disposition
Dismissed; Special Leave Petition dismissed with costs and directions issued regarding costs and accountability for delay.

Parties to the Case

Appellants / Petitioners

  • State of Madhya Pradesh

Respondents

  • Ramkumar Choudhary

Legal Representation & Advocates

Counsels for Petitioners

  • • Mr. Harmeet Singh Ruprah, Deputy Advocate General

Provisions of Law Cited

Article 227 of the Constitution of India

Legal Doctrines & Maxims

  • Sufficient cause doctrine for condonation of delay
  • Delay should not be condoned as a matter of generosity; substantial justice should not prejudice the opposite party
  • Rigour in applying the law of limitation; publicity of public policy and equity in limitation

Submissions & Arguments

Contentions of Appellants / Petitioners

The State contends that the delay in filing the second appeal, though lengthy (1788 days), is explained by administrative processes and communications within the State machinery. It asserts that the merits of the case—namely the rights to land over 1,300 hectares at Majhganwa, Katni, and the trial court’s dismissal followed by the first appellate court’s reversal—were not properly considered by the High Court which dismissed the appeal solely on delay. The State emphasizes that condonation of delay requires a close, case-specific assessment of sufficient cause, and that the High Court should have weighed merits against delay rather than foreclosing the matter on time without due exploration of the factual record.

Contentions of Respondents

The respondent contends that the delay is inordinate (nearly 4.9 years) and not satisfactorily explained. It argues that the delay was caused by Government inaction or negligence, and that ordinarily such delay cannot be condoned, particularly where valuable Government lands are involved. The Respondent asserts that the merits of the title and land rights concerns were overshadowed by the procedural default, and that condonation should be denied to avoid prejudice to the party relying on timely adjudication.

Legal Doctrine & Issue Explorer

Explore This Legal Issue

Find relevant judgments and authoritative positions on the legal questions discussed here.

Cited Precedents (5)

Case NameCitationTreatmentExplanation
Majji Sannemma v. Reddy Sridevi2021 SCC Online SC 1260PositiveCited to support the principle that sufficient cause for delay must be rigorous and not liberally interpreted; the court must apply limitation rules with strictness.
Ajay Dabra v. Pyare Ram2023 SCC Online SC 92Mentioned OnlyReferenced in the context of prior discussions on delay and limitation, but not pivotal to the judgment’s outcome.
Basawaraj v. Special Land Acquisition Officer(2013) 14 SCC 81PositiveCited for the established test that ‘sufficient cause’ must be genuine and cannot be invented after the fact; governs condonation of delay.
Union of India v. Jahangir Byramji Jeejeebhoy (D) through his legal heir—PositiveUsed to emphasize that delay should not be excused as generosity and substantial justice should not prejudice the opposite party; length and bona fides are crucial.
Ajit Singh Thakur Singh and Another v. State of GujaratAIR 1981 SC 733PositiveCited to illustrate that events arising after the expiry of limitation cannot constitute sufficient cause; emphasizes the need for timely action within limitation.
Case Applicability Diagnostic

Apply This to My Facts

Share your situation and test whether this judgment governs, supports, or challenges your case.

Official Judgment Record
•2,528 words•~12 min read

In The Court Record

State of Madhya Pradesh v. Ramkumar Choudhary

_REPORTABLE_ 2024 INSC 932 **==> picture [72 x 72] intentionally omitted <==** IN THE SUPREME COURT OF INDIA ## CIVIL APPELLATE JURISDICTION ## SPECIAL LEAVE PETITION (C) Diary No. 48636 of 2024 State of Madhya Pradesh …Petitioner Versus Ramkumar Choudhary ...Respondent ## O R D E R 1. This Special Leave Petition is filed by the petitioner - State of Madhya Pradesh against the judgment dated 24.01.2024 passed by the Hon’ble High Court of Madhya Pradesh at Jabalpur[1] in Second Appeal No.2895 of 2019, whereby, the High Court dismissed the appeal on the ground that it was filed with inordinate delay of 5 years 10 months and 16 days and no satisfactory reason was adduced for the same. > Signature Not Verified 2. We have heard Mr. Harmeet Singh Ruprah, learned Deputy Advocate General Digitally signed by VISHAL ANAND Date: 2024.12.05 11:03:08 IST > Reason: appearing for the petitioner, who submitted that the delay caused in filing the 1 Hereinafter shortly referred to as “the High Court” Page 1 of 11 second appeal was well explained by the State and the same was not intentional. However, the High Court erroneously dismissed the second appeal on the ground of delay, without considering the merits of the case, wherein, valuable Government lands measuring total extent of 1,300 Hectare situated at Village Majhganwa, Tehsil and District Katni, were involved. He further submitted that though the trial Court passed the well-reasoned judgment dismissing the suit filed by the respondent herein, the first Appellate Court reversed the same and allowed the appeal in favour of the respondent, thereby affecting the right of the petitioner in respect of the said lands. 3. It appears from the materials on record that originally, the respondent filed Civil Suit No.79A/2011 before the Civil Judge, Class-2, Katni[2] seeking declaration of title and permanent injunction in respect of lands in Survey Nos.107, 108, 115, respectively measuring an extent of 0.36, 0.40, 0.54 hectare situated at village Majhganwa, Katni, stating that that he has been in possession of the said lands since 1970 and has been given leasehold right by the Settlement Officer in the year 1989. By judgment and decree dated 29.08.2013, the trial Court dismissed the said suit. Challenging the same, the respondent preferred Civil Appeal No.25A/2013 which was allowed by the 3[rd] Additional District Judge, Katni[3] by judgment and decree dated 21.08.2014. Stating that the land in Khasra No.107 admeasuring 0.36 hectare was registered in the name of Bhu-Dan Board, - 2 Hereinafter shortly referred to as “the trial Court” > 3 Hereinafter referred to as “the First Appellate Court” Page 2 of 11 Government of M.P. and the land in Khasra Nos.108 and 115 was reserved for Charokhar, Grass, Beed or Chara as per Nistar Patrak; and the respondent was not in possession of the said lands and leasehold right was not given to him by any settlement officer and no consent was also given in this regard, the State preferred Second Appeal No.2895 of 2019 along with an Interlocutory Application No.13106 of 2019 seeking to condone the delay of 5 years 10 months and 16 days in filing the same. The High Court declined to condone the delay and dismissed the second appeal by the judgment impugned herein. 4. Evidently, there was enormous delay occurred at every stage i.e., from the date of receipt of the judgment passed by the First Appellate Court to till the date of filing the second appeal by the State. The judgement was passed by the First Appellate Court on 21.08.2014 and the same was communicated by the Government Advocate representing the State to the Collector, only on 25.08.2015 i.e., after a delay of one year. Causing 3 months’ delay, by letter dated 10.12.2015, the Collector informed to the Principal Secretary, Revenue Department, about the passing of the judgment against the State and preferring a second appeal against the same. Thereafter, the Law Department took three years’ time and gave permission for filing appeal on 26.10.2018, which was sent to the Collector on 31.10.2018. Based on the said opinion, after preparation of the appeal papers, the State filed the second appeal only on 18.10.2019. Page 3 of 11 Hence, there was inordinate delay of 1788 days occasioned in preferring the second appeal, but the same was not properly explained by the State. 5. The legal position is that where a case has been presented in the Court beyond limitation, the petitioner has to explain the Court as to what was the "sufficient cause" which means an adequate and enough reason which prevented him to approach the Court within limitation. In _Majji Sannemma v. Reddy Sridevi[4]_ , it was held by this Court that even though limitation may harshly affect the rights of a party, it has to be applied with all its rigour when prescribed by statute. A reference was also made to the decision of this Court in _Ajay Dabra v. Pyare Ram[5]_ wherein, it was held as follows: _**"13.** This Court in the case of Basawaraj v. Special Land Acquisition Officer [(2013) 14 SCC 81] while rejecting an application for condonation of delay for lack of sufficient cause has concluded in Paragraph 15 as follows:_ _“15. The law on the issue can be summarised to the effect that where a case has been presented in the court beyond limitation, the applicant has to explain the court as to what was the “sufficient cause” which means an adequate and enough reason which prevented him to approach the court within limitation. In case a party is found to be negligent, or for want of bona fide on his part in the facts and circumstances of the case, or found to have not acted diligently or remained inactive, there cannot be a justified_ > 4 2021 SCC Online SC 1260 > 5 2023 SCC Online SC 92 Page 4 of 11 _ground to condone the delay. No court could be justified in condoning such an inordinate delay by imposing any condition whatsoever. The application is to be decided only within the parameters laid down by this Court in regard to the condonation of delay. In case there was no sufficient cause to prevent a litigant to approach the court on time condoning the delay without any justification, putting any condition whatsoever, amounts to passing an order in violation of the statutory provisions and it tantamounts to showing utter disregard to the legislature.”_ _**14.** Therefore, we are of the considered opinion that the High Court did not commit any mistake in dismissing the delay condonation application of the present appellant."_ Thus, it is crystal clear that the discretion to condone the delay has to be exercised judiciously based on facts and circumstances of each case and that, the expression 'sufficient cause' cannot be liberally interpreted, if negligence, inaction or lack of _bona fides_ is attributed to the party. 5.1. In _Union of India v. Jahangir Byramji Jeejeebhoy (D) through his legal heir[6]_ , wherein, one of us (J.B.Pardiwala, J) was a member, after referring to various decisions on the issue, it was in unequivocal terms observed by this Court that delay should not be excused as a matter of generosity and rendering substantial > 6 2024 INSC 262 : 2024 SCC OnLine SC 489 Page 5 of 11 justice is not to cause prejudice to the opposite party. The relevant passage of the same is profitably extracted below: _“24. In the aforesaid circumstances, we made it very clear that we are not going to look into the merits of the matter as long as we are not convinced that sufficient cause has been made out for condonation of such a long and inordinate delay._ _25. It hardly matters whether a litigant is a private party or a State or Union of India when it comes to condoning the gross delay of more than 12 years. If the litigant chooses to approach the court long after the lapse of the time prescribed under the relevant provisions of the law, then he cannot turn around and say that no prejudice would be caused to either side by the delay being condoned. This litigation between the parties started sometime in 1981. We are in 2024. Almost 43 years have elapsed. However, till date the respondent has not been able to reap the fruits of his decree. It would be a mockery of justice if we condone the delay of 12 years and 158 days and once again ask the respondent to undergo the rigmarole of the legal proceedings._ _26. The length of the delay is a relevant matter which the court must take into consideration while considering whether the delay should be condoned or not. From the tenor of the approach of the appellants, it appears that they want to fix their own period of limitation for instituting the proceedings for which law has prescribed a period of limitation. Once it is held that a party has lost his right to have the matter considered on merits because of his own inaction for a long, it cannot be presumed to be non-deliberate delay and in such circumstances of the case, he cannot be heard to plead that the substantial justice deserves to be preferred as against the technical considerations. While considering the plea for condonation of delay, the court must not start with the merits of the main matter. The court owes a duty to first ascertain the bona fides_ Page 6 of 11 _of the explanation offered by the party seeking condonation. It is only if the sufficient cause assigned by the litigant and the opposition of the other side is equally balanced that the court may bring into aid the merits of the matter for the purpose of condoning the delay._ _27. We are of the view that the question of limitation is not merely a technical consideration. The rules of limitation are based on the principles of sound public policy and principles of equity. We should not keep the ‘Sword of Damocles’ hanging over the head of the respondent for indefinite period of time to be determined at the whims and fancies of the appellants._ _xxx xxx xxx_ _34. In view of the aforesaid, we have reached to the conclusion that the High Court committed no error much less any error of law in passing the impugned order. Even otherwise, the High Court was exercising its supervisory jurisdiction under Article 227 of the Constitution of India._ _35. In a plethora of decisions of this Court, it has been said that delay should not be excused as a matter of generosity. Rendering substantial justice is not to cause prejudice to the opposite party. The appellants have failed to prove that they were reasonably diligent in prosecuting the matter and this vital test for condoning the delay is not satisfied in this case._ _36. For all the foregoing reasons, this appeal fails and is hereby dismissed. There shall be no order as to costs.”_ Page 7 of 11 Applying the above legal proposition to the facts of the present case, we are of the opinion that the High Court correctly refused to condone the delay and dismissed the appeal by observing that such inordinate delay was not explained satisfactorily, no sufficient cause was shown for the same, and no plausible reason was put forth by the State. Therefore, we are inclined to reject this petition at the threshold. 6. At the same time, we cannot simply brush aside the delay occurred in preferring the second appeal, due to callous and lackadaisical attitude on the part of the officials functioning in the State machinery. Though the Government adopts systematic approach in handling the legal issues and preferring the petitions/applications/appeals well within the time, due to the fault on the part of the officials in merely communicating the information on time, huge revenue loss will be caused to the Government exchequer. The present case is one such case, wherein, enormous delay of 1788 days occasioned in preferring the second appeal due to the lapses on the part of the officials functioning under the State, though valuable Government lands were involved. Therefore, we direct Page 8 of 11 the State to streamline the machinery touching the legal issues, offering legal opinion, filing of cases before the Tribunal / Courts, etc., fix the responsibility on the officer(s) concerned, and penalize the officer(s), who is/are responsible for delay, deviation, lapses, etc., if any, to the value of the loss caused to the Government. Such direction will have to be followed by all the States scrupulously. 7. There is one another aspect of the matter which we must not ignore or overlook. Over a period of time, we have noticed that whenever there is a plea for condonation of delay be it at the instance of a private litigant or State the delay is sought to be explained right from the time, the limitation starts and if there is a delay of say 2 years or 3 years or 4 years till the end of the same. For example if the period of limitation is 90 days then the party seeking condonation has to explain why it was unable to institute the proceedings within that period of limitation. What events occurred after the 91st day till the last is of no consequence. The court is required to consider what came in the way of the party that it was unable to file it between the 1[st] day and the 90[th] day. It is true that a party is entitled to wait until the last day of limitation for filing an appeal. But when it allows the limitation to expire and pleads sufficient cause for not filing the appeal earlier, the sufficient cause must establish that because of some event or circumstance arising before the limitation expired it was not possible to Page 9 of 11 file the appeal within time. No event or circumstance arising after the expiry of limitation can constitute such sufficient cause. There may be events or circumstances subsequent to the expiry of limitation which may further delay the filing of the appeal. But that the limitation has been allowed to expire without the appeal being filed must be traced to a cause arising within the period of limitation. (See: _**Ajit Singh Thakur Singh and Another v. State of Gujarat**_ , AIR 1981 SC 733). 8. Accordingly, we dismiss this Special Leave Petition with costs of Rs.1,00,000/to be deposited by the State within a period of two weeks from today with the Supreme Court Mediation Centre and file proof thereof. If the said amount, as directed, is not deposited by the State, the Registry shall take necessary steps for recovery of the same, in accordance with law. 9. We have deemed it necessary to impose costs to send a stern message that the States must not misuse the Supreme Court’s time by filing appeals against the well-reasoned and conscious decisions rendered by the High Courts without proper grounds. Page 10 of 11 10. Pending application(s), if any, shall stand disposed of. ……………………………….J. (J. B. PARDIWALA) ………………………………J. (R. MAHADEVAN) New Delhi. November 29, 2024. Page 11 of 11
End of Judgment Record
Browse All Landmark Cases Judgments
2019-01-22

State of Himachal Pradesh & Anr. v. Pinju Ram & Others; State of Himachal Pradesh & Ors. v. Ganesh Dutt & Anr.

This batch of appeals concerns regularisation and monetary benefits of part‑time employees in Himachal Pradesh who were converted to daily‑wage status. The State had issued a policy on 27 February 2004: part‑time Class‑IV employees who had completed ten years of continuous service as on 31 December 2003 would be made daily wagers with prospective effect, and posts vacated by such employees would stand abolished; Education and Ayurveda were excluded from the policy. Revenue Chowkidars, engaged by Panchayats, were not covered by that policy and received separate treatment. Following writ petitions and an order of the Himachal Pradesh High Court and in light of later developments, the State drew‑up directions in 2011 (22 September) to give seniority to Revenue Chowkidars on the basis of ten years of service, but with wages from the date of actual appointment and without back‑dated monetary benefits; 7 July 2012 further instructions reiterated this stance for remaining part‑time employees, with monetary benefits not guaranteed in the interregnum. The respondents pressed for back wages dating from 1 January 2007 and broader coverage. The Supreme Court held that the 2007 back‑pay direction was unsustainable, clarified that seniority would count from ten years without past benefits, and that the 2011 policy and Moti Singh principle should guide the approach. The appeals are allowed; no costs. The related writ petitions are to be disposed of consistent with these directions.

2018-08-14

Union Bank of India and Others v. C.G. Ajay Babu and Anr.

This is a Supreme Court of India appeal concerning the forfeiture of gratuity under the Payment of Gratuity Act, 1972. The respondent was a branch manager of the appellant bank and was dismissed on 3 June 2004 after disciplinary proceedings. A show-cause notice sought to forfeit gratuity due to misconduct involving moral turpitude, which was ordered on 20 April 2004. The High Court upheld the dismissal but held that gratuity could be paid since there was no financial loss to the bank, and that a bipartite settlement between the bank and employees permitted forfeiture only where misconduct caused financial loss. The Division Bench, however, held that forfeiture under Section 4(6) must be read together with Section 4(5) and that no loss was proven, thus entitling the employee to gratuity in accordance with the bipartite settlement. The Supreme Court agreed with the High Court that forfeiture is not automatic; it is controlled by Sections 4(5) and 4(6) of the Act and by the bipartite settlement, which requires loss to justify forfeiture. The Court emphasized that an act must constitute an offence involving moral turpitude and that conviction is generally required for forfeiture under 4(6)(b)(ii). The appeal is dismissed with no costs.

2018-09-25

Reema Salkan v. Sumer Singh Salkan

This is a Supreme Court of India criminal appeal under the Criminal Appellate Jurisdiction arising from a maintenance dispute under Section 125 Cr.P.C. The parties, married in 2002, had a protracted litigation history. The Family Court granted maintenance to the wife from 17 July 2003 to 8 December 2010, and held no maintenance thereafter. The High Court, in revision, partly allowed the application, directing Rs.9,000 per month from 9 December 2010 onward, while upholding the earlier period’s Rs.10,000 per month. This Court had earlier granted interim maintenance of Rs.20,000 per month in 2014 (Criminal Appeal Nos. 2347-2349 of 2014). The appellant contends there has been no change in circumstances since the interim order and that the respondent’s substantial assets, education, and overseas earnings establish the capacity to pay higher maintenance. The respondent defends the High Court’s reasoning, arguing that the Family Court’s assessment, demeanor observations, and the principle that maintenance should not be perpetual require careful scrutiny, and that the notional minimum wage approach used by the High Court is flawed. The overarching issue is the quantum of monthly maintenance payable to the appellant and whether the interim amount should be augmented beyond the period up to 2010.”

2019-12-03

M/s Embassy Property Developments Pvt. Ltd. v State of Karnataka & Ors.

This judgment concerns three Civil Appeals filed by a Resolution Applicant, the Corporate Debtor (through its Resolution Professional) and the Committee of Creditors, challenging an Interim Order of the Karnataka High Court staying an NCLT order in proceedings under the Insolvency and Bankruptcy Code, 2016. The NCLT Chennai had admitted an application under Section 7 of the IBC against M/s Tiffins Barytes Asbestos & Paints Ltd. and directed a moratorium under Section 14. The Interim Resolution Professional then sought a deemed extension of a mining lease under MMDR Act, 1957 and the Government of Karnataka rejected it. The NCLT, by an order dated 11.12.2018, set aside the Government’s order and directed execution of Supplement Lease Deeds for the period up to 31.03.2020. The Government of Karnataka challenged this in a High Court writ petition, which stayed the impugned NCLT order. The core issues were: (i) whether the High Court may interfere under Article 226/227 with an NCLT order in IBC when an appeal lies to the NCLAT, and (ii) whether fraud can be inquired into by NCLT/NCLAT in CIRP. The Court reiterates that IBC is a complete, umbrella code with a three‑tier mechanism (NCLT, NCLAT, Supreme Court) and that public‑law disputes arising from MMDR Act obligations lie outside IBC. It ultimately holds that while NCLT/NCLAT may inquire into fraud, they cannot adjudicate MMDR‑related public legal disputes; and the High Court’s writ jurisdiction in public‑law contexts remains permissible. The appeals are dismissed.